MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap...

24
MAFC Pre-Design Concepts August 22, 2017

Transcript of MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap...

Page 1: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

MAFC Pre-Design Concepts

August 22, 2017

Page 2: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Recap of Previous Discussions

Page 3: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Recap

• Council priorities for a concept design1. Year-round, indoor aquatic facility with 6-lane pool and separate

multi-use pool and play area

2. New locker room addition to access the pools directly

3. Expand parking to accommodate expanded services (110-120 spaces) and relocating the driveway

4. Relocate 2nd floor weight room to existing locker rooms on 1st floor

5. Expand group fitness space into the vacated weight room area

6. Replace the tennis courts with 2-3 new courts

• Ratio would present 2-3 layout for renovations based on scope and budget

• Each layout would include various options and associated cost estimates

Page 4: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Recap (continued)

• Proposed driveway relocation

• The aquatics component of this project will be the largest and most expensive priority

– The enclosure will be the most expensive item of this priority

• The PARTF grant awards will be announced on Friday, August 25

Page 5: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Project Considerations

• Fire Department Access

• Traffic Impact – No TIA required; DOT Permitting

• Stormwater Mitigation Needs

• Building Code Requirements

• UDO Guidelines

• Contingency Budget

Page 6: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

What Is Not Included

• FF&E: can reuse some existing; but some new purchases may be needed

• Road Improvements: may not be required

• Pool play structures: bid as alternate

• Unsuitable soils allowance: contingency provided

• Cost for phased construction: $125-150K

• Separate tap for AFSS if existing water pressure is not adequate

Page 7: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Goals For Tonight

Page 8: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Goals

• Town Council’s review and consideration of renovation concepts and information

• Selection of Preferred Site Layout

• Discussion/Potential Decision on Options

• Identify Additional Information Town Council Need to Continue Discussion

Page 9: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Layouts and Concepts

Page 10: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,
Page 11: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,
Page 12: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,
Page 13: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,
Page 14: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Pool Design/Enclosures

Page 15: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

2 Pools 3 Pools

Page 16: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Sprung

Page 17: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

OpenAire

Page 18: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Cost Estimates/Project Timeline

Page 19: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,
Page 20: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,
Page 21: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Staff Evaluation

Page 22: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Preferred Option

• Staff reviewed the layouts and options

• Option 1 is the preferred layout

– Driveway relocation

– Diversity of parking areas

– Location of tennis courts

Page 23: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Estimated Operational Impacts

• Recommendation for construction – close facility

• Estimated budget impacts

– Current Subsidy – Approximately $250,000

– Revenue Loss - $320,000 - $330,000

– Personnel - $166,000 in personnel savings

– Operations - $120,000 in operational savings

• Retention of Full-Time Staff - $273,000

– Utilized employees in other job functions during closure

• Net Impact remains approx. $250,000 -$275,000 Subsidy

Page 24: MAFC Pre-Design Concepts - Amazon Web Services · MAFC Pre-Design Concepts August 22, 2017. Recap of Previous Discussions. Recap •Council priorities for a concept design 1. Year-round,

Questions and Discussion