Kilkenny County Grid Review
Transcript of Kilkenny County Grid Review
KilkennyCounty Grid Review
Lot 1 Deliverable:Grid Study and Capacity Training for Communities
No representation or warranty, express or implied is made by the authors as to the accuracy or
completeness of any information contained in this report. Mullan Grid Consulting and Bioxl accepts no
responsibility in relation to such information whether fact, opinion, expectation or otherwise, or for any
opinion or conclusion which the addressee may draw from this report.
Issue No Revision Comment Issue Date Author Reviewer Approver
1 Original 24/03/2021
Document Reference:795-101 Kilkenny R&I Centre County Review v1
Table of Contents1. Introduction
2. Scope of Works
3. Connection Guide to Energisation
4. Connection Offer Process
5. The Electricity Network in Ireland
6. Renewable Generation in Ireland
7. ECP-2 Decision for Community Projects
8. ECP-2 Decision Nodal Assignment Rules
9. ESBN Application Requirements
10. Application Fees
11. Geographical vs Electrical Scope
12. Existing and Planned Network Generation in Kilkenny
13. Single Line Diagram of Kilkenny 110kV Substation
14. 110kV Transformer Calculation Methodology
15. Transformer Capacity at the Kilkenny Node Substations
16. Ballyhale 38kV Substation
17. Callan 38kV Substation
18. Capacity on 38kV Loop to Ballyhale & Callan substations
19. Goresbridge 38kV Substation
20. Graiguenamanagh 38kV Substation
21. McDonagh 38kV Substation
22. Purcells Inch 38kV Substation
23. Rosehill 38kV Substation
24. Talbots Inch 38kV Substation
25. Transformer Capacity at Carlow 110kV Substation
26. Bagenalstown 38kV Substation
27. Transformer Capacity at Waterford 110kV Substation
28. Rosbercon 38kV Substation
29. Rosbercon 38kV Loop
30. Belview 38kV Substation
31. Mount Misery 28kV Substation
32. Granagh 38kV Substation
33. Transformer Capacity at Ballyragget 110kV Substation
34. Castlecomer 38kV Substation
35. Ballyragget 38kV Substation
36. Eirgrid Tomorrow’s Energy Scenarios
37. Southeast Area H2 ECP-1 Constraint Report
38. Eirgrid ECP1 Constraint Solar Projections
39. Eirgrid ECP1 Constraint Wind Projections
40. Summary of Co. Kilkenny Grid Potential
1. Introduction
3Counties Energy Agency (hereafter referred to as the Client) are carrying out a review on the potential grid connection
options for community generation projects in Co. Kilkenny with the financial support of Kilkenny Leader Partnership.
MullanGrid Consulting and Bioxl were commissioned to undertake a grid analysis to determine the capacity of the
distribution and transmission system in Co. Kilkenny for connection of new community projects.
2. Scope of Works
The scope of work undertaken is in accordance with the following;
1. Overview of the connection offer process for medium/large scale, community, small scale and micro generation projects.
2. Review of the transmission and distribution infrastructure in Co. Kilkenny including 110kV and 38kV networks and
substations.
3. Review of existing connected and contracted renewable generation in Co. Kilkenny as well as renewable energy projects
currently in the planning system.
4. Review of the available transformer capacities at the 110kV and 38kV substations.
5. Review of capacity for additional generation on existing 38kV circuits.
6. This review is focused on identifying opportunities for 1-5MW projects. It also highlights any areas on the High Voltage
(HV) distribution network with capacity bottlenecks that would impact on small scale connections (11kW-1MW).
3. Connection Guide to Energisation
The slide provides a high level overview of the process of connecting a generator to the electricity network. The main
tasks are briefly outlined below in Figure 1 which set out the stages of development for the connection of a generator
installation:
• Connection application submitted by developer
• Application processed by relevant system operator(ESBN or EirGrid)
Connection Offer Process
• Connection works scoping and design
• Consents for connection assets acquired
• Procure equipment
Pre-Construction Works
• Construction of civil works
• Install electrical equipment
• Testing and commissioningConstruction Works
Feasibility Studies
Energisation
Figure 1: Connection Guide to Energisation
Planning Consent Obtained
4. Connection Offer Process • To connect into the electricity grid in Ireland renewable projects have to receive and accept a connection offer from EirGrid or
ESB Networks. The Commission for the Regulation of Utility (CRU) have the role of deciding the connection policy for the
processing of connection applications for generators.
• In the early 2000s ESB Networks and EirGrid processed connection applications sequentially, i.e. they only processed one
connection application in an area at a time. With the large number of connection applications from windfarms it was decided to
change to a batch application process, known as the Group Processing Approach (GPA).
• Large number of applications were processed at the same time in what were known as Gates. Gate 1, 2 and 3 were processed
from 2005-2011. This provided the connection capacity for the windfarms required to achieve the 2020 RES-E targets.
• Non wind renewables continued to be processed outside the batch process in a sequential process. This included a large number
of solar connection applications in the period 2015-2018. As connection applications were generally being processed on a ‘first
come first served basis’, the gate and sequential processes resulted at times in connection capacity being allocated to generation
projects that were only at an early stage of development.
• Due to the large number of solar applications being processed through the sequential process and the requirement to process
more connection applications from windfarms, the CRU started in 2017 to design a new connection offer process known as the
Enduring Connection Process (ECP).
4. Connection Offer Process (Continued) • To avoid the potential hoarding of grid capacity, planning permission of the generation facility has been a requirement, and will
probably remain a requirement to submit an application into ECP (with some exceptions for community projects). The processing
of connection offers in batches is maintained in ECP but all generators over 500kW will be processed in ECP batches, rather than
just wind projects that were processed in the GPA Gate process. The processing of the first batch of applications in ECP-1 is now
complete and the processing of the second ECP2.1 batch started in 2021.
4. Connection Offer Process (Continued)
• The CRU published their decision paper on ECP-2 in 2020. The document sets out the framework for ECP-2 which
encompasses one batch application window each September for three years starting from 2020. The three batches are ECP-
2.1, ECP-2.2 and ECP-2.3. The CRU decided on a target of 115 connection offers to be processed in each of the batches.
• This target consists of 85 offers for generation, storage and system services projects (MEC > 500kW), prioritised by the 25
largest renewable generation projects and then by planning permission grant date (Category A). In addition, there will be 15
connection offers per batch for non-batch projects (<500kW & auto-producing generators) (Category B) and 15 connection
offers per batch for community-led projects (Category C).
• The connection offer process for Community Projects is explained in detail in Section 5. Table 1 below outlines the indicative
timelines for the three ECP-2 batches. At the end of January 2021, EirGrid published the list of category A, B & C applicants to
be processed in ECP2.1, see link below:
https://www.eirgridgroup.com/site-files/library/EirGrid/2020-Batch-(ECP-2.1)-Results-Joint-SO-Publication_January-2021.pdf
Table 1: Proposed ECP Batch Timelines
400 kV
220 kV
38 kV
110 kV
20/10 kV (Medium Voltage/MV)
400/230 V (Low Voltage/LV)
5. The Electricity Network in Ireland
BusinessCustomers
Domestic Customers
Wind Generation
Conventional Generation
• Distribution System Operator- ESB Networks
• Transmission System Operator-EirGrid
• A good analogy to the Electricity Network is the Road network.
• The Transmission network is the motorway for delivering electricity and provides the bulk of the electricity to cities and large towns in Ireland.
• The Distribution Network is the national or regional road that supplies small towns, villages and domestic customers with electricity.
Small Scale & Community
Projects
6. Renewable Generation in Ireland
• Micro Generation
• 6kW (Single phase) or 11kW (three phase) connections for small projects connected to the LV network
• Figure 1 is an example of a small hydro generator and domestic PV installation
• There is a Government led group currently discussing creating a new category of 11-50kW connections that will have a similar offer process as micro generation
• Small Scale Generation
• 11-500kW connections to LV or MV network
• Zero Export Projects, all generation used on-site and with no export of generation onto the grid
• Auto-production with some generation being exported onto the grid (Typically 50% or less export)
• Figure 2 is an example of a rooftop solar installation that could be zero export or auto-production
Figure 1: 6kW Hydro Generator and a domestic PV installation
Figure 2: Rooftop Solar Installation-Export and/or Autoproduction (O’Sheas Farm, Kilkenny)
6. Renewable Generation in Ireland-Continued
• Community Renewable Electricity Projects
• 500kW-5MW
• Example of Renewable Generation: Wind, Solar PV, Hydro (excluding pumped storage), Waste to Energy, Biomass and Biogas Projects
• In Ireland a 4-5MW project generally connects with a 10kV or 20kV circuit to an existing 38kV substation.
• Figure 3 is an example of a 4.8MW solar farm.
• Commercial Renewable projects
• 500kW to 200 MW.
• Projects <5MW considered small.
• Connections at 10kV, 20kV, 38kV and 110kV.
• Figure 4 is an example of a large scale wind farm in Co. Galway.
Figure 3: Ground Mounted Solar Farm( Co.Antrim)
Figure 4: Large Scale Wind farm(Co. Galway)
7. ECP-2 Decision for Community Projects
• On the 10/06/2020 the CRU published the final ECP-2 decision that stated there
would be 15 community projects per ECP batch. This number could be higher if
there is a low number of non-batch applications.
• Community projects are projects with an MEC greater than or equal to 0.5MW
and less than or equal to 5MW.
• Community projects application fees are initially capped at a €2,000 deposit,
please see Section 9 for details of the eventual application costs.
• Planning permission is not a requirement to submit an application to ESB
Networks but planning must be in place to accept the connection offer.
• ESB Networks have stated that they will undertake a connection assessment for
the project once the deposit for the application has been received. Assuming
the assessment is positive and the project can be processed outside of the
batch, ESB Networks will hold the capacity for two years to allow projects
achieve planning permission at the connection location.
• Once planning has been achieved and the balance of the application fee has
been paid, ESB Networks will issue the connection offer for the project.
• If planning permission is not received within the two-year period, projects will
be re-studied at no additional cost at the next available opportunity once
planning permission is confirmed (i.e. on a batch or non-batch basis).
https://www.cru.ie/wp-content/uploads/2020/06/CRU20060-ECP-2-Decision.pdf
8. ECP-2 Decision Nodal Assignment Rules
• ESB Networks and EirGrid published new voltage and node assignment rules in
September 2020. These rules help identify the connection point for a generator onto the
existing ESB Networks and EirGrid network.
• As highlighted below a project with an MEC ≤5MW will be assigned to the nearest
MV(10kV or 20kV) busbar.
• Small projects ≤1MW can connect to the MV network but connections are dependant on
capacity on the network and the 38kV substation the network is supplied through.
• The 38kV substations in Ireland are equipped with 38/MV transformers and there are
some 110kV substation's that are equipped with 110/MV or 38/MV transformers.
Guidance for node assignment at distribution level
Guidance for node assignment at transmission level
ECP-2.1 Node Assignment Ruleshttps://www.eirgridgroup.com/site-files/library/EirGrid/Node-Assignment-Rules-ECP-2.pdf
12
9. ESBN Application Requirements
• To apply for a grid connection for a generator, a developer or community must submit a
connection application form. This form is called an NC5 application and can be downloaded
from the ESB Networks website. The information requested on the form is broken into the
following sections:
• Applicant, Site and general details
• Maps and diagrams
• Technical details of the generator
• Transformer data, if applicable
• 3 Declarations - see section 9
• The technical information required to complete this form may not be publicly available and
generator manufacturers or suppliers may be required to assist developers with the
completion of the application form.
• Once the application has been checked by the system operators and deemed complete, and if
successful in being included in the batch or non-batch process, then the project is listed on
the ESB Networks/EirGrid website. The published information from the application form
includes:
• Project name
• Company name
• Contact details; contact name, phone number, email address
• Location and co-ordinates
• MEC
ESB NC5
10. Application Fees
• To apply to the ECP batch a non-refundable €2,000 deposit is
required to be submitted with the application for projects over
1MW.
• The balance of the application fee for community projects is only
required after the system operators have completed the
connection assessment for the project and planning has been
achieved.
• If the connection assessment is not positive or the project
otherwise proves not commercially viable then the application can
be withdrawn without incurring any additional fees.
• Table 2 lists the full application fees for the ECP-2.1 batch.
• As per the Table 2 below the application fee for export capacity of,
500kW-1MW is €9,037, 1-4MW’s is €18,512, 5MW is €37,464 excl
VAT.
• Due to the application fee structure, many projects apply for 4MW,
rather than 5MW of capacity.
Table 2: ESB Networks Generator Application Fees
11. Geographical vs Electrical Scope
• Figure 5 below highlights the proposed study area to be considered in this review.
• The electricity network is not bound by the county borders and therefore there are some small transformers that are located
outside the county but are supplied through larger 38kV substations in the county.
• There are also 38kV substations that are located in Kilkenny but are supplied through 110kV substations outside the county
such as Waterford and Carlow 110kV substations. These 38kV substations have been included in this review.
Figure 5: Study Area Considered in this review
12. Existing and Planned Network and Generation in KilkennyKilkenny 110kV substation is located approximately 5km south east of Kilkenny City and is connected to the wider 110kV network
through two 110kV circuits to Great Island 110kV substation (Co. Waterford) and Kellis 220kV substation (Co. Carlow). Kilkenny
110kV substation normally feeds, Ballyhale, Callan, Goresbridge, Graiguenamanagh, Talbots Inch, Purcells Inch, McDonagh,
Ballyragget, and Rosehill 38kV substations. There are four 38kV substations that are connected in a 38kV loop around Kilkenny
City. These substations are McDonagh, Purcells Inch, Talbots Inch and Rosehill, please see Figure 6 for reference. Callan and
Ballyhale 38kV substations are connected to Kilkenny on a rural 38kV loop that is over 50km in length. Kilkenny 110kV substation
is equipped with 2 nr.63MVA 110/38kV transformers.
There is approximately 8.3MW of connected and contracted generation associated with Kilkenny 110kV substation. There were
three ECP-1 projects with live connection offers at the Kilkenny node. There are 3 solar projects with a combined MEC of 15MW
that are being processed in the ECP-2.1 batch at the Kilkenny 110kV node. There are also four other solar projects at 38kV
substations fed from Kilkenny with consented planning in the queue for the ECP2.2 batch. In addition there is a 50-60MW solar
farm in planning approximately 4km south of Kilkenny as well as an 80-90MW windfarm in planning near Ballyhale. Please see
Table 3 and Figure 7 & 8 for reference.
As part of EirGrids Laois-Kilkenny reinforcement project it is planned to build a new 110kV substation adjacent to the existing
38kV substation at Ballyragget. This new substation would then be connected to Kilkenny 110kV substation and a new
400/110kV substation in Laois. When this substation is completed it is expected to feed Castlecomer 38kV substation which is
currently fed from Carlow 110kV substation. The substation is also expected to be equipped with one 31.5MVA 110/38kV
transformer. There is a 35MW ECP-2.1 solar farm being processed at Ballyragget 110kV substation.
12. Existing and Planned Network and Generation in Kilkenny -Continued
There are also a number of 38kV substations that are in county Kilkenny but are fed from 110kV substations outside of the
county. Bagenalstown 38kV substation is connected on a 38kV circuit between Goresbridge and Carlow 110kV substation. There
is approximately 36.8MW of connected and contracted generation associated with Carlow 110kV substation. There were two
ECP-1 projects with live connection offers at the Carlow node totalling 19MW, it is unclear if these offers were accepted. In
addition to this generation there are two solar farms totalling 9.9MW and a 6MW windfarm that are being processed in the
ECP-2.1 batch. There are 4 other solar projects eligible for future ECP2 batches at the Carlow node, the estimated combined
size of these projects is 34.8MW. Carlow 110kV substation is equipped with 2 nr. 63MVA 110/38kV transformers.
Belview, Granagh and Mount Misery 38kV substations are located close to the Suir River in Kilkenny but are normally fed from
Waterford 110kV substation. Rosbercon 38kV substation is located in Kilkenny on the outskirts of New Ross and is also
connected on a 38kV loop from Waterford 110kV substation and Great Island 220kV substation. There is approximately
23.1MW of connected and contracted generation associated with Waterford 110kV substation. There is 1 solar project eligible
for future ECP batches at the Waterford node, the estimated size of this project is 4.95MW. Waterford 110kV substation is
equipped with 2 nr. 63MVA 110/38kV transformers. Please see Figures 9-11 for reference.
There is also a 38kV substation named Blanchfield that is in Kilkenny but is connected to Thurles 110kV substation in Tipperary.
This substation was constructed to connect wind generation. As Thurles substation has currently no capacity for new
generation, Blanchfield substations not been considered further in this review.
13. Single Line Diagram of Kilkenny 110kV Substation
110kV
63MVA 110/38kV DSO Transformer
To Great Island110kV substation(Co. Waterford)
To Kellis220kV substation
(Co. Carlow)
38kV
63MVA 110/38kV DSO Transformer
Circuit BreakerKilkenny
110kV Substation
38kV 38kV
38kV
Callan Ballyhale McDonagh
38kV
Purcells Inch
38kV
Goresbridge
To Ballyragget110kV substation
• This is the single line diagram (SLD) for the Kilkenny 110kV node, including 38kV substations fed from the substation. The
110kV circuit to Ballyragget is a planned 110kV circuit but is expected to be completed in the next 2-3 years.
Rosehill
Talbots Inch
Graiguenamanagh
Bagenalstown
Figure 6: Kilkenny 110kV Node Existing and Planned Network
Figure 7: Kilkenny 110kV Node Existing and Planned Network and Committed Generation
Figure 8: Kilkenny 110kV Node Existing and Planned Network and Future Generation
Figure 9: South Kilkenny 38kV Network
Figure 10: South Kilkenny 38kV Network and Existing and Committed Generation
Figure 11: South Kilkenny 38kV Network and Future Generation
14. 110kV Transformer Calculation Methodology
Non-Firm Access Connections for Distribution Connected Distributed Generators
• In Ireland most 110kV substations are equipped with two 110kV transformers. ESB
Networks’ current planning standards assume that one of these transformers is not
available, for example due to maintenance, when calculating the available capacity in
a substation. This is known as the N-1 (Normal-1) policy which ensures that there is
redundancy on both 38kV and MV networks.
• For example in Kilkenny 110kV substation the combined rating of the transformers is
126MVA however using the N-1 policy only one 63MVA transformer can be
considered in the calculation. The same policy is implemented at 38kV substations
with two transformers.
• ESB Networks have been investigating over the last 2-3 years whether the second
transformer in the substation could be used for generator connections. These are
known as NFA (Non-Firm Access) connections. In this scenario a generator could
connect to the second transformer and if there is an issue with that transformer then
the generator will be turned off until it has been resolved.
• ESB published a guide to NFA connections in September 2020. Initially NFA is only
being made available at a small number of substations but it is hoped later in the
decade it will be rolled out at more substations.
• Any substation in the proposed study area where a NFA connection is possible has
been accounted for in this review.
15. Transformer Capacity at the Kilkenny node substations
Table 3: Available 110/38kV transformer Capacity in Kilkenny 110kV substation.
• Table 3 below outlines the available capacity on the 110/38kV transformers in Kilkenny considering varying amounts of
generation.
• There appears to be capacity available on the 110/38kV transformers in Kilkenny after all of the generation has been
considered for future generation.
• The 50-60MW solar farm in planning 4km south of Kilkenny and the 80-90MW windfarm near Ballyhale and are assumed to
be a transmission projects and as such have not been considered in this transformer calculation.
• It should be noted that there may be additional projects in planning or with planning consent in the area that have not been
included in this calculation.
• Currently connections at 110/38kV substations are not viable for a community project (5MW or less) due to the high cost of
connecting at these voltages.
Project Name Technology MEC 38kV Substation StatusMinimum
Demand(MW)
Transformer
Capacity(Connected,
Contracted,ECP-1)
Transformer
Capacity(Connected,
Contracted,ECP-1,ECP-
2.1)
Transformer
Capacity(All
Generation)
Ballytobin Biogas (1) (BEOFS) Biogas 0.18 Callan Connected
Nicholas Mosse Small Hydro 0.029 Purcells Inch Connected
Ormond Mills Hydro (1) Small Hydro 0.05 Purcells Inch Connected
Bleach Green Elec Hydro (1) Small Hydro 0.075 Talbots Inch Connected
Ballytobin Solar PV Solar 4 Callan Contracted
Castlekelly Solar PV Farm Solar 4 Goresbridge Contracted
Knocktopher Solar Solar 4.00 Ballyhale ECP-2.1
Clashmagrath PV Solar 4.99 Goresbridge ECP-2.1
Keatingstown Solar Fam Solar 6 Talbots Inch ECP-2.1
Derrynahinch & Kiltorcan Solar 15.00 Ballyhale Planned Project
8.3
8.3
23.3
38.3
Sionhermitage BESS Battery Storage 80
Castlebanny WF Wind 84.00
Clashwilliam Solar Farm Solar 56.44
254156.319.1
Total
Subtotal Connected, Contracted,ECP-1 and ECP-2.1
Subtotal Connected, Contracted and ECP-1
Subtotal Connected and Contracted
16. Ballyhale 38kV Substation
38kV Substation Ballyhale
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 2x5
Transformer Configuration T42(10kV)
Secondary Voltage Level 10kV & 20kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 0.0
Available Firm Capacity(ESB)(MW) 5.4
Available Non-Firm Capacity(ESB)(MW) 3.3
Available Capacity(MG)(MW)(Connected,
Contracted, Live)0.0
Available Capacity(MG)(MW)(All
Generation)0.0
Risk of Chargeable Transformer UpgradesHigh
Risk of 38kV Network Upgrades High
Development Potential Low
Comment
There does not appear to be capacity at this
substation for new generation.There are multiple
solar farms associated with Ballyhale 38kV
substation. There is 1x4MW solar project that was
successful in the ECP-2.1 batch at Ballyhale and an
additional 15MW of planned solar generation at
the substation.
17. Callan 38kV Substation
38kV Substation Callan
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 2x5
Transformer Configuration T41∥T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.5
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 0.5
Available Firm Capacity(ESB)(MW) 1.6
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)1.1
Available Capacity(MG)(MW)(All
Generation)1.1
Risk of Chargeable Transformer UpgradesModerate
Risk of 38kV Network Upgrades High
Development Potential Low
Comment
There is a 4MW community project currently
associated with the substation. Potential for 1MW
project connecting to Callan or on MV network
supplied by Callan. With the addition of solar
generation at Callan and Ballyhale the capacity on
the 38kV loop is considered low.
18. Capacity on 38kV Loop to Ballyhale & Callan Substations
• As outlined previously Callan and Ballyhale are connected on
a 38kV loop out of Kilkenny 110kV substation as is shown in
Figure 12.
• As a general rule of thumb a 38kV loop circuit can
accommodate c.20MW’s of generation before the thermal
capacity and voltage rise along the circuit becomes a
limitation on the network.
• The total existing or planned generation at Callan and
Ballyhale 38kV substation is currently estimated at 23.2MW.
• Therefore it is likely that a future projects connecting to this
section of the 38kV network will be required to uprate the
existing 38kV network.
• There is a 4MW MEC community-led solar project
connecting into Callan 38kV substation.Figure 12: 38kV Loop to Ballyhale & Callan Substations
19. Goresbridge 38kV Substation
38kV Substation Goresbridge
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 2x5
Transformer Configuration T41∥T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 0.0
Available Firm Capacity(ESB)(MW) 1.9
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)1.2
Available Capacity(MG)(MW)(All
Generation)0.0
Risk of Chargeable Transformer UpgradesHigh
Risk of 38kV Network Upgrades Low/moderate
Development Potential Low
Comment
There does not appear to be capacity at this
substation for new generation.
20. Graiguenamanagh 38kV Substation
38kV Substation Graiguenamanagh
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 2x2
Transformer Configuration T41∥T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 0.0
Available Firm Capacity(ESB)(MW) 1.8
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)1.7
Available Capacity(MG)(MW)(All
Generation)1.7
Risk of Chargeable Transformer UpgradesLow
Risk of 38kV Network Upgrades Low/moderate
Development Potential Moderate
Comment
Potential for small project to connect to 2MVA
transformers. Due to generation upstream at
Goresbridge and at Bagnalstown the risk of 38kV
network upgrades is considered low/moderate.
21. McDonagh 38kV Substation
38kV Substation McDonagh
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 2x10
Transformer Configuration T42 & T41(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.1
Contracted Generation(MW) 4.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 4.3
Total Generation(MW) 8.4
Available Firm Capacity(ESB)(MW) 11.7
Available Non-Firm Capacity(ESB)(MW) 6.7
Available Capacity(MG)(MW)(Connected,
Contracted, Live)8.4
Available Capacity(MG)(MW)(All
Generation)8.4
Risk of Chargeable Transformer UpgradesLow
Risk of 38kV Network Upgrades Low
Development Potential Low/Moderate
Comment
Potential to connect a project to the 10MVA
transformer in the substation however the
substation is located within Kilkenny City. There is
still potential for rooftop installations in Kilkenny
city.
22. Purcells Inch 38kV Substation
38kV Substation Purcells Inch
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 1x5,1x10
Transformer Configuration T42&T41(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.6
Contracted Generation(MW) 0.5
ECP-1 Generation(MW) 4.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 5.1
Available Firm Capacity(ESB)(MW) 7.0
Available Non-Firm Capacity(ESB)(MW) 7.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)7.0
Available Capacity(MG)(MW)(All
Generation)7.0
Risk of Chargeable Transformer UpgradesLow
Risk of 38kV Network Upgrades Low
Development Potential High
Comment
Potential to connect a project to the 5MVA and
10MVA transformer in the substation. Substation is
located on outskirts of Kilkenny City
23. Rosehill 38kV Substation
38kV Substation Rosehill
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 2x10
Transformer Configuration T42&T41(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 4.0
Planned Generation(MW) 15.0
Total Generation(MW) 19.0
Available Firm Capacity(ESB)(MW) 11.9
Available Non-Firm Capacity(ESB)(MW) 6.7
Available Capacity(MG)(MW)(Connected,
Contracted, Live)8.7
Available Capacity(MG)(MW)(All
Generation)8.7
Risk of Chargeable Transformer UpgradesLow
Risk of 38kV Network Upgrades Low
Development Potential High
Comment
Potential to connect a project to the 10MVA
transformer in the substation. Substation is located
on the outskirts of Kilkenny City
24. Talbots Inch 38kV Substation
38kV Substation Talbots Inch
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 2x5
Transformer Configuration T41∥T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.2
Contracted Generation(MW) 4.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 4.2
Available Firm Capacity(ESB)(MW) 5.8
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)5.3
Available Capacity(MG)(MW)(All
Generation)0.0
Risk of Chargeable Transformer UpgradesHigh
Risk of 38kV Network Upgrades Low
Development Potential Low
Comment
There does not appear to be capacity at this
substation for new generation.
25. Transformer Capacity at Carlow 110kV Substation
Table 4: Available 110/38kV transformer Capacity in Carlow 110kV substation.
• Table 4 below outlines the available capacity on the 110/38kV transformers in Carlow considering varying amounts of generation.
• There appears to be no available capacity on the 110/38kV transformers in Carlow after all of the generation has been considered.
• Carlow is equipped with 2x63MVA transformers which is the largest 110/38kV transformer in ESB’s standards, as a result they cannot be uprated.
• Therefore some of the generation planning to connect to a 38kV substation fed from Carlow may have to connect directly to a new 110kV transformer
in Carlow 110kV substation in the future.
• Until more information is available from ESB on how they plan to connect the ECP-2.1 and future generation at Carlow it is difficult to determine the
available capacity on the existing transformers in Carlow substation.
• It should be noted that there may be additional projects in or with planning in the area that have not been included in this calculation.
Project Name Technology MEC 38kV Substation StatusMinimum
Demand(MW)
Transformer
Capacity(Connected,
Contracted,ECP-1)
Transformer
Capacity(Connected,
Contracted,ECP-1,ECP-
2.1)
Transformer
Capacity(All
Generation)
Avonmore Foods Hydro (1) Small Hydro 0.11 Bagnalstown Connected
Ballon Wind Wind 0.499 Bagnalstown Connected
Gortahile 1 Wind 21 Graigue Connected
Strongstream Electric Hydro (1) Small Hydro 0.38 Graigue Connected
Ballynultagh Windfarm Wind 0.499 Shillelagh Connected
Cronelea Upper Wind 2.55 Shillelagh Connected
Cronelea Upper (2) Wind 1.7 Shillelagh Connected
Cronelea 1 Wind 4.99 Tullow Connected
Cronelea 2 Wind 4.5 Tullow Connected
Tullow Mushroom Growers Ltd Wind 0.133 Tullow Connected
Muine Bheag Wind Wind 0.5 Bagnalstown Contracted
Kilcarrig Solar Solar 4 Bagnalstown ECP-1 Live
Bilboa Wind Farm Wind 15 N/A ECP-1 Live
Loan PV Solar 4.99 Castlecomer ECP-2.1
Bilboa Wind Farm Ext. Wind 6 Graigue ECP-2.1
Farm Power Generation Solar 5 Tullow ECP-2.1
Ardenhue PV Solar 4.99 Pollerton Planned Project
Johnstown Solar farm Solar 10.00 N/A Planned Project
Friarstown Solar Park Solar 11.40 N/A Planned Project
Friarstown/Tullow Solar 8.45 Pollerton Planned Project
36.9
55.9
71.9
106.7
0
Subtotal Connected and Contracted
Subtotal Connected, Contracted and ECP-1
Subtotal Connected, Contracted,ECP-1 and ECP-2.1
Total
20.3 12.1 0
26. Bagenalstown 38kV Substation
38kV Substation Bagnalstown
Feeding 110kV Substation Carlow
Number of Transformers & MVA Rating 2x5
Transformer Configuration T41∥T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.1
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 0.1
Available Firm Capacity(ESB)(MW) 0.9
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)0.6
Available Capacity(MG)(MW)(All
Generation)0.6
Risk of Chargeable Transformer UpgradesHigh
Risk of 38kV Network Upgrades Moderate
Development Potential Low
Comment
There does not appear to be capacity at this
substation for new generation. The available
capacity on the 38kV network may be limited.
27. Transformer Capacity at Waterford 110kV Substation
Table 5: Available 110/38kV transformer Capacity in Waterford 110kV substation.
• Table 5 below outlines the available capacity on the 110/38kV transformers in Waterford considering different amounts of generation.
• There appears to be available capacity on the existing transformers in Waterford 110kV substation for future generation.
• However some parts of the 38kV network in Kilkenny that is fed from Waterford appear to be saturated with existing generation. This will be
explained in greater detail in the following sections.
Project Name Technology MEC 38kV Substation StatusMinimum
Demand(MW)
Transformer
Capacity(Connected,
Contracted,ECP-1)
Transformer
Capacity(Connected,
Contracted,ECP-1,ECP-
2.1)
Transformer
Capacity(All
Generation)
Benedict Behal Hydro (1) Small Hydro 0.083 Granagh Connected
Kilmacow Mill - Behal Small Hydro 0.023 Granagh Connected
Michael Aylward Wind 0.5 Mount Misery Connected
Ballymartin (2) Wind 8.28 Rosbercon Connected
Ballymartin Smithstown Wind 6 Rosbercon Connected
Rahora Wind 4.25 Rosbercon Connected
Curraghmartin Solar Park Solar 3.99 Granagh Contracted
Farranmacedmond Solar Farm Solar 4.35 Granagh Planned Project
23.1
23.1
23.1
27.5
Subtotal Connected, Contracted and ECP-1
Subtotal Connected, Contracted,ECP-1 and ECP-2.1
Total
36414129.6
Subtotal Connected and Contracted
28. Rosbercon 38kV Substation
38kV Substation Rosbercon
Feeding 110kV Substation Waterford
Number of Transformers & MVA Rating 1x2,1x5, 1x10
Transformer Configuration T41(10kV)
Secondary Voltage Level 10kV & 20kV
Connected Generation(MW) 18.5
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 18.5
Available Firm Capacity(ESB)(MW) 1.3
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)1.0
Available Capacity(MG)(MW)(All
Generation)1.0
Risk of Chargeable Transformer UpgradesHigh
Risk of 38kV Network Upgrades High
Development Potential Low
Comment
Potential for 1MW project connecting to
Rosbercon but the risk of 38kV network upgrades
for a project connecting here are considered high.
29. Rosbercon 38kV Loop
• Similar to Callan and Ballyhale 38kV substations, Rosbercon and New
Ross 38kV substations are connected on a 38kV loop fed from
Waterford 110kV substation as shown in Figure 13.
• As a general rule of thumb a 38kV loop circuit can accommodate
c.20MW’s of generation before the thermal capacity and voltage rise
along the circuit becomes a limitation on the network.
• The total existing or planned generation at Rosbercon 38kV substation
is currently estimated at 18.5MW.
• Therefore it is likely that a future projects connecting to this section of
the 38kV network will be required to uprate the existing 38kV network.
Figure 13: 38kV Loop to Rosbercon and New Ross
30. Belview 38kV Substation
38kV Substation Belview
Feeding 110kV Substation Waterford
Number of Transformers & MVA Rating 2x15
Transformer Configuration T421&T422(20kV)
Secondary Voltage Level 20kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 5.0
Planned Generation(MW) 0.0
Total Generation(MW) 5.0
Available Firm Capacity(ESB)(MW) 18.2
Available Non-Firm Capacity(ESB)(MW) 10.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)12.8
Available Capacity(MG)(MW)(All
Generation)12.8
Risk of Chargeable Transformer UpgradesLow
Risk of 38kV Network Upgrades Moderate
Development Potential High
Comment
Potential to connect a project to the 15MVA
transformer in the substation.
31. Mount Misery 38kV Substation
38kV Substation Mount Misery
Feeding 110kV Substation Waterford
Number of Transformers & MVA Rating 2x10
Transformer Configuration T41&T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.1
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 6.0
Planned Generation(MW) 0.0
Total Generation(MW) 6.1
Available Firm Capacity(ESB)(MW) 10.6
Available Non-Firm Capacity(ESB)(MW) 6.7
Available Capacity(MG)(MW)(Connected,
Contracted, Live)7.3
Available Capacity(MG)(MW)(All
Generation)7.3
Risk of Chargeable Transformer UpgradesLow
Risk of 38kV Network Upgrades Moderate
Development Potential High
Comment
Potential to connect a project to the 10MVA
transformer in the substation.
32. Granagh 38kV Substation
38kV Substation Granagh
Feeding 110kV Substation Waterford
Number of Transformers & MVA Rating 2x5
Transformer Configuration T41∥T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 4.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 5.0
Planned Generation(MW) 0.0
Total Generation(MW) 9.0
Available Firm Capacity(ESB)(MW) 1.7
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)1.1
Available Capacity(MG)(MW)(All
Generation)0.0
Risk of Chargeable Transformer UpgradesModerate
Risk of 38kV Network Upgrades Moderate
Development Potential Low
Comment
There does not appear to be capacity at this
substation for new generation as there is a solar
farm with consented planning in the area.
33. Transformer Capacity at Ballyragget 110kV Substation
Table 6: Available 110/38kV transformer Capacity in Ballyragget 110kV substation.
• Table 6 below outlines the available capacity on the planned 110/38kV transformers in Ballyragget considering different amounts of generation.
• It is assumed that once the substation is complete the existing project at Glanbia and the windfarm will be normally fed from Ballyragget 110kV
substation.
• There is a large ECP-2.1 solar farm adjacent to the substation. It is possible that this project gets planning for additional MW’s and connects at 110kV
to Ballyragget thereby allowing for more generation to connect to the 31.5MVA transformers in the substation.
• There appears to be available capacity on the planned transformer in Ballyragget 110kV substation for future generation.
• It should be noted that there may be additional projects in planning or with planning consent in the area that have not been included in this
calculation.
• It is expected that once the substation is complete Castlecomer 38kV substation will be fed from Ballyragget. The existing 38kV compound at
Ballyragget has also been considered in this review.
Project Name Technology MEC 38kV Substation StatusMinimum
Demand(MW)
Transformer
Capacity(Connected,
Contracted,ECP-1)
Transformer
Capacity(Connected,
Contracted,ECP-1,ECP-
2.1)
Transformer
Capacity(All
Generation)
Glanbia Nat. Gas 7.5 Ballyconra Connected
INCH HYDRO Small Hydro 0.042 N/A Connected
Lisdowney Wind 9.2 Ballyconra Connected
16.7
16.7
16.7
16.7
Parksgrove Solar Farm Solar 35.00 N/A ECP-2.1
Subtotal Connected and Contracted
Subtotal Connected, Contracted and ECP-1
Subtotal Connected, Contracted,ECP-1 and ECP-2.1
Total
10.810.810.81.7
34. Castlecomer 38kV Substation
38kV Substation Castlecomer
Feeding 110kV Substation Ballyragget
Number of Transformers & MVA Rating 2x5
Transformer Configuration T41∥T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 0.0
Available Firm Capacity(ESB)(MW) 5.9
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)5.3
Available Capacity(MG)(MW)(All
Generation)0.0
Risk of Chargeable Transformer UpgradesHigh
Risk of 38kV Network Upgrades High
Development Potential Low
Comment
There does not appear to be capacity at this
substation for new generation. The ECP-2.1 solar
farm at this substation will affectively take all of
the available capacity on the 38/10kV
transformers. MullanGrid understand that this part
of the 38kV network is saturated.
35. Ballyragget 38kV Substation
38kV Substation Ballyragget
Feeding 110kV Substation Kilkenny
Number of Transformers & MVA Rating 1x5
Transformer Configuration T42(10kV)
Secondary Voltage Level 10kV
Connected Generation(MW) 0.0
Contracted Generation(MW) 0.0
ECP-1 Generation(MW) 0.0
ECP-2.1 Generation(MW) 0.0
Planned Generation(MW) 0.0
Total Generation(MW) 0.0
Available Firm Capacity(ESB)(MW) 5.7
Available Non-Firm Capacity(ESB)(MW) 0.0
Available Capacity(MG)(MW)(Connected,
Contracted, Live)4.1
Available Capacity(MG)(MW)(All
Generation)4.1
Risk of Chargeable Transformer UpgradesLow
Risk of 38kV Network Upgrades Low
Development Potential Moderate
Comment
Potential to connect a project to the 5MVA
transformer in the substation.
36. EirGrid’s Tomorrow Energy Scenario (TES) Systems Analysis 2019
• The recently published 2019 TES System Needs Analysis provided information on thecapacity of the transmission system in 2030 under a number of scenarios. EirGridwill use this information to identify areas of the transmission system that needreinforcements.
• MullanGrid have analysed one of the scenarios in EirGrid’s TES report that achievethe 2030 70% RES-E target. The Coordinated Action scenario is a high onshore windscenario with approximately 4000MW of new onshore wind, 1800MW of offshorewind and 2000MW of solar generation assumed. This scenario also has relativelyhigh levels of electrification of heat and transport.
• The overloads on the 110kV network in the Kilkenny region for the CoordinatedAction and scenario mapped in Figure 14. The scenario indicates low/moderateoverloads on the transmission network in the region. This is positively showing thetransmission network in Co. Kilkenny has capacity for additional generation.
36. EirGrid Tomorrow’s Energy Scenarios (Contd)
Figure 14: TES Analysis: Coordinated Action 110 kV overloads for the South East
37. Southeast Area H2 ECP-1 Constraint Report• EirGrid dispatch down the output of generation if the local
transmission network is being overloaded, this is referred to as constraints.
• EirGrid have recently completed constraint analysis for the ECP-1 generators. The analysis is presented in reports for projects located in Area H2, see Figure 15.
• The analysis is focussed on ECP-1 and all preceding connected and contracted generation, and therefore does not account for post ECP-1 generation.
• The analysis only covered a relatively short timeframe of 2020-2022. However EirGrid also included a “Future Grid” scenario that included transmission reinforcements likely to happen in the 2022 to 2030 period.
• There are multiple scenarios included in the EirGrid reports. MullanGrid have presented the results of scenarios in the years 2020, 2022 and ‘Future Grid’. The inputs to the scenarios are displayed in Table 7.
• Initial 2020 – connected generation and network upgrades completed up to 2020.
• 2022 All - all contracted and ECP-1 generation connected in 2022, with only limited changes to the existing transmission system. It is probably the most onerous scenario and generally shows the highest constraints. Results are presented for 33%, 66% and 100% build out of all planned contracted and ECP1 generation.
• Future Grid - all contracted and ECP-1 generation connected but with planned upgrades to the transmission system complete.
• The results from these scenarios indicate low levels of constraints in 2020 and 2022, with no constraints in the Future Grid scenario.
Figure 15: EirGrid Area H2
Initial 2020 2022 All Future Grid
Generation
-Connected Generation up to 2020
-All Gate 3 -All Non-GPA -All ECP1
-All Gate 3 -All Non-GPA -All ECP1
Demand -2020 Demand (32.2 TWh)
-2022 Demand (36.2 TWh)
-2022 Demand (36.2 TWh)
Interconnection -Moyle: 255/210 MW -EWIC: 530 MW
-Moyle: 210/138 MW -EWIC: 530 MW
-Moyle: 500 MW -EWIC: 530 MW -Celtic: 700 MW -Greenlink: 500 MW
DS3 Programme
-SNSP: 75% -RoCoF: 1Hz/Sec -Inertia: 17,500 MWs -Large Generator Must Run: ROI 5, NI 3
-SNSP: 75% -RoCoF: 1Hz/Sec -Inertia: 17,500 MWs -Large Generator Must Run: ROI 5, NI 3
-SNSP: 80% -RoCoF: 1Hz/Sec -Inertia: 17,500 MWs -Large Generator Must Run: ROI 4, NI 2 -Reserve provided from alternative sources
Table 7 - EirGrid constraint reports input scenarios
38. EirGrid’s ECP1 Constraint Solar Projections
Figure 16: Constraints in the 2022 All Scenario-Solar
39. EirGrid’s ECP1 Constraint Wind Projections
Figure 17: Constraints in the 2022 All Scenario-Wind
40. Summary of County Kilkenny Grid Potential (Table)
38kV
Substation
Feeding
110kV
Substation
Number of
Transforme
rs & MVA
Rating
Transformer
Configuration
Secondary
Voltage
Level
Total
Generation(
MW)
Available Firm
Capacity(ESB)
(MW)
Available
Capacity(MG)(
MW)
Risk of
Chargeable
Transformer
Upgrades
Risk of 38kV
Network
Upgrades
Potential for
Non-Firm
Access
Connection
Development
Potential
Purcells Inch Kilkenny 1x5,1x10 T42&T41(10kV) 10kV 5.11 7.000 7 Low Low Yes High
Rosehill Kilkenny 2x10 T42&T41(10kV) 10kV 19.00 11.947 8.7 Low Low Yes High
Belview Waterford 2x15 T421&T422(20kV) 20kV 4.99 18.216 12.8 Low Moderate Yes High
Mount Misery Waterford 2x10 T41&T42(10kV) 10kV 6.08 10.600 7.3 Low Moderate Yes High
Graiguenama
naghKilkenny 2x2 T41∥T42(10kV) 10kV 0.00 1.836 1.7 Low Low/moderate No Moderate
Ballyragget Kilkenny 1x5 T42(10kV) 10kV 0.00 5.718 4.1 Low Low No Moderate
McDonagh Kilkenny 2x10 T42 & T41(10kV) 10kV 8.44 11.689 8.4 Low Low Yes Low/Moderate
Granagh Waterford 2x5 T41∥T42(10kV) 10kV 8.99 1.739 0 Moderate Moderate No Low
Bagenalstown Carlow 2x5 T41∥T42(10kV) 10kV 0.12 0.869 0.6 High Moderate No Low
Ballyhale Kilkenny 2x5 T42(10kV)10kV &
20kV0.00 5.395 0 High High No Low
Callan Kilkenny 2x5 T41∥T42(10kV) 10kV 0.50 1.569 1.1 Moderate High No Low
Castlecomer Ballyragget 2x5 T41∥T42(10kV) 10kV 0.00 5.947 0 High High No Low
Goresbridge Kilkenny 2x5 T41∥T42(10kV) 10kV 0.00 1.940 0 High Low/moderate No Low
Talbots Inch Kilkenny 2x5 T41∥T42(10kV) 10kV 4.18 5.788 0 High Low No Low
Rosbercon Waterford1x2,1x5,
1x10T41(10kV)
10kV &
20kV18.53 1.349 1 High High No Low
40. Summary of County Kilkenny Grid Potential (Map)
Figure 18: Summary of Grid Potential