    Working Notes:

    Justification- The minimum price for bid should be the price that ends up

    with no profit no loss. The bidder can sell the product at minimum price

    OF 11.98 and still cover the direct costs incurred. Indirect costs can becovered in the other product ranges since we can't trace the indirect

    costs to a particular product.

    1. The minimum Selling Price for Washable Trousers will be 11.98.

    The ideal price will be the price which earns the firm a profit margin

    of 23%.

    2. The minimum Selling Price for Cargo Pants is 12.27

    Calculations

    1.) Factory overhead costs will be 80 % of the total overhead costs.

    Rent-80%of 56400= 45120

    Utilities- 80 % of 15600=12480

    Maintenance= 2000

    2.) Administration overhead costs will be 20 % of total overhead costs

    3.) Direct material cost

    Fabric cost - price per metre of fabric used*length of fabric used for

    one unit.

    Washable trousers= 3.1*1.5=4.65

  • 7/29/2019 Kreative Kasuals Woeking Notes

    2/3

    Cargos= 1.7*2.9=4.93

    T-shirt=1.07

    Boxers=1.12*0.95=1.06

    Coveralls=2.7*3=8.1

    4.) Cost of zippers, elastic and dye directly given

    5.) Calculate of costs of sewer

    Washable trousers:

    35 pairs can be made in 8 hours

    1hr= 35/8 pairs= 4.37 pairs

    $15 is the salary 4.37 pairs

    For 1 pair salary will be 15/4.37=3.43

    Similarly well calculate forothers.

    6.)Calculation of cost of Knitters for T-shirts

    Knitters can knit 4250m of fabric in 8 hrs1hr= 531.2 m of fabric

    1T-shirt= 1.1m

    531.2m of fabric can produce 531.3*1.1 t-shirts

    =584.3 tshirts

    $20 for 584.3 T-shirts=0.034

    Similarly we can calculate for others.

    7.)Calculation of factory and admin over head costs per unit

    Washable trousers:

    Time taken for one unit=8/35=0.2285

    For 22840= 28450*0.2285=6502.8

    Total time (including sewing hours)=6502.8+15840=22342

  • 7/29/2019 Kreative Kasuals Woeking Notes

    3/3

    Factory overhead cost per hour will be= 59600/22342=2.66

    Factory overhead cost per unit will be=2.66*0.228=0.606

    Similarly we can calculate for cargos

    Admin overhead cost = 94800/22342=4.24*0.22=0.96

    Similarly we can calculate for cargos.

    Full cost= indirect cost+ direct cost