Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic...

83
Level 1 - Implementation Overview Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC EUROCONTROL

Transcript of Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic...

Page 1: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

Level 1 - Implementation Overview

Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC

EUROCONTROL

Page 2: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

 

 

 

 

Page 3: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 4: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 5: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic Released Issue

 

 

 

Document Title  LSSIP Year 2017 for Czech Republic 

Infocentre Reference  18/02/26/13 

Date of Edition  22/05/2018 

LSSIP Focal Point   T. TRŽICKÝ ‐ [email protected]  

LSSIP Contact Person  A. DYBOWSKA ‐ [email protected]  

Status  Released 

Intended for  Agency Stakeholders 

Available in  http://www.eurocontrol.int/articles/lssip  

 

 

 

Reference Documents   

LSSIP Documents  http://www.eurocontrol.int/articles/lssip 

LSSIP Guidance Material  http://www.eurocontrol.int/articles/lssip 

Master Plan Level 3 – Plan Edition 2017 

http://www.eurocontrol.int/articles/european‐atm‐master‐plan‐level‐3‐implementation‐plan  

Master Plan Level 3 – Report Year 2016 

http://www.eurocontrol.int/articles/european‐atm‐master‐plan‐level‐3‐implementation‐report  

European ATM Portal  https://www.eatmportal.eu and http://www.atmmasterplan.eu/  

STATFOR Forecasts  http://www.eurocontrol.int/statfor 

Acronyms and abbreviations  http://www.eurocontrol.int/articles/glossaries 

National AIP  http://lis.rlp.cz/ais_data/www_main_control/frm_en_aip.htm  

FAB Performance Plan  Latest FAB CE Performance Plan V2.0  For details contact:   Mr Matej Eljon matej.eljon@fab‐ce.eu 

 

 

 

 

   

Page 6: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 7: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 8: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 9: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic Released Issue

CONTENTS  

 

 

 

1.  National ATM Environment ............................................................. 5   Geographical Scope .............................................................................................5 1.1.  National Stakeholders .........................................................................................7 1.2.

2.  Traffic and Capacity ....................................................................... 16   Evolution of traffic in Czech Republic .............................................................. 16 2.1.  ACC Prague ....................................................................................................... 17 2.2.

3.  Master Plan Level 3 Implementation Report conclusions ............. 21 

4.  Implementation Projects ............................................................... 22   National projects .............................................................................................. 22 4.1.  FAB projects ..................................................................................................... 23 4.2.  Regional projects .............................................................................................. 25 4.3.

5.  Cooperation activities .................................................................... 26   FAB Co‐ordination ............................................................................................ 26 5.1.  Regional cooperation ....................................................................................... 27 5.2.

6.  Implementation Objectives Progress ............................................. 30   State View......................................................................................................... 30 6.1.  Detailed Objectives Implementation progress ................................................ 36 6.2.

 

Annexes 

 

Page 10: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 11: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 1 Released Issue

Executive Summary  

 

 

 

 

National ATM Context   

Civil Aviation in the Czech Republic is the responsibility of the Ministry of Transport (MoT).  

The  National  Supervisory  Authority  (hereinafter  referred  to  as  the  NSA),  is,  as  per  SES  Service  Provision Regulation, the Civil Aviation Authority (CAA). The CAA is institutionally separated from the ANSP. 

The Military Authorities in the Czech Republic are the Military Aviation Authority of MoD (MAA), the Air Force Development Department of the Capability Development and Planning Division (CDPD) and the Czech Air Force Headquarters. The Military Aviation Authority, Supervision and Inspection Division (MAA) is the main regulator for military aviation.  

Technical  investigations following accidents or serious  incidents are carried out by Air Accident  Investigation Institute  (AAII)  which  performs  its  functions  independently  in  compliance  with  European  legislation  and reports only to the Government of the Czech Republic. In case of civil‐military accidents / incidents both, civil and military accident / incident investigation authorities have to cooperate. The MoD has its own occurrence reporting and data sharing system. 

 

Traffic and Capacity  

Traffic in the FIR Praha increased by 1.8 % during summer 2016 (May to October inclusive) when compared to the same period during 2016. The EUROCONTROL Seven‐Year Forecast predicts (for 2017 – 2021) an average annual growth between 0.8% and 4.8%, with a baseline growth of 2.7%.  

The average en‐route delay per flight increased from 0.01 minutes per flight in Summer 2016 to 0.07 minutes per flight in the Summer 2017.  

The  capacity  gap may  be  expected  in  Prague ACC  if  traffic  continues  to  fly  on  currents  routes  during  the planning  period.  In  2019  the  preparation  for  airspace  reorganisation  (expected  in  2019/20)  and  the  new system (expected in 2020/21) will start, and the capacity gap may occur in 2019.   

The major  international  airport of  the Czech Republic  is Praha/Ruzyně Airport operated by Prague Airport, (Letiště Praha, a. s.)  a joint stock company.  

 

Progress per SESAR Phase  

The figure below shows the progress made so far in the implementation of the pre‐SESAR and PCP elements. The  percentage  is  calculated  as  an  average  of  the  relevant  objectives  as  shown  in  Chapter  6.1.2  ‐  PCP objectives are marked as such, the rest except AOP14, ATC02.9, ATC18 and NAV12 are considered pre‐SESAR. The  four  aforementioned  objectives  are  neither  pre‐SESAR  nor  PCP  and will  be  part  of  an  overall  future indicator covering the SESAR 1 phase. 

Note that two objectives – AOM19.1 and FCM05 – are considered as both part of the pre‐SESAR and PCP so their progress contributes to the percentage of both phases.  

Page 12: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 2 Released Issue

The objectives declared ‘Achieved’ in previous editions (up to, and including, ESSIP Edition 2011‐2015) are also taken into account for as long as they were linked to the Level 2 of the ATM Master Plan and implemented by the State. 

 

Pre‐SESAR Implementation 

2010  2019

73%    

PCP Implementation 

2015  2023 

18%    

  

Progress per SESAR Key Feature and Phase  

The figure below shows the progress made so far, per SESAR Key Feature, in the implementation of the SESAR baseline and the PCP elements. The percentages are calculated as an average, per Key Feature, of the same objectives as in the previous paragraph. 

 

ICAO ASBUs Progress Implementation  

The figure below shows the progress made so far in the implementation of the ICAO ASBUs Block 0. The overall percentage is calculated as an average of the relevant Objectives contributing to each of the relevant ASBUs; this is a summary of the table explained in Chapter 6.1.3.  

 

Block 0 2010  2018

74%    

 

   

n/a 

 66% 

7% 

Pre‐SESAR 

64% 

29% 

88% 

 

79% 

14% 

Pre‐SESAR 

Pre‐SESAR 

Pre‐SESAR

PCP 

PCP 

PCP

PCP

Optimised ATM Network Services 

Advanced Air Traffic Services  High Performing 

Airport Operations 

Enabling Aviation Infrastructure 

 

  

Page 13: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 3 Released Issue

ATM Deployment Outlook  

State objectives 

Deployed in 2016‐2017: ‐ Data Link  [ITY‐AGDL] 100% progress ‐ 8,33 kHz below FL195 [ITY‐AGVCS2] 100% progress  

 

 

‐ Enhanced STCA for TMAs [ATC02.9] 95% progress ‐ Collaborative Flight Planning [FCM03] 84% progress ‐ STCA En‐Route [ATC02.2] 68% progress ‐ eTOD [INF07] 65% progress ‐ AMAN to en‐route   [ATC15.1] 63% progress ‐ Ground‐Based Safety Nets [ATC02.8] 63% progress ‐ Traffic Complexity [FCM06] 30% progress ‐ Aeronautical Information [ITY‐ADQ] 22% progress ‐ STAM Phase 2 [FCM04.2] 5% progress  

‐ Coordination and transfer [ATC17] 48% progress ‐ AMHS [COM10] 33% progress  

‐ Surveillance Performance & Interoperability [ITY‐SPI] 71% progress ‐ Voice over IP [COM11] 68% progress ‐ Runway excursions [SAF11] 18% progress ‐ NewPENS [COM12] 0% progress  

‐ MTCD & CORA [ATC12.1] 26% progress ‐ Free Route Airspace [AOM21.2] 15% progress ‐ ASM Tools  [AOM19.1] 10% progress ‐ Interactive Rolling NOP [FCM05] 3% progress ‐ Real‐Time Airspace Data [AOM19.2] 0% progress  

 

 

Airport objectives – LKPR ‐ Praha Airport 

 

      ‐ AMAN  [ATC07.1] 0% progress  

 

 

   

By 12/2018 By 12/2019 By 12/2020 2021+

By 12/2018 By 12/2019 By 12/2020 2021+

Page 14: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 15: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 4 Released Issue

 

Introduction  

 

 

The  Local  Single  Sky  ImPlementation  (LSSIP) documents,  as  an  integral part of  the Master  Plan  (MP)  Level 3 (L3)  / LSSIP  mechanism,  constitute  a  short/medium  term  implementation  plan  containing  ECAC  States’ actions  to  achieve  the  Implementation  Objectives  as  set  out  by  the  MP  Level  3  and  to  improve  the performance of  their national ATM System.   This LSSIP document describes  the situation  in  the State at  the end of December 2017, together with plans for the next years. 

 

Chapter 1 provides an overview of the ATM  institutional arrangements within the State, the membership of the State in various international organisations, the organisational structure of the main ATM players ‐ civil and military  ‐  and  their  responsibilities  under  the  national  legislation.  In  addition,  an  overview  of  the Airspace Organisation and Classification, the ATC Units, the ATM systems operated by the main ANSP are also provided; 

Chapter 2 provides a comprehensive picture of the situation of Air Traffic, Capacity and ATFM Delay per each ACC in the State. It shows the evolution of Air Traffic and Delay in the last five years and the forecast for the next five years. It gives also the achieved performance in terms of delay during the summer season period and the planned projects assumed to offer the required capacity which will match the foreseen traffic increase and keep the delay at the agreed performance level; 

Chapter 3 provides  a  set of  conclusions extracted  from  the MP  L3  Implementation Report 2016 which  are relevant to the State/stakeholders concerned. The State reports how they have handled those conclusions and the actions taken during the year to address the concerns expressed by those conclusions; 

Chapter 4 provides  the main  Implementation Projects  (at national, FAB and regional  level) which contribute directly  to  the  implementation of  the MP Operational  Improvements  and/or  Enablers  and  Implementation Objectives. Level 1 document covers high level list of the projects showing the applicable links. All other details like  description,  timescale,  progress made  and  expected  contribution  to  the  ATM  Key  Performance  Areas provided by the State per each project are available in Level 2 document; 

Chapter 5 deals with other cooperation activities beyond Implementation Projects. It provides an overview of the FAB cooperation and also all other regional initiatives which are out of the FAB scope. The content of this chapter generally is developed and agreed in close cooperation between the States concerned; 

Chapter  6  contains  aggregated  information  at  State  level  covering  the  overall  level  of  implementation, implementation  per  SESAR  Key  Feature  and  implementation  of  ICAO  ASBUs.  In  addition  the  high‐level information on progress and plans of each  Implementation Objective  is presented. The  information for each Implementation Objective is presented in boxes giving a summary of the progress and plans of implementation for each Stakeholder. The conventions used are presented at the beginning of the section. 

Level 1 document is completed with a separate document called LSSIP Level 2. This document consists of a set of  tables  organised  in  line with  the  list  of  Implementation  Objectives.  Each  table  contains  all  the  actions planned by  the  four national  stakeholders  to achieve  their  respective Stakeholder  Lines of Action  (SLoAs) as established  in  the  European  ATM Master  Plan  L3  Implementation  Plan  Edition  2017.  In  addition  it  covers detailed description of the Implementation Projects for the State as extracted from the LSSIP Data Base.  

The  information contained  in Chapter 6  is deemed sufficient  to satisfy State  reporting  requirements  towards ICAO in relation to ASBU (Aviation System Block Upgrades) monitoring. 

   

Page 16: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference
Page 17: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 5 Released Issue

1. National ATM Environment  

 

 

Geographical Scope 1.1. 

International Membership  

Czech Republic is a Member of the following international organisations in the field of ATM: 

 

Organisation    Since 

ECAC    1993 (1991*) 

EUROCONTROL    1996 

European Union    2004 

EASA    2004 

ICAO    1993 (1944*) 

NATO    1999 

ITU    1993 (1918*) 

    * as Czechoslovakia 

 

Geographical description of the FIR(s)  

The geographical scope of this document addresses the Czech Republic FIR Praha. The Czech Republic FIR  is surrounded by  FIRs of 4  States, namely Germany UIR Rhein  and  FIR München; Poland with  FIR Warszawa, Slovak Republic with FIR Bratislava and Austria with FIR Wien (see Figure 1). 

Vertical limits of FIR Praha are ground level and FL 660. 

The Division Flight Level (DFL) separating upper from lower ATS airspace is FL 245. 

The controlled airspace of FIR Praha comprises: 

•  4 Control Areas (CTA), CTA Praha from 1000ft AGL to FL660, CTA Karlovy Vary, CTA Brno, CTA Ostrava, from 1000ft AGL to FL125, with the exception of TMA / CTR and MTMA / MCTR; 

•  TMAs / CTRs; 

•  MTMAs / MCTRs 

Page 18: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 6 Released Issue

 

Figure 1: Praha FIR and neighbouring FIR’s 

 

Airspace Classification and Organisation  

The Czech Republic is following the ICAO classification. The Figure below shows the classification of Airspace of the FIR Praha and CTA Praha. The Czech Republic has  implemented  ICAO Class C above FL095 to FL660. See Figure 2. 

 

 

Figure 2: FIR Praha airspace classification 

Page 19: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 7 Released Issue

National Stakeholders 1.2. 

The main National Stakeholders involved in ATM in Czech Republic are the following: 

 

‐  The Ministry of Transport (MoT) and the Civil Aviation Department (CAD) of the Ministry of Transport; 

‐  The Civil Aviation Authority (CAA) which acts as a National Supervisory Authority (NSA); 

‐  The Air Accidents Investigation Institute (AAII); 

‐  The  Institute  of  Aviation  Medicine,  Ústav  leteckého  zdravotnictví  (ÚLZ)  is  an  independent  State Agency; 

‐  The Ministry of Defence (MoD); 

The Military Aviation Authority, Supervision and Inspection Division (MAA); 

The Air Force Development Department of the Capability Development and Planning Division (CDPD); 

‐  The Czech Air Force; 

‐  The Air Navigation Services of the Czech Republic (ANS CR) is the main ANS provider; 

‐  The Prague Airport, Joint Stock Company is the operator of the major airport Praha‐Ruzyně. 

 

Their activities are detailed in the following subchapters and their relationships are shown in the chart below. 

 

 

Ministry of Defence 

GOVERNMENT 

Ministry of Transport (Civil Aviation Department)

Air Accidents Investigation Institute 

Civil Aviation Authority 

 

Air Navigation Services  

of the Czech Republic 

Prague Airport 

Military Aviation Authority, Supervision and Inspection 

Division of MoD 

Institute of Aviation Medicine 

 

Other Airport Operators 

Other ATC Providers 

Civil Aircraft Operators 

Czech Air Force 

Air Force Development of the Capability Development and Planning Division ‐ MoD 

Page 20: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 8 Released Issue

Civil Regulator(s) 

 

General Information  

Civil Aviation in the Czech Republic is the responsibility of the Ministry of Transport (MoT). 

An organisational chart of  the Czech Republic Aviation structure,  the CAA,  the AAII,  the ANS CR and Prague Airport is in Annex B. 

The different national entities having regulatory responsibilities in ATM are summarised in the table below. 

 

Activity in ATM:  Organisation responsible  Legal Basis 

Rule‐making  Ministry of Transport  Civil Aviation Act no. 49/1997 Coll.   

Safety Oversight  NSA (CAA)  Civil Aviation Act no. 49/1997 Coll.   

Enforcement actions in case of non‐compliance with safety regulatory requirements 

NSA (CAA)  Civil Aviation Act no. 49/1997 Coll.   

Airspace  NSA (CAA) and MoD 

(close cooperation with approval of both organisations) 

Civil Aviation Act no. 49/1997 Coll.   

Economic  Ministry of Transport (MoT) acts as an Economic Regulator in the field of unit rates. 

Civil Aviation Act no. 49/1997 Coll.   

Environment  Ministry of Health / Regional Hygienic Stations 

Ministry of Environment 

Act No. 2/1969 Coll. 

Act No. 258/ 2000 Coll. 

Act No. 173/1989 Coll. 

Security  CAA/Ministry of Transport (MoT)  

(CAA fully acts as a responsible authority according to EU Reg.  300/2008; MoT acts as a policy maker and holds chairmanships in Intragovernmental Commission for Aviation Security) 

Civil Aviation Act no. 49/1997 Coll. 

Accident investigation  Air Accidents Investigation Institute (AAII) 

Civil Aviation Act no. 49/1997 Coll. 

 

   

Page 21: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 9 Released Issue

 

CAA  

The National  Supervisory Authority  (NSA),  as  per  SES  Service  Provision  Regulation,  is  the  CAA.  The  CAA  is institutionally separated from the ANSP and has been nominated by the Czech Aviation Act No. 49/1997 Coll. as the National Supervisory Authority (NSA). 

 

Annual Report published:  Y  CAA Annual Reports (in Czech only):  

http://www.caa.cz/urad/vyrocni‐zpravy  

 

     

 

Website: www.caa.cz  

The organisational chart of the CAA is in Annex B. 

   

Page 22: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 10 Released Issue

Air Navigation Services of the Czech Republic (ANS CR) 

Services provided  

Governance:  State enterprise  Ownership:  100% Ministry of Transport 

Services provided  Y/N  Comment 

ATC en‐route  Y   

ATC approach  Y  Partly; APP Service is provided in TMA Praha, Ostrava‐Mosnov, Brno‐Turany and Karlovy Vary 

ATC Aerodrome(s)  Y  Partly; TWR service is provided at Praha‐Ruzyně, Ostrava‐Mosnov, Brno‐Turany and Karlovy Vary 

AIS  Y  Only civil side 

CNS  Y   

MET  N  MET service is provided by the Czech Hydrometeorological Institute re‐certified in 4/2017 by NSA (valid indefinitely) 

ATCO training  Y   

Others  N   

Additional information:   

Provision of services in other State(s): 

Y  ATC services are provided for small parts of Polish, German and Austrian airspace around states boundaries. See AIP CR accessible at http://lis.rlp.cz/ais_data/www_main_control/frm_en_aip.htm  

Annual Report published:  Y  http://www.rlp.cz/en/company/performance/Pages/reports.aspx  

Website: www.ans.cz  

The organisation chart  is in Annex B. 

 

ATC systems in use  

Main ANSP part of any technology alliance1  N  ‐ 

 

FDPS 

Specify the manufacturer of the ATC system currently in use:  Thales – EUROCAT 2000 system (main system on EC position) 

CS SOFT – ESUP (main FDP system) 

ICC – IDP/WALDO (main system on PC position and backup system for EC, main system for APP of regional airports) 

Upgrade2 of the ATC system is performed or planned?  Regular updates twice per year 

Replacement of the ATC system by the new one is planned?   Public tender for the new system finished in 2014. Operation of the new system planned for 2021. 

ATC Unit  ACC Praha, APP Praha,  

APP/TWR of regional airports 

                                                            1Technology alliance  is an alliance with another  service provider  for  joint procurement of  technology  from a particular supplier (e.g. COOPANS alliance) 2  Upgrade  is  defined  as  any modification  that  changes  the  operational  characteristics  of  the  system  (SES  Framework Regulation 549/2004, Article 2 (40))

Page 23: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 11 Released Issue

 

SDPS 

Specify the manufacturer of the ATC system currently in use:  EUROCONTROL  – ARTAS (main SDPS) 

Upgrade of the ATC system is performed or planned?  Finalization of hardware upgrade planned for 2018, 

Software upgrade performed regularly based on a new SW version provided by EUROCONTROL. 

Replacement of the ATC system by the new one is planned?   N/A 

ATC Unit  ACC Praha, APP Praha 

 

ATC Units  

The ATC units in the Czech Republic airspace, which are of concern to this LSSIP are the following: 

 

ATC Unit  Number of sectors  Associated FIR(s)  Remarks 

En‐route  TMA 

Praha ACC 10/12*  ‐  FIR Praha  MIL ACC terminated, provision of en‐

route services was transferred to ANS CR since May 2014 

Praha APP  ‐  4    Praha‐Ruzyně 

Brno APP  1  1    Brno‐Tuřany 

Karlovy Vary APP  1  1    Karlovy Vary 

Ostrava APP  1  1    Ostrava‐Mošnov 

MIL APP  ‐  4    Čáslav, Náměšť, Kbely, Pardubice 

* 10 sectors opened during peaks in summer 2017; 12 sectors are technically available in ACC Prague. 

 

   

Page 24: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 12 Released Issue

Airports  

General information  

The major  international  airport of  the Czech Republic  is Praha‐Ruzyně Airport operated by Prague Airport, (Letiště Praha, a. s.)  a joint stock company.  

Other  smaller  airports  such  as  Brno‐Tuřany,  Ostrava‐Mošnov  and  Karlovy  Vary  have  been  progressively transferred to respective regional governments. 

Brno‐Tuřany Airport was leased to a private operator Letiště Brno, a.s. on 1st July 2002, followed by Ostrava‐Mošnov Airport (leased to Letiště Ostrava, a.s.) and Karlovy Vary (leased to Letiště Karlovy Vary, s.r.o.) on 1st July 2004. 

There are two  industry airports, AERO‐Vodochody Plc  in Vodochody (airport Prague Vodochody) and Aircraft Industries Plc in Kunovice. 

There is one military airport with civil traffic operations in Pardubice. 

Airport(s) covered by the LSSIP  

Referring to the List of Airports in the European ATM Master Plan Level 3 Implementation Plan Edition 2017 – Annex 2, it is up to the individual State to decide which additional airports will be reported through LSSIP for those Objectives.  So the following airports are covered in this LSSIP: Praha‐Ruzyně (known as Václav Havel Airport Prague, LKPR).  The EUROCONTROL Public Airport Corner also provides information for the following airport(s):    https://ext.eurocontrol.int/airport_corner_public/LKPR  

 

Military Authorities  

The Military Authorities involved in ATM in Czech Republic are composed of: 

‐  The Military Aviation Authority, Supervision and Inspection Division of MoD (MAA); 

‐  The Air Force Development Department of  the Capability Development and Planning Division MoD (CDPD); 

‐  The Air Force Headquarters. 

 

Their regulatory, service provision and user role in ATM are detailed below. 

An organisational chart of the Czech Republic Aviation structure is in Annex B. 

   

Page 25: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 13 Released Issue

 

Regulatory role  

Regulatory framework and rule‐making 

 

Oversight  

 

   

OAT  GAT 

OAT and provision of service for OAT governed by national legal provisions? 

Y  Provision of service for GAT by the Military governed by national legal provisions? 

Level of such legal provision:  State Law  and Ministerial Decree 

Level of such legal provision:  State Law and Ministerial Decree 

Authority signing such legal provision:  the President of the CR, Prime Minister, Chairman of Parliament and Minister of Defence 

Authority signing such legal provision: the President of the CR, Prime Minister, Chairman Parliament  and Minister of Defence 

These provisions cover:  These provisions cover: 

Rules of the Air for OAT  Y     

Organisation of military ATS for OAT  Y  Organisation of military ATS for GAT  Y 

OAT/GAT Co‐ordination  Y  OAT/GAT Co‐ordination  Y 

ATCO Training  Y  ATCO Training  Y 

ATCO Licensing  Y  ATCO Licensing  Y 

ANSP Certification  Y  ANSP Certification  Y 

ANSP Supervision  Y  ANSP Supervision  Y 

Aircrew Training  Y  ESARR applicability  Y 

Aircrew Licensing  Y     

Additional Information: ‐  Additional Information: Special agreements between MoD and MoT exist that cover the responsibilities; ongoing process 

Means used to inform airspace users (other than military) about these provisions: 

Means used to inform airspace users (other than military) about these provisions: 

National AIP  Y  National AIP  Y 

National Military AIP  Y  National Military AIP  Y 

EUROCONTROL eAIP  N  EUROCONTROL eAIP  N 

Other:  CENOR FLIP (Central and Northern Region Flight Information Publication) 

Y  Other:   N 

OAT  GAT 

National oversight body for OAT:  MAA, Czech Air Force Headquarters 

NSA (as per SES Reg.  550/2004) for GAT services provided by the military: MAA 

Additional information: None  Additional information: MoD is an oversight body according to Civil aviation act. 

Page 26: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 14 Released Issue

Service Provision role  

 

Military ANSP providing GAT services SES certified? 

N  If YES, since:  ‐  Duration of the Certificate: 

‐ 

Certificate issued by:   ‐  If NO, is this fact reported to the EC in accordance with SES regulations? 

Additional Information: None 

 

User role  

 

 

 

 

OAT  GAT 

Services Provided:  Services Provided: 

En‐Route  Y  MIL (limited, GCI only)*  En‐Route  N 

Approach/TMA  Y  MIL ANSP (MAPPs)  Approach/TMA  Y 

Airfield/TWR/GND  Y  MIL ANSP (MTWR)  Airfield/TWR/GND  Y 

AIS  Y  MIL  AIS  Y 

MET  Y  MIL  MET  Y 

SAR  Y  Integrated civil military  SAR  Y 

TSA/TRA monitoring  Y    FIS  Y 

Other:   ‐  Other:   ‐ 

Additional Information: 

Tactical co‐ordination with Air Defence (AD) unit 

 

* GCI ‐ Ground Control Intercept unit 

Additional Information:  Above information are concerned of military services provided basically for State aircraft, in specific cases (joint used airports, etc.) also for civil traffic.  

FIS is provided by AD ATC unit only, no specific working position is established. 

IFR inside controlled airspace, Military aircraft can fly?  

OAT only    GAT only    Both OAT and GAT  Y 

If Military fly OAT‐IFR inside controlled airspace, specify the available options: 

Free Routing  Y  Within specific corridors only  N 

Within the regular (GAT) national route network  N  Under radar control  Y 

Within a special OAT route system  N  Under radar advisory service  N 

If Military fly GAT‐IFR inside controlled airspace, specify existing special arrangements:   

No special arrangements  N  Exemption from Route Charges  N 

Exemption from flow and capacity (ATFCM) measures  Y  Provision of ATC in UHF  Y 

CNS exemptions:  RVSM  Y  8.33  Y  Mode S  Y  ACAS  Y 

Others:  Above mentioned CNS exemptions are applied case by case to state aircraft when requested in the flight plan. 

Page 27: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 15 Released Issue

Flexible Use of Airspace (FUA)  

 

 

   

Military in CZ applies FUA requirements as specified in the Regulation No 2150/2005:     Y 

FUA Level 1 implemented: Y 

FUA Level 2 implemented: Y 

FUA Level 3 implemented: Y 

Page 28: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 16 Released Issue

2. Traffic and Capacity  

 

Evolution of traffic in Czech Republic 2.1. 

 

 

 

 

 

2017 

Traffic in the Czech Republic increased by 1.8% during Summer 2017 (May to October inclusive), when compared to the same period during 2016.    

 

2018‐2022 

The EUROCONTROL Seven‐Year Forecast predicts an average annual growth between 0.8% and 4.8%, with a baseline growth of 2.7%.   

   

0

200.000

400.000

600.000

800.000

1.000.000

1.200.000

2013 A 2014 A 2015 A 2016 A 2017 F 2018 F 2019 F 2020 F 2021 F 2022 F 2023 F

IFR

flig

hts

Czech Republic - Annual IFR Movements

IFR movements - Actuals

IFR movements - Baseline forecast

IFR movements - High forecast

IFR movements - Low forecast A = ActualF = Forecast

2014 A 2015 A 2016 A 2017 F 2018 F 2019 F 2020 F 2021 F 2022 F 2023 FH 3.8% 7.2% 4.9% 4.6% 3.8% 3.4% 2.7%B 3.1% 6.5% 6.9% 3.4% 5.0% 2.4% 2.3% 1.9% 2.1% 2.1%L 2.9% 3.0% -0.2% 0.7% 0.1% 0.3% 0.3%

ECAC B 1.7% 1.6% 2.8% 4.5% 2.8% 2.1% 1.9% 1.5% 1.7% 1.7%

EUROCONTROL Seven-Year Forecast (September 2017)IFR flights yearly growth

Czech Republic

Page 29: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 17 Released Issue

 

ACC Prague 2.2. 

Traffic and en‐route ATFM delays 2013‐2022  

 

Performance summer 2017  

Traffic Evolution  2017 Capacity Baseline En‐route Delay (min/flight) ‐ Summer  Capacity 

gap Ref value  Actual 

+1.5 %  187 (+3%)  0.16  0.07  No 

The average en‐route delay per flight increase from 0.01 minutes per flight in Summer 2016 to 0.07 minutes per flight in the Summer 2017.  

62% of the delays were due to Weather, 29% were for the reason ATC Capacity and 8% due to ATC Staffing.  

Capacity Plan: +0%  Achieved  Comments 

Additional  FRA DCTs  Yes   

Improved coordination with military  Yes   

Improved flow and capacity management techniques, including STAM 

Yes  

Improved ATS route network  Yes  Implementation in Nov. 2017 

Enhanced sectorisation according to the FABCE Airspace Plan Yes  Implementation in Nov. 2017 at the 

interface with Austria 

CPDLC  Yes   

Optimised opening schemes  Yes   

   

2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

Peak Day Traffic 2358 2416 2561 2690 2731

Summer Traffic 2063 2120 2280 2403 2440

Yearly Traffic* 1804 1849 1976 2098 2204

Summer Traffic Forecast 2516 2588 2642 2695 2755

High Traffic Forecast - Summer 2576 2699 2822 2937 3038

Low Traffic Forecast - Summer 2466 2466 2486 2496 2502

Summer enroute delay (all causes) 0.07 0.02 0.01 0.01 0.07

Yearly enroute delay (all causes) * 0.04 0.01 0.01 0.01 0.04

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

0

500

1000

1500

2000

2500

3000

3500

En

rou

te D

ela

y (m

inu

tes

pe

r fli

gh

t)

IFR

flig

hts

(Dai

ly A

vera

ge)

LKAAACC - Traffic and en-route ATFM delays

*From 01/01/2017 to 31/10/2017

Page 30: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 18 Released Issue

Datalink  Yes   

Adaptation of sector opening times depending on available staff  Yes   

Monitoring of traffic evolution and evaluation of possible scenarios  Yes   

Maximum configuration: 9/10 sectors  Yes  10 sectors were opened 

Summer 2017 performance assessment 

The ACC capacity baseline was measured with ACCESS and was assessed to be at 187. The peak 1 hour demand was 180 flights and the peak 3 hour demand was 169 flights. 

 

 

Planning Period 2018‐2022  

The planning focuses on the Summer season to reflect the most demanding period of the year from a capacity perspective. This approach ensures consistency with the previous planning cycles. 

         Capacity Profiles 

ACC 2017 

baseline  

   Profiles (hourly movements and % increase over previous year) 

   2018  2019 

LKAA  187 

H  187  0%  187  0% 

Ref.  187  0%  187  0% 

L  187  0%  187  0% 

Open  187  0%  187  0% 

C/R  193  3%  197  2% 

Summer Capacity Plan 

  2018  2019  2020  2021  2022 

Free Route Airspace         Full FRA 

Impl. in Dec 2021 

Airspace Management Advanced FUA 

 ASM tool (equiv. to LARA) 

     

Airport & TMA Network Integration 

         

Cooperative Traffic Management Improved flow and capacity management 

techniques, including STAM    

Airspace 

Improved ATS route network       

 New 

sectorisation    

Procedures           

Staffing    Additional controllers   Additional controllers 

Technical       Implementation of a new system 

 

Capacity  Adaptation of sector opening times depending on available staff 

Significant Events 

   Reconstruction of the OPS room and implementation of the new 

ATM system  

 Training for the new 

sectorisation 

Training for the new system 

Training for the FRA 

 

Page 31: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 19 Released Issue

Max sectors  10  10  13  13  15 

Planned Annual Capacity Increase 

0%  0%  2%  1%  2% 

Reference Profile Annual % Increase 

0%  0%  N/A  N/A  N/A 

Current Routes Profile % Increase 

3%  2%  N/A  N/A  N/A 

Difference Capacity Plan v. Reference Profile 

0.0%  0.0%  N/A  N/A  N/A 

Difference Capacity Plan v. Current Routes Profile 

‐3.1%  ‐5.1%  N/A  N/A  N/A 

Annual Reference Value (min)  0.10  0.10  N/A  N/A  N/A 

Summer reference value (min)  0.16  0.16  N/A  N/A  N/A 

Additional information 

The training for the new sectorisation and the implementation will be subject of the transition planning process in 2019/20. From 2020 the OPS room will be split into two parts with the maximum number of 10 sectors available for the current ATM system. However, the new sectorisation will deliver three additional sectors in 2020 in a lower airspace (3 terminal sectors up to FL 285 served from regional ATC Units). The migration to the new system is planned for winter season 2020/21. The capacity availability throughout the project lifecycle will be subject the transition planning process. 

 

The graphs above shows an outline of available sector configurations for a typical weekday and a weekend day for summer 2018. 

 

0

1

2

3

4

5

6

7

8

9

10

00:00

02:00

04:00

06:00

08:00

10:00

12:00

14:00

16:00

18:00

20:00

22:00

Sectors available ‐ Summer 2018Mon. ‐Wed.

0

1

2

3

4

5

6

7

8

9

10

00:00

02:00

04:00

06:00

08:00

10:00

12:00

14:00

16:00

18:00

20:00

22:00

Sectors available ‐ Summer 2018Thu. ‐ Fri.

Page 32: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 20 Released Issue

2018‐2022 Planning Period Outlook 

The capacity gap may be expected in Prague ACC if traffic continues to fly on currents routes during the planning period. 

In 2019 the preparation for airspace reorganisation (expected in 2019/20) and the new system (expected in 2020/21) will start, and the capacity gap may occur in 2019.  

 

   

2016 2017 2018 2019 2020 2021 2022

2018‐2019 Reference Capacity Profile 187 187

Capacity Profile ‐ Shortest Routes (Open) 187 187

Capacity Profile ‐ Current Routes 193 197

Capacity Profile ‐ High 187 187

Capacity Profile ‐ Low 187 187

Capacity Baseline 181 187

2018 ‐ 2022 Plan 187 187 191 193 197

100

120

140

160

180

200

220

Cap

acity profile (movements per hour)

LKAAACC - Reference capacity profile and alternative scenarios

Page 33: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 21 Released Issue

3. Master Plan Level 3 Implementation Report conclusions 

 

 

Conclusions  issued  from  the European ATM Master Plan  Level 3  Implementation Report 2016 applicable  to the Czech Republic for all items that require corrective actions and improvements.  

 

Conclusion  Applicable to VERY GOOD PROGRESS IN IMPLEMENTATION OF BOTH FREE ROUTE AND DIRECT 

ROUTING. 

THIS MOMENTUM SHOULD BE KEPT AND SUPPORTED BY ALL INVOLVED STAKEHOLDERS. 

(page 14 of the Report) 

All State that are 

implementing 

AOM21.1 and 

AOM21.2 State’s action planned for this conclusion: YES  

Description of the planned action: Objective AOM21.1 is completed. As for objective AOM21.2, the 

completion is planned for 2021.  

Conclusion  Applicable to ADQ IMPLEMENTATION ISSUES HAVE TO BE ADDRESSED AS SOON AS POSSIBLE AS THEY 

CAN IMPACT ON SWIM IMPLEMENTATION. (page 25 of the Report)  All States + EC 

State’s action planned for this conclusion: YES  

Description of the planned action: Further implementation of ADQ requirements depends on successful 

upgrade of AIM system, which is planned for 2018.  

 

 

Page 34: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 22 Released Issue

4. Implementation Projects  

National projects 4.1. 

The main projects currently ongoing in Czech Republic are depicted in the table below. 

 

Name of project:  Organisation(s):  Schedule:  Status:  ATM MP Links: 

AMHS  ASP ANS CR (CZ)  Start: 2011 Finish: 1/2018 

Compeleted  L3: COM10 

AOP / APOC  Prague Airport (CZ)  ‐  ‐  ‐ 

Aeronautical Information Distribution Service (2015_243_AF5) 

ASP ANS CR (CZ)  01/06/2016 ‐ 31/12/2018  ‐  DP2016: 201_243_AF5 

Airport CDM  ASP ANS CR (CZ), Prague Airport (CZ)  Start: 2008  Finish 2015 

Completed in 2015  L3: AOP05 

Conversion to the 8.33 kHz channel spacing below FL195 

ASP ANS CR (CZ), MIL ASP (CZ), Prague Airport (CZ) 

Start: 2016  Finish: 11/2017 

Completed  L3: ITY‐AGVCS2 

Flexible ASM and Free Route (2015_239_AF3) 

ASP ANS CR (CZ)  01/03/2016 ‐ 01/12/2021  ‐  DP2016: 2015_239_AF3 

Free Route implementation into ATM system of ANS CR (2015_242_AF3) 

ASP ANS CR (CZ)  01/03/2016 ‐ 04/11/2021  ‐  DP2016: 2015_242_AF3 

Meteorological Information Exchange Service (2015_241_AF5) 

ASP ANS CR (CZ)  01/03/2016 ‐ 01/12/2020  ‐  DP2016: 2015_241_AF5 

NEOPTERYX ‐ the new DPS system for ACC/APP Praha 

ASP ANS CR (CZ)  Start 2010 Finish 2021 

Ongoing  ‐ 

Page 35: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 23 Released Issue

Name of project:  Organisation(s):  Schedule:  Status:  ATM MP Links: 

RET J  Prague Airport (CZ)  Start: 2019, End: 2019  ‐  ‐ 

RET Y  Prague Airport (CZ)  ‐  ‐  ‐ 

RWY 06R/24L  Prague Airport (CZ)  Start: 2021 Finish: 2024 

Preparatory phase. The EIA process is completed. 

‐ 

Traffic Complexity Tools (2015_240_AF4) 

ASP ANS CR (CZ)  15/02/2016 ‐ 31/12/2018  ‐  DP2016: 2015_240_AF4 

VoIP  ASP ANS CR (CZ), CDPD (CZ), CZ Air Force (CZ) 

Start 2007 Finish 2020 

Ongoing  L3: COM11 

pRWY  Prague Airport (CZ)  ‐  ‐  ‐ 

 

FAB projects 4.2. 

Name of project:  Organisation(s):  Schedule:  Status:  Links: 

FAB CE Strategic Operational Planning Project (incl. FAB CE X‐Border Free Route Airspace Study) (FAB CE Project 1) 

ASP ANS CR (CZ), Austrocontrol (AT), BHANSA (BA), CCL Service Provider (HR), Hungarocontrol (HU), Letové prevádzkové služby Slovenskej republiky, štátny podnik (SK), Slovenia Control (SI) 

Project 1:  Start 3.1.2011, End: Continuous  Project 1 FAB CE FRA Study: Start: 1.9.2015, End: 21.4.2017 

FAB CE FRA Study is completed Other activities, including monitoring FRA implementation, are ongoing 

L3: AOM21.1, AOM21.2 

RP2 PP: FAB CE FRA Project (described under NSP actions 'FAB CE Airspace and route structure planning' and 'Free Route Airspace') 

DP2016: 102AF3 – Free route airspace from the Black Forest to the Black Sea 

Page 36: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 24 Released Issue

Name of project:  Organisation(s):  Schedule:  Status:  Links: 

FAB CE‐wide Study of Dynamic Airspace Management (DAM) and STAM (FAB CE DAM/STAM Study) 

ASP ANS CR (CZ), Austrocontrol (AT), BHANSA (BA), CCL Service Provider (HR), Hungarocontrol (HU), Letové prevádzkové služby Slovenskej republiky, štátny podnik (SK), Slovenia Control (SI) 

DAM/STAM Study: Start: 7.2.2017, End: 31.12.2018 

Ongoing  L3: AOM19.1, AOM19.2, AOM19.3, FCM04.1, FCM04.2, FCM05, FCM06 

RP2 PP: Advanced Airspace Management (described under NSP actions) 

DP2016: 2016_075_AF3_A 

FAB CE wide Study of DAM and STAM (PCP under CEF2016 Call) 

Surveillance Infrastructure Optimisation (FAB CE Project 18) 

ASP ANS CR (CZ), Austrocontrol (AT), BHANSA (BA), CCL Service Provider (HR), Hungarocontrol (HU), Letové prevádzkové služby Slovenskej republiky, štátny podnik (SK), Slovenia Control (SI) 

Start: 6.7.2016, End: 28.2.2018  Ongoing, in the finalization phase 

RP2 PP: Optimisation of CNS resources 

 

X‐Bone HW Procurement (FAB CE Project 17) 

ASP ANS CR (CZ), Austrocontrol (AT), CCL Service Provider (HR), Hungarocontrol (HU), Letové prevádzkové služby Slovenskej republiky, štátny podnik (SK), Slovenia Control (SI) 

Start: 19.2.2016, End: 30.4.2018  Common procurement finalized, in the implementation phase 

RP2 PP: Optimisation of CNS resources 

 

   

Page 37: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 25 Released Issue

 

Regional projects 4.3. 

Name of project:  Organisation(s):  Schedule:  Status:  ATM MP Links: 

AMAN LOWW initial (AMAN LOWW initial) 

ASP ANS CR (CZ), Austrocontrol (AT), Hungarocontrol (HU), Letové prevádzkové slu by Slovenskej republiky, štátny podnik (SK) 

Start: 2.1.2016 End: 31.12.2020 

Ongoing  L3: ATC07.1, ATC15.1 DP2016: 2015_234_AF1 AMAN LOWW initial RP2 PP: Project taken into account under 3.1.(c).(ii) ‐ Capacity KPI #2: Terminal and airport ANS ATFM arrival delay per flight 

Extended AMAN in Czech Airspace (2015_196_AF1_B) 

ASP ANS CR (CZ), Belgocontrol (BE), DSNA (FR), LVNL ‐ Luchtverkeersleiding Nederland (NL), MUAC ANSP (MAS), Skyguide (CH) 

15/02/2016 ‐ 31/12/2020  ‐  DP2016: 2015_196_AF1_B 

Gate One Free Route Airspace Operational Framework Study (GO FRA OF Study) 

ASP ANS CR (CZ), Austrocontrol (AT), BHANSA (BA), BULATSA (BG), CCL Service Provider (HR), Hungarocontrol (HU), Letové prevádzkové slu by Slovenskej republiky, štátny podnik (SK), M‐NAV (MK), ORO NAVIGACIJA (LT), PANSA (PL), ROMATSA (RO), SMATSA (BA), Slovenia Control (SI) 

Start: 1.9.2017, End: 30.11.2019  Planned CEF Application is being finalised under CEF Call 2016 

L3: AOM21.1, AOM21.2 DP2016: CEF Application will be submitted as a part of PCP under CEF2016 Call 

Page 38: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 26 Released Issue

5. Cooperation activities  

 

FAB Co‐ordination 5.1. 

Having signed and ratified the Agreement on the Establishment of Functional Airspace Block Central Europe, Austria, Bosnia and Herzegovina, Croatia, the Czech Republic, Hungary, Slovakia and Slovenia are part of FAB CE. 

The  FAB CE  States  agreed on  establishment of  the  following permanent bodies  ‐  the  FAB CE Council, NSA Coordination Committee  and  Joint Civil‐Military Airspace Coordination Committee. The  FAB CE Council  can also establish other bodies necessary for the implementation, operation and further development of the FAB CE Project. For  this  reason  the FAB CE Legal Committee and  the FAB CE Performance Body  (responsible  for preparation of FAB CE Performance Plan for RP2) have been established.   

The  air  navigation  service  providers  of  the  FAB  CE  countries  established  a  joint  company  FABCE  Aviation Services,  Ltd  already  in 2014  and  the  company  is  responsible  for  the professional management of  various regional air navigation projects. The establishment of  this  joint venture  is not only effectively aiming at  the progress of the FAB CE programme, but at the same time the Single European Sky programme of the European Union. 

In 2016,  there was a major update of  the FAB CE Strategy. The FAB CE Strategic Objectives, defined  in  this version of the Strategy, cover the period until 2020, and address also the FAB CE  long term strategic vision. This was followed by the update of the FAB CE High Level Plan which provides the link how the FAB CE intends to achieve  full compliance with  the Deployment Programme and achievement of all  strategic goals  through cooperation’s,  projects  and  tasks.  This  is  done  by  assessing  existing  gaps  between  the  present  state  of implementation activities and  the SESAR DP and by pointing  towards activities and  initiatives established  to close  those  ‘gaps’ and  reach achievement of all  the high‐level  targets. The High Level Plan  is going  through regular updates on an annual basis. 

In addition to FAB CE projects, the FAB CE ANSPs coordinate also their regional Free Route Airspace initiatives including South Eastern Europe Night Free Route Airspace  (SEEN FRA)  involving Hungary and DANUBE FAB, SEAFRA  (South‐East Axis  Free  Route Airspace)  involving  Croatia,  Bosnia  and Herzegovina, Montenegro  and Serbia and SAXFRA (Slovenian Austrian Cross Border Free Route Airspace). In 2017, the ANSPs worked hard on merging  the SEAFRA and SAXFRA  initiatives  into  the South East Common Sky  Initiative Free Route Airspace (SECSI FRA) which has been successfully implemented, with the support of the Network Manager. 

FAB CE continues to actively cooperate and share information and lessons learnt with other FABs. In 2017, FAB CE participated in a number of inter‐FAB workshops, including Inter‐FAB communications workshop in Langen, Inter‐FAB Point of Contact (PoC) workshop in Malta and Inter‐FAB operational workshop organised by FAB CE in  Ljubljana.  FAB CE  also  continues  to  coordinate  its  activities with other ANSPs of  the Gate One  initiative consisting of three FABs (Baltic FAB, DANUBE FAB and FAB CE) and two non‐EU ANSPs (MNAV and SMATSA).  

   

Page 39: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 27 Released Issue

 

Regional cooperation 5.2.

Regional cooperation initiatives  

The  Czech  Republic  is  involved  in  international  activities  in  the  field  of  ATM  like  the  EATM  and  NM 

developments. The ANS of CR actively participates in a number of working teams of international organisation 

(e.g.  EUROCONTROL,  CANSO),  Co‐operation  and  co‐ordination  exists with  bordering  ECAC  States  (Austria, 

Germany, Poland, and the Slovak Republic) especially on the field of airspace design. In order to achieve some 

of the ATM MP L3  Implementation Objectives, Praha ACC will have to co‐ordinate some of  its actions with a 

number of  foreign  adjacent ACCs/UAC. Military  regional  coordination within NATO environment  (Germany, 

Poland and Slovak Republic) is based on common NATO procedures. 

The Czech Republic has been involved in a process of establishing a more formalized framework in the field of 

cross‐border provision of air navigation services with two of its neighbouring countries: Germany and Poland. 

In each case,  the ultimate goal  is  to have a  three‐layer scheme of agreements: on  the  level of  (i) states,  (ii) 

ANSPs and (iii) NSAs. Still, the process of concluding a bilateral international treaty approved by a law‐making 

body is generally a lengthy and difficult one. Therefore, for sake of flexibility, the countries involved opted for 

a more flexible solution.  

In December 2014, relevant agreements were concluded on the  level of Czech and German NSAs as well as 

ANSPs  (ANS  CR  and  DFS)  even  before  the  state  level  treaty  would  be  finalized.  Similar  agreement  was 

subsequently concluded also between Czech and Polish NSAs in December 2015. 

The Agreement between Czech and German NSAs  (as well as  the agreement between  the Czech and Polish 

NSAs) provide for mutual cooperation of the relevant bodies concerning supervision of cross‐border provision 

of  ANS.  It  covers  in  particular  exchange  of  information,  procedures  for  joint  supervision  and  mutual 

recognition of supervisory tasks. The Agreement  is  intended to fulfill requirements of Art. 2(5) of Regulation 

(EC) 550/2004. 

The two ANSP level agreements between ANS CR and DFS represent agreements within the sense of Art. 10(2) 

and (3) of Regulation (EC) 550/2004. They are complex arrangements between the providers covering cross‐

border  provision  of  ANS,  including,  e.g.,  procedures  and  principles  for  compliance  with  applicable  rules, 

occurrence reporting, notifications, liability or insurance. 

   

B4 Consortium 

B4 Consortium was set up formally on 8 September 2014 by PANSA (Poland), ANS CR (Czech Republic), LPS SR 

(Slovak  Republic)  and  „Oro  navigacija”  (Lithuania)  representing  small  and  medium‐sized  European  Air 

Navigation Service Providers. 

The B4 Consortium is a member of A6+ on SESAR 2020 Programme content. As outcome of SJU membership 

negotiation the B4 Consortium has become a member of SJU from July 6, 2016. 

By the end of 2016 the B4 Consortium has started elaborating Industrial research projects within the SJU. The 

outcomes of the commonly financed projects are expected to pave the way towards the new generation air 

traffic management system capable of ensuring improved safety and efficiency of air transport in Europe. 

   

Page 40: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 28 Released Issue

B4 Consortium considers the vast expertise of its members in ATM operational and technical domains, Project 

and Quality management and experience in execution of several high complexity ATM projects as well as the 

expertise and experience of its Linked Third Parties ranging from scientific research, concept developments, up 

to product prototyping and manufacturing highly beneficial  for  the successful accomplishment of  the SESAR 

2020 program objectives. 

B4  Consortium  together with  its  Linked  Third  Parties  can  see  its  role  in  SESAR  2020  Projects  not  only  in 

eliminating  current  absence  of  small  and medium‐sized  ANSPs  in  the  SESAR  projects  but  also  in  bringing 

different experiences and approaches  to  the SESAR 2020 programme by providing  the SJU with  its broadly 

experienced and highly motivated staff and well‐equipped facilities.  

 

Regional projects  

Project MALORCA 

ANS CR has been  actively  involved  in  SESAR  2020  Exploratory Research project  called MALORCA  (Machine 

Learning of  Speech Recognition Models  for Controller Assistance)  since April 1, 2016. ANS CR  is one of  five 

beneficiaries involved in this projects (other member of Consortium are DLR – Germany (Coordinator), USAAR ‐ 

Germany, IDIAP ‐  Switzerland and Austrocontrol – Austria). 

In  2017,  the  ABSR  (Assistant  Based  Speech  Recognition)  prototype  created  by  DLR  and  USAAR  was 

demonstrated  at  the 1st MALORCA  Stakeholder workshop  in Prague  (2017‐04‐12) organized by ANS CR.  Its 

purpose was to get early feedback from the users, i.e. the controllers and speech recognition/machine learning 

experts, with respect to the planned proof‐of‐concept trials. The feedback was used to improve the prototype, 

and was demonstrated again  to  controllers at pre‐proof‐of‐concept  trials  in Prague  (2017‐10‐10). The main 

work of ANS CR was  focussed on Work package 5 – Proof of Concept, preparation of proof‐of‐concept trials 

planned in January 2018, where the hypothesis that unsupervised learning will improve command recognition 

rates and reduce the adaptation costs was set as the main objective.  

 

INEA CEF Call 2014 projects with ANS CR contribution 

Project ID  Project Name  Project Leader / Contributors  (if any) 

Project Duration  

 

102AF3  Free Route Airspace from the Black Forest to the Black Sea 

HCL / ANS CR + FAB CE ANSPs  1.9.2015 ‐ 21.4.2017   

 

   

Page 41: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 29 Released Issue

 

INEA CEF Call 2015 projects with ANS CR contribution 

Project ID  Project Name  Project Leader / Contributors  (if any) 

Project Duration  

 

2015_234_AF1_B  AMAN LOWW initial  ACG / ANS CR + LPS + HCL  1.3.2016 ‐ 31.12.2018   

2015_196_AF1_B*  Extended AMAN in Czech airspace 

ANS CR / DFS+others(separate proposal) 

1.2.2016 ‐ 31.12.2017   

2015_239_AF3  Flexible ASM and Free Route  ANS CR  1.3.2016 ‐ 1.12.2020   

2015_242_AF3  Free Route implementation into ATM system of ANS CR 

ANS CR  1.3.2016 ‐ 31.3.2020   

2015_240_AF4  Traffic Complexity Tools  ANS CR  15.2.2016 ‐ 31.12.2018   

2015_174_AF5_B  NewPENS Stakeholders contribution for the procurement and deployment of NewPENS 

EUROCONTROL / ANS CR + others  15.2.2016 ‐ 31.12.2020 

 

2015_243_AF5  Aeronautical Information Distribution Service 

ANS CR  1.6.2016 ‐ 31.12.2018   

2015_145_AF5_B  AIM Deployment Toolkit  EUROCONTROL / ANS CR + others  1.4.2016 ‐ 31.12.2020   

2015_241_AF5  Meteorological Information Exchange Service 

ANS CR / CHMI (Czech Hydrometeorological Institute) 

1.3.2016 ‐ 1.12.2020   

2015‐EU‐TM‐0242‐W 

Deployment of harmonised and interoperable high Performance European Surveillance System 

EUROCONTROL / ANS CR + NAV Portugal 

1.3.2016 ‐ 31.12.2020 

 

 

INEA CEF Call 2016 projects with ANS CR contribution 

Project ID  Project Name  Project Leader / Contributors  (if any) 

Project Duration  

 2016_075_AF3_B  FAB CE wide Study of DAM and 

STAM ‐ Cohesion Call FAB CE Ltd/ ANS CR + other FAB CE ANSPs 

7.2.2017 ‐ 31.12.2018   

2016_064_AF5  AIMSIL ‐ AIM Systems Integration Layer 

ANS CR  1.5.2017 ‐ 30.11.2020   

2016_065_AF5  SWIM implementation into ATS INFO/ARO system of ANS CR 

ANS CR  1.9.2017 ‐ 1.12.2020 

 

 

Page 42: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 30 Released Issue

6. Implementation Objectives Progress  

 

State View 6.1. 

Overall Objective Implementation  

Progress distribution for applicable Implementation Objectives  

 

 

A  number  of  ESSIP  objectives  have  been  already  completed:  AOM13.1  (Harmonise Operational  Air  Traffic 

(OAT) and General Air Traffic (GAT) handling), AOM21.1 (Direct Routing), AOP04.1 (Implement ASMGC Level1), 

AOP04.2  (Implement  A‐SMGCS  Level  2),  AOP05  (Implement  Airport  Collaborative Decision Making  (CDM)), 

ENV02 (Implement Collaborative Environmental Management (CEM) at Airports), FCM04.1 (Short Term ATFCM 

Measures  (STAM)  ‐  Phase  1),  ITY‐ACID  (Aircraft  identification),  ITY‐AGDL  (Initial  ATC  Air‐ground  Data  Link 

Services), ITY‐AGVCS2 (8,33 kHz Air‐Ground Voice Channel Spacing below FL195), ITY‐FMTP (Apply a common 

flight message  transfer  protocol), NAV03.1  (RNAV  1  in  TMA Operations), NAV10  (APV  procedures),  ATC16 

(Implement  ACAS  II  compliant  with  TCAS  II  change  7.1),  FCM01  (Implement  enhanced  tactical  flow 

management  services),  INF04  (Implement  integrated briefing),  ITY‐COTR  (Implementation of ground‐ground 

automated co‐ordination processes); from which FCM04.1, ITY‐AGDL and ITY AGVCS2 were completed during 

the last LSSIP cycle. 

With regard to objectives due for 2015–2017 and earlier, the Czech Republic is late in implementing objectives 

ATC02.2  (Implement  ground  based  safety  nets  ‐  Short  Term  Conflict  Alert  (STCA)  ‐  level  2  for  en‐route 

operations)  and ATC02.8  (Ground‐based  Safety Nets) which  are  both  implemented  for  the main ATC  units 

(Prague  ACC/APP),  APP Ostrava  and  APP  Karlovy  Vary,  but  implementation  at  APP  Brno  is  planned  to  be 

completed by 2018, ATC15.1 (Information Exchange with En‐route in Support of AMAN) where basic algorithm 

of  production  of  AMA message  is  implemented  in  our  en‐route  system,  but  operational  use  depends  on 

implementation  of  AMAN  system  in Munich,  Vienna  and  other  airports.  Also  FCM03  (Collaborative  Flight 

Planning)  is  late – AFP messages were technically  implemented and operational  internal tests and tests with 

NM  are  planned  for  2018.  Furthermore  ITY‐ADQ  (Ensure  Quality  of  Aeronautical  Data  and  Aeronautical 

Information) is late, but there is a plan for implementation for 2018. 

17; 37%

8; 18%

2; 4%

11; 24%

8; 17%

Completed

Ongoing

Planned

Late

No Plan

Not Applicable

Missing Data

Undefined

Page 43: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 31 Released Issue

Plans  for  completing Objectives, especially  those due  for 2018 and 2019: AOP11  (Initial Airport Operations 

Plan)  is  ongoing  with  expected  completion  in  2019,  AOP12  (Improve  Runway  and  Airfield  Safety  with 

Conflicting ATC Clearances  (CATC) Detection and Conformance Monitoring Alerts  for Controllers  (CMAC))  is 

ongoing with planned completion in 2018, ATC02.8 (Ground‐Based Safety Nets) planned for 2018 and ATC02.9 

(Enhanced  Short  Term  Conflict  Alert  (STCA)  for  TMAs)  both  objectives  are  ongoing  and  planned  for  2018, 

ATC15.1  (Information  Exchange  with  En‐route  in  Support  of  AMAN)  planned  for  2018,  ATC17  (Electronic 

Dialogue as Automated Assistance to Controller during Coordination and Transfer) planned for 2019, COM10 

(Migrate  from AFTN    to AMHS) planned  for 2019,  FCM03  (Collaborative  Flight Planning) planned  for 2018, 

FCM04.2  (Short Term ATFCM Measures  (STAM)  ‐ Phase 2)  is ongoing and planned  for  completion  in 2018, 

FCM06  (Traffic  Complexity  Assessment)  is  ongoing  and  planned  for  completion  in  2018,  INF07  (Electronic 

Terrain and Obstacle Data) planned for 2018, ITY‐ADQ (Ensure Quality of Aeronautical Data and Aeronautical 

Information)  planned  for  2018,  ATC02.2  (Implement  ground  based  safety  nets  ‐  Short  Term  Conflict  Alert 

(STCA) ‐ level 2 for en‐route operations) is also planned for 2018. 

 

 

Objective Progress per SESAR Key Feature  

Note: The detailed table of links between Implementation Objectives and SESAR Key Features is available in Annex C. 

 

Legend: 

 ## %  = Expected completion / % Progress    = ESSIP Timeline (different colour per KF)  

 100%  = Objective Completed    = Completion beyond ESSIP Timeline  

 

 

 Optimised ATM Network Services 

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

AOM13.1 Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) handling  

      100% 

 

AOM19.1 (PCP)  ASM Support Tools to Support AFUA       10% 

 

AOM19.2 (PCP)  ASM Management of Real‐Time Airspace Data      0% 

 

AOM19.3 (PCP) Full rolling ASM/ATFCM Process and ASM Information Sharing 

     0% 

-  

FCM01  Enhanced Tactical Flow Management Services      100% 

 

FCM03  Collaborative Flight Planning       84% 

 

FCM04.1  STAM Phase 1      100% 

 

FCM04.2 (PCP)  STAM Phase 2      5% 

 

FCM05 (PCP)  Interactive Rolling NOP      3% 

 

FCM06 (PCP)  Traffic Complexity Assessment      30% 

 

 

Page 44: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 32 Released Issue

Advanced Air Traffic Services 

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

AOM21.1 (PCP)  Direct Routing      100% 

 

AOM21.2 (PCP)  Free Route Airspace      15% 

 

AOP14  Remote Tower Services  Local objective    0% 

-  

ATC02.2  STCA En‐Route       68% 

 

ATC02.8  Ground‐Based Safety Nets       63% 

 

ATC02.9  Enhanced STCA for TMAs      95% 

 

ATC07.1  AMAN Tools and Procedures         

  LKPR ‐ Praha Airport  0% 

ATC12.1 Automated Support for Conflict Detection, Resolution Support Information and Conformance Monitoring 

     26% 

 

ATC15.1 Information Exchange with En‐route in Support of AMAN 

      63% 

 

ATC15.2 (PCP) Arrival Management Extended to En‐route Airspace 

      0% 

-  

ATC16  ACAS II Compliant with TCAS II Change 7.1      100% 

 

ATC17 Electronic Dialogue as Automated Assistance to Controller during Coordination and Transfer 

      48% 

 

ATC18  Multi Sector Planning En‐route ‐ 1P2T  Local objective    0% 

-  

ENV01  Continuous Descent Operations        

 LKPR ‐ Praha Airport  (Outside Applicability Area) 

n/a  

ENV03  Continuous Climb Operations   Local objective     

  LKPR ‐ PRAHA/RUZYNE  - 0%  

ITY‐COTR Ground‐Ground Automated Co‐ordination Processes 

     100% 

 

NAV03.1  RNAV 1 in TMA Operations       100% 

 

NAV03.2 (PCP)  RNP 1 in TMA Operations       0% 

-  

NAV10  APV procedures      100% 

 

NAV12 Optimised Low‐Level IFR Routes in TMA for Rotorcraft 

 Local objective    0% 

-  

 

   

Page 45: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 33 Released Issue

 

 

  High Performing Airport Operations 

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

AOP04.1  A‐SMGCS Level 1        

  LKPR ‐ Praha Airport  100% 

AOP04.2  A‐SMGCS Level 2        

  LKPR ‐ Praha Airport  100% 

AOP05  Airport CDM        

  LKPR ‐ Praha Airport  100% 

AOP10 (PCP)  Time‐Based Separation         

 LKPR ‐ Praha Airport  (Outside Applicability Area) 

n/a  

AOP11 (PCP)  Initial Airport Operations Plan        

 LKPR ‐ Praha Airport  (Outside Applicability Area) 

9% 

AOP12 (PCP) Improve Runway and Airfield Safety with ATC Clearances Monitoring 

       

 LKPR ‐ Praha Airport  (Outside Applicability Area) 

35% 

AOP13 (PCP) Automated Assistance to Controller for Surface Movement Planning and Routing 

       

 LKPR ‐ Praha Airport  (Outside Applicability Area) 

n/a  

ENV02  Collaborative Environmental Management        

  LKPR ‐ Praha Airport  100% 

SAF11 Improve Runway Safety by Preventing Runway Excursions 

      18% 

   

 

   

Page 46: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 34 Released Issue

 

 Enabling Aviation Infrastructure  

    <15  15  16  17  18  19  20  21  22  23  24  ≥25  

COM10  Migrate from AFTN to AMHS       33% 

   

COM11  Voice over Internet Protocol (VoIP)      68% 

   

COM12 (PCP)  NewPENS       0% 

   

FCM08 (PCP)  Extended Flight Plan      0% 

 -  

INF04  Integrated Briefing      100% 

  

INF07  Electronic Terrain and Obstacle Data (eTOD)       65% 

   

ITY‐ACID  Aircraft Identification      100% 

  

ITY‐ADQ Ensure Quality of Aeronautical Data and Aeronautical Information 

      22% 

   

ITY‐AGDL  Initial ATC Air‐Ground Data Link Services     100% 

   

ITY‐AGVCS2 8,33 kHz Air‐Ground Voice Channel Spacing below FL195 

    100% 

   

ITY‐FMTP  Common Flight Message Transfer Protocol      100% 

   

ITY‐SPI  Surveillance Performance and Interoperability     71% 

   

   

Page 47: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 35 Released Issue

ICAO ASBU Implementation  

The following table shows, for each of the ASBU Block 0 modules, the overall status, the final date foreseen for completion and the percentage of progress achieved in the current cycle.    

These  results were  determined  using  the  LSSIP  Year  2017  declared  statuses  and  progress  of  the  relevant Implementation objectives  in accordance with the mapping approved by  ICAO EUR EANPG/59 (European Air Navigation Planning Group).     

 

Legend: 

   = Completed (during 2017 or before)  

  = Missing planning date  

 = Progress achieved in 2017    = Not applicable  

 

    <16     16  17  18  19  20  21  22  23  24   ≥25  

B0‐APTA  Optimization of Approach Procedures including vertical guidance 

       100% 

  

B0‐SURF  Safety and Efficiency of Surface Operations (A‐SMGCS Level 1‐2) 

       100% 

  

B0‐FICE  Increased Interoperability, Efficiency and Capacity through Ground‐Ground Integration 

       100% 

83%  

B0‐DATM  Service Improvement through Digital Aeronautical Information Management 

       100% 

61%  

B0‐ACAS  ACAS Improvements        100% 

 

B0‐SNET  Increased Effectiveness of Ground‐Based Safety Nets 

       100% 

79%  

B0‐ACDM  Improved Airport Operations through        100% 

  

B0‐RSEQ  Improved Traffic flow through Runway sequencing (AMAN/DMAN)  

       100% 

32%  

B0‐FRTO  Improved Operations through Enhanced En‐Route Trajectories 

       100% 

70%  

B0‐NOPS  Improved Flow Performance through Planning based on a Network‐Wide view 

       100% 

92%  

B0‐ASUR  Initial capability for ground surveillance         100% 

71%  

B0‐CDO  Improved Flexibility and Efficiency in Descent Profiles (CDO) 

   

  

B0‐TBO  Improved Safety and Efficiency through the initial application of Data Link En‐Route 

       100% 

  

 

 

   

Page 48: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 36 Released Issue

 

Detailed Objectives Implementation progress 6.2. 

Note: The detailed table of applicability area for the Implementation Objectives is available in Annex C. 

 

Objective/Stakeholder Progress Code: 

Completed    No Plan   

Ongoing    Not Applicable   

Planned    Missing Data   

Late       

 

 

 

   

Page 49: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 37 Released Issue

Main Objectives   

AOM13.1 

Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) Handling Timescales: Initial operational capability: 01/01/2012 Full operational capability: 31/12/2018 

100%  Completed 

 ‐  

Completed as of May 1, 2014. (establishment of integrated CIV‐MIL ACC).    31/12/2014 

REG (By:12/2018) 

MoT CR  ‐  ‐  100% Completed 

31/12/2014 

MAA  ‐  ‐  100% Completed 

31/12/2012 

ASP (By:12/2018) 

CZ Air Force Completed as of May 1, 2014 (establishment of integrated CIV‐MIL ACC). 

‐  100% Completed 

31/12/2014 

ASP ANS CR  ‐  ‐  100% Completed 

31/12/2014 

MIL (By:12/2018) 

CZ Air Force  ‐  ‐  100% Completed 

‐ 

MAA  ‐  ‐  100% Completed 

31/12/2012 

   

AOM19.1 

ASM Support Tools to Support Advanced FUA (AFUA) Timescales: Initial operational capability: 01/01/2011 Full operational capability: 31/12/2018 

10%  Late 

 ‐  

ASP: Improved ASM/ATFCM process, ASP plans the implementation of remaining SLOAs for 2021.  MoD participates on national level of implementation of these objectives.  Objective is linked with one of the FAB CE projects ‐ see details in Chapter 5 of Level 1 document. 

31/12/2021 

ASP (By:12/2018) 

CZ Air Force MoD participates on national level of implementation of these objectives.  

‐  10% Late 

31/12/2021 

CDPD MoD participates on national level of implementation of these objectives.  

‐  10% Late 

31/12/2021 

ASP ANS CR Improved ASM/ATFCM process, ASP plans the implementation of remaining SLOAs for 2021. 

FAB CE‐wide Study of Dynamic Airspace 

Management (DAM) and 

STAM 

10% 

Late 

31/12/2021 

     

Page 50: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 38 Released Issue

 

AOM19.2 

ASM Management of Real‐Time Airspace Data Timescales: Initial operational capability: 01/01/2017 Full operational capability: 31/12/2021 

0%  Planned 

 ‐  

Objective is linked with one of the FAB CE projects ‐ see details in Chapter 5 of Level 1 document. 

31/12/2021 

ASP (By:12/2021) 

ASP ANS CR  Planned for 2021 (according to SDM). 

FAB CE‐wide Study of Dynamic Airspace 

Management (DAM) and 

STAM 

0% 

Planned 

31/12/2021 

   

AOM19.3 

Full Rolling ASM/ATFCM Process and ASM Information Sharing Timescales: Initial operational capability: 01/01/2014 Full operational capability: 31/12/2021 

0%  No Plan 

 ‐  

Objective is linked with one of the FAB CE projects ‐ see details in Chapter 5 of Level 1 document. 

‐ 

ASP (By:12/2021) 

ASP ANS CR  ‐ 

FAB CE‐wide Study of Dynamic Airspace 

Management (DAM) and 

STAM 

0% 

No Plan 

‐ 

     

Page 51: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 39 Released Issue

 

AOM21.1 

Direct Routing Timescales: Initial Operational Capability: 01/01/2015 Full Operational Capability: 31/12/2017 

100%  Completed 

 ‐  

FRA has been implemented since February 5, 2015. See also FAB CE projects context ‐ details in Chapter 5. 

05/02/2015 

ASP (By:12/2017) 

ASP ANS CR  FRA has been implemented since February 5, 2015.  

FAB CE Strategic 

Operational Planning 

Project (incl. FAB CE X‐Border Free 

Route Airspace Study) / Gate One Free Route Airspace 

Operational Framework 

Study 

100% 

Completed 

05/02/2015 

   

AOM21.2 

Free Route Airspace Timescales: Initial operational capability: 01/01/2015 Full operational capability: 31/12/2021 

15%  Ongoing 

 ‐  

Objective is planned in the context of FAB CE projects – see details in Chapter 5.  04/11/2021 

ASP (By:12/2021) 

ASP ANS CR  Elementary FRA feasibility study was created.  

FAB CE Strategic 

Operational Planning 

Project (incl. FAB CE X‐Border Free 

Route Airspace Study) / Gate One Free Route Airspace 

Operational Framework 

Study 

15% 

Ongoing 

04/11/2021 

     

Page 52: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 40 Released Issue

 

AOP04.1 

Advanced Surface Movement Guidance and Control System A‐SMGCS Surveillance (former Level 1) Timescales: Initial operational capability: 01/01/2007 Full operational capability: 31/12/2011 

100%  Completed 

LKPR ‐ Praha Airport 

Czech Republic has implemented the Objective. ANS CR was member of BETA research project (2000‐2002) which evaluated operational impact of A‐SMGCS. System NOVA 9000 (produced by Park Air Systems) is installed in Prague Ruzyne airport. 

‐ 

REG (By:12/2010) 

CAA CR  All actions are completed.  ‐  100% Completed 

‐ 

MoT CR  ‐  ‐  100% Completed 

‐ 

ASP (By:12/2011) 

ASP ANS CR  All actions are completed.  ‐  100% Completed 

‐ 

APO (By:12/2010) 

Prague Airport 

All actions are completed.  ‐  100% Completed 

‐ 

   

AOP04.2 

Advanced Surface Movement Guidance and Control System (A‐SMGCS) Runway Monitoring and Conflict Alerting (RMCA) (former Level 2) Timescales: Initial operational capability: 01/01/2007 Full operational capability: 31/12/2017 

100%  Completed 

LKPR ‐ Praha Airport 

Czech Republic has implemented the Objective. The implementation and operation is the responsibility of the ASP and thus the Objective is not applicable for APO. 

‐ 

ASP (By:12/2017) 

ASP ANS CR A‐SMGCS Level 2 functionality was installed in Prague/Ruzyne airport and is in full operation. 

‐  100% Completed 

‐ 

APO (By:12/2017) 

Prague Airport 

Not required (A‐SMGCS control function installed and operated by ASP). 

‐  % Not 

Applicable 

‐ 

     

Page 53: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 41 Released Issue

 

AOP05 

Airport Collaborative Decision Making (A‐CDM) Timescales: Initial operational capability: 01/01/2004 Full operational capability: 31/12/2016 

100%  Completed 

LKPR ‐ Praha Airport 

Airport CDM at Praha/Ruzyne launched October 2009; TOBT is provided by GHA. TSAT procedure, DEP sequencing and CDM De‐icing procedures launched in September 2011. FUM/DPI implemented in 2015. 

31/12/2015 

ASP (By:12/2016) 

ASP ANS CR  ‐  Airport CDM  100% Completed 

31/12/2013 

APO (By:12/2016) 

Prague Airport 

Airport CDM at Praha/Ruzyne launched 6 Oct. 2009; TOBT is provided by GHA. TSAT procedure, DEP sequencing and CDM De‐icing procedures implemented  in September 2011. FUM/DPI implemented in September 2015. 

Airport CDM  100% 

Completed 

31/12/2015 

ASP ANS CR 

Airport CDM at Praha/Ruzyne launched 6 Oct. 2009; TOBT is provided by GHA. TSAT procedure, DEP sequencing and CDM De‐icing procedures implemented  in September 2011. FUM/DPI implemented in September 2015.  

Airport CDM  100% 

Completed 

31/12/2015 

   

AOP10 Time‐Based Separation Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

LKPR ‐ Praha Airport  (Outside Applicability Area) 

Prague Ruzyne Airport (LKPR) is not in the applicability area.  ‐ 

REG (By:12/2023) 

ASP (By:12/2023) 

   

AOP11 Initial Airport Operations Plan Timescales: ‐ not applicable ‐ 

9%  Ongoing 

LKPR ‐ Praha Airport  (Outside Applicability Area) 

Gap analysis in progress in relation to CDM procedures.  31/12/2019 

ASP (By:12/2021) 

ASP ANS CR  ‐  ‐  0% Planned 

31/12/2019 

APO (By:12/2021) 

Prague Airport 

‐  ‐  12% Ongoing 

31/12/2019 

     

Page 54: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 42 Released Issue

 

AOP12 

Improve Runway and Airfield Safety with Conflicting ATC Clearances (CATC) Detection and Conformance Monitoring Alerts for Controllers (CMAC) Timescales: ‐ not applicable ‐ 

35%  Ongoing 

LKPR ‐ Praha Airport  (Outside Applicability Area) 

ANS CR project "Advanced Safety Nets for Prague Airport" is scheduled for years 2016 ‐ 2018; CBA for the project was finished beginning of 2016. 

31/12/2018 

ASP (By:12/2020) 

ASP ANS CR ANS CR project "Advanced Safety Nets for Prague Airport" is scheduled for years 2016‐ 2018; CBA for the project was finished beginning of 2016. 

‐  47% Ongoing 

31/12/2018 

APO (By:12/2020) 

Prague Airport 

‐  ‐  0% Planned 

31/12/2018 

   

AOP13 

Automated Assistance to Controller for Surface Movement Planning and Routing Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

LKPR ‐ Praha Airport  (Outside Applicability Area) 

CZ (LKPR) is not in the applicability area.  ‐ 

REG (By:12/2023) 

ASP (By:12/2023) 

ASP ANS CR  ‐  ‐  % Not 

Applicable 

‐ 

   

ATC02.8 

Ground‐Based Safety Nets Timescales: Initial operational capability: 01/01/2009 Full operational capability: 31/12/2016 

63%  Late 

 ‐  

The APW and MSAW functions are fully implemented for ACC/APP Prague, APP Ostrava and APP Karlovy Vary. Implementation for regional APP Brno  is scheduled for 2018.  There is currently no plan for APM implementation. 

31/12/2018 

ASP (By:12/2016) 

ASP ANS CR  ‐  ‐  60% Late 

31/12/2018 

CZ Air Force  ‐  ‐  100% Completed 

31/12/2015 

     

Page 55: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 43 Released Issue

 

ATC02.9 

Enhanced Short Term Conflict Alert (STCA) for TMAs Timescales: Initial operational capability: 01/01/2018 Full operational capability: 31/12/2020 

95%  Ongoing 

 ‐  

The STCA functions are fully implemented for ACC/APP Prague, APP Ostrava and APP Karlovy Vary. Implementation for regional APP Brno  is scheduled for 2018.  

31/12/2018 

ASP (By:12/2020) 

ASP ANS CR 

The STCA functions are fully implemented for ACC/APP Prague, APP Ostrava and APP Karlovy Vary. Implementation for regional APP Brno  is scheduled for 2018.  

‐  95% 

Ongoing 

31/12/2018 

   

ATC07.1 

AMAN Tools and Procedures Timescales: Initial operational capability: 01/01/2007 Full operational capability: 31/12/2019 

0%  Late 

LKPR ‐ Praha Airport 

There was an intention to implement AMAN based on the result of feasibility study and CBA for Prague Ruzyne AMAN/DMAN. The project is currently planned for the implementation in time span  2019 ‐ 2022 based on LKPR traffic evolution. 

31/12/2022 

ASP (By:12/2019) 

ASP ANS CR 

There was an intention to implement AMAN based on the result of feasibility study and CBA for Prague Ruzyne AMAN/DMAN. Currently the project is planned for the implementation in time span  2019 ‐ 2022 based on LKPR traffic evolution. 

AMAN LOWW initial 

0% 

Late 

31/12/2022 

   

ATC12.1 

Automated Support for Conflict Detection, Resolution Support Information and Conformance Monitoring Timescales: Initial operational capability: 01/01/2015 Full operational capability: 31/12/2021 

26%  Ongoing 

 ‐  

Specification is part of a new ANS CR ATM System (Neopteryx) project. Full implementation is planned for 2021. 

31/12/2021 

ASP (By:12/2021) 

ASP ANS CR Specification is part of Neopteryx project. Full implementation is planned for 2021.  

‐  26% Ongoing 

31/12/2021 

     

Page 56: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 44 Released Issue

  

ATC15.1 

Information Exchange with En‐route in Support of AMAN Timescales: Initial operational capability: 01/01/2012 Full operational capability: 31/12/2017 

63%  Late 

 ‐  

Basic algorithm of production of AMA message is implemented in our en‐route system. Operational use depends on implementation of AMAN system in Munich, Vienna and other airports. 

31/12/2018 

ASP (By:12/2017) 

ASP ANS CR 

Basic algorithm of production of AMA message is implemented in our en‐route system. Operational use depends on implementation of AMAN system in Munich, Vienna and other airports. 

AMAN LOWW initial 

63% 

Late 

31/12/2018 

   

ATC15.2 

Arrival Management Extended to En‐route Airspace Timescales: Initial operational capability: 01/01/2015 Full operational capability: 31/12/2023 

0%  No Plan 

 ‐  

There is currently no approved plan.  ‐ 

ASP (By:12/2023) 

ASP ANS CR  There is currently no approved plan.  ‐  0% No Plan 

‐ 

   

ATC17 

Electronic Dialogue as Automated Assistance to Controller during Coordination and Transfer Timescales: Initial operational capability: 01/01/2013 Full operational capability: 31/12/2018 

48%  Late 

 ‐  

The implementation is ongoing; COF and MAS messages are in operational use. TIM and ROF messages are installed but not in operational use yet.  The implementation of missing messages is planned before 12/2019. 

31/12/2019 

ASP (By:12/2018) 

ASP ANS CR  ‐  ‐  48% Late 

31/12/2019 

   

COM10 

Migrate from AFTN  to AMHS  Timescales: Initial operational capability: 01/12/2011 Full operational capability: 31/12/2018 

33%  Late 

 ‐  

ANS CR implemented the capability of AMHS in January, 2018. Intention of MoD is to follow ASP but implementation depends on available budget. 

31/12/2019 

ASP (By:12/2018) 

CDPD Intention of MoD is to follow ASP but implementation depends on available budget. 

‐  0% Late 

31/12/2019 

ASP ANS CR ANS CR implemented the capability of AMHS in January, 2018. 

AMHS  100% Completed 

04/01/2018 

CZ Air Force Intention of MoD is to follow ASP but implementation depends on available budget. 

‐  0% Late 

31/12/2019 

Page 57: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 45 Released Issue

   

COM11 

Voice over Internet Protocol (VoIP) Timescales: Initial operational capability: 01/01/2013 Full operational capability: 31/12/2020 

68%  Ongoing 

 ‐  

Implementation planned for 2020  31/12/2020 

ASP (By:12/2020) 

ASP ANS CR Implemented on regional airports. Implementation in APP/TWR Prague and ACC Prague planned for 12/2020. 

VoIP  32% Ongoing 

31/12/2020 

CDPD  For the military, planned for 12/2020.  VoIP  87% Ongoing 

31/12/2020 

CZ Air Force  For the military, planned for 12/2020.  VoIP  87% Ongoing 

31/12/2020 

   

COM12 

New Pan‐European Network Service (NewPENS) Timescales: Initial operational capability: 01/01/2018 Full operational capability (33 ANSPs): 31/12/2020 

0%  Planned 

 ‐  

ASP plans to join NewPENS. APO communication with NM ensured via ASP.  31/12/2020 

ASP (By:12/2024) 

ASP ANS CR  ‐  ‐  0% Planned 

31/12/2020 

APO (By:12/2024) 

   

ENV01 Continuous Descent Operations (CDO) Timescales: ‐ not applicable ‐ 

% Not 

Applicable 

LKPR ‐ Praha Airport  (Outside Applicability Area) 

CDO test flights were performed in 2011 and assessed in 2012. The test results proved no significant benefits. Based on results of the tests ASP decided not to publish specific CDO procedures yet. CDO is provided by "distance‐to‐go" information to A/C. 

‐ 

ASP (By:12/2013) 

ASP ANS CR 

CDO test flights were performed in 2011 and assessed in 2012. The test results proved no significant benefits.  Based on these results ASP decided not to publish specific CDO procedures yet. CDO is provided by "distance‐to‐go" information to A/C. 

‐  % 

Not Applicable 

‐ 

APO (By:12/2013) 

Prague Airport 

Implementation depends on ASP plans.  ‐  % Not 

Applicable 

‐ 

     

Page 58: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 46 Released Issue

 

ENV02 

Airport Collaborative Environmental Management Timescales: Initial operational capability: 01/09/2004 Full operational capability: 31/12/2016 

100%  Completed 

LKPR ‐ Praha Airport 

CEM was officially launched in June 2010. Meetings are organized twice a year and on demand. Agreements on the care for the ennvironment and environmental impacts if the APO operations were signed with subjects concerned. 

31/12/2012 

ASP (By:12/2016) 

ASP ANS CR 

CEM was officially launched in June 2010. Meetings are organized twice a year and on demand. Environmental implications of aircraft operations are part of ATCO training. 

‐  100% 

Completed 

30/06/2010 

APO (By:12/2016) 

Prague Airport 

CEM was officially launched in June 2010. With regard to communication with concerned subjects, agreements on the care for the ennvironment and environmental impacts if the APO operations were signed. 

‐  100% 

Completed 

31/12/2012 

   

FCM03 

Collaborative Flight Planning Timescales: Initial operational capability: 01/01/2000 Full operational capability: 31/12/2017 

84%  Late 

 ‐  

AFP messages were technically implemented, but not in operational use yet. Operational internal tests are planned for 2018, further tests with NM will follow.  Full implementation is expected in 2018. 

31/12/2018 

ASP (By:12/2017) 

ASP ANS CR 

AFP messages were technically implemented, but not in operational use yet. Operational internal tests are planned for 2018, further tests with NM will follow.  Full implementation is expected in 2018. 

‐  84% 

Late 

31/12/2018 

   

FCM04.1 

Short Term ATFCM Measures (STAM) ‐ Phase 1 Timescales: Initial operational capability: 01/09/2013 Full operational capability: 31/10/2017 

100%  Completed 

 ‐  

Objective is linked with one of the FAB CE projects ‐ see details in Chapter 5 of Level 1 document. 

‐ 

ASP (By:10/2017) 

ASP ANS CR   

FAB CE‐wide Study of Dynamic Airspace 

Management (DAM) and 

STAM 

100% 

Completed 

‐ 

     

Page 59: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 47 Released Issue

 

FCM04.2 

Short Term ATFCM Measures (STAM) ‐ Phase 2 Timescales: Initial operational capability: 01/11/2017 Full operational capability: 31/12/2021 

5%  Ongoing 

 ‐  

Initial actions have started as part of FAB CE DAM/STAM Project (ex. P3). It is likely that STAM phase 2 will be implemented with the availability of this function in the N‐connect Tool, planned for implementation end of 2018. Objective is linked with one of the FAB CE projects ‐ see details in Chapter 5 of Level 1 document. 

31/12/2018 

ASP (By:12/2021) 

ASP ANS CR  ‐ 

FAB CE‐wide Study of Dynamic Airspace 

Management (DAM) and 

STAM 

5% 

Ongoing 

31/12/2018 

   

FCM05 

Interactive Rolling NOP Timescales: Initial operational capability: 01/09/2013 Full operational capability: 31/12/2021 

3%  Ongoing 

 ‐  

Project objectives will be accomplished by developing a national ASM tool. The national ASM tool will also be interconnected to the military ASM tool and interoperable with NM. For the military, the decision has not been taken yet, however the MIL will closely cooperate with civil side. MIL is considered as low key stakeholder.  AT FAB CE level implementation of interactive rolling NOP is planned through upgrade of the automated ASM support system with the capability of AIXM 5.1 B2B data exchange with NM and Perform an integration of the automated ASM support systems with the Network. All these projects will be fulfilled in accordance with the NM support, the guidance and the relevant provisions of the NM B2B Reference Manuals. Objective is linked with one of the FAB CE projects ‐ see details in Chapter 5 of Level 1 document. 

31/12/2021 

ASP (By:12/2021) 

ASP ANS CR  ‐ 

FAB CE‐wide Study of Dynamic Airspace 

Management (DAM) and 

STAM 

0% 

Planned 

31/12/2021 

APO (By:12/2021) 

Prague Airport 

‐  ‐  5% Ongoing 

31/12/2021 

     

Page 60: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 48 Released Issue

 

FCM06 

Traffic Complexity Assessment Timescales: Initial operational capability: 01/01/2015 Full operational capability: 31/12/2021 

30%  Ongoing 

 ‐  

The objective is to provide support in the management of the traffic load over LKAA area. Support should be primarily provided to Prague ACC Flow Manager position. Secondary service would be provided to Prague ACC/APP control sectors. Planned for 2018. At FAB CE level several options are discussed on whether ANSP will procure a ready‐made Complexity Assessment Tool, or will commit to develop such a tool using own resources. One solution is being discussed on the possibility to have a common FAB CE Complexity Tool, more details will be available end 02/2017. Initial actions have been made, with advanced use of CHMI functions (Associated Flows etc). Objective is linked with one of the FAB CE projects ‐ see details in Chapter 5 of Level 1 document. 

31/12/2018 

ASP (By:12/2021) 

ASP ANS CR 

The objective is to provide support in the management of the traffic load over LKAA area. Support should be primarily provided to Prague ACC Flow Manager position. Secondary service would be provided to Prague ACC/APP control sectors. 

FAB CE‐wide Study of Dynamic Airspace 

Management (DAM) and 

STAM 

30% 

Ongoing 

31/12/2018 

   

FCM08 

Extended Flight Plan Timescales: Initial operational capability: 01/01/2016 Full operational capability: 31/12/2021 

0%  No Plan 

 ‐  

Currently there is no plan for the implementation.  ‐ 

ASP (By:12/2021) 

ASP ANS CR  Currently there is no plan for the implementation.  ‐  0% No Plan 

‐ 

     

Page 61: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 49 Released Issue

 

INF07 

Electronic Terrain and Obstacle Data (eTOD) Timescales: Initial operational capability: 01/11/2014 Full operational capability: 31/05/2018 

65%  Late 

 ‐  

Planned for 12/2018.  31/12/2018 

REG (By:05/2018) 

MoT CR The national policy on TOD is covered by relevant provisions of the Aviation Act No 49/1997 Coll. and by associated Ministerial Decree No 108/1997 Coll.  

‐  100% Completed 

‐ 

CAA CR 

The current NSA processes will be used to verify implementation of the requirements at ANS providers and other stakeholders.  The regulatory compliance shall be conducted in compliance with national TOD policy and Implementation programme.  

‐  5% 

Late 

31/12/2018 

ASP (By:05/2018) 

ASP ANS CR 

ETOD is maintained by AIS ANS CR. Terrain data supplied by MIL are in conformity with requirements of ICAO Annex 15. Data supplied by airports operators do not fulfill all requirements of the Annex. 

‐  100% 

Completed 

31/12/2014 

APO (By:05/2018) 

Prague Airport 

Planned for   ‐  55% Late 

31/12/2018 

   

ITY‐ACID 

Aircraft Identification Timescales: Entry into force of the Regulation: 13/12/2011 System capability: 02/01/2020 

100%  Completed 

 ‐  

The objective has been achieved by implementation of Mode S capability.  31/12/2012 

ASP (By:01/2020) 

ASP ANS CR  All actions completed.  ‐  100% Completed 

31/12/2012 

     

Page 62: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 50 Released Issue

 

ITY‐ADQ 

Ensure Quality of Aeronautical Data and Aeronautical Information Timescales: Entry into force of the regulation: 16/02/2010 Article 5(4)(a), Article 5(4)(b) and Article 6 to 13 to be implemented by: 30/06/2013 Article 4, Article5(1) and Article 5(2), Article 5(3) and Article 5(4)(c) to be implemented by: 30/06/2014 All data requirements implemented by: 30/06/2017 

22%  Late 

 ‐  

The working group at national level was established and all required actions including time schedule are in preparation. Part of the requirements are fulfilled as a part of the standard NSA oversight process with regard to ICAO and SES legislation requirements. The objective will be completed when ANS CR provides new AIM system planned for 2018. MIL has its own system. The upgrade of MIL systems to be fully compliant with Regulation (EC) 73/2010 is planned for 2018, however their implementation fully depends on the MIL budget limitations. 

31/12/2018 

REG (By:06/2017) 

CAA CR The working group at national level was established and all required actions including time schedule are in preparation. 

‐  53% Late 

31/12/2018 

MAA 

The working group at national level was established. MIL has its own system. The upgrade of MIL systems to be fully compliant with Regulation (EC) 73/2010 is planned for 2018, however their implementation fully depends on the MIL budget limitations. 

‐  10% 

Late 

31/12/2018 

CDPD 

MIL has its own system. The upgrade of MIL systems to be fully compliant with Regulation (EC) 73/2010 is planned for 2018, however their implementation fully depends on the MIL budget limitations. 

‐  10% 

Late 

31/12/2018 

ASP (By:06/2017) 

ASP ANS CR 

The working group at national level was established. Part of required actions are implemented; see details below. The objective will be completed when ANS CR provides new AIM system planned for 2018. 

‐  41% 

Late 

31/12/2018 

CZ Air Force 

The working group at national level was established. MIL has its own system. The upgrade of MIL systems to be fully compliant with Regulation (EC) 73/2010 is planned for 2018, however their implementation fully depends on the MIL budget limitations. 

‐  10% 

Late 

31/12/2018 

CDPD 

MIL has its own system. The upgrade of MIL systems to be fully compliant with Regulation (EC) 73/2010 is planned for 2018, however their implementation fully depends on the MIL budget limitations. 

‐  10% 

Late 

31/12/2018 

APO (By:06/2017) 

Prague Airport 

The working group at national level was established and all required actions including time schedule are in preparation. APO is in proces of SW procurement to meet the requirements. 

‐  13% 

Late 

31/12/2018 

     

Page 63: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 51 Released Issue

 

ITY‐AGDL 

Initial ATC Air‐Ground Data Link Services Timescales: Entry into force: 06/02/2009 ATS unit operational capability: 05/02/2018 Aircraft capability: 05/02/2020 

100%  Completed 

 ‐  

ANS CR implemented A/G data link services on February 6, 2017.  MIL has completed for state transport aircraft able to fly at or above FL 285 in compliance with EU regulation. 

06/02/2017 

REG (By:02/2018) 

CAA CR CAA CR acts accordingly based upon the ASPs implementation plans in line with established procedures.  

‐  100% Completed 

31/12/2016 

MoT CR  ‐  ‐  100% Completed 

31/12/2016 

ASP (By:02/2018) 

ASP ANS CR ANS CR implemented A/G data link services on February 6, 2017. 

‐  100% Completed 

06/02/2017 

MIL (By:01/2019) 

CDPD Completed for state transport aircraft able to fly at or above FL 285 in compliance with EU regulation. 

‐  100% Completed 

31/12/2014 

     

Page 64: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 52 Released Issue

ITY‐AGVCS2 

8,33 kHz Air‐Ground Voice Channel Spacing below FL195 Timescales: Entry into force: 07/12/2012 New and upgraded radio equipment: 17/11/2013 New or upgraded radios on State aircraft: 01/01/2014 Interim target for freq. conversions: 31/12/2014 All radio equipment: 31/12/2017 All frequencies converted: 31/12/2018 State aircraft equipped, except those notified to EC: 31/12/2018 State aircraft equipped, except those exempted [Art 9(11)]: 31/12/2020 

100%  Completed 

 ‐  

NSA has enforced the requirements for voice channels spacing for new introduced radios since 2013. The safety oversight of changes in ATM will be performed as a standard procedure in terms defined by AIC C 02/13 with regard to Implementing Regulation (EU) No 1079/2012.  According to AIC A 8/15, the conversion of Frequency Plan was scheduled in 3 steps (from November 2016 to November 2017).  

31/12/2017 

REG (By:12/2018) 

MoT CR According to AIC 8/15, the conversion of Frequency Plan was scheduled in 3 steps (from November 2016 to November 2017).  

‐  100% Completed 

‐ 

CDPD  ‐  ‐  100% Completed 

31/12/2017 

MAA  ‐  ‐  100% Completed 

31/12/2017 

ASP (By:12/2018) 

CZ Air Force According to AIC 8/15, the conversion of the frequency was scheduled in 3 steps (from November 2016 to November 2017).  

‐  100% Completed 

31/12/2017 

CDPD According to AIC 8/15, the conversion of Frequency Plan was scheduled in 3 steps (from November 2016 to November 2017).  

‐  100% Completed 

31/12/2017 

MAA According to AIC 8/15, the conversion of the frequency was scheduled in 3 steps (from November 2016 to November 2017).  

‐  100% Completed 

31/12/2017 

ASP ANS CR 

According to AIC A 8/15, the conversion of Frequency Plan was scheduled in 3 steps (from November 2016 to November 2017). ASP followed the Transition plan developed by MoT. RCOM system was upgraded in 2017.  

Conversion to the 8.33 kHz channel spacing 

below FL195 

100% 

Completed 

31/12/2017 

MIL (By:12/2020) 

CZ Air Force MIL follows the national plan established by MoT with agreement of MoD. 

‐  100% Completed 

31/12/2017 

CDPD MIL follows the national plan established by MoT with agreement of MoD. 

‐  100% Completed 

31/12/2017 

   

Page 65: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 53 Released Issue

APO (By:12/2018) 

CZ Air Force  ‐  ‐  100% Completed 

31/12/2017 

ASP ANS CR  ‐ 

Conversion to the 8.33 kHz channel spacing 

below FL195 

100% 

Completed 

31/12/2017 

Prague Airport 

‐ 

Conversion to the 8.33 kHz channel spacing 

below FL195 

Not Applicable 

‐ 

   

ITY‐FMTP 

Common Flight Message Transfer Protocol (FMTP) Timescales: Entry into force of regulation: 28/06/2007 All EATMN systems put into service after 01/01/09: 01/01/2009 All EATMN systems in operation by 20/04/11: 20/04/2011 Transitional arrangements: 31/12/2012 Transitional arrangements when bilaterally agreed between ANSPs: 31/12/2014 

100%  Completed 

 ‐  

FMTP has already been implemented and is already operationally used internally (ANS CR, MIL, regional airports) and externally with exception of PL. 

31/12/2014 

ASP (By:12/2014) 

ASP ANS CR 

For ANS CR, all actions are completed. FMTP implemented with neighbours except PL. IPv4 protocol is used internally. There is a translation device for conversion from IPv4 to IPv6 on communication interface with neighbouring states.  

‐  100% 

Completed 

31/12/2014 

CDPD 

For MIL all actions are completed. IPv4 protocol is used internally. There is a translation device for conversion from IPv4 to IPv6 on communication interface with ANS CR.  

‐  100% 

Completed 

31/12/2014 

CZ Air Force 

For MIL all actions are completed. IPv4 protocol is used internally. There is a translation device for conversion from IPv4 to IPv6 on communication interface with ANS CR.  

‐  100% 

Completed 

31/12/2014 

MIL (By:12/2014) 

CZ Air Force  Completed  ‐  100% Completed 

31/12/2014 

CDPD  Completed  ‐  100% Completed 

31/12/2014 

     

Page 66: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 54 Released Issue

 

ITY‐SPI 

Surveillance Performance and Interoperability Timescales: Entry into force of regulation: 13/12/2011 ATS unit operational capability: 12/12/2013 EHS and ADS‐B Out  in transport‐type State aircraft : 07/06/2020 ELS in transport‐type State aircraft : 07/06/2020 Ensure training of MIL personnel: 07/06/2020 Retrofit aircraft capability: 07/06/2020 

71%  Ongoing 

 ‐  

ASP and REG completed.  MIL ongoing.  07/06/2020 

REG (By:02/2015) 

CAA CR The oversight of this objective's implementation falls into the CAA CR Annual Safety and Regulatory Oversight Programme. 

‐  100% Completed 

31/12/2013 

ASP (By:02/2015) 

ASP ANS CR  ‐  ‐  100% Completed 

31/12/2013 

MIL (By:06/2020) 

CDPD The most of MIL transport aircraft have been equipped by EHS and ADS‐B out. Training partly completed. 

‐  23% Ongoing 

07/06/2020 

CZ Air Force The most of MIL transport aircraft have been equipped by EHS and ADS‐B out. Training partly completed. 

‐  23% Ongoing 

07/06/2020 

   

NAV03.1 

RNAV 1 in TMA Operations Timescales: Initial operational capability: 01/01/2001 Full operational capability: 31/12/2023 

100%  Completed 

 ‐  

RNAV1 procedures are implemented in TMA Prague.   31/12/2010 

ASP (By:12/2023) 

ASP ANS CR RNAV1 procedures were implemented in TMA Prague (in 2010).  

‐  100% Completed 

31/12/2010 

CAA CR 

The Czech Republic started implementation of PBN very soon and PBN procedures (RNAV‐1 SID,STAR, RNP APCH) are published at almost all Czech IFR airports. For the period 2016+ there is a plan for just marginal improvements of these procedures.The implementation Road Map of the PBN procedures was described within PBN questionnaire document addressed to the Network Manager. 

‐  100% 

Completed 

31/12/2010 

   

NAV03.2 

RNP 1 in TMA Operations Timescales: Initial operational capability: 01/01/2018 Full operational capability: 31/12/2023 

0%  No Plan 

 ‐  

There is currently no plan for the implementation.   ‐ 

ASP (By:12/2023) 

ASP ANS CR  There is currently no plan for the implementation.   ‐  0% No Plan 

‐ 

   

Page 67: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 55 Released Issue

NAV10 

APV Procedures Timescales: Initial operational capability: 01/06/2011 Full operational capability: 31/12/2016 

100%  Completed 

 ‐  

APV/Baro procedures have been implemented for Praha Ruzyne and published in AIP in 2010. APV SBAS was implemented for regional airports (LKTB, LKMT, LKKV) in 2014. 

31/12/2014 

REG (By:04/2016) 

CAA CR  Material published on CAA website.   ‐  100% Completed 

30/04/2011 

ASP (By:12/2016) 

ASP ANS CR 

APV/Baro procedures have been implemented for Praha Ruzyne and publised in AIP in 2010. APV SBAS was implemented for regional airports (LKTB, LKMT, LKKV) in 2014. 

‐  100% 

Completed 

31/12/2014 

   

SAF11 

Improve Runway Safety by Preventing Runway Excursions Timescales: Initial operational capability: 01/09/2013 Full operational capability: 31/01/2018 

18%  Late 

 ‐  

Implementation of SAF 11 is planned. Runway Safety Team was established during implementation of Runway Incursion Programme so general requirements (Part 3.1) are already implemented.   Runway Safety Programme for the Czech Republic was published on 27.10.2016 in AIC 25/16. 

31/12/2020 

REG (By:01/2018) 

CAA CR Documentation for the European Action Plan for the Prevention of Runway Excursions was published in 2016. Subsequent steps will follow. 

‐  25% Late 

31/12/2020 

ASP (By:12/2014) 

MAA 

Appropriate military airports concerned need to be defined at national level, in accordance with EAPPRE. Only one MIL airport (Pardubice) has been considered for implementing the Objective; MoD uses own system on other airports.  

‐  0% 

Late 

31/12/2018 

ASP ANS CR  ‐  ‐  20% Late 

31/12/2018 

CZ Air Force 

Appropriate military airports concerned need to be defined at national level, in accordance with EAPPRE. Only one MIL airport (Pardubice) has been considered for implementing the Objective; MoD uses own system on other airports.  

‐  0% 

Late 

31/12/2018 

APO (By:12/2014) 

Prague Airport 

‐  ‐  100% Completed 

‐ 

CZ Air Force 

Appropriate military airports concerned need to be defined at national level, in accordance with EAPPRE. Only one MIL airport (Pardubice) has been considered for implementing the Objective; MoD uses own system on other airports.  

‐  0% 

Late 

31/12/2018 

MAA 

Appropriate military airports concerned need to be defined at national level, in accordance with EAPPRE. Only one MIL airport (Pardubice) has been considered for implementing the Objective; MoD uses own system on other airports.  

‐  0% 

Late 

31/12/2018 

Page 68: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 56 Released Issue

  

Additional Objectives for ICAO ASBU Monitoring  

ATC02.2 

Implement ground based safety nets ‐ Short Term Conflict Alert (STCA) ‐ level 2 for en‐route operations Timescales: Initial operational capability: 01/01/2008 Full operational capability: 31/01/2013 

68%  Late 

 ‐  

STCA function is fully implemented for ACC/APP Prague, APP Ostrava and APP Karlovy Vary. Implementation for regional APP Brno is scheduled for 2018.  The system is implemented also by MIL and upgrade to OAT traffic specifications and validation was done in 2012. 

31/12/2018 

ASP (By:01/2013) 

CZ Air Force 

Military system is also equipped with the STCA functionality which was successfully tested. An upgrade regarding to MIL traffic specification (OAT) and validation was done. 

‐  100% 

Completed 

31/12/2012 

ASP ANS CR STCA function is fully implemented for ACC/APP Prague, APP Ostrava and APP Karlovy Vary. Implementation for regional APP Brno  is scheduled for 2018.  

‐  55% Late 

31/12/2018 

   

ATC16 

Implement ACAS II compliant with TCAS II change 7.1   Timescales: Initial operational capability: 01/03/2012 Full operational capability: 31/12/2015 

100%  Completed 

 ‐  

ASP has completed in 03/2012.  MIL completed for VIP transport a/c only (type Airbus 319‐115). 

31/12/2015 

REG (By:12/2015) 

CAA CR  ‐  ‐  100% Completed 

31/12/2015 

ASP (By:03/2012) 

ASP ANS CR  ‐  ‐  100% Completed 

31/03/2012 

MIL (By:12/2015) 

CZ Air Force MIL completed for VIP transport a/c only (type Airbus 319‐115). 

‐  100% Completed 

31/12/2015 

CDPD MIL completed for VIP transport a/c only (type Airbus 319‐115). 

‐  100% Completed 

31/12/2015 

     

Page 69: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 57 Released Issue

 

FCM01 

Implement enhanced tactical flow management services Timescales: Initial operational capability: 01/08/2001 Full operational capability: 31/12/2006 

100%  Completed 

 ‐  

The implementation is completed. Some SLoAs are considered as not applicable. Military system receives and processes ATFM data via ANS CR. 

31/12/2014 

ASP (By:07/2014) 

MIL ASP Military system receives and processes ATFM data via ANS CR. 

‐  100% Completed 

31/12/2014 

ASP ANS CR 

ANS CR has already implemented processing of CPR and FSA messages for ATFM purposes. Processing of FSA in case of rerouting inside FDPA and in case of aircraft holding is considered as not applicable  in terms of cost/benefit ratio. Processing of DPI is part of A‐CDM Project. 

‐  100% 

Completed 

31/12/2014 

   

INF04 

Implement integrated briefing Timescales: Initial operational capability: 01/07/2002 Full operational capability: 31/12/2012 

100%  Completed 

 ‐  

IBS system was implemented at ARO in 12/2010. This system fulfiles Level 5 requirements for integrated briefing.  

31/12/2010 

ASP (By:12/2012) 

CZ Air Force For the military, the objective has been implemented in 12/2008. 

‐  100% Completed 

31/12/2010 

ASP ANS CR IBS system was implemented at ARO in 12/2010. This system fulfiles Level 5 requirements for integrated briefing. 

‐  100% Completed 

31/12/2010 

   

ITY‐COTR 

Implementation of ground‐ground automated co‐ordination processes Timescales: Entry into force of Regulation: 27/07/2006 For putting into service of EATMN systems in respect of notification and initial coordination processes: 27/07/2006 For putting into service of EATMN systems in respect of Revision of Coordination, Abrogation of Coordination, Basic Flight Data and Change to Basic Flight Data: 01/01/2009 To all EATMN systems in operation by 12/2012: 31/12/2012 

100%  Completed 

 ‐  

All mandatory requirements of IR COTR are implemented.   31/12/2014 

ASP (By:12/2012) 

ASP ANS CR 

All mandatory requirements of IR COTR are implemented. Implementation of "Logon Forward " (ASP08) and "Next Authority Notified" (ASP09) processes is planned in frame of A/G Datalink implementation with the implementation date in 2017. 

‐  100% 

Completed 

‐ 

MIL (By:12/2012) 

CDPD  ‐  ‐  100% Completed 

31/12/2014 

CZ Air Force  Completed  ‐  100% Completed 

31/12/2014 

Page 70: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 58 Released Issue

  

Local Objectives  

AOP14 Remote Tower Services Applicability and timescale: Local 

%  No Plan 

LKPR ‐ PRAHA/RUZYNE 

There is currently no plan to implement Remote Tower Services in Czech Republic.   ‐  

ATC18 Multi‐Sector Planning En‐route ‐ 1P2T   Applicability and timescale: Local 

%  No Plan 

 ‐  

There is currently no plan for the implementation.  ‐  

ENV03 Continuous Climb Operations (CCO) Applicability and timescale: Local 

%  No Plan 

LKPR ‐ PRAHA/RUZYNE 

There is no plan at the moment for application of CCO due to high traffic complexity.  Future implementation of CCO is intended, but the target date has not been set. 

‐ 

 

NAV12 Optimised Low‐Level IFR Routes in TMA for Rotorcraft   Applicability and timescale: Local 

%  No Plan 

 ‐  

There is currently no plan for implementation.  ‐ 

 

Note:  Local  Objectives  are  addressing  solutions  that  are  considered  beneficial  for  specific  operating environments,  therefore  for which  a  clear widespread  commitment  has  not  been  expressed  yet.  They  are characterised with no deadline and voluntary applicability area. 

 

 

 

Page 71: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 59 Released Issue

 

ANNEXES 

 

ANNEX A ‐ Specialists involved in the LSSIP Process  

 

LSSIP Co‐ordination  

 

LSSIP Focal Points  Organisation  Name 

LSSIP National Focal Point for Czech Republic 

ANS CR  Tomáš TRŽICKÝ 

LSSIP Focal Point for NSA/CAA  CAA  Jaroslav PEKÁREK 

LSSIP Focal Point for ANSP  ANS CR  Martin LINDNER 

LSSIP Focal Point for Airport  Prague Airport  Miroslav ŠPÁK 

LSSIP Focal Point for Military  MoD  Miloslav BENEŠ 

LSSIP Focal Point for MoT  MoT  Zdeněk JELÍNEK 

LSSIP Focal Point for AAII  AAII  Stanislav SUCHÝ 

 

EUROCONTROL LSSIP Support 

 

Function  Directorate  Name 

LSSIP Contact Person for Czech Republic 

DPS/PEPR  Agnieszka DYBOWSKA 

    

Page 72: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 60 Released Issue

 

Implementation Objectives 

 

Implementation Objective 

EUROCONTROL PEPR Objective Coordinator 

EUROCONTROL Objective Owners 

National Stakeholder Specialist 

AOM13.1  A. DYBOWSKA  O. MROWICKI/ C. LUCCIOLI  Lumír HOVANČÍK (ANS CR) 

AOM19.1  O. ALFARO G. ACAMPORA /  

O. MROWICKI  

Lumír HOVANČÍK (ANS CR) 

AOM19.2  O. ALFARO G. ACAMPORA /  

O. MROWICKI  

Lumír HOVANČÍK (ANS CR) 

AOM19.3  O. ALFARO G. ACAMPORA /  

O. MROWICKI  

 

AOM21.1  A. DYBOWSKA  C. BRAIN  Václav VORÁČEK (ANS CR) 

AOM21.2  A. DYBOWSKA  C. BRAIN  Václav VORÁČEK (ANS CR) 

AOP04.1  P. VRANJKOVIC  R. GRAHAM  Jan KUBÍČEK (ANS CR) 

AOP04.2  P. VRANJKOVIC  R. GRAHAM  Jan KUBÍČEK (ANS CR) 

AOP05  F. ROOSELEER  M. BIRENHEIDE  (PRAGUE AIRPORT) 

AOP10  F. ROOSELEER  R. GRAHAM  Petr KUNC (ANS CR) 

AOP11  F. ROOSELEER  M. BIRENHEIDE  (PRAGUE AIRPORT) 

AOP12  P. VRANJKOVIC  R. GRAHAM  Jan KUBÍČEK (ANS CR) 

AOP13  P. VRANJKOVIC  R. GRAHAM   

AOP14  A. DYBOWSKA  R. GRAHAM / G. ASSIRE   

ATC02.8  F. ROOSELEER  S. DROZDOWSKI  Vladimír ČÍŽEK (ANS CR) 

ATC02.9  F. ROOSELEER  S. DROZDOWSKI  Vladimír ČÍŽEK (ANS CR) 

ATC07.1  L. DELL’ORTO  pending  Vladimír ČÍŽEK (ANS CR) 

ATC12.1  L. DELL’ORTO  pending  Vladimír ČÍŽEK (ANS CR) 

ATC15.1  L. DELL’ORTO  pending  Vladimír ČÍŽEK (ANS CR) 

ATC15.2  L. DELL’ORTO  P. HOP   

ATC17  L. DELL’ORTO  S. MORTON  Vladimír ČÍŽEK (ANS CR) 

ATC18  L. DELL’ORTO  I. PENDACHANSKI  Tomáš NAVRÁTIL (ANS CR) 

COM10  J. PINTO  Y. EYUBOGLU  Ivo PŘÍPLATA (ANS CR) 

COM11  J. PINTO  L. POPESCU  Milan DVOŘÁK (ANS CR) 

COM12  J. PINTO  W. JANSSENS  Martin JELÍNEK (ANS CR) 

ENV01  B. HILL  D. BRAIN  Petr KUNC (ANS CR) 

ENV02  B. HILL  S. MAHONY  (PRAGUE AIRPORT) 

ENV03  A‐P. FRANGOLHO  D. BRAIN   

FCM03  O. CIOARA C. BOUMAN/I. PENDACHANSKI 

Vladimír ČÍŽEK (ANS CR) 

FCM04.1  I. MARCETIC P. HOP/I. PENDACHANSKI  Lumír HOVANČÍK (ANS CR) 

FCM04.2  I. MARCETIC  P. HOP/I. PENDACHANSKI  Lumír HOVANČÍK (ANS CR) 

FCM05  O. CIOARA I. MENDES VIDEIRA/I. PENDACHANSKI 

Lumír HOVANČÍK (ANS CR) 

FCM06  F. ROOSELEER  P. HOP/I. PENDACHANSKI  Vladimír ČÍŽEK (ANS CR) 

Page 73: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 61 Released Issue

FCM08  O. CIOARA  K. BREIVIK/I. PENDACHANSKI   

INF07  A‐P. FRANGOLHO  A. PETROVSKY  Jiří LATIOK (ANS CR) 

ITY‐ACID  O. CIOARA pending Ivan UHLÍŘ (ANS CR)

ITY‐ADQ  A‐P. FRANGOLHO M. UNTERREINER Radek HODAČ (ANS CR)

ITY‐AGDL  B. HILL D. ISAAC Milan KORÁB (ANS CR)

ATY‐AGVCS2  B. HILL J. POUZET Martin LEHKÝ (ANS CR)

ITY‐FMTP  O. ALFARO L. POPESCU Vladimír ČÍŽEK (ANS CR)

ITY‐SPI  O. CIOARA  M. BORELY  Ivan UHLÍŘ (ANS CR) 

NAV03.1  I. MARCETIC  F. PAVLICEVIC  Tomáš DUKA (ANS CR) 

NAV03.2  I. MARCETIC  F. PAVLICEVIC  Tomáš DUKA (ANS CR) 

NAV10  I. MARCETIC  R. FARNWORTH  Tomáš DUKA (ANS CR) 

NAV12  I. MARCETIC  B. RABILLER / F. RIQUET    

SAF11  F. ROOSELEER  pending  (CAA) 

 

 

 

   

Page 74: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 62 Released Issue

ANNEX B ‐ National Stakeholders Organisation charts  

 

CZECH REPUBLIC AVIATION ORGANISATIONAL STRUCTURE 

The  overall  organisational  structure  of  the  aviation  regulation  in  the  Czech  Republic  is  represented  in  the following  

 

 

Figure:  Organisational structure of the Czech Republic Aviation Regulation 

   

Ministry of Defence 

GOVERNMENT 

Ministry of Transport (Civil Aviation Department) 

Air Accidents Investigation Institute 

Civil Aviation Authority 

 

Air Navigation Services  

of the Czech Republic 

Prague Airport 

Military Aviation Authority, Supervision and Inspection 

Division of MoD 

Institute of Aviation Medicine 

 

Other Airport Operators 

Other ATC Providers 

Civil Aircraft Operators 

Czech Air Force 

Air Force Development of the Capability Development and Planning Division ‐ MoD 

Page 75: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 63 Released Issue

CAA CR ESTABLISHMENT 

 

The  Civil  Aviation  Authority  of  the  Czech  Republic  was  established  by  the  Czech  Civil  Aviation  Act  as  a 

government agency  in charge of civil aviation. It  is subordinate to the Ministry of Transport. See also current 

detailed organisational structure at: http://www.caa.cz/authority/organisational‐structure‐1   

Spokesperson Management System Manager

Security Director Quality Auditor

Internal Quality Control Safety Inspector

Secretary of the CAA Director

Informatics Section

Economic Section

Payroll Accountant

Logistics Department

Flight Operations Security Section

Air Cargo Security Section

Security Department

AdministrativeFunctioning Section

Legal Section

Legal Department

Internal Servicesand Security Division Director

Secretary

Inspector Pilot Section

Flight Operations InspectionSection

Specialised Operations Section

Non-commercial OperationsSection

Ramp Inspections Section

Aircraft OperationsDepartment

Training OrganisationSupervising Section

Aicraft Register

Personnel ExaminationSection

Practical Skill and MedicalSection

Personnel LicensingDepartment

Parachuting Section

Flight Division Director

Secretary

Product CertificationSection

Aircraft Design Section

ProductionSection

Aircraft Certification andEngineering Department

Transport AircraftSection

Maintenance Section

Small Aircraft Section

Aircraft ContinuousAirworthiness Department

Technical Division Director

Secretary

Regulation Section

Unmanned AerialSystem Section

External Relations andSpecial Activities Department

Aerodromes Section

Unmanned AerialSystem Section

External Relations andSpecial Activities Department

Interoperability Section

Supervision Section

Development Manager

FAB Coordinator

Air Navigation ServicesDepartment

Operators Section

Aeronautical OperationsDivision Director

Director of the CAA

Page 76: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 64 Released Issue

AIR ACCIDENT INVESTIGATION INSTITUTE (AAII) 

 

The overall organisational chart of the AAII is shown in Figure below: 

 

Figure:  Organisational chart of the AAII 

Note: With regard to a new systematization by 1. 1. 2017. 

Page 77: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 65 Released Issue

Prague Airport Organisational Chart 

 

Page 78: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 66 Released Issue

SIMPLIFIED ORGANISATIONAL CHART OF THE MINISTRY OF TRANSPORT 

 

Minister of Transport 

 Transport Section 

Civil Aviation Department  

Air Operation, Technology and  

Development Division

Air Transport Division 

Aerodromes Infrastructure Division 

Page 79: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 67 Released Issue

SIMPLIFIED ORGANISATIONAL CHART OF ANS CR (as of January 1, 2018) 

Director General 

Safety Unit 

Operations Unit 

CNS/ATM Systems Operation Division 

    

ATM Division   

ATM Training and Business Unit 

Flight Inspection Section 

Business and Marketing Section 

ATM Training Section 

Finance and Administration Unit 

Central Logistics Section 

Audit and Investigation 

Finance  Section 

Human Resources Section 

Office of the Director General 

Strategy and Management Support 

ANS Planning and Development Division 

    

Area Control Navigation 

Services Section 

Approach and Aerodrome 

Control Services 

Regional Airport Air Navigation Services Section 

Aeronautical Telecommunications 

Services Centre 

Radar and Information Systems Centre 

NAVCOM Centre 

Air Navigation Services 

Methodology 

Project and Investments 

Implementation 

AIM Section 

Page 80: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 68 Released Issue

ANNEX C – Implementation Objectives’ Applicability  

Objective SESAR 

Key Feature 

ICAO ASBU 

B0 European ATM Masterplan Level 3 Applicability area 

AOM13.1  

‐ All ECAC States except Albania, Latvia, Luxembourg, Maastricht UAC and 

Moldova. 

AOM19.1  

B0‐FRTO All ECAC States except Armenia, FYROM, Malta, Luxembourg, and 

Moldova 

AOM19.2  

‐  All ECAC States except Armenia, Luxembourg and Moldova 

AOM19.3  

‐  All ECAC States except Armenia, Luxembourg and Moldova 

AOM21.1  

B0‐FRTO  25 ECAC States 

AOM21.2  

‐ All ECAC States except Azerbaijan, Belgium, Luxembourg and the 

Netherlands 

AOP04.1  

B0‐SURF  25 PCP airports, 22 non‐PCP airports 

AOP04.2  

B0‐SURF  25 PCP airports, 22 non‐PCP airports 

AOP05  

B0‐ACDM  25 PCP airports, 21 non‐PCP airports 

AOP10  

‐  16 PCP Airports 

AOP11  

‐  24 PCP airports, 15 non‐PCP airports 

AOP12  

‐  25 PCP airports 

AOP13  

‐  25 PCP airports 

AOP14  

‐  Local: Low to medium complexity aerodromes, subject to local needs 

ATC02.2    B0‐SNET Additional for ICAO ASBU monitoring: applicable all ECAC States that did 

not yet implement it 

ATC02.8  

B0‐SNET  All ECAC States except the Netherlands 

ATC02.9  

B0‐SNET  TMAs, according to local business needs 

ATC07.1  

B0‐RSEQ  23 PCP Airports, 8 non‐PCP airports 

ATC12.1  

‐  All ECAC States except Luxembourg 

ATC15.1 

 

 B0‐RSEQ 

EU States except Cyprus, Greece, Lithuania, Luxembourg, Malta, Slovak 

Republic, Slovenia. Plus: Bosnia and Herzegovina, Maastricht UAC, 

Norway, Switzerland, Turkey 

ATC15.2  

‐ ACCs within the extended AMAN horizon, including those adjacent to 

TMAs serving/associated to PCP airports 

ATC16    B0‐ACAS Additional for ICAO ASBU monitoring: applicable to all ECAC States that 

did not yet implement it 

ATC17  

B0‐FICE  All ECAC States except Ireland, Slovak Republic and Ukraine 

ATC18  

‐  Local: Subject to local needs and complexity 

COM10  

‐   All ECAC States 

COM11  

‐  All ECAC States 

Page 81: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 69 Released Issue

COM12 

 

 ‐ 

‐ Area 1 (ANSPs signatories of the NewPENS Common Procurement 

Agreement): 33 ANSPs 

‐ Area 2 (Other stakeholders): Stakeholders from all ECAC States not part 

of Area 1 

ENV01  

B0‐CDO  59 Airports 

ENV02  

‐  47 Airports 

ENV03  

B0‐CCO  Local: Aerodromes subject to local needs and complexity 

FCM01    B0‐NOPS Additional for ICAO ASBU monitoring: applicable to all ECAC States that 

did not yet implement it 

FCM03  

B0‐NOPS  All ECAC States 

FCM04.1  

B0‐NOPS Austria, Belgium, Croatia, Czech Republic, France, Germany, Italy, Poland, 

Spain, Switzerland 

FCM04.2  

B0‐NOPS  All EU+ States 

FCM05  

B0‐NOPS All ECAC States except Armenia, FYROM, Luxembourg, Maastricht UAC 

and Moldova 

FCM06  

B0‐NOPS  All EU+ States 

FCM07  

‐  All EU+ States 

FCM08  

‐  All ECAC States 

FCM09  

‐  All ECAC States 

INF04    B0‐DATM Additional for ICAO ASBU monitoring: applicable to all ECAC States that 

did not yet implement it 

INF07  

‐  All ECAC States except Maastricht UAC 

INF08.1  

‐  All EU+ States 

INF08.2  

‐  All EU+ States 

ITY‐ACID  

‐  All EU+ States 

ITY‐ADQ  

B0‐DATM  All EU+ States except FYROM, Georgia and Maastricht UAC 

ITY‐AGDL  

B0‐TBO  All EU+ States except Georgia, Luxembourg and Netherlands 

ITY‐AGVCS2  

‐  All EU+ States except Georgia and Moldova 

ITY‐COTR    B0‐FICE Additional for ICAO ASBU monitoring: applicable all EU+ States that did 

not yet implement it 

ITY‐FMTP  

B0‐FICE  All ECAC States 

ITY‐SPI  

B0‐ASUR  All EU+ States 

NAV03.1  

B0‐CDO,  

B0‐CCO All ECAC States except Luxembourg, Maastricht UAC and Slovak Republic 

NAV03.2  

‐ Mandatory for TMAs listed in section 1.2.1 of the Annex of the PCP 

Regulation. For all other ECAC TMAs, according to local business needs 

NAV10  

B0‐APTA  All ECAC States except Maastricht UAC 

NAV12  

‐  Local: TMAs subject to local needs and complexity 

SAF11  

‐  All ECAC States except Malta 

Page 82: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 70 Released Issue

 

Legend:  

 

 

Objective’s link to SESAR Key Feature: 

 

Optimised ATM Network Services  

High Performing Airport Operations 

 

Advanced Air Traffic Services  

Enabling Aviation Infrastructure 

 

   

Page 83: Local Single Sky ImPlementation LSSIP 2017 - CZECH REPUBLIC · LSSIP Year 2017 Czech Republic Released Issue Document Title LSSIP Year 2017 for Czech Republic Infocentre Reference

LSSIP Year 2017 Czech Republic 71 Released Issue

ANNEX D ‐ Glossary of Abbreviations  

This Annex mostly shows only the Abbreviations that are specific to the LSSIP Czech Republic.  

Other  general  abbreviations  are  in  the  Acronyms  and  Abbreviations  document  in http://www.eurocontrol.int/articles/glossaries 

 

Term  Description 

AAII   Air Accidents Investigation Institute 

AF  ATM Functionality 

AHA  Active Hazard Assessment 

Airport CDM  Airport Collaborative Decision Making 

ANS CR  Air Navigation Services of the Czech Republic 

A‐SMGCS  Advanced Surface Movement Guidance & Control System 

CAA   Civil Aviation Authority 

CAD  Civil Aviation Department (MoT) 

CHMI  Czech Hydrometeorological Institute 

CDPD The Air Force Development of the Capability Development and Planning Division MoD 

CTR  Control Area 

DFL  Division Flight Level 

FT  Fast Track 

IATCC  Integrated Air Traffic Control Centre 

MAA  Military Aviation Authority, Supervision and Inspection Division of MoD 

MCTR   Military CTR 

MoD  Ministry of Defence 

MoT  Ministry of Transport 

MTMA  Military TMA 

NOP  Network Operation Plan 

NSA  National Supervisory Authority 

PCP  Pilot Common Project 

PDP  Preliminary Deployment Programme 

RET  Rapid Exit Taxiway 

SRA  Security Restricted Area 

S‐AF  Sub ATM Functionality 

TWR  Tower 

UIR  Upper Flight Information Region