EN LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K. Foraz Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 1

Transcript of LS1 general planning and strategy for LHC, LHC...

Page 1: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN

LS1 general planning and strategy for LHC, LHC injectors

LHC Performance Workshop

Chamonix 2012 K. Foraz

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 1

Page 2: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Outline

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 2

• General frame

• Injectors

• LHC machine : Main activities and risks

• Organization

• Conclusion

• General frame

• Injectors

• LHC machine : Main activities and risks

• Organization

• Conclusion

Page 3: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Draft 10 years plan (27/10/11)

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 3

2012 2013 2014 2015 2016

2017 2018 2019 2020 2021

Operation period 1 (OP1)

Long Shutdown 1 (LS1)

• Machine : Splices consolidation… • ATLAS: - Consolidation and new forward beam pipes • ALICE: detector completion • CMS:FWD muons upgrade + Consolidation & infrastructure

improvements • LHCb: consolidations

• Machine: Collimation & prepare for crab cavities & RF cryo system • ATLAS: new pixel detect. - detect. for ultimate luminosity. • ALICE - Inner vertex system upgrade • CMS - New Pixel. New HCAL Photodetectors. Completion of FWD muons upgrade • LHCb - full trigger upgrade, new vertex detector etc.

Long Shutdown 2 (LS2)

Operation period 3 (OP3)

Operation period 2 (OP2)

OP2

LINAC 4 connection ?

Page 4: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN LS1 - Goal

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 4

Take all measures for a safe and reliable operation of LHC @ 7TeV/beam

Full maintenance Consolidation & upgrade

LHC machine & experiments

Injectors

Page 5: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN LS1 - Time window

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 5

• 20 months from Beam OFF to Beam ON

– Actual total duration agreed between experiments and machine

• LHC machine: 20 months

• ALICE: 12 months (up to 15 months)

• ATLAS: 15 months (but from April 2013)

• CMS: 20 months

• LHCb: 12 months

Marzio: “ LHC experiments upgrade & maintenance”

Page 6: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Requests Approval

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 6

• Meetings being held with stakeholders to understand Goal of activities Time key drivers Support needed

• For accelerator complex: database of requests

is being filled : LHC and injectors

To detect conflicts/overloads & to decide what is compulsory, what we can afford & what we have to postpone to LS2

Priorities set for LHC machine

– P1: Beam to 6.5-7TeV, nominal performance – P2: Reliable operation – P3: CERN approved projects – P4: no CERN approved projects

• Mauro : “EN-CV upgrade & consolidation” • Francois: “EN-EL upgrade & consolidation” • Erk : “RF upgrade program in LHC injectors

and LHC machine“

Page 7: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Outline

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 7

• General frame

• Injectors

• LHC machine : Main activities and risks

• Organization

• Conclusion

Page 8: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

BA

2

BA

1

BA

4

BA

3

BA

6

BA

5

TI2

BA

7

BA

80

TI8

Sec.

2

Sec.

1

Sec.

4

Sec.

3

Sec.

6

Sec.

5

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

20

13

2

01

4

EN

Sec.

2

Sec.

1

Sec.

4

Sec.

3

Lin

ac 3

Lin

ac 2

CTF

Lin

ac 4

AD

$ E

LEN

A

HI-

ISO

LDE SPS PS PS Booster

v v

General Shutdown works: ABT, Magnets, RP, lifts…

General Shutdown works: ABT, Magnets, RP, lifts…

Injectors

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 8

Irra

dia

ted

ca

ble

s

Irra

dia

ted

ca

ble

s

RF

Up

grad

e

Dec

ablin

g ca

mp

aign

Survey: Tilt & vertical - Quads

Survey

Surv

ey

Surv

ey

Survey: Alignment maintenance

Survey: Vertical & Radial measurements & Alignment

• “Normal” Xmas shutdown (*2) • Survey: measurements, til, alignment • SPS:

• EL: clear unused cables & irradiated cables in SPS • RF upgrades • Power converter consolidation • Other groups works Courtesy D. McFarlane

V. Chohan

Will be detailed during

IEFC workshop

Page 9: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

BA

2

BA

1

BA

4

BA

3

BA

6

BA

5

TI2

BA

7

BA

80

TI8

Sec.

2

Sec.

1

Sec.

4

Sec.

3

Sec.

6

Sec.

5

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

20

13

2

01

4

EN

Sec.

2

Sec.

1

Sec.

4

Sec.

3

Lin

ac 3

Lin

ac 2

CTF

Lin

ac 4

AD

$ E

LEN

A

HI-

ISO

LDE SPS PS PS Booster

v v

General Shutdown works: ABT, Magnets, RP, lifts…

Injectors

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 9

Irra

dia

ted

ca

ble

s

Irra

dia

ted

ca

ble

s

RF

Up

grad

e

Dec

ablin

g ca

mp

aign

Survey: Tilt & vertical - Quads

Survey

Surv

ey

Surv

ey

General Shutdown works: ABT, Magnets, RP, lifts…

Renovation of Vacuum control system

Survey: Alignment maintenance

Survey: Vertical & Radial measurements & Alignment

New access system commissioning

• PS & PS booster • Renovation of vacuum control system • Cooling & ventilation maintenance and renovation • RF maintenance & upgrade • New access system • Other groups works • Interlock

Interlck

Interlck

Interlck

Interlck

Courtesy D. McFarlane V. Chohan

General Shutdown works: ABT, Magnets, RP, lifts…

Page 10: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Injectors access system

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 10

Rui: “Access strategy in the accelerator complex and experimental area”

Courtesy E. Sanchez

Page 11: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

BA

2

BA

1

BA

4

BA

3

BA

6

BA

5

TI2

BA

7

BA

80

TI8

Sec.

2

Sec.

1

Sec.

4

Sec.

3

Sec.

6

Sec.

5

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

20

13

2

01

4

EN

Sec.

2

Sec.

1

Sec.

4

Sec.

3

Lin

ac 3

Lin

ac 2

CTF

Lin

ac 4

AD

$ E

LEN

A

HI-

ISO

LDE SPS PS PS Booster

v v

General Shutdown works: ABT, Magnets, RP, lifts…

General Shutdown works: ABT, Magnets, RP, lifts…

Injectors

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 11

Irra

dia

ted

ca

ble

s

Irra

dia

ted

ca

ble

s

RF

Up

grad

e

Dec

ablin

g ca

mp

aign

Survey: Tilt & vertical - Quads

Survey

Surv

ey

Surv

ey

Cold Checkout & Start-up

Renovation of Vacuum control system

Survey: Alignment maintenance

Survey: Vertical & Radial measurements & Alignment

Interlck

Interlck

Interlck

Interlck

New access system commissioning

Cold Checkout & Start-up

Set

up

of

Arg

on

&

Xen

on

bea

m

(1)

Set

up

of

Arg

on

&

Xen

on

bea

m (

2)

LIN

AC

4 c

om

mis

sio

nin

g

AD

ha

ll p

rep

ara

tio

n f

or

ELEN

A

CV

CTF

op

era

tio

na

l da

tes

TBC

• Early 2014 :Cold check-out and Start up • LINAC3 : set up of Argon and Xenon beam • LINAC4 commissioning • CTF operational – dates TBC • HI-ISOLDE: Cooling & Ventilation works • AD & ELENA: AD hall preparation for ELENA

Courtesy D. McFarlane V. Chohan

Page 12: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Outline

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 12

• General frame

• Injectors

• LHC machine : Main activities and risks

• Organization

• Conclusion

Page 13: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN LHC machine – Time key drivers

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 13

• Time key drivers in LHC machine

– Superconducting circuits consolidation

– Radiation To Electronics R2E

– Maintenance

– …. And many other activities (already > 100 entries in the db for LHC machine)

Page 14: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN One typical sector

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 14

Powering and ELQA tests prior to Warm-up (4+4 d) • qualify circuits except mains to 7TeV • fault localization.. • CSCM (1 sector)

Warm-up: incl. vacuum leak tests at 80K (1wk) to localize leaks

Maintenance & consolidation

Preparation for & cool-down

Powering tests

Mirko: “Powering tests before LHC warm-up: What is new from Chamonix 2011? ”

Page 15: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

20

13

2

01

4

EN Splices

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 15

PT PT PT PT

PT PT PT PT

Powering Tests

Powering Tests Powering

Tests Powering Tests

Powering Tests

Powering Tests

Powering Tests Powering

Tests

Powering Tests Splices

Warm-up Preparation for cool-down

Cool-down

Splices Splices

Splices Splices

Splices Splices

Splices Splices

Jean-Philippe : “LHC consolidation of the

superconducting circuits ”

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

Cool-down

Cool-down Cool-down

Cool-down

Cool-down

Cool-down

Cool-down Cool-down

Page 16: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

20

13

2

01

4

EN Other superconducting circuits

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 16

PT PT PT PT

PT PT PT PT

Splices Splices

Splices Splices

Splices Splices

Splices Splices

Magnets exchange

DN200

Consolidation of SAM

Inner triplets braid Connection Cryostat

Y lines

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

Powering Tests

Powering Tests Powering

Tests Powering Tests

Powering Tests

Powering Tests

Powering Tests Powering

Tests

Cool-down

Cool-down Cool-down

Cool-down

Cool-down

Cool-down

Cool-down Cool-down

Page 17: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

20

13

2

01

4

EN Maintenance

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 17

PT PT PT PT

PT PT PT PT

Splices Splices

Splices Splices

Splices Splices

Splices Splices

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

Cryogenics : 18 weeks per cryoplant + Maintenance of all the equipment: CV, EL, RF…, mainly in service areas

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

Powering Tests

Powering Tests Powering

Tests Powering Tests

Powering Tests

Powering Tests

Powering Tests Powering

Tests

Cool-down

Cool-down Cool-down

Cool-down

Cool-down

Cool-down

Cool-down Cool-down

Page 18: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN R2E mitigation measures

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 18

• Detailed & graphical schedules ready, except P7 in progress

Courtesy M. Barberan

Anne-Laure : “R2E strategy and activities during LS1 ”

Page 19: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

20

13

2

01

4

EN

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

R2E mitigation measures

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 19

PT PT PT PT

PT PT PT PT

Splices Splices

Splices Splices

Splices Splices

Splices Splices

Powering Tests Splices

Warm-up Preparation for cool-down

Cool-down

R2E

R2

E

R2

E

Just in time for CD of s.12 Delay by 2 wks CD of S.81

R2

E

Delay Cool-down of 56 (1st sector) Delay Powering tests of 56 But 1 month marginw.r.t s45

Powering Tests

Powering Tests Powering

Tests Powering Tests

Powering Tests

Powering Tests

Powering Tests Powering

Tests

Cool-down

Cool-down Cool-down

Cool-down

Cool-down

Cool-down

Cool-down Cool-down

P7

to

be

fin

aliz

ed

Page 20: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

20

13

2

01

4

Jan.

EN Skeleton schedule – Physics to physics

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 20

PT PT PT PT

PT PT PT PT

Splices Splices

Splices Splices

Splices Splices

Splices Splices

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

Cold check-out & Beam Commissioning

Physics 1 week stand-by 2014-2015

Ezio : What is the maximum reasonable energy

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

Powering Tests

Powering Tests Powering

Tests Powering Tests

Powering Tests

Powering Tests

Powering Tests Powering

Tests

Cool-down

Cool-down Cool-down

Cool-down

Cool-down

Cool-down

Cool-down Cool-down

Page 21: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

20

13

2

01

4

EN Risks (possible changes in schedule): IC trains

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 21

Powering Tests Splices

Warm-up Preparation for cool-down

Cool-down

From installation experience, first 2 sectors took ~ 20% longer

PT PT PT PT

PT PT PT PT

Powering Tests

Powering Tests Powering

Tests Powering Tests

Powering Tests

Powering Tests

Powering Tests Powering

Tests

Splices Splices

Splices Splices

Splices Splices

Splices Splices

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

Cool-down

Cool-down Cool-down

Cool-down

Cool-down

Cool-down

Cool-down Cool-down

+ 20% +

20%

But leak detection and electrical tests at the end can reserve bad surprises in the last sectors…

Page 22: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

20

13

2

01

4

EN Risks (possible changes in schedule): R2E mitigation measures

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 22

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

PT PT PT PT

PT PT PT PT

Splices Splices

Splices Splices

Splices Splices

Splices Splices

Powering Tests Splices

Warm-up Preparation for cool-down

Cool-down

R2E

R2

E

R2

E

R2

E Powering

Tests Powering Tests Powering

Tests

Powering Tests

Powering Tests Powering

Tests

Cool-down

Cool-down Cool-down

Cool-down

Powering Tests

Cool-down

Cool-down

Cool-down

Powering Tests

Cool-down

P7

to

be

fin

aliz

ed

P1 & P5 are tight in schedule : Effect of 6 weeks delay

No direct impact on end dates but will delay the powering tests of 3rd and following sectors.

0

1

2

3

4

5

6

7

Nov Dec Jan Feb Mar Apr May Jun

Nb

of

sect

ors

Harwdware commissioning workload

6 weeks delay no delay

Page 23: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

S12 P1 S23 P2 S34 P3 S45 P4 S56 P5 S67 P6 S78 P7 S81 P8

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

Jan.

Feb.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Sep.

Oct.

Nov.

Dec.

20

13

2

01

4

Jan.

EN Risk (possible changes in schedule): additional activities

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 23

PT PT PT PT

PT PT PT PT

Splices Splices

Splices Splices

Splices Splices

Splices Splices

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

Cry

o M

ain

t.

Cold check-out & Beam Commissioning

Physics

-> 10K

CSCM CSCM preparation

Warm-up Warm-up Warm-up Warm-up

Warm-up Warm-up Warm-up

Warm-up

Powering Tests

Powering Tests Powering

Tests

Powering Tests

Powering Tests

Powering Tests

Powering Tests

Cool-down

Cool-down

Cool-down

Cool-down Cool-down

CSCM

Cool-down CSCM

Cool-down CSCM

Powering Tests

Cool-down CSCM

CSCM

CSCM CSCM CSCM

Additional activities, especially those requiring supports from other groups can disorganize the global schedule, and induce delays. CSCM tests in all sectors will cost around 4 weeks

Page 24: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Outline

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 24

• General frame

• Injectors

• LHC machine : Main activities and risks

• Organization

• Conclusion

Page 25: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Organization

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 25

• Schedule & logistics – Lots’of work still to be done in matter of schedule &

logistics for all the other activities w.r.t. skeleton schedule

• Preparation – ECR have to be written prior to works

– Modification of the envelope of your equipment ICL

– DIMR

– Materials have to be ready in due time…..This has often induced delays !!!

• Follow-up – Weekly coordination and scheduling meeting

Reiner : “QPS upgrade and machine protection during LS1 ” Miguel : “Vacuum upgrade” Laurent: “Cryogenics system: strategy to achieve nominal performance and reliable operation “

Page 26: LS1 general planning and strategy for LHC, LHC injectorscds.cern.ch/record/1492974/files/KF_5_01_talk.pdf · EN Draft 10 years plan (27/10/11) Feb. 8th 2012 K. Foraz - LHC Performance

EN Conclusions

Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 26

• Analysis of requests well advanced (LHC & experiments, injectors)

– w.r.t. priorities & resources & time & interaction between groups

– New requests will be scrutinized, especially the support form overloaded groups (VSC, EL, CV)

• “Skeleton” schedules for LHC machine & injectors ready

• Workload is huge and the schedule is tight

• Worksites have to be well prepared. Please do not forget layout, integration & safety