Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup,...

21
Lower Baker Unit 4 Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New Hydro Installation Shane Richards, PE Mechanical Engineer/Project Manager Hydro Group 2015 NWHA Tech Seminar Hood River, OR May 7th, 1 pm

Transcript of Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup,...

Page 1: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Lower Baker Unit 4 –

Startup, Commissioning,

and the Efforts to Resolve

Vibration & Performance

Issues on a New Hydro

Installation

Shane Richards, PE

Mechanical Engineer/Project Manager

Hydro Group

2015 NWHA Tech Seminar

Hood River, OR

May 7th, 1 pm

Page 2: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

2

What will you learn?

Background on LBU4

Timeline of Issues (2013 Startup & Commissioning)

What is Going On?

Steps Towards Resolution

Ultimate Conclusions

Questions

Page 3: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

3

Where is LBU4?

South of Mt. Baker on WA

State Hwy-20 just outside

Concrete, WA – Approx. 2

hours north and east of

Seattle, WA

Page 4: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

4

Baker River Hydroelectric Project

Page 5: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

5

FERC License Required Improvements

2x Floating Surface Collectors (FSCs)

Adult Fish Trap (AFT)

Fish Hatchery Upgrades

Various Auxiliary Investments

New Powerhouse – LBU4 ***

Page 6: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

6

Lower Baker Unit 4

~$50 MM Design-Build Contract for design & construction (PCL Construction, Black & Veatch Engineering)

~$11 MM Turbine Supply Package (Litostroj-Koncar – Slovenia/Croatia)

30 MW or 1500 cfs Minimum Instream Flow Turbine

SBV included – For ensuring flow continuation

~$20 MM ARRA Funded Tax Grant

My Role – Project Mechanical Engineer

Page 7: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

7

Lower Baker – Before & After

Page 8: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

8

~$90MM Later

Page 9: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Early Commissioning Timeline - 2013

May 21 – Bearing Heat Runs

May 28 – Balancing Adjustments Made

June 2 – First Sync to the Grid

June 3 – Load Rejections, High Vibrations @ 85%

June 4 – Lower Generator Guide Bearing Adjustment Work

June 12 – High Vibrations at LGB Persist

June 14 – Dewatered and Discovered Missing Seals

June 20 – Air Vent Making Loud Noises

June 26 – Index Test Prelim results not favorable, vibrations

analysis ongoing, vibrations persistent 9

Page 10: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

What is going on?

Bearing Vibrations?

Unbalanced Unit?

Seals Issue?

Air Vent Problems?

Efficiency Issues?

Other Problems? Von Karman Vortices?

10

Page 11: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Unit Disassembly – August/September ‘13

August 12 – Start Reshaping Guide Vanes

August 24 – Reshaping Completed, Different Hz Vibration

August 30 – Re-run Unit, No Vibrations to 100%

September 9 – Drop Bottom Ring, Machine it, Replace Seals,

Recoat Spiral Case

October 10 – Re-run Unit, Vibrations Return @ 85%

11

Page 12: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Vibration Timeline (June – October 2013)

12

Page 13: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Before & After Reshaping (CFD Modeling)

13

Page 14: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Axial WG Vibration Measurements

14

Guide Vane AXIAL vibration

0

2

4

6

8

10

12

14

16

18

20

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Gui de Vane Nr . [- ]

A [

mm

/s

]

2013.06.04 - BEFORE Stay Vane trailing edge modification

2013.08.24 - AFTER Stay Vane trailing edge modification

2013.10.07 - AFTER bottom ring machining

Page 15: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Unit Underperformance (Shifted Curve)

15

Page 16: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Review Design & On Site Testing - 2014

Planned Model Test Design & Prep – 1st half of 2014

June 2014 – Model Testing in Blansko, Czech Rep.

Final proposed solution – New Runner Only

August 2014 – Resumed site testing, removed paint

16

Page 17: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Stay Vane Strain Gages & Testing (Aug ’14)

17

Page 18: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Effect of Improper Coating

18

Page 19: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Ongoing Testing & New Runner

19

Page 20: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

Conclusions & Lessons Learned

Coating Actually Matters

CFD versus Real Life makes a difference

Avoid changing too many variables at one time

There’s varying levels of commissioning (contractor,

equipment provider, owner)

Patience pays off (hopefully)

Thanks for the support

20

Page 21: Lower Baker Unit 4 Startup, Commissioning, and the Efforts ... · Lower Baker Unit 4 – Startup, Commissioning, and the Efforts to Resolve Vibration & Performance Issues on a New

21

Questions [email protected]