    LOWER BAKER

    UNIT 4

    POWERHOUSE

  • 7/21/2019 Lower Baker Presentation (1)

    2/43

    INTRODUCTIONS

    DANNY ROBERTSFIELD ENGINEER

    JASON MCLAUCHLINPROJECT ENGINEER

  • 7/21/2019 Lower Baker Presentation (1)

    3/43

    PROJECT TEAM

  • 7/21/2019 Lower Baker Presentation (1)

    4/43

    32 MW Francis Turbine/Gen

    1000 Steel Lined Power Tunnel

    Subterranean Concrete Structure

    and Tailrace: 7,949CY placed Mechanical and Electrical Building

    Systems

    Integrated Facility Controls of

    Units 3 and 4 Upgraded Unit 3 controls and

    Governor

    Synchronous Bypass

    THE PROJECT

  • 7/21/2019 Lower Baker Presentation (1)

    5/43

    Manage In-streamFlows of the Baker andSkagit Rivers

    Restore FacilityGenerating CapacityLost in 1960s landslide

    Maintain Water Supplyto Lower Baker AdultFish Trap

    PROJECT GOALS

  • 7/21/2019 Lower Baker Presentation (1)

    6/43

    Design-Build Delivery

    Collaborative Team Approach

    Focus on achieving PSEsperformance requirements

    Phased Design and

    Construction

    PROJECT STRATEGY

  • 7/21/2019 Lower Baker Presentation (1)

    7/43

    CONSTRUCTION

  • 7/21/2019 Lower Baker Presentation (1)

    8/43

    PHASE I - EXCAVATION

  • 7/21/2019 Lower Baker Presentation (1)

    9/43

    PHASE 1 EXCAVATION

  • 7/21/2019 Lower Baker Presentation (1)

    10/43

    PHASE 1 EXCAVATION

  • 7/21/2019 Lower Baker Presentation (1)

    11/43

    PHASE 1 EXCAVATION

  • 7/21/2019 Lower Baker Presentation (1)

    12/43

    PHASE 1 EXCAVATION

  • 7/21/2019 Lower Baker Presentation (1)

    13/43

    PHASE IITUNNELING

  • 7/21/2019 Lower Baker Presentation (1)

    14/43

    PHASE II - TUNNELING

    Surge Shaft Tie In

    1000LF

    Drill and shoot 12 dia steel lining

    Full Penetration Welding

    Carboline Coating

  • 7/21/2019 Lower Baker Presentation (1)

    15/43

    PHASE II - TUNNELING

    Unit 4 Tie-In

    Bottom of 270

    Surge Shaft

    50LF in 22day

    shutdown

    Laser Scanned

  • 7/21/2019 Lower Baker Presentation (1)

    16/43

    PHASE II - TUNNELING

  • 7/21/2019 Lower Baker Presentation (1)

    17/43

    PHASE II - TUNNELING

  • 7/21/2019 Lower Baker Presentation (1)

    18/43

    PHASE II - TUNNELING

  • 7/21/2019 Lower Baker Presentation (1)

    19/43

    PHASE IIIPOWERHOUSE

  • 7/21/2019 Lower Baker Presentation (1)

    20/43

    PHASE III - POWERHOUSE

    Draft TubeElbow

    Liner

  • 7/21/2019 Lower Baker Presentation (1)

    21/43

    PHASE III - POWERHOUSE

    Scrollcase andStay Vanes

  • 7/21/2019 Lower Baker Presentation (1)

    22/43

    PHASE III - POWERHOUSE

    Inlet Pipelowering

    into

    position forfit up to

    Scroll Case

  • 7/21/2019 Lower Baker Presentation (1)

    23/43

    PHASE III - POWERHOUSE

    Fitting PitLiner onto

    Scroll Case

  • 7/21/2019 Lower Baker Presentation (1)

    24/43

    PHASE III - POWERHOUSE

    Structural work builtconcurrently with

    embedment of

    turbine components

  • 7/21/2019 Lower Baker Presentation (1)

    25/43

    PHASE III - POWERHOUSE

    GeneratorFoundation Core

  • 7/21/2019 Lower Baker Presentation (1)

    26/43

    PHASE III - POWERHOUSE

    Removable Draft Tube Cone Tripping Runner/Turbine Shaft

  • 7/21/2019 Lower Baker Presentation (1)

    27/43

    PHASE III - POWERHOUSE

    Installing Wicket Gates Runner and Turbine Shaftlowered onto Bottom Ring

  • 7/21/2019 Lower Baker Presentation (1)

    28/43

    PHASE III - POWERHOUSE

    LoweringHead Cover

    over the

    TurbineShaft

  • 7/21/2019 Lower Baker Presentation (1)

    29/43

    PHASE III - POWERHOUSE

    LoweringBottom Ring

    into

    Powerhouse

  • 7/21/2019 Lower Baker Presentation (1)

    30/43

    PHASE III - POWERHOUSE

    LowerBearing

    Bracket

    and Statorprepped

    for Rotor

    install

  • 7/21/2019 Lower Baker Presentation (1)

    31/43

    PHASE III - POWERHOUSE

    Tipping the Rotor 90tons

  • 7/21/2019 Lower Baker Presentation (1)

    32/43

    PHASE III - POWERHOUSE Shaft Coupling

    Lower Bearing Assembly

  • 7/21/2019 Lower Baker Presentation (1)

    33/43

    PHASE III - POWERHOUSE

    Installingthe Slip Ring

    Housing

  • 7/21/2019 Lower Baker Presentation (1)

    34/43

    PHASE III - POWERHOUSE

    Turbine Pit and Coolingwater piping systemsnearing completion

  • 7/21/2019 Lower Baker Presentation (1)

    35/43

    PHASE III - POWERHOUSE

    Gate Guides for theDraft Tube Gate

  • 7/21/2019 Lower Baker Presentation (1)

    36/43

    PHASE III - POWERHOUSE

    GSU andTransmission

    Structures

  • 7/21/2019 Lower Baker Presentation (1)

    37/43

    PHASE IVTAILRACE

  • 7/21/2019 Lower Baker Presentation (1)

    38/43

    PHASE IV - TAILRACE

  • 7/21/2019 Lower Baker Presentation (1)

    39/43

    PHASE IV - TAILRACE

  • 7/21/2019 Lower Baker Presentation (1)

    40/43

    PHASE IV - TAILRACE

  • 7/21/2019 Lower Baker Presentation (1)

    41/43

    FINISHED PRODUCT

  • 7/21/2019 Lower Baker Presentation (1)

    42/43

    Tunneling Operation Extremely Accurate

    Achieved all Tolerances in Stacking Unit

    Digital Upgrade of Unit 3 Control Room and

    hydraulic system Commercially Operational 100 days ahead of

    schedule

    Successful Overall Design Coordination withOwner provided Unit

    No interruptions to ongoing Unit 3 generation

    SUCCESSFUL PROJECT

  • 7/21/2019 Lower Baker Presentation (1)

    43/43

    LOWER BAKER

    UNIT 4

    POWERHOUSE

    QUESTIONS?