Lecture Slides CPE 676_Introduction to Equipment

download Lecture Slides CPE 676_Introduction to Equipment

of 38

Transcript of Lecture Slides CPE 676_Introduction to Equipment

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    1/38

    REFINERY ANDPETROCHEMICAL

    EQUIPMENT(CPE 671)

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    2/38

    COURSE OVERVIEW :

    REFINERY AND PETROCHEMICAL

    EQUIPMENT (CPE 671)

    Equipment related to refinery and

    petrochemical processes

    Conception of the overall plant and

    the equipment design

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    3/38

    INTRODUCTION

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    4/38

    INTRODUCTION

    Lesson objectives :

    By the end of the class, the students are

    expected to be able :

    to identify the necessary and the most appropriate

    equipment for refinery and petrochemical plant.

    to understand the importance of safety in plantoperation and equipment.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    5/38

    INTRODUCTION

    What are the petrochemical plants that are

    available in Malaysia ?

    ..can you name some?

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    6/38

    Petrochemical Plants in Pasir Gudang,

    Johor

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    7/38

    Petrochemical Plants in Kertih,Terengganu

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    8/38

    Petrochemical Plants in Bintulu

    Sarawak

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    9/38

    Petrochemical Plants in Gebeng,Pahang

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    10/38

    Major equipment in refinery andpetrochemical plant

    1. Heat exchange equipment :

    examples : heat exchanger, fired heaters,

    air-cooled exchangers, condenser,

    reboiler

    - what are the fundamentals

    of heat transfer?

    - basic heat transfer relations ??

    phase change

    no phase change

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    11/38

    Examples of common equipment inrefinery and petrochemical plant

    2. Separator Equipment

    fractionators (distillation column), absorbers (packed

    column), scrubber, vapor-liquid separator (knockout

    drum/ flash drum, knock-out pot, compressorsuction drum or compressor inlet drum), filterseparator, fixed bed separator.

    what are the fundamentals of

    separation process?

    types of phases

    boiling point of

    component

    relative volatility

    pressure difference

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    12/38

    Examples of common equipment inrefinery and petrochemical pant

    3. Reactor

    stirred tanks, packed tubes or vessels,

    shell-and-tube devices or highly specialized

    configurations (specially fabricated)

    what are the fundamentals of

    reaction process?

    Chemical kinetics

    Stoichiometry of theparticipating reactions

    Heats of reaction,

    equilibrium data,

    rate of reaction,

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    13/38

    Examples of common equipment inrefinery and petrochemical plant

    4. Transport and storage of fluids

    - pumps

    - compressors

    - storage tanks

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    14/38

    Why accidents happen??

    Accidents in petrochemical industry can be

    due to..

    poorly designed,

    poorly operated, or

    poorly maintained

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    15/38

    Poorly designed: A stripper columncollapsed.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    16/38

    close-up of collapsed strippercolumn..

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    17/38

    Why??Due to improperly protected distillation system

    the situation..

    Column was flooded with water.

    Drain the water by pumping it

    out

    thus creating vacuum condition

    Vacuum relief devices are notoriginally provided on the stripper

    Corrective method

    Installed vacuum breakers at the

    top of the column

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    18/38

    Vacuum relief devices: A pressure reliefdevice which is designed to allow fluid toenter a pressure vessel in order to avoid

    extreme internal vacuum. Vacuum breaker: A device used to

    relieve a vacuum formed in a water

    supply line to prevent backflow. Alsoknown as backflow preventer.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    19/38

    Poorly operated: Furnace temperaturesafeguard is altereda major fire

    erupted

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    20/38

    a tube in furnace ruptured due to

    overheating :

    1800 gallons (6800L) of combustible

    heat transfer fluid spilled and burned

    intensively.

    Witnesses stated flames were over

    50-ft. (15m) high in approximately fiveseconds after fire started.

    in 25 minutes, four-level of structures

    and associated process equipment

    were damaged.

    estimated loss :

    > USD 1.5 mill

    property damageUSD 4 mill - business interruption

    Situation..

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    21/38

    What happen ?

    The heater was designed to automatically

    shutdown and alarm in the control room

    in response to high heat-transfer oil pressure,

    high tube-wall temperature, low-pressure fuel

    gas, or flame failure.

    The shutdown setpoint was found to have

    been mistakenly raised to the maximum of

    the instrument's setpoint range, or 1,600 F

    (870 C).

    The tube metal high-temperature alarm

    should have been fixed at 850 F(454 C ).

    The limited burner shutdown instrumentation had not been properly inspected and

    tested to ensure the necessary high degree of reliability.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    22/38

    Poorly designed material: Wrongmaterial.

    Caustic soda leaks due to an improper gasket used.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    23/38

    Molten caustic soda at about 700oF(370oC) sprayed and dripped for about2.5 hours from elevated equipment in a

    well maintained unit. The blistering hot caustic soda leak

    discovered during the day shift - melted

    insulation on wiring and destroyedplastic electrical junction boxes andinstrument control boxes.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    24/38

    The situation was inadvertently createdwhen someone installed a compressedasbestos gasket (the nearly universal

    gasket for this chemical complex at thattime) on a thermocouple flange in thevapor space.

    Specifications dictated a metallic nickelgasket, but the compresses asbestoswas installed in error.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    25/38

    Estimated 15 tons (13,600 kg) of causticsoda (about 98- percent strength) leaked out

    of the concentrator.

    It cost about USD $40,000 to clean up and

    recover from the damages. Luckily, there

    were no injuries or environmental insults.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    26/38

    Poorly designed material: Anothercostly gasket error

    A serious oil refinery resulted from theinstallation of the wrong gasket on a heatexchanger.

    The unit was operating normally, processing avery flammable naphtha for about six weekfollowing an outage in which the heat

    exchangers were clean and tested A spiral-wound metal asbestos gasket was

    required by specification, but a compressed

    asbestos gasket was installed.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    27/38

    The gasket failed causing a leakfollowed by a fire.

    The heat from the initial fire caused anadjacent hydrogen exchanger flange toopen.

    Vapors flashed and impinged on an 18-inch (46cm) hydrogen-oil line which thenruptured.

    This piping failure released oil andhydrogen under 185 psig (1275kPa/12.6 atm) pressure.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    28/38

    The fire was brought under control afterabout two hours, but it was allowed toburn another hour and twenty minutes to

    consume the remaining fuel. The fire damages affected the electrical

    and instrument systems, piping and

    structural steel equipment.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    29/38

    Corrective action/ counter measure

    Preventive measures included a review ofgasket installation and purchasespecification procedures.

    Drawings appropriate for turnaround workwere developed to conform to new facilitypractices and have flange ratings marked.

    A retaining program covering gasket

    installation procedures for craftsmen wasconducted.

    Purchasing specifications for gasket now

    require color coding.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    30/38

    Flanges gasket

    In some plants three or four types of gasket

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    31/38

    In some plants, three or four types of gasketservices are needed where previously all pressurehandled with compressed asbestos-type gaskets.

    For high temperature applications the relativelyexpensive flexible graphite-type gaskets can beused.

    For a wide variety of process services, such aspetroleum-based solvents, oxygen, and chlorine,an expensive Teflon-like gasket may be required.

    Today, there exists a serious need to spendsufficient time to educate all maintenancepersonnel on details of gasket selection,installation, and the limitations of each type of

    gasket.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    32/38

    A water drain line is altered.a reactor exploded

    A supervisor of a solvents plant was concerned about trace

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    33/38

    A supervisor of a solvents plant was concerned about traceemissions of heat transfer fluid from a small diameter waterdrain line.

    He, no doubt, felt that with just about 30 ft, (9m) of small1.5 inch (3.8cm) piping, a couple of valves, and a smallconical bottom tank, this heat transfer fluid could berecovered.

    The aim was to reduce pollution potentials and wastewatertreatment costs.

    The supervisor probably only focused on one area ofconcern. However, this small change in just a cooling

    water system contributed to the destruction of a 110 psig(760 kPa) rated 9ft (2.3m) in diameter pressure vessel.

    A short-lived fire ensued. The severe overpressuredamage to this highly engineered nickel-clad reactor

    resulted in over $500,000 in property damages.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    34/38

    A water drain line is altered.a reactor exploded

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    35/38

    The modification involved the rerouting

    of the discharge water from thebarometric condenser .

    Rather than being discharged intoachemical sewer via a sump, the waterstream had been routed to a hopper thatallowed the entrained heat transfer fluiddroplets to drop out of solution and be

    recovered. Decontaminated water overflowed to the

    chemical sewer.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    36/38

    Other accidents

    A fire in giant floating roof in crude oil tank.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    37/38

    After the top opened,

    the fire burned butthe liquid was still

    contained.

  • 8/2/2019 Lecture Slides CPE 676_Introduction to Equipment

    38/38

    Collapsed coker

    drum in a

    refinery.