JUAN MANUEL VALDEZ POWER PLANT GUIRIA, …...JUAN MANUEL VALDEZ POWER PLANT GUIRIA, VENEZUELA FEB....
Transcript of JUAN MANUEL VALDEZ POWER PLANT GUIRIA, …...JUAN MANUEL VALDEZ POWER PLANT GUIRIA, VENEZUELA FEB....
SMART LOGISTICS UNLOCK A TIME-SAVING ROUTE.
JUAN MANUEL VALDEZ POWER PLANTGUIRIA, VENEZUELA
MAR. 23FEB. 22 MOBILIZATION OF MTC-15 ON ITS WAY TO PROJECT SITE
Discover more on www.mammoet.com
MAR. 22 OFFLOADING A GENERATORFEB. 25 READY FOR MAIDEN JOB
A Z
AN INNOVATION THAT SAVED TWO MONTHS AND US$ 10 MILLION.
Building the right power
infrastructure is often the first on
the list of developing nations, but
getting the job done frequently
means accessing remote locations
in uncertain conditions. Such was
the case in Venezuela’s Guiria,
a small fisherman’s port near the
Juan Manuel Valdez power plant.
Guiria was an ideal site to transship
45,000 freight tons of oversized and
heavy cargo destined for the plant.
However, without the necessary
heavy lifting capacity and
insufficient draught for a heavy lift
vessel, the town’s port was initially
ruled out by the client. By putting
one of their innovations in play,
Mammoet unlocked a faster and
more cost-effective route.
Mammoet was contracted to deliver
two turbines, two generators and
associated cargo; key components
necessary to build the 900MW
combined cycle power plant for
the growing Venezuelan market.
With the load coming from factories
across Europe and the United States,
key was determining the most efficient
route to site without impacting project
costs, safety and timelines.
Guiria’s local port would be ideal, as it
is located 20 kilometers from the site
and the nearest alternative, Guanta,
was 350 kilometers away and had its
own logistical challenges. However this
port was found unsuitable: its shallow
draught did not allow the use of a
heavy lift vessel. And its ground
bearing capacity was too limited to
accommodate a conventional crane
with sufficient lifting capacity,
Exploring the possibilities thoroughly,
Mammoet soon identified a much
faster approach that would also save a
significant amount of money. Thanks to
a Mammoet innovation, we took the
bold step of recommending the route
previously ruled out. The MTC-15 is a
containerized terminal crane with a
capacity up to 600 tons and a low
ground bearing pressure. The crane is
specifically designed to quickly turn
any quayside into a heavy lifting facility.
For a more efficient cargo flow, the
turbines and generators were first
consolidated in Texas before shipping
to Guiria. The transformers arrived at
the same location via Trinidad.
Meanwhile in Guiria, the MTC-15 had
turned the port into a heavy lifting
terminal. Once offloaded, the cargo
was transported by road to the plant
site.
A clever and more efficient logistics
concept, that avoided logistical
challenges that came with other routes.
Together with the MTC-15 Mammoet
reduced the project timeline by two
months, saving around $10M on the
plant’s logistics bill. The Juan Manuel
Valdez plant was erected efficiently,
allowing Venezuela to continue its
growth spurt unbridled.
RESOURCES
CRANES 1 Mammoet Terminal Crane (MTC-15)1 hydraulic crane1 gantry crane
SPECIAL EQUIPMENT Mammoet Skidding System1 forklift
TRANSPORT 28 axle lines of conventional trailers5 prime movers2 low bed trailers 2 flatbed trailers
CREW 25 Mammoet Professionals