LIL HCM Implementation Plan

download LIL HCM Implementation Plan

of 8

Transcript of LIL HCM Implementation Plan

  • 7/28/2019 LIL HCM Implementation Plan

    1/8

    ID Task Name Duration Start Finish

    1 LIL_HCM Implementation 98.88 days Fri 1/1/10 Sat 5/1/10

    2 Project Preparation 1 day Fri 1/1/10 Fri 1/1/10

    3 Project Kickoff 1 day Fri 1/1/10 Fri 1/1/10

    4 Kickoff Presentatin 1 day Fri 1/1/10 Fri 1/1/10

    5 Client Familiarization 1 day Fri 1/1/10 Fri 1/1/10

    6 System Access 1 day Fri 1/1/10 Fri 1/1/10

    7 Blueprint Phase 18 days Mon 1/4/10 Thu 1/28/10

    8 Business Process workshops 12 days Mon 1/4/10 Wed 1/20/10

    9 Organization Structure workshop and confirmation 2 days Mon 1/4/10 Wed 1/6/10

    10 Business Process reviews and Confirmation 10 days Wed 1/6/10 Wed 1/20/10

    11 Gap Analysis 10 days Wed 1/6/10 Wed 1/20/10

    12 Master Data Workshop 2 days Wed 1/20/10 Fri 1/22/1013 Freeze Master Data Formats 2 days Wed 1/20/10 Fri 1/22/10

    14 Review and sign off Business Blue Print 4 days Fri 1/22/10 Thu 1/28/10

    15 Review and Incorporate Changes 3 days Fri 1/22/10 Wed 1/27/10

    16 Sign off 1 day Wed 1/27/10 Thu 1/28/10

    17 Realization Phase 34 days Thu 1/28/10 Wed 3/10/10

    18 System Configuration and Development 20 days Thu 1/28/10 Mon 2/22/10

    19 System Configuration 20 days Thu 1/28/10 Mon 2/22/10

    20 Develop Customer scripts, conversions & Enchancements 20 days Thu 1/28/10 Mon 2/22/10

    21 Aut hor izati on Matrix 2 days Mon 2/22/10 Wed 2/24/10

    22 Freeze Authorization Matrix 2 days Mon 2/22/10 Wed 2/24/10

    23 Unit Testing 4 days Wed 2/24/10 Mon 3/1/10

    24 Conduct Unit testing 2 days Wed 2/24/10 Fri 2/26/10

    25 Sign off Unit testing 2 days Fri 2/26/10 Mon 3/1/10

    26 Master Data validation and collection 3 days Mon 3/1/10 Thu 3/4/10

    27 Verify and Freeze Master Data Collection 3 days Mon 3/1/10 Thu 3/4/10

    28 Integration Testing 4 days Thu 3/4/10 Tue 3/9/10

    29 Transport requests to (DEV or QAS) 1 day Thu 3/4/10 Fri 3/5/10

    30 Upload Master Data 1 day Thu 3/4/10 Fri 3/5/10

    31 Conduct Integration Testing 3 days Fri 3/5/10 Tue 3/9/10

    32 Review and Sign off Test results 3 days Fri 3/5/10 Tue 3/9/10

    W T F S S M T W TJ an 3, '10

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 1

    Project: Project1

    Date: Mon 1/4/10

  • 7/28/2019 LIL HCM Implementation Plan

    2/8

    ID Task Name Duration Start Finish

    33 Review and Sign off Realization 1 day Tue 3/9/10 Wed 3/10/10

    34 Sign off realization Phase 1 day Tue 3/9/10 Wed 3/10/10

    35 Final Preparation 16 days Wed 3/10/10 Tue 3/30/10

    36 End User Training 5 days Wed 3/10/10 Wed 3/17/10

    37 Conduct End User Training Program 5 days Wed 3/10/10 Wed 3/17/10

    38 Prepare for Go Live 6 days Wed 3/17/10 Wed 3/24/10

    39 Prepare Cut over Templates & strategy 4 days Wed 3/17/10 Mon 3/22/10

    40 Transport Requests to Production 1 day Wed 3/17/10 Thu 3/18/10

    41 Upload Master Data 2 days Mon 3/22/10 Wed 3/24/10

    42 Cut Over 5 days Wed 3/24/10 Tue 3/30/10

    43 Close Current System 2 days Wed 3/24/10 Fri 3/26/10

    44 Upload Cutover Data 3 days Fri 3/26/10 Tue 3/30/1045 Go-live & Support 28 days Tue 3/30/10 Sat 5/1/10

    46 Go Live 2 days Tue 3/30/10 Thu 4/1/10

    47 Go Live Sign off 2 days Tue 3/30/10 Thu 4/1/10

    48 Post Production Support 25 days Thu 4/1/10 Fri 4/30/10

    49 Resolve Day to Day issues 25 days Thu 4/1/10 Fri 4/30/10

    50 Complete all pending issues 25 days Thu 4/1/10 Fri 4/30/10

    51 Review and Sign off 1 day Fri 4/30/10 Sat 5/1/10

    52 Signoff and Project Closure 1 day Fri 4/30/10 Sat 5/1/10

    W T F S S M T W TJ an 3, '10

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 2

    Project: Project1

    Date: Mon 1/4/10

  • 7/28/2019 LIL HCM Implementation Plan

    3/8

    F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S MJ an 10, '10 J an 17, '10 J an 24, '10 J an 31, '10 Feb 7, '10 Feb 14, '

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 3

    Project: Project1

    Date: Mon 1/4/10

  • 7/28/2019 LIL HCM Implementation Plan

    4/8

  • 7/28/2019 LIL HCM Implementation Plan

    5/8

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F0 Feb 21, '10 Feb 28, '10 Mar 7, '10 Mar 14, '10 Mar 21, '10

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 5

    Project: Project1Date: Mon 1/4/10

  • 7/28/2019 LIL HCM Implementation Plan

    6/8

    T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F0 Feb 21, '10 Feb 28, '10 Mar 7, '10 Mar 14, '10 Mar 21, '10

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 6

    Project: Project1Date: Mon 1/4/10

  • 7/28/2019 LIL HCM Implementation Plan

    7/8

    S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TMar 28, '10 Apr 4, '10 Apr 11, '10 Apr 18, '10 Apr 25, '10 May 2, '10

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 7

    Project: Project1Date: Mon 1/4/10

  • 7/28/2019 LIL HCM Implementation Plan

    8/8

    S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TMar 28, '10 Apr 4, '10 Apr 11, '10 Apr 18, '10 Apr 25, '10 May 2, '10

    Task

    Split

    Progress

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Deadline

    Page 8

    Project: Project1Date: Mon 1/4/10