1
LOMAS MSW TREATMENT PLANT Client Madrid City Government Residents served 1,100,000 residents Processes • Treated waste (total): 477,093 t • Pre-treatment: 19,668 t of recovered materials • Energy generation from the energy valuation of waste: 189,727 MWh e (50% renewable) 2016 data Treatment capacity • 532,000 t/year of MSW 140.1 kt CO 2 prevented Installed power • 29 MW Energy Valuation
Transcript of LOMAS MSW TREATMENT PLANT - Urbaser · LOMAS MSW TREATMENT PLANT Client Madrid City Government...
LOMAS MSW TREATMENT PLANT
ClientMadrid City Government
Residents served1,100,000 residents
Processes• Treated waste (total): 477,093 t• Pre-treatment: 19,668 t of recovered
materials• Energy generation from the energy
valuation of waste: 189,727 MWhe (50% renewable)
2016 data
Treatment capacity• 532,000 t/year of MSW
140.1 kt CO2 prevented
Installed power• 29 MW Energy Valuation