9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS...

15
9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning LCLS Commissioning Schedule and Startup Schedule and Startup Plan Plan
  • date post

    22-Dec-2015
  • Category

    Documents

  • view

    233
  • download

    6

Transcript of 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS...

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

LCLS Commissioning LCLS Commissioning Schedule and Startup PlanSchedule and Startup Plan

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Schedule OverviewSchedule Overview

2002 2003 2004 2005 2006 FY2008 FY2009

Construction Operation

FY2003 FY2004 FY2005 FY2006 FY2007

CD-2a CD-2b

CD-3a CD-3b

Start of Operations(X-Rays to Far Hall)

CD-4

Project Engineering Design Long-LeadProcurement

FY2010

TimeNow

UV BeamTo cathode

1st beam onLinac axis

Start LTU commissioning

Start Undulatorcommissioning

Start XTODcommissioning

BTH, FHUHDUMP

Beneficial Occupancies

NH{

CLOC

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

SLAC linac tunnelSLAC linac tunnel LTULTU

Linac-0Linac-0

Linac-1Linac-1 Linac-2Linac-2 Linac-3Linac-3

BC-1BC-1 BC-2BC-2DL-2DL-2

DL-1DL-1

UndulatorUndulator

6 MeV6 MeV 150 MeV150 MeV 250 MeV250 MeV 4.54 GeV4.54 GeV 14.35 GeV14.35 GeV

Linac-Linac-XX

X Ray X Ray Diag.Diag.

Far HallFar Hall

DumpDumpTune upTune upDumpDump

BSYBSY

Single beamSingle beamDumperDumper

12/06

newnew

rfrfgungun

7/07

25-1a25-1a30-8c30-8c

21-1b21-1b21-1d21-1d

21-3b21-3b24-6d24-6d

4/08

7/08

12/06 UV Beam to Cathode

7/07 First Beam on Linac Axis

4/08 Start LTU Commissioning

7/08 Start Undulator Commissioning

Start XTOD Commissioning

XX

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Startup Test PlanStartup Test PlanPRD 1.1-002PRD 1.1-002

• Spells out our plan for turning on the LCLS systems. Currently working on rev-1.

• Evolved from "Commissioning Document" discussed at previous workshop.

• The editors continue to welcome your contributions!

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Startup PhasesStartup Phases

• Phase I - low beam quality– BBA, radiation reduction, x-ray diagnostics, SR

measurements

• Phase II - high beam quality– low emittance tuning, gain curve measurement,

precision x-ray measurements

• Phase III - transition to operation– Full rep rate, stable operating conditions, full energy

range, finalize operational procedures

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

End of StartupEnd of Startup

• Startup Plan goes well beyond "Start of Operations" which is met when X Rays are detected at the Far Hall

• At the end of Phase III we leave the machine with operators who are then able to provide users with required beams on a daily basis.

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Phase I Performance GoalsPhase I Performance Goals

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Phase I DemonstratesPhase I Demonstrates

• Bunch compression and bunch length control• Orbit control and stability• Xray diagnostics functionality• SR measurement capability• Beam collimation and radiation protection

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Phase II Performance Phase II Performance GoalsGoals

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Phase II DemonstratesPhase II Demonstrates

• SASE FEL process is working • Requires

– FEL quality orbit straightness and stability

– Good linewidth

– Good emittance

– High bunch current

– Gain length measurements

• Areas of physics concern: CSR, instabilities, wakefield effects, new physics effects,…

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Phase III Performance Phase III Performance GoalsGoals

9/22/04 J. Welch, LCLS Commissioning Worskhop, SLAC

Completion of Phase III Completion of Phase III DemonstratesDemonstrates

• We are ready to turn the machine over to the operators and the users

• We need another project!