LOS ALAMOS COUNTYJUDICIAL / POLICE – JAIL
COMPLEX60% SUBMITTALAugust 8, 2008
SITE PLAN
Judicial Parking
Public & Staff parking
`
ENTRANCE POINTS TO SITE
Police Parking
Public & Staff parking
SITE PLAN
C-JUDICIAL
B-POLICE-EXISTING
A-JAIL/POLICE
Overall Plan – 1st FloorA-JAIL/POLICE B-POLICE-EXISTING
C-JUDICIAL
Overall Plan – 2nd Floor
C-JUDICIAL
A-JAIL/POLICE
Mechanical / Support
B-POLICE-EXISTING
Mechanical / Support
Bu
ildin
g A
-
Jail
Firs
t floor
JAIL
POLICE
MAIN ENTRANCE
SECURE ENTRANCE
Bu
ildin
g B
-
Polic
eFi
rst
Floor
ACCESS TO COURTS
UNASSIGNED SPACE
POLICE
POLICE
JAIL
Bu
ildin
g C
-
Jud
icia
lFi
rst
Floor
MAIN LOBBY
HEARING ROOM
COURT NON-JURY
SECURE ENTRANCE
EXIT
Bu
ildin
g c
-
Jud
icia
lS
eco
nd
floor
UPPER LOBBYCOURT - JURY
Bu
ildin
g A
-
Jail
Futu
re S
eco
nd
floor
A-JAIL
VERTICAL CIRCULATION
SOUTH ELEVATION (TRINITY DRIVE)
NORTH ELEVATION (MAIN PARKING LOT)
WEST ELEVATION
EAST ELEVATION
WEST ELEVATION FROM STREET
SOUTH ELEVATION @ SW CORNER
NORTH ELEVATION @ NW CORNER
FROM NORTHEAST
FROM SOUTHEAST
FROM SOUTHWEST
• Bullets here– Bullets here
• Bullets here
FROM NORTHWEST
STREET LEVEL AT SCREEN WALL
MATERIALS
MATERIALS
MATERIALS
MATERIALS
CHANGES SINCE 2007
• EXISTING GENERATOR RELOCATED• PUMPS FOR DOMESTIC WATER ADDED• PUMPS FOR FIRE PROTECTION ADDED• MECHANICAL ROOM ADDED FOR PUMP• 4” GAS SERVICE LINE RELOCATED• TRINITY SIDE SITE IMPROVEMENTS
CHANGED TO MEET NEW DOWNTOWN REQUIREMENTS
CHANGES SINCE 2007
• FOUNDATIONS CHANGE TO DRILLED PIER AFTER ADDITIONAL SOIL INVESTIGATION
• ASBESTOS CONTAINING MATERIALS (LAC)
• ADD RECYCLE DUMPSTER – SCREENED• ADD SCREEN WALL AT WEST PARKING
CHANGES SINCE 2007
Rem
ove
Sew
er
Remove SewerN
ew S
ewer
New Sewer
Rem
ove
Gas
line
Remove Gas line
New Gas lineNew Gas line
ACM’s Removal
ACM’s Removal
Pump bldg
Pump bldg
Gen bldg
Generator bldg
Drilled Pier foundation system
BUILDING AREASCHEMATIC DESIGN ‘07
• Existing Police/Jail– 1st Floor 11,586 gsf– 2nd Floor 1,361 gsf
• 12,947 total gsf
DESIGN DEVELOPMENT ‘08
• Existing Police/Jail– 1st Floor 11,075 gsf– 2nd Floor 1,361 gsf
• 12,436 total gsf
BUILDING AREASCHEMATIC DESIGN ‘07
• New Jail– 1st Floor
• 12,529 gsf
– 2nd Floor• none
– Total = 12,529 gsf
DESIGN DEVELOPMENT ‘08
• New Jail– 1st Floor
• Added Generator 469 nsf• Added Stair 173 nsf• Added Elevator 69 nsf• Added Elev eq. elec 151 nsf• Added Pump room 220 nsf
– 2nd Floor (req’d for expansion)• Added 2nd Floor mech, plumb,
stair, elec, elevator space, equipment room 1,436 nsf
– Total = 15,905 gsf
BUILDING AREASCHEMATIC DESIGN ‘07
• Judicial– 1st Floor 8,289 gsf– 2nd Floor 7,514 gsf
• 15,803 total gsf
• Total Building New & Old– 41,279 gsf
DESIGN DEVELOPMENT ‘08
• Judicial– 1st Floor 8,315 gsf– 2nd Floor 7,282 gsf
• 15,497 total gsf
• Total Building New & Old– 43,938 gsf
SCHEDULEIMPORTANT DATES
• Los Alamos County Council approval of 60% - 8/21/08• WHPacific continue to 90% Construction Docs – 8/22/08• Submit JPJ for Foundation Only Permit – 8/25/08• CMAR Approved by Los Alamos County Council – 9/9/08• CMAR/WHPacific/Los Alamos Staff project refinement
and cost savings measures (September & October)• Begin Construction – September 08• Submit Final Construction Documents – 11/26/08• Los Alamos County Council approval of FINAL- 12/16/08• Submit for Building Permit – 12/17/08• Complete Construction – 5/15/10 or sooner