Draft Workplan for Lao PDR for first year, April-December 2013

Activities

Semester 1 Semester 2

Output

Indicative Budget/resources*

(Euro)

Person responsible Months

4 5 6 7 8 9 10 11 12

1. Request Regional PMU to officially submit project document to GOL (AIT- FAO, FAO-Ministry of Foreign Affairs and Ministry of Planning and Investment with copy to Ministry of Agriculture and Forestry )

X

Official communication with

project document received by relevant

ministries for consideration

NIL

Lao Team (Khamphoui(done))

& AIT (Dr. Kumar and Dr. Abha)

2. To follow-up with GOL for consideration, acceptance, and appointment of relevant departments to be responsible for project implementation

X

To Relevant departments were officially assigned,

appointed/endorsed by GOL to be

responsible for project

implementation

NIL DOA, MAF

(Khamphoui)

3. Draft Country Strategy Paper

X

Draft country paper reviewed by FAO

and AIT, and available for

discussion in Inception Workshop

NIL

Lao (Khamphoui, Vorn, etc), FAO

Regional (JWK), AIT (Dr. Kumar & Dr.

Abha)

4. Consultation Meeting among representative from responsible agencies, institutions & departments

X

Goals & objectives of the project

discussed and well understood by

Stakeholders (relevant agencies and departments)

Selected provinces

200

Representative from relevant

agencies, institutions,

departments

Page 2: Laos Draft Activity Plan for AIT EU SRI Project

(villages and districts) are agreed

upon

5. Develop baseline survey form

X Baseline survey

formed finalized and available for

Country team (??), Academic

Institution, NGO, AIT & JWK

6. Organize National Inception and Planning Workshop in Vientiane Capital with 35+ participants (3 days + 2 days travel for participants from provinces)

X

CSP discussed, adjustment made,

agreed upon and finalized;

Participants are well aware and clearly

understood of project goal,

objectives and activities.

Workplan for each province developed.

7,000 (Khamphoui, Vorn),

Dr. Kumar or Dr. Abha and/or JWK

7. Conduct baseline survey

X

Survey results compiled,

documented & available for activity

planning

10,000

DAFO Staff, Representative

from relevant departments and

academic institution.

8. Design CFPAR and develop curricular for National TOT

X PAR developed, TOT

curriculum developed

300

International resource person (s)

(Dr. Kumar or Dr. Abha) are needed.

Total Indicative Budget (Euro)

17,500