John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year...

9
John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in New England

Transcript of John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year...

Page 1: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

John Norden, Manager, Renewable Resource IntegrationISO New England Inc.

2009 NASUCA Mid-Year MeetingJune 30, 2009

Roadmap to Renewable Integration in New England

Page 2: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

New England’s Future Grid

• Distributed and renewable resources becoming main-stream

– Demand Resources

– Storage devices such as flywheels, batteries and plug-in electric vehicles

– Wind and other intermittent renewable resources

• Wind resources present the largest source of renewable generation in New England

© 2009 ISO New England Inc. 2

Page 3: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

Integrating Wind Resources

• Will need:

– Transmission infrastructure to deliver large-scale wind from remote areas to load centers

– Transmission funding mechanisms

• i.e., participant funding, cost sharing agreements, federal incentives

– Favorable investment and regulatory environment

– Identification and resolution of operational challenges

© 2009 ISO New England Inc. 3

Page 4: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

Wind Integration Challenges:Operational

• Near-term forecast uncertainty– Can cause over/under commitment

• Variability– Regulation time-scale

• May require increased regulation capability

– Load following time-scale• May require additional ramping capability

– Day ahead time-frame• Complicates unit commitment

• Minimum generation issues• Congestion management

© 2009 ISO New England Inc. 4

Page 5: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

Wind Integration Challenges:Operational, Cont.

• Coordination with other Balancing Areas– Sharing the variability (and reduce overall variability)– Wind from other areas (who pays/who owns?)

• Spinning reserve– Usually no effect—only large generators/lines

• Unless loss of wind (or forecast error) exceeds 2nd largest contingency

• Non-spin reserve– Wind may increase non-spin reserve requirements

© 2009 ISO New England Inc. 5

Page 6: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

Wind Integration Challenges:Markets & Planning

• Markets– Over-commitment of wind may:

• Lead to inefficient use of resources

• Depress LMPs and/or raise out-of-merit compensation

– Under-commitment of wind may:• Increase price volatility

– Real-time vs. Day-ahead

• Planning– Resource adequacy issues– Effective Load Carrying Capacity (ELCC)

• System wide, zonal, per generator (incremental)?

© 2009 ISO New England Inc. 6

Page 7: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

ME 1255 MW

NH 330 MW

VT155 MW

MA 30 MW

MA Off-Shore 460 MW

RI Off-Shore 350 MW

On-Shore = 1770 MWOff-Shore = 810 MW Total = 2580 MW

7© 2009 ISO New England Inc.

* ISO-NE Interconnection Queue, June 2009

Wind Projects Proposed in ISO Queue

Page 8: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

New England Wind Integration Study

• Objectives:

– Determine technical requirements

– Create wind model including on-shore and off-shore capability

– Assess impact of wind development scenarios on system operations

– Identify best practices to forecast wind

– Determine contribution of wind to system adequacy

© 2009 ISO New England Inc. 8

Page 9: John Norden, Manager, Renewable Resource Integration ISO New England Inc. 2009 NASUCA Mid-Year Meeting June 30, 2009 Roadmap to Renewable Integration in.

Conclusions

• The New England power system will undergo major changes in the next two decades

• The integration of wind will cause an evolution in the operation and planning of the power system

• ISO-NE is responding to the immediate challenges of the evolving grid and planning for the future needs of the power system

© 2009 ISO New England Inc. 9