• Program Manual Updateso 1 for 1 Fixture Replacement
o 1 for 1 Retrofit Kit Replacement
o Lighting Controls
• Con Edison Lighting Audit Templateo General Information
o Existing and Proposed Lighting Equipment
o Lighting Controls
o Overview
• Con Edison Electric Toolo Lighting – By Fixture Code
o Lighting Controls – Interior
o Lighting Controls – Bi-Level
• Incentive Navigatoro Methods of submitting lighting project
o Uploading the Con Edison Excel Tool
o Creating an Estimate
o Converting Your Estimate to an Application
Table of Content
2
Program Manual Update – 1 for 1 Fixture Replacement
DLC/Energy Star Category Existing Equipment Incentive
Per Fixture
ENERGY STAR Downlights Fixture w. Screw-In or Pin-Based Lamps
Screw or Pin Base - Incandescent Fixture
≤60W $10
Screw or Pin Base - CFL Fixture ≤32W
Screw or Pin Base - Incandescent Fixture >60W $25
Screw or Pin Base - CFL Fixture >32W
Track or Mono-point Luminaires Incandescent Track or Mono Point
Luminaires $20
Direct Linear Ambient Luminaires
Linear Ambient Luminaires w/ Indirect Components
1-Lamp Fluorescent Fixture $10
2-Lamp Fluorescent Fixture $15
1x4 Luminaires for Ambient Lighting of Interior Commercial Spaces
1x4 Troffer - 1 Lamp Fluorescent Fixture $10
1x4 Troffer - 2 Lamp Fluorescent Fixture $15
2x2 Luminaires for Ambient Lighting of Interior Commercial Spaces
2x2 Troffer - 2 Lamp Fluorescent Fixture $10
2x4 Luminaires for Ambient Lighting of Interior Commercial Spaces
2x4 Troffer - 2 Lamp Fluorescent Fixture $15
2x4 Troffer - 3 Lamp Fluorescent Fixture $20
2x4 Troffer - 4 Lamp Fluorescent Fixture $30
High Bay Luminaires for Commercial and Industrial Buildings
Low Bay Luminaires for Commercial
and Industrial Buildings
High Bay Aisle Luminaires
T5 HighBay - 2 Lamp Fluorescent Fixture $25
T5 HighBay - 3 Lamp Fluorescent Fixture $50
T5 HighBay - 4 Lamp Fluorescent Fixture $75
T8 HighBay - 4 Lamp Fluorescent Fixture $35
T8 HighBay - 6 Lamp Fluorescent Fixture $50
T8 HighBay - 8 Lamp Fluorescent Fixture $75
HID Interior Fixture <250W $30
HID Interior Fixture 250W to 399W $60
HID Interior Fixture 400W to 999W $90
HID Interior Fixture ≥1000W $100
Bollards
Landscape/Accent Flood and Spot Luminaires
Architectural Flood and Spot Luminaires
HID Exterior Fixture ≤100W $25
HID Exterior Fixture 101 - 249 Watts $70
HID Exterior Fixture ≥ 250 Watts $100
DLC Category Existing Equipment Incentive
Per Fixture
Parking Garage Luminaires
Fuel Pump Canopy Luminaires
HID Parking Garage Fixture ≤100W $75
HID Parking Garage Fixture 101W to 249W $100
HID Parking Garage Fixture ≥250W $160
Outdoor Pole/Arm-Mounted Area and Roadway Luminaires
Outdoor Pole/Arm-Mounted Decorative
Luminaires
HID Pole Fixture ≤100W $20
HID Pole Fixture 101W to 249W $60
HID Pole Fixture 250W to 399W $80
HID Pole Fixture 400W to 999W $100
HID Pole Fixture ≥1000W $120
Outdoor Full-Cutoff Wall-Mounted Area Luminaires
Outdoor Non-Cutoff and Semi-Cutoff
Wall-Mounted Area Luminaires
HID Exterior Wall Pack Fixture ≤100W $50
HID Exterior Wall Pack Fixture 101W to 399W
$90
HID Exterior Wall Pack Fixture ≥400W $135
LED Exit Sign Incandescent or CFL Exit Sign $10
3
Program Manual Update – 1 for 1 Retrofit Kit Replacement
DLC Category Existing Equipment
Retrofit Kit for ENERGY STAR Downlights w. Screw-In or Pin-Based Lamps
Screw or Pin Base - Incandescent Fixture ≤60W
Screw or Pin Base - CFL Fixture ≤32W
Screw or Pin Base - Incandescent Fixture >60W
Screw or Pin Base - CFL Fixture >32W
Retrofit Kit for 1x4 Luminaires for Ambient Lighting of Interior Commercial Spaces
1x4 Troffer - 1 Lamp Fluorescent Fixture
1x4 Troffer - 2 Lamp Fluorescent Fixture
Retrofit Kit for 2x2 Luminaires for Ambient Lighting of Interior Commercial Spaces
2x2 Troffer - 2 Lamp Fluorescent Fixture
Retrofit Kit for 2x4 Luminaires for Ambient Lighting of Interior Commercial Spaces
2x4 Troffer - 2 Lamp Fluorescent Fixture
2x4 Troffer - 3 Lamp Fluorescent Fixture
2x4 Troffer - 4 Lamp Fluorescent Fixture
Retrofit Kit for High Bay Luminaires for Commercial and Industrial Buildings
Retrofit Kit for Low Bay Luminaires for Commercial and Industrial Buildings
HID Interior Fixture <250W
HID Interior Fixture 250W to 399W
HID Interior Fixture 400W to 999W
HID Interior Fixture ≥1000W
DLC Category Existing Equipment
Retrofit Kit for Parking Garage Luminaires
Retrofit Kit for Fuel Pump Canopy Luminaires
HID Parking Garage Fixture ≤100W
HID Parking Garage Fixture 101W to 249W
HID Parking Garage Fixture ≥250W
Retrofit Kit for Outdoor Pole/Arm-Mounted Area and Roadway Luminaires
Retrofit Kit for Outdoor Pole/Arm-Mounted
Decorative Luminaires
HID Pole Fixture ≤100W
HID Pole Fixture 101W to 249W
HID Pole Fixture 250W to 399W
HID Pole Fixture 400W to 999W
HID Pole Fixture ≥1000W
Retrofit Kit for Outdoor Full-Cutoff Wall-Mounted Area Luminaires
HID Exterior Wall Pack Fixture ≤100W
HID Exterior Wall Pack Fixture 101W to 399W
HID Exterior Wall Pack Fixture ≥400W
4
Program Manual Update – Lighting Controls
Measure Application Eligibility Criteria Incentive Unit
Daylight Dimming, Daylight Stepped, or Occupancy
Interior Spaces
Existing Switched Control Only
$35 Sensor
Networked Controls Interior Spaces
Existing Switched Control Only
$50 Per
controlled fixture
5
Lighting Project Submission Change
Note: These changes only apply to Retrofit and not LPD
Before After
• Tedious data entry – entering
measures line by line in the Con
Edison Electric Tool, regardless of
location, measure type etc.…
• Spec Sheets
• DLC Screenshots
• Submit lighting audit
• Submit your own unlocked
Excel/csv file OR
• Submit the Con Edison
Lighting Audit Template.
• Spec Sheets still needed
• DLC Screenshots still needed
• Con Edison Electric Tool acts as a
summary of lighting audit
6
Con Edison Lighting Audit Template
7
Con Edison Lighting Audit TemplateGeneral Information(Part 1 of 4) Please enter these fields.
They can be copied into
the Electric Tool
REMINDER:
Please do not
leave any of
the fields blank
REQUIRED!
8
Con Edison Lighting Audit TemplateExisting/Proposed Lighting Equipment(Part 2 of 4)
Quantity, a description of
the fixture type, existing
wattage, and reported hours
The quantity,
make and model
of the DLC fixture
you are installing
If hours are
unknown,
please enter
"Sector"
The proposed wattage
that matches the fixture
spec sheet.
9
Con Edison Lighting Audit TemplateLighting Controls(Part 3 of 4)
Total Watts Controlled
• Automatically sums
number of fixtures
controlled to the
proposed wattage
How many fixtures will be
controlled by the sensor?
• For the respective row,
provide the total
quantity that will be
controlled
If So, What Type?
• Options are:
i. Occupancy
ii. Dimming
iii. Stepped
iv. Network
v. Bi-Level
Will sensors be
added?
(Select Yes or
No)
10
Con Edison Lighting Audit TemplateOverview(Part 4 of 4)
PC audit lighting template
will be submitted only as
an unlock excel/csv file
IMPORTANT!
11
Con Edison Electric Tool
Lighting By Fixture Code
12
Con Edison Electric ToolLighting – By Fixture CodeFacility CharacteristicsPart (1/8)
Here you can enter a master
Building Type, HVAC Type,
and Heating Fuel Type. This
will auto populate each
measure line in the tab.
Here you can enter
whether the hours of
the facility are reported
or sector and you can
enter the full load
hours.
13
Con Edison Electric ToolLighting – By Fixture CodePart (2/8)
Lighting Type possible
choices are:
• LED_Fixture
• LED_Retrofit
DLC Category must match
what is on the proposed lighting
DLC screenshot that is required
in application submittal.
Existing Equipment is a
filtered dropdown to the
DLC category, these are
available in the program
manual
Location
Description is a
summary, please
enter the rows it
matches on the
lighting audit
submitted with the
tool.
14
Con Edison Electric ToolLighting – By Fixture CodePart (3/8)
Building Type is auto populated
from the master drop down;
however, it can be modified. If
the same DLC fixture
replacement has different
building types, they should be
separate lines.
HVAC Type is auto populated from the
master drop down. Can be modified. If
the same DLC fixture replacement has
different HVAC types, they should be
separate lines. (exterior and mechanical
spaces should select "No Temperature
Control System")
Existing watts per unit is one of
the defining columns that should
segregate measures. If the same
DLC fixture replacement has
different existing wattages, they
should be separate lines.
15
Reported or Sector
• Sector hours defaults to NYS
TRM value for the building type.
• Reported hours shall match the
lighting audit provided.
• If the same DLC fixture
replacement has different hours,
they should be separate lines.
Heating Fuel
Type is auto
populated from
master drop
down.
Con Edison Electric ToolLighting – By Fixture CodePart (4/8)
16
Con Edison Electric ToolLighting – By Fixture CodePart (5/8)
Proposed Make is
obtained from spec
sheet (Must be
highlighted on Spec
Sheet)
Proposed Model is
obtained from spec
sheet (Must be
highlighted on Spec
Sheet)
Material Cost should be the
sum of all fixtures in measure
line
17
Labor Cost
should be
summation of
all fixtures in
measure line
Total Cost is
automatically
calculated
Notes: Any
additional
information for
review team
Con Edison Electric ToolLighting – By Fixture CodePart (6/8)
18
Con Edison Electric ToolLighting – By Fixture CodePart (7/8)
Sample of Lighting – By Fixture Code (1)
19
Con Edison Electric ToolLighting – By Fixture CodePart (8/8)
Sample of Lighting – By Fixture Code (2)
20
Con Edison Electric Tool
Lighting Controls -Interior
21
Con Edison Electric ToolLighting Controls – Interior
Part (1/5)
Sensor Type available options are:
• Daylight Control
• Occupancy Control
• Networked Control
Location Description is a
sum of rows in audit tool
that are applicable to the
measure
22
Con Edison Electric ToolLighting Controls – InteriorPart (2/5)
Sensor Quantity
is the total
number of
sensors to be used
in the locations
Total Watts Controlled is a
summation of all watts
controlled by the sensors
Building Type is a Dropdown
and matches lighting - by fixture
code tab
23
Con Edison Electric ToolLighting Controls – InteriorPart (3/5)
HVAC Type has a dropdown list and
matches lighting - by fixture code tab
Reported or Sector
• Sector hours defaults to
NYS TRM value for the
building type.
• Reported hours shall match
the lighting audit provided.
• If the same sensor add-on
has different hours, they
should be separate lines.
Heating Fuel Type has a
dropdown list and matches
lighting - by fixture code tab
24
Material Cost should
be summation of all
fixtures in measure line
Labor Cost should
be summation of all
fixtures in measure
line
Estimated
Incentive will
be tied to sensor
incentive
Con Edison Electric ToolLighting Controls – Interior
Part (4/5)
25
Con Edison Electric ToolLighting Controls – Interior
Part (5/5)
Sample of Lighting Controls - Interior
26
Con Edison Electric Tool
Lighting Controls –Bi-Level
27
Con Edison Electric ToolLighting Controls – Bi-level
Part (1/5)
Proposed Measure is a dropdown of these
available measures:
Lighting Control - Bi-Level Stairwell
Lighting
Lighting Control - Bi-Level Corridor
Lighting
Bi-Level Lighting - Parking Lot (with
varying wattage)
Bi-Level Lighting - Parking Garage
(with varying wattage)
Location Description is a
summation of rows in
audit tool that are
applicable to the measureQuantity is the total
number of fixtures for
the measure
28
Con Edison Electric ToolLighting Controls – Bi-level
Part (2/5)
Watts Existing is a baseline
wattage in the tool. If the same
Bi-level fixture replacement has
different existing wattages, they
should be separate lines.
Low-Power Factor
is user submitted, if
plant, default will be
used
Building Type is a
dropdown menu and
matches lighting - by
fixture code tab
29
Con Edison Electric ToolLighting Controls – Bi-level
Part (3/5)
Material Cost
should be summation
of all fixtures in
measure line
Labor Cost should
be summation of all
fixtures in measure
line
Estimated
Incentive will be
tied to sensor
incentive
Notes: Any additional
information for review team
30
Con Edison Electric ToolLighting Controls – Bi-Level
Part (4/5)
Sample of Lighting Controls - Bi-Level (1)
31
Con Edison Electric ToolLighting Controls – Bi-Level
Part (5/5)
Sample of Lighting Controls - Bi-Level (2)
32
Lighting Audit Summation in the CE Tool
33
Con Edison Incentive Navigator
34
1. Uploading the Con Edison Excel Tool
2. Using the Estimates Calculator
35
Con Edison Incentive NavigatorMethods to submit lighting project
1. Start the project application submission process by clicking on Programs,
then click on Commercial 2019
2. Complete the first six steps of the project application, then skip the
measures page.
36
Con Edison Incentive NavigatorUploading the Con Edison Excel ToolPart (1/2)
3. Attach the excel tool in the attachments
page
4. Submit the project application
37
Con Edison Incentive NavigatorUploading the Con Edison Excel ToolPart (2/2)
Creating an Estimate
38
Con Edison Incentive NavigatorCreating an Estimate - Dashboard
Part (1/5)
39
After clicking on Estimates
Calculator in the primary navigation
you will be brought to the
Dashboard. Here you will be able to
start a new estimate, as well as
view information about and edit
recent estimates.
Create a new estimate by clicking
on the button labeled “Create New
Estimate”.
Con Edison Incentive NavigatorCreating an Estimate – Choosing Building Type & HVAC Type
Part (2/5)
40
The next question is the type of
building used.
Click on the input for a dropdown of
the available Building Type.
1.
1.
The next question is the type of
HVAC system used.
Select the primary HVAC Type
from the dropdown menu.
Once selected, click Continue to
Measure Selection
1.
2.
Con Edison Incentive NavigatorCreating an Estimate – Selecting The Measure
Part (3/5)1. Select the Category Type from the dropdown
2. Based on the Category, another dropdown will
pop up with the Equipment Type. Select your
equipment type.
3. When you have selected your Equipment Type,
click Add This Measure.
When you have selected
all of your Equipment
Types, click Continue
with selected measures.
Con Edison Incentive NavigatorCreating an Estimate – Measure Parameters
Part (4/5)
1.2.
Next you will be prompted
to answer some questions
around the parameters of
your measure.
The questions will vary
based on the particular
measure. When all inputs
are populated, the View
Summary button will
become active.
Con Edison Incentive NavigatorCreating an Estimate – Summary Page
Part (5/5)
The Project Summary page displays
incentives, savings, and simple payback.
Below you can see the details of the
estimate.
1. To add another measure to this
proposal, click add measure.
2. To edit a measure, click “…” on the
respective measure card.
Once verifying that all of your project
information is accurate, click
Proceed To The Application.
Converting Your Estimate to an Application
44
Con Edison Incentive NavigatorConverting your estimate to an application – Checking customer eligibility
Part (1/5)
In order to submit a project, you must first confirm whether or not the customer
is eligible for the program.
1. 2. 3.
Note: The continue button will
redirect you to the Project
Application
Con Edison Incentive NavigatorConverting your estimate to an application – Measures Page
Part (2/5)
After completing the initial steps of
the project application you will
arrive at the measures page.
Initially you will see a list of all
program measures. Filter these by
choosing the option “Show Only
Selected”.
You’ll now see the measures you
created previously in the
Estimates Calculator.
Con Edison Incentive NavigatorConverting your estimate to an application – Measures Page
Part (3/5)Here are the measures that you
previously selected while creating your
estimate.
The information you entered while
creating the estimate has been auto
populated; however, there are fields that
still need to be populated such as:
• Make and Model
• Measure Location (This is a
summary, please enter the
rows that the measure appears
on the lighting audit submitted.)
• Cost – You are able to modify
these fields.
After confirming that the measure
information is accurate, press
Save & Next in order to complete the
project applicationNote: The existing model field is
a field that is automatically
populated.
Con Edison Incentive NavigatorConverting your estimate to an application – Attachments Page
Part (4/5)
In the attachments page,
you will upload all necessary
documents for the project
application.
Note:
1. The Customer
Proposal field is where
you will upload the
Lighting Audit Template
2. You can attach the
Con Edison Electric
Tool in the Electric Tool
attachment line and
skip the measures
page in lieu of using
the estimates
calculator
Con Edison Incentive NavigatorConverting your estimate to an application – Submitting the Project Application
Part (5/5)
Click Send Application for
eSignature to submit the
Project Application.
Clicking this link will produce a
copy of the application with all
of the data entered throughout
the application process filled in
Schedule you Pre Inspection
Want to learn more
about the Incentive
Navigator?
Read our
Reference Guide51
• Main Objective: Simplify the process of submitting a lighting project.
• Con Edison provides lighting audit template OR contractor can use their own as long as it has
these required fields:
• Floor
• Interior or Exterior?
• Conditioned/Unconditioned
• Location
• Existing Lighting Equipment
• Proposed Lighting Equipment
• For every LED measure that is under the same make and model, HVAC Type and existing
wattage, the Contractor will aggregate the same LED product into one line in the Con Edison
lighting tool.
Note: Location must match rows of audit
• Lighting Projects are easily submitted via the Incentive Navigator. Projects can be submitted
via the Estimates Calculator OR by uploading the Con Edison Electric Tool
• All C&I projects must be submitted via Incentive Navigator starting August 1st 2019
Summary
52
Q&A
53
Upcoming Events and Webinars
•Wednesday July 31st @ Building Energy Exchange, Inc.
Attending in person? REGISTER HERE Password:
ConEdForum2019
Attending Via Webinar? REGISTER HERE
• Incentive Navigator Training Webinars will take place on
August 15th and August 29th
54
55
Thank You!
C&I Inquiries Email
Website
ConEd.com/Commercial
Incentive Navigator
IncentiveNavigator.coned.com