K. Long, 14 June, 2015 Target K. Long, Friday, 24 th April 2009.
4
K. Long, 23 June 2022 Target K. Long, Friday, 24 th April 2009
-
date post
20-Dec-2015 -
Category
Documents
-
view
215 -
download
1
Transcript of K. Long, 14 June, 2015 Target K. Long, Friday, 24 th April 2009.
K. Long, 18 April 2023
Target
K. Long, Friday, 24th April 2009
Critical path:
• No particular issues, but:– Vacuum tubes ready to be sent to Sheffield– Stator assembly ready for vacuum tubes at Sheffield– Weld trials successful– Parts in manufacture
Manufacturing: highlights:
Installation and commissioning schedule:• Presented / discussed at Target w/s last Friday• Revised version to be presented / discussed at
CM24• Need to have Target w/s with ISIS in June:
– Make sure manufacturing remains on track;– Discuss installation and commissioning plans;– Ensure manpower assumptions for shutdown are valid