Monday / Friday Market Updates

March 07, 2008

Page 2: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 2Lead from the front

Texas Nodal

Agenda

• Antitrust Admonition• Submissions Update

– This Week’s Activities– Submissions Status

• Updates / Questions / Reminders• External Interface Specification 1.09 Review• LFC Update• Q&A / Open Forum• Roll Call

Page 3: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 3Lead from the front

Texas Nodal

Antitrust Admonition

ANTITRUST ADMONITION

ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

Page 4: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 4Lead from the front

Texas Nodal

Submission Times for 03/10/08

• Activities for Week of 03/10/08– Submit the following during the 12:00 – 4:00pm submission

window:• COP• TPO for trade date +2• Output Schedule (open to all resources)• INC/DEC (DSR resources only)

– Submit RT COP adjustments during business hours– Submit RT OS adjustments during business hours

Page 5: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 5Lead from the front

Texas Nodal

Submissions Status

2/29/2008 3/1/2008 3/2/2008 3/3/2008

93% 85%  11 82% 73% 9 76% 71% 9 90% 83% 9

COPTPOIDO OS COP

TPOIDO OS COP

TPOIDO OS COP

TPOIDO OS

Submissions still variable but improved ERCOT continues to have system issues on a daily basis

This is being investigated by support If ERCOT system issues are preventing dailies, contact ERCOT for assistance

3/4/2008 3/5/2008 3/6/2008 3/7/2008

98% 93%  10 96% 91% 12 95% 96% 3 88% 88% 2

COPTPOIDO OS COP

TPOIDO OS COP

TPOIDO OS COP

TPOIDO OS

Page 6: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 6Lead from the front

Texas Nodal

Updates / Questions / Reminders

• DST Issues:– For Sunday 3/9, in addition to the DST adjustment, omit the

final hour of the day (e.g. do not include 23:00:00 – 00:00:00)

– For submissions made prior to Sunday for Trade Dates after Sunday, omit the first hour of your submissions

– For submissions made after Sunday 04:00:00, submit as normal (including the first interval of the trade date) with the new GMT offset -05:00:00

– DST Adjustment for Short Day:DST adjustment for short dayHour Ending 01:00:00 -06:00Hour Ending 02:00:00 -06:00<HE 03:00:00 is skipped>Hour Ending 04:00:00 -05:00 ( note the GMT offset change)Etc…

Page 7: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 7Lead from the front

Texas Nodal

Updates / Questions / Reminders

• Reminder: Changes to Offer Curve Submissions– QSE’s can now start

• Adjusting for FIP/FOP• Moving between 80/120 percent of cost

– Week of 3/17, QSE’s will submit any desired curve based on assigned intervals

• Current FIP/FOP to be Used for Week of 3/10/08– FIP = 9.505– FOP = 21.65

• EDS Environment Outages– 3/03 – App Server Core Dump (root cause in review)– 3/04 – Storage detached from app server– 3/06 – App Server Core Dump (root cause in review)

• New Draft Version of Settlement Points Posted to EDS 4 Readiness Center– Sent out for comment 3/6/08– EDS 4 Readiness Center:

http://nodal.ercot.com/readiness/eds4/documents/index.html

Page 8: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 8Lead from the front

Texas Nodal

External Interface Specification 1.09 Review

• Outage Schedule – Section 7– Corrected payload of “Get” AwardSet– Added the “Outage” to the payload of the “Create” OS Reply– Changed the verb from “Update” to “Change” in OutageSet to be

consistent with the BidSets– 5.3.12 Updated Outage notification structure– For Outage Query added for Request/ID to name value pair:

OuatgeID or GroupID– Updated all Outage Scheduler XML Schema figures– Added description for Outage Types

Page 9: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 9Lead from the front

Texas Nodal

External Interface Specification 1.09 Review

• Short mRID

– Corrected the Short mRID logic to include needed tokens for CRR, EB, EOO, PTP

BID Type Type (XML tag)  Short mRID Key String

Ancillary Service Offer ASOffer <QSE>.<TradingDate>.ASO

Ancillary Service Trade ASTrade <QSE>.<TradingDate>.AST

Capacity Trade CapacityTrade <QSE>.<TradingDate>.CT

Current Operating Plan COP <QSE>.<TradingDate>.COP

CRR Offer CRR <QSE>.<TradingDate>.CRR.Source.Sink

DC Tie Schedule DCTieSchedule <QSE>.<TradingDate>.DCT

DAM Energy Bid EnergyBid <QSE>.<TradingDate>.EB.SP

DAM Energy-Only Offer EnergyOnlyOffer <QSE>.<TradingDate>.EOO.SP

Energy Trade EnergyTrade <QSE>.<TradingDate>.ET

Inc Dec Energy Offer IncDecOffer <QSE>.<TradingDate>

Output Schedule OutputSchedule <QSE>.<TradingDate>.OS

PTP Obligation Bid PTPObligation <QSE>.<TradingDate>.PTP.Source.Sink

Self-Arranged AS SelfArrangedAS <QSE>.<TradingDate>.SAA

Self-Schedule SelfSchedule <QSE>.<TradingDate>.SS

Three Part Supply Offer ThreePartOffer <QSE>.<TradingDate>.TPO

Page 10: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 10Lead from the front

Texas Nodal

External Interface Specification 1.09 Review

• Wind Forecasting– 5.3.14 Updated the Wind Generation Notification Structure and

section• Tagged startTime and

endTime as not used and deprecated (reviewSpec for effectedTransactions

• Additionally severalGeneral Updates

Page 11: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 11Lead from the front

Texas Nodal

LFC Update

• QSE Organizations which tested this week: – Coral Power

• Issue encountered: – Data Point Mapping

• QSE Organization(s) Scheduled to test next week: – BTU Wednesday 9:00 AM CT

• Test Form revisions will be posted to the readiness center as necessary.• Test Form submissions are to be submitted two business days before the test.• All submissions should be sent to [email protected]. • Phase II Testing

– Test Procedure & Test Forms posted on Nodal Readiness Center– Link: http://nodal.ercot.com/readiness/eds3/documents/index.html

• Phase III Testing• LFC Phase III Pre Testing Workshop:

– ERCOT will hold a market workshop at the ERCOT Austin Offices on Friday, March 14, 2008 from 9:00 am to 3:00 pm. 

– Workshop will provide • A detailed overview of the pre-testing activities• Required ICCP data submittals• Schedule for EDS 3 Release 6.3 LFC pre-testing.  This meeting will address test activities as called for in

Section 5.2 of the EDS 3 - LFC Testing Market Participant Handbook v1.0, located at http://nodal.ercot.com/readiness/eds3/documents/index.html under the Release 6 – LFC section.

• The workshop will provide participants an opportunity to discuss EDS 3 Release 6.3 LFC testing activities and take part in a workshop with ERCOT personnel responsible for the test.

Page 12: Lead from the front Texas Nodal  1 EDS 3 Release 5 Monday / Friday Market Updates March 07, 2008.

http://nodal.ercot.com 12Lead from the front

Texas Nodal

Q&A