24/06/2008 I. Lehmann, Magnets Krako w 1 Magnet Meeting 24/06/2008 - Krakow Topics for discussion: Fixing interfaces and the interface document. The work on the TDR (what needs to be done, who does it, and editorial issues) The status of producing a field map for the simulations, and how this can be compared and cross checked.

description

Magnet Meeting 24/06/2008 - Krakow. Topics for discussion: Fixing interfaces and the interface document. The work on the TDR (what needs to be done, who does it, and editorial issues) The status of producing a field map for the simulations, and how this can be compared and cross checked. - PowerPoint PPT Presentation

Transcript of Magnet Meeting 24/06/2008 - Krakow

Page 1: Magnet Meeting 24/06/2008 - Krakow

24/06/2008 I. Lehmann, Magnets Krakow

1

Magnet Meeting 24/06/2008 - Krakow

Topics for discussion:• Fixing interfaces and the interface

document.• The work on the TDR (what needs to be done,

who does it, and editorial issues)• The status of producing a field map for the

simulations, and how this can be compared and cross checked.

Page 2: Magnet Meeting 24/06/2008 - Krakow

24/06/2008 I. Lehmann, Magnets Krakow

2

Agenda• Minutes of last meeting • The interface document: Evie Downie

– Discussion: Scope and timelines• Technical Design Report: Inti Lehmann

– Discussion: • Missing parts• Distribution of work• Timelines

• Field and Cryogenics: Andrea Bersani• Yoke design: Yuri Lobanov• Status and method to create a field map: Jost Luehning• Space in the Endcap: Genadii Alexeev• AoT

Page 3: Magnet Meeting 24/06/2008 - Krakow

24/06/2008 I. Lehmann, Magnets Krakow

3

Technical Design Report

Layout

• Executive Summary to be filled• Introduction to be filled• Requirements on the Spectrometer Magnets to be filled• Target Spectrometer Overview migration?• Coil and Cryostat of the Target Spectrometer drafted• Iron Yoke of the Target Spectrometer drafted• Forward Spectrometer part. drafted• Infrastructure Requirements to be filled• Organisation and Management part. drafted• Conclusions to be filled

Page 4: Magnet Meeting 24/06/2008 - Krakow

24/06/2008 I. Lehmann, Magnets Krakow

4

Technical Design Report

Distribution of work• Executive Summary GR• Introduction IL• Organisation and Management IL• Spectrometer Overview RP,AV,GR,GA• Target Spectrometer

– Requirements AB, YL– Coil and Cryostat AB– Instrumented Flux Return YL– Detector and Target Integration AB,YL– Performance

• Forward Spectrometer IL + JL + EL• Infrastructure BL,DP• Timelines ILTimelines

1st full draft in September? Submit by Jan 2009.