Lecture Slides CPE 676_Introduction to Equipment
-
Upload
lim-ying-pei -
Category
Documents
-
view
221 -
download
0
Transcript of Lecture Slides CPE 676_Introduction to Equipment
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
1/38
REFINERY ANDPETROCHEMICAL
EQUIPMENT(CPE 671)
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
2/38
COURSE OVERVIEW :
REFINERY AND PETROCHEMICAL
EQUIPMENT (CPE 671)
Equipment related to refinery and
petrochemical processes
Conception of the overall plant and
the equipment design
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
3/38
INTRODUCTION
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
4/38
INTRODUCTION
Lesson objectives :
By the end of the class, the students are
expected to be able :
to identify the necessary and the most appropriate
equipment for refinery and petrochemical plant.
to understand the importance of safety in plantoperation and equipment.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
5/38
INTRODUCTION
What are the petrochemical plants that are
available in Malaysia ?
..can you name some?
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
6/38
Petrochemical Plants in Pasir Gudang,
Johor
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
7/38
Petrochemical Plants in Kertih,Terengganu
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
8/38
Petrochemical Plants in Bintulu
Sarawak
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
9/38
Petrochemical Plants in Gebeng,Pahang
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
10/38
Major equipment in refinery andpetrochemical plant
1. Heat exchange equipment :
examples : heat exchanger, fired heaters,
air-cooled exchangers, condenser,
reboiler
- what are the fundamentals
of heat transfer?
- basic heat transfer relations ??
phase change
no phase change
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
11/38
Examples of common equipment inrefinery and petrochemical plant
2. Separator Equipment
fractionators (distillation column), absorbers (packed
column), scrubber, vapor-liquid separator (knockout
drum/ flash drum, knock-out pot, compressorsuction drum or compressor inlet drum), filterseparator, fixed bed separator.
what are the fundamentals of
separation process?
types of phases
boiling point of
component
relative volatility
pressure difference
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
12/38
Examples of common equipment inrefinery and petrochemical pant
3. Reactor
stirred tanks, packed tubes or vessels,
shell-and-tube devices or highly specialized
configurations (specially fabricated)
what are the fundamentals of
reaction process?
Chemical kinetics
Stoichiometry of theparticipating reactions
Heats of reaction,
equilibrium data,
rate of reaction,
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
13/38
Examples of common equipment inrefinery and petrochemical plant
4. Transport and storage of fluids
- pumps
- compressors
- storage tanks
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
14/38
Why accidents happen??
Accidents in petrochemical industry can be
due to..
poorly designed,
poorly operated, or
poorly maintained
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
15/38
Poorly designed: A stripper columncollapsed.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
16/38
close-up of collapsed strippercolumn..
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
17/38
Why??Due to improperly protected distillation system
the situation..
Column was flooded with water.
Drain the water by pumping it
out
thus creating vacuum condition
Vacuum relief devices are notoriginally provided on the stripper
Corrective method
Installed vacuum breakers at the
top of the column
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
18/38
Vacuum relief devices: A pressure reliefdevice which is designed to allow fluid toenter a pressure vessel in order to avoid
extreme internal vacuum. Vacuum breaker: A device used to
relieve a vacuum formed in a water
supply line to prevent backflow. Alsoknown as backflow preventer.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
19/38
Poorly operated: Furnace temperaturesafeguard is altereda major fire
erupted
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
20/38
a tube in furnace ruptured due to
overheating :
1800 gallons (6800L) of combustible
heat transfer fluid spilled and burned
intensively.
Witnesses stated flames were over
50-ft. (15m) high in approximately fiveseconds after fire started.
in 25 minutes, four-level of structures
and associated process equipment
were damaged.
estimated loss :
> USD 1.5 mill
property damageUSD 4 mill - business interruption
Situation..
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
21/38
What happen ?
The heater was designed to automatically
shutdown and alarm in the control room
in response to high heat-transfer oil pressure,
high tube-wall temperature, low-pressure fuel
gas, or flame failure.
The shutdown setpoint was found to have
been mistakenly raised to the maximum of
the instrument's setpoint range, or 1,600 F
(870 C).
The tube metal high-temperature alarm
should have been fixed at 850 F(454 C ).
The limited burner shutdown instrumentation had not been properly inspected and
tested to ensure the necessary high degree of reliability.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
22/38
Poorly designed material: Wrongmaterial.
Caustic soda leaks due to an improper gasket used.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
23/38
Molten caustic soda at about 700oF(370oC) sprayed and dripped for about2.5 hours from elevated equipment in a
well maintained unit. The blistering hot caustic soda leak
discovered during the day shift - melted
insulation on wiring and destroyedplastic electrical junction boxes andinstrument control boxes.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
24/38
The situation was inadvertently createdwhen someone installed a compressedasbestos gasket (the nearly universal
gasket for this chemical complex at thattime) on a thermocouple flange in thevapor space.
Specifications dictated a metallic nickelgasket, but the compresses asbestoswas installed in error.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
25/38
Estimated 15 tons (13,600 kg) of causticsoda (about 98- percent strength) leaked out
of the concentrator.
It cost about USD $40,000 to clean up and
recover from the damages. Luckily, there
were no injuries or environmental insults.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
26/38
Poorly designed material: Anothercostly gasket error
A serious oil refinery resulted from theinstallation of the wrong gasket on a heatexchanger.
The unit was operating normally, processing avery flammable naphtha for about six weekfollowing an outage in which the heat
exchangers were clean and tested A spiral-wound metal asbestos gasket was
required by specification, but a compressed
asbestos gasket was installed.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
27/38
The gasket failed causing a leakfollowed by a fire.
The heat from the initial fire caused anadjacent hydrogen exchanger flange toopen.
Vapors flashed and impinged on an 18-inch (46cm) hydrogen-oil line which thenruptured.
This piping failure released oil andhydrogen under 185 psig (1275kPa/12.6 atm) pressure.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
28/38
The fire was brought under control afterabout two hours, but it was allowed toburn another hour and twenty minutes to
consume the remaining fuel. The fire damages affected the electrical
and instrument systems, piping and
structural steel equipment.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
29/38
Corrective action/ counter measure
Preventive measures included a review ofgasket installation and purchasespecification procedures.
Drawings appropriate for turnaround workwere developed to conform to new facilitypractices and have flange ratings marked.
A retaining program covering gasket
installation procedures for craftsmen wasconducted.
Purchasing specifications for gasket now
require color coding.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
30/38
Flanges gasket
In some plants three or four types of gasket
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
31/38
In some plants, three or four types of gasketservices are needed where previously all pressurehandled with compressed asbestos-type gaskets.
For high temperature applications the relativelyexpensive flexible graphite-type gaskets can beused.
For a wide variety of process services, such aspetroleum-based solvents, oxygen, and chlorine,an expensive Teflon-like gasket may be required.
Today, there exists a serious need to spendsufficient time to educate all maintenancepersonnel on details of gasket selection,installation, and the limitations of each type of
gasket.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
32/38
A water drain line is altered.a reactor exploded
A supervisor of a solvents plant was concerned about trace
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
33/38
A supervisor of a solvents plant was concerned about traceemissions of heat transfer fluid from a small diameter waterdrain line.
He, no doubt, felt that with just about 30 ft, (9m) of small1.5 inch (3.8cm) piping, a couple of valves, and a smallconical bottom tank, this heat transfer fluid could berecovered.
The aim was to reduce pollution potentials and wastewatertreatment costs.
The supervisor probably only focused on one area ofconcern. However, this small change in just a cooling
water system contributed to the destruction of a 110 psig(760 kPa) rated 9ft (2.3m) in diameter pressure vessel.
A short-lived fire ensued. The severe overpressuredamage to this highly engineered nickel-clad reactor
resulted in over $500,000 in property damages.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
34/38
A water drain line is altered.a reactor exploded
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
35/38
The modification involved the rerouting
of the discharge water from thebarometric condenser .
Rather than being discharged intoachemical sewer via a sump, the waterstream had been routed to a hopper thatallowed the entrained heat transfer fluiddroplets to drop out of solution and be
recovered. Decontaminated water overflowed to the
chemical sewer.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
36/38
Other accidents
A fire in giant floating roof in crude oil tank.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
37/38
After the top opened,
the fire burned butthe liquid was still
contained.
-
8/2/2019 Lecture Slides CPE 676_Introduction to Equipment
38/38
Collapsed coker
drum in a
refinery.