Kghm international, victoria project, past, present and what's next cim presentation for...

27
Victoria Advance Exploration Project Past, Present and What’s Next

Transcript of Kghm international, victoria project, past, present and what's next cim presentation for...

Page 1: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

Victoria Advance Exploration Project Past, Present and What’s Next

Page 2: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

KGHMI “Status” Presentation

2

Purpose: Introduce KGHM International & provide overview of the Victoria Advanced Exploration Project

Expectation: You will have an understanding of the:

• Overall project scope & schedule• Phases of the project• Current status of the project

In & Out of ScopeIN Out

Project Phaseso Advanced Explorationo Production Expansion

Geoscience & Metallurgy Stakeholder Status Advanced Exploration Shaft

o Project Managemento Milestones

Detailed Mine Design Commercial terms Processing Financials

Page 3: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

Forward Looking Statement

3

KGHM International press releases and information on Victoria Project together with supplemental data about our property portfolio and other information, are available on the Company’s Web site at www.kghminternational.com.

All Company audio, visual and written presentations normally contain forward-looking statements, including those identified by the expressions “anticipate”, “believe”, “plan”, “estimate”, “expect”, “intend” and similar expressions to the extent they relate to the Company or its management. The forward-looking statements are not historical facts but reflect the Company’s current expectations regarding future results or events and are based on information currently available to management. Certain material factors and assumptions are applied in providing these forward-looking statements.

Management believes that the expectations reflected in forward-looking statements are based upon reasonable assumptions; however, management can give no assurance that actual results will be consistent with these forward-looking statements. Statements about potential discoveries or extensions of mineralization and deposits are examples of forward-looking statements. There is no guarantee that any discovery of commercial mineralization will be made on KGHMI properties. The material factors or assumptions that were applied in providing these forward-looking statements are contained in various securities filings, all of which are available on SEDAR at www.sedar.com and the Company’s web site.

Undue reliance should not place on any of the Company's audio, visual or written forward-looking statements. Further, a forward-looking statement speaks only as of the date on which such statement is made. The Company undertakes no obligation to publicly update any such statement or to reflect new information or the occurrence of future events or circumstances, except as may be required under applicable securities law.

KGHMI’s qualified persons are responsible for verification and quality assurance of the exploration data and analytical results set forth in this presentation. KGHMI complies with all NI 43-101 rules and regulations.

Page 4: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

KGHM International Ltd.

4

Ajax Project

Page 5: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Past

5

2004

009

2011

2008

Operations initiated at Victoria Mine (Mond Nickel Co)

Mine Closed

Victoria Mine re-opened by Inco Ltd 2010

2011

1899

20021970- 1978

1923

FNX Mining Company options Victoria Property from Inco Ltd.

FNX Mining Co. begins explorationat Victoria

Zone 4 Discovery

Inferred resource announced

2013

Project Start

Page 6: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Start - Environmental Baseline

6

• Surface water Volume, flow rate, quality

• Ground water Depth, flow direction, quality

• Weather Temperature, precipitation, wind,

• Geochemistry of rock Drill program & geochemical testing

• Aquatic organism surveys Benthos, fish, wetland habitat

• Terrestrial organism surveys Species at Risk, fauna, forest habitat

Page 7: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

Surface Water Monitoring

7

Page 8: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Reason

• 14.2 M tonnes of Inferred Resource in a Ni-Cu-PGE Deposit

• 2.5% Cu, 2.5% Ni, 0.23 oz/ton TPM

• 700 M lbs Cu, 700 M lbs Ni, 3.6 M oz TPM (Contained)

8

Page 9: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Location

9

WanapiteiLake

Sudbury Igneous ComplexSublayer & Offset Rocks

10 km

Foy Offset and North RangeFoy Offset and North RangePodolskyPodolsky

KirkwoodKirkwood

LevackLevack

McCreedy WestMcCreedy West

VictoriaVictoria

Falconbridge FWFalconbridge FW

SudburySudbury

Worthington Offset

Sudbury Igneous Contact

Page 10: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Neighbours

10

Page 11: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

Historic Victoria Mine

Crean Hill

Rd

Fairbank East Rd

VICTORIA PROPERTYDENISON TOWNSHIP

HWY 17

The Property

Victoria Project

11

Page 12: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Geology

12

Creighton Fault

Powerline Zone

Far W

est

Mai

n

No.

2 W

est

No.

2N

o. 1

No.

4Metabasalt

Quartz DioriteNoriteOlivine Diabase

2,000 ft0

Sudbury Breccia

RhyoliteMetasediment

Metagabbro

Victoria Deposit

Page 13: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Deposit

13

13

Quartz DioriteSulphide Mineralization

Creighton Fault

Quartz Diorite HostedMineralization

Sudbury Breccia Hosted Mineralization

0 ~ 200m

Quartz Diabase

Page 14: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Management

14

GM

External Affairs Safety“E”

Technical Services

“P”

Procurement & Finance

“M1”

Shaft, Hoisting Plant & UG Infrastructure

“C1”

Shaft, Hoisting Plant & UG Infrastructure

(Sole Source – DMC)

“M2”

Surface Infrastructure

“C2”

Surface Infrastructure (Tender)

“M3”

Energy Infrastructure

“C3”

Energy Infrastructure

(Tender)

EPCM• Safety & External Affairs led by UG Operations Management• KGHMI “E” Manager keeper of baselines, project controls• KGHMI “P” Manager controls finance & purchase of assets• KGHMI “M” Managers direct contact for the “C” Contractors• “C” Contracts (3) – Design / Build

Legend

Owner’s Team

Major Contract Manager

Page 15: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Status

Project Team▪ Established organization structure▪ 9 critical hires, 27 secondary hires, total project team = 42▪ Established integration with Operations

Permitting ▪ MNR – Timbering & SAR permits in hand▪ MOE – PTTW & ECA’s in review, anticipate issuance Nov./13▪ MNDM – Closure Plan submitted, anticipate approval Oct. 20/13

CommunityStakeholders

▪ Vale Agreement complete▪ Road Upgrade Agreement with City of Greater Sudbury for

approval▪ First Nations

– MOU’s in hand– Exchanging IBA drafts

Project Controls

▪ Project Charter approved▪ Project Management Plan (PMI) in developed▪ WBS & Chart of Accounts established▪ Project budget established

15

Page 16: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Contracts

Site Preparation

▪ E – Earthworks at IFT (90%)▪ P – Earthworks tender in October▪ C – Timbering initiated, complete end of October▪ M – Scope, schedule & cost defined

Shaft Sinking & Hoist Plant(DMC)

▪ E – GA’s complete (30%), detailed engineering progressing▪ P – Sinking hoists ordered▪ C – Mobilize Apr./14▪ M – Developing construction contract

Energy Infrastructure

▪ E – GA’s complete, 230kV & 69kV engineering progressing▪ P – 69kV transformers & switch gear in hand▪ C – Mobilize Jan./14▪ M - Developing tendering packages

Surface Infrastructure

▪ E – Site GA’s complete (30%), detailed engineering progressing▪ P – WWTP equipment being fabricated▪ C – Mobilize Apr./14▪ M – Developing tendering packages

16

Page 17: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Timeline

17

17

Mine Development & Production

2013

Exploration Shaft Sinking

Site Preparation &Infrastructure Construction

LOM Production

Advanced Exploration Project

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024

DefinitionDrilling

Production ShaftSinking

Expansion Project

U/GDevelopment

2034?

Commercial Production

Early Production

Page 18: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Phases

CAPITAL PROJECTS

Advanced Exploration (2013-18)

• Site preparation

• Construction of surface infrastructure

• Sinking of exploration shaft

• UG definition drilling & bulk sample

• Construction of UG infrastructure

• Production Expansion Decision Study

OPERATIONS

Early Production (2019-22)

• Ramp connection between 18L, 16L and 14L

• Develop sublevel accesses & ventilation

• Production from Blocks 2, 3 and 4

Production Expansion (2019-22)

• Additional surface infrastructure

• Sinking of production shaft

• Construction of UG infrastructure

LOM Production (2023 – 34?)

• Operations

18

Page 19: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Site Plan – Advanced Exploration

19

Page 20: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Deliverables

14L

16L

18L – Bulk Sample

100,000 m of definition drillingMine Plan

20

Geotechnical Design

Page 21: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Procurement

21

• Site Timbering

• Tendering Overburden Stripping & Rockworks

• Sinking & Auxiliary Hoists ordered

• Sinking Winches – order being finalized

• 69kV Power substations partially refurbished

• Communication fiber optics to site work package being finalized

• Natural gas to site being engineered by Union Gas

Page 22: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Development

22

Page 23: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Production

23

• Primary / Secondary sequence

• Paste Backfill – 150 t/hr

• Average 25,000 tonnes per stope

• Average 16% dilution & 90% recovery

• Average 90 day cycle time

o Drilling 150 m/day, 11t/m

o Blasting 0.44kg emulsion / tonne

Page 24: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Site Plan – Production Expansion

24

Page 25: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Future

25

KGHMI

• Advance IBA’s with First Nations

• Build Project Team

• Closure Plan Approval

• Receive Environmental Permits

• Continue Engineering

• Complete Timbering

• Initial Earthworks

• Following activities– Secure remaining hoists & winches

– Construction & permanent power

– Natural gas supply

– Road upgrades

Important dates• Closure Plan Oct.

20/13• Timbering completion Nov. 1/13• MOE Permits Nov./13• Initiate stripping Nov./13• Rock Work 2014

Page 26: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

The Project Facts

26

Category Qty UnitsInferred Resource 14.2 MtDilution 16 %Recovery 90 %Tonnes / Metre 20,000 t/mDevelopment (Cap) 52 kmDevelopment (Op) 17 kmDrilling 140 km

Metal Grade Units Qty Units

Cu 2.5 % 710 MlbsNi 2.5 % 720 MlbsCo 0.05 % 15 MlbsPt 0.08 oz/Ton 1,310 KozPd 0.12 oz/Ton 1,890 KozAu 0.03 oz/Ton 420 KozAg 0.40 oz/Ton 6,260 Koz

Contained Metal

Team QtyProject Owners Team 40Contractor 300Manpower - Phase 1 150Manpower - Phase 2 280

Page 27: Kghm international, victoria project, past, present and what's next   cim presentation for distribution

Thank you