LS1 general planning and strategy for LHC, LHC injectors
LHC Performance Workshop
Chamonix 2012 K. Foraz
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 1
EN Outline
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 2
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
EN Draft 10 years plan (27/10/11)
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 3
2012 2013 2014 2015 2016
2017 2018 2019 2020 2021
Operation period 1 (OP1)
Long Shutdown 1 (LS1)
• Machine : Splices consolidation… • ATLAS: - Consolidation and new forward beam pipes • ALICE: detector completion • CMS:FWD muons upgrade + Consolidation & infrastructure
improvements • LHCb: consolidations
• Machine: Collimation & prepare for crab cavities & RF cryo system • ATLAS: new pixel detect. - detect. for ultimate luminosity. • ALICE - Inner vertex system upgrade • CMS - New Pixel. New HCAL Photodetectors. Completion of FWD muons upgrade • LHCb - full trigger upgrade, new vertex detector etc.
Long Shutdown 2 (LS2)
Operation period 3 (OP3)
Operation period 2 (OP2)
OP2
LINAC 4 connection ?
EN LS1 - Goal
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 4
Take all measures for a safe and reliable operation of LHC @ 7TeV/beam
Full maintenance Consolidation & upgrade
LHC machine & experiments
Injectors
EN LS1 - Time window
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 5
• 20 months from Beam OFF to Beam ON
– Actual total duration agreed between experiments and machine
• LHC machine: 20 months
• ALICE: 12 months (up to 15 months)
• ATLAS: 15 months (but from April 2013)
• CMS: 20 months
• LHCb: 12 months
Marzio: “ LHC experiments upgrade & maintenance”
EN Requests Approval
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 6
• Meetings being held with stakeholders to understand Goal of activities Time key drivers Support needed
• For accelerator complex: database of requests
is being filled : LHC and injectors
To detect conflicts/overloads & to decide what is compulsory, what we can afford & what we have to postpone to LS2
Priorities set for LHC machine
– P1: Beam to 6.5-7TeV, nominal performance – P2: Reliable operation – P3: CERN approved projects – P4: no CERN approved projects
• Mauro : “EN-CV upgrade & consolidation” • Francois: “EN-EL upgrade & consolidation” • Erk : “RF upgrade program in LHC injectors
and LHC machine“
EN Outline
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 7
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
BA
2
BA
1
BA
4
BA
3
BA
6
BA
5
TI2
BA
7
BA
80
TI8
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Sec.
6
Sec.
5
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
20
13
2
01
4
EN
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Lin
ac 3
Lin
ac 2
CTF
Lin
ac 4
AD
$ E
LEN
A
HI-
ISO
LDE SPS PS PS Booster
v v
General Shutdown works: ABT, Magnets, RP, lifts…
General Shutdown works: ABT, Magnets, RP, lifts…
Injectors
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 8
Irra
dia
ted
ca
ble
s
Irra
dia
ted
ca
ble
s
RF
Up
grad
e
Dec
ablin
g ca
mp
aign
Survey: Tilt & vertical - Quads
Survey
Surv
ey
Surv
ey
Survey: Alignment maintenance
Survey: Vertical & Radial measurements & Alignment
• “Normal” Xmas shutdown (*2) • Survey: measurements, til, alignment • SPS:
• EL: clear unused cables & irradiated cables in SPS • RF upgrades • Power converter consolidation • Other groups works Courtesy D. McFarlane
V. Chohan
Will be detailed during
IEFC workshop
BA
2
BA
1
BA
4
BA
3
BA
6
BA
5
TI2
BA
7
BA
80
TI8
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Sec.
6
Sec.
5
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
20
13
2
01
4
EN
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Lin
ac 3
Lin
ac 2
CTF
Lin
ac 4
AD
$ E
LEN
A
HI-
ISO
LDE SPS PS PS Booster
v v
General Shutdown works: ABT, Magnets, RP, lifts…
Injectors
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 9
Irra
dia
ted
ca
ble
s
Irra
dia
ted
ca
ble
s
RF
Up
grad
e
Dec
ablin
g ca
mp
aign
Survey: Tilt & vertical - Quads
Survey
Surv
ey
Surv
ey
General Shutdown works: ABT, Magnets, RP, lifts…
Renovation of Vacuum control system
Survey: Alignment maintenance
Survey: Vertical & Radial measurements & Alignment
New access system commissioning
• PS & PS booster • Renovation of vacuum control system • Cooling & ventilation maintenance and renovation • RF maintenance & upgrade • New access system • Other groups works • Interlock
Interlck
Interlck
Interlck
Interlck
Courtesy D. McFarlane V. Chohan
General Shutdown works: ABT, Magnets, RP, lifts…
EN Injectors access system
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 10
Rui: “Access strategy in the accelerator complex and experimental area”
Courtesy E. Sanchez
BA
2
BA
1
BA
4
BA
3
BA
6
BA
5
TI2
BA
7
BA
80
TI8
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Sec.
6
Sec.
5
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
20
13
2
01
4
EN
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Lin
ac 3
Lin
ac 2
CTF
Lin
ac 4
AD
$ E
LEN
A
HI-
ISO
LDE SPS PS PS Booster
v v
General Shutdown works: ABT, Magnets, RP, lifts…
General Shutdown works: ABT, Magnets, RP, lifts…
Injectors
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 11
Irra
dia
ted
ca
ble
s
Irra
dia
ted
ca
ble
s
RF
Up
grad
e
Dec
ablin
g ca
mp
aign
Survey: Tilt & vertical - Quads
Survey
Surv
ey
Surv
ey
Cold Checkout & Start-up
Renovation of Vacuum control system
Survey: Alignment maintenance
Survey: Vertical & Radial measurements & Alignment
Interlck
Interlck
Interlck
Interlck
New access system commissioning
Cold Checkout & Start-up
Set
up
of
Arg
on
&
Xen
on
bea
m
(1)
Set
up
of
Arg
on
&
Xen
on
bea
m (
2)
LIN
AC
4 c
om
mis
sio
nin
g
AD
ha
ll p
rep
ara
tio
n f
or
ELEN
A
CV
CTF
op
era
tio
na
l da
tes
TBC
• Early 2014 :Cold check-out and Start up • LINAC3 : set up of Argon and Xenon beam • LINAC4 commissioning • CTF operational – dates TBC • HI-ISOLDE: Cooling & Ventilation works • AD & ELENA: AD hall preparation for ELENA
Courtesy D. McFarlane V. Chohan
EN Outline
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 12
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
EN LHC machine – Time key drivers
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 13
• Time key drivers in LHC machine
– Superconducting circuits consolidation
– Radiation To Electronics R2E
– Maintenance
– …. And many other activities (already > 100 entries in the db for LHC machine)
EN One typical sector
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 14
Powering and ELQA tests prior to Warm-up (4+4 d) • qualify circuits except mains to 7TeV • fault localization.. • CSCM (1 sector)
Warm-up: incl. vacuum leak tests at 80K (1wk) to localize leaks
Maintenance & consolidation
Preparation for & cool-down
Powering tests
Mirko: “Powering tests before LHC warm-up: What is new from Chamonix 2011? ”
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
20
13
2
01
4
EN Splices
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 15
PT PT PT PT
PT PT PT PT
Powering Tests
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
Splices Splices
Splices Splices
Splices Splices
Splices Splices
Jean-Philippe : “LHC consolidation of the
superconducting circuits ”
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
Cool-down
Cool-down Cool-down
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
20
13
2
01
4
EN Other superconducting circuits
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 16
PT PT PT PT
PT PT PT PT
Splices Splices
Splices Splices
Splices Splices
Splices Splices
Magnets exchange
DN200
Consolidation of SAM
Inner triplets braid Connection Cryostat
Y lines
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
Powering Tests
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-down
Cool-down Cool-down
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
20
13
2
01
4
EN Maintenance
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 17
PT PT PT PT
PT PT PT PT
Splices Splices
Splices Splices
Splices Splices
Splices Splices
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
Cryogenics : 18 weeks per cryoplant + Maintenance of all the equipment: CV, EL, RF…, mainly in service areas
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
Powering Tests
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-down
Cool-down Cool-down
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
EN R2E mitigation measures
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 18
• Detailed & graphical schedules ready, except P7 in progress
Courtesy M. Barberan
Anne-Laure : “R2E strategy and activities during LS1 ”
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
20
13
2
01
4
EN
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
R2E mitigation measures
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 19
PT PT PT PT
PT PT PT PT
Splices Splices
Splices Splices
Splices Splices
Splices Splices
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
R2E
R2
E
R2
E
Just in time for CD of s.12 Delay by 2 wks CD of S.81
R2
E
Delay Cool-down of 56 (1st sector) Delay Powering tests of 56 But 1 month marginw.r.t s45
Powering Tests
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-down
Cool-down Cool-down
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
P7
to
be
fin
aliz
ed
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
20
13
2
01
4
Jan.
EN Skeleton schedule – Physics to physics
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 20
PT PT PT PT
PT PT PT PT
Splices Splices
Splices Splices
Splices Splices
Splices Splices
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
Cold check-out & Beam Commissioning
Physics 1 week stand-by 2014-2015
Ezio : What is the maximum reasonable energy
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
Powering Tests
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-down
Cool-down Cool-down
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
20
13
2
01
4
EN Risks (possible changes in schedule): IC trains
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 21
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
From installation experience, first 2 sectors took ~ 20% longer
PT PT PT PT
PT PT PT PT
Powering Tests
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Splices Splices
Splices Splices
Splices Splices
Splices Splices
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
Cool-down
Cool-down Cool-down
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
+ 20% +
20%
But leak detection and electrical tests at the end can reserve bad surprises in the last sectors…
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
20
13
2
01
4
EN Risks (possible changes in schedule): R2E mitigation measures
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 22
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
PT PT PT PT
PT PT PT PT
Splices Splices
Splices Splices
Splices Splices
Splices Splices
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
R2E
R2
E
R2
E
R2
E Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests Powering
Tests
Cool-down
Cool-down Cool-down
Cool-down
Powering Tests
Cool-down
Cool-down
Cool-down
Powering Tests
Cool-down
P7
to
be
fin
aliz
ed
P1 & P5 are tight in schedule : Effect of 6 weeks delay
No direct impact on end dates but will delay the powering tests of 3rd and following sectors.
0
1
2
3
4
5
6
7
Nov Dec Jan Feb Mar Apr May Jun
Nb
of
sect
ors
Harwdware commissioning workload
6 weeks delay no delay
S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
20
13
2
01
4
Jan.
EN Risk (possible changes in schedule): additional activities
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 23
PT PT PT PT
PT PT PT PT
Splices Splices
Splices Splices
Splices Splices
Splices Splices
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
Cry
o M
ain
t.
Cold check-out & Beam Commissioning
Physics
-> 10K
CSCM CSCM preparation
Warm-up Warm-up Warm-up Warm-up
Warm-up Warm-up Warm-up
Warm-up
Powering Tests
Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests
Powering Tests
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
CSCM
Cool-down CSCM
Cool-down CSCM
Powering Tests
Cool-down CSCM
CSCM
CSCM CSCM CSCM
Additional activities, especially those requiring supports from other groups can disorganize the global schedule, and induce delays. CSCM tests in all sectors will cost around 4 weeks
EN Outline
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 24
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
EN Organization
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 25
• Schedule & logistics – Lots’of work still to be done in matter of schedule &
logistics for all the other activities w.r.t. skeleton schedule
• Preparation – ECR have to be written prior to works
– Modification of the envelope of your equipment ICL
– DIMR
– Materials have to be ready in due time…..This has often induced delays !!!
• Follow-up – Weekly coordination and scheduling meeting
Reiner : “QPS upgrade and machine protection during LS1 ” Miguel : “Vacuum upgrade” Laurent: “Cryogenics system: strategy to achieve nominal performance and reliable operation “
EN Conclusions
Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 26
• Analysis of requests well advanced (LHC & experiments, injectors)
– w.r.t. priorities & resources & time & interaction between groups
– New requests will be scrutinized, especially the support form overloaded groups (VSC, EL, CV)
• “Skeleton” schedules for LHC machine & injectors ready
• Workload is huge and the schedule is tight
• Worksites have to be well prepared. Please do not forget layout, integration & safety