Laos Draft Activity Plan for AIT EU SRI Project
Click here to load reader
Transcript of Laos Draft Activity Plan for AIT EU SRI Project
Draft Workplan for Lao PDR for first year, April-December 2013
Activities
Semester 1 Semester 2
Output
Indicative Budget/resources*
(Euro)
Person responsible Months
4 5 6 7 8 9 10 11 12
1. Request Regional PMU to officially submit project document to GOL (AIT- FAO, FAO-Ministry of Foreign Affairs and Ministry of Planning and Investment with copy to Ministry of Agriculture and Forestry )
X
Official communication with
project document received by relevant
ministries for consideration
NIL
Lao Team (Khamphoui(done))
& AIT (Dr. Kumar and Dr. Abha)
2. To follow-up with GOL for consideration, acceptance, and appointment of relevant departments to be responsible for project implementation
X
To Relevant departments were officially assigned,
appointed/endorsed by GOL to be
responsible for project
implementation
NIL DOA, MAF
(Khamphoui)
3. Draft Country Strategy Paper
X
Draft country paper reviewed by FAO
and AIT, and available for
discussion in Inception Workshop
NIL
Lao (Khamphoui, Vorn, etc), FAO
Regional (JWK), AIT (Dr. Kumar & Dr.
Abha)
4. Consultation Meeting among representative from responsible agencies, institutions & departments
X
Goals & objectives of the project
discussed and well understood by
Stakeholders (relevant agencies and departments)
Selected provinces
200
Representative from relevant
agencies, institutions,
departments
(villages and districts) are agreed
upon
5. Develop baseline survey form
X Baseline survey
formed finalized and available for
Country team (??), Academic
Institution, NGO, AIT & JWK
6. Organize National Inception and Planning Workshop in Vientiane Capital with 35+ participants (3 days + 2 days travel for participants from provinces)
X
CSP discussed, adjustment made,
agreed upon and finalized;
Participants are well aware and clearly
understood of project goal,
objectives and activities.
Workplan for each province developed.
7,000 (Khamphoui, Vorn),
Dr. Kumar or Dr. Abha and/or JWK
7. Conduct baseline survey
X
Survey results compiled,
documented & available for activity
planning
10,000
DAFO Staff, Representative
from relevant departments and
academic institution.
8. Design CFPAR and develop curricular for National TOT
X PAR developed, TOT
curriculum developed
300
International resource person (s)
(Dr. Kumar or Dr. Abha) are needed.
Total Indicative Budget (Euro)
17,500