Javier A. Sevilla MMF [email protected] FAC Review October 27, 2005 1 Magnetic...

24
Javier A. Sevilla MMF Status [email protected] .edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements Team Facility Layout Pre-Construction Activities Construction activities and Status to Date Safety Program Budget and Schedule Technical Challenges (Risks) Management Challenges Path Forward
  • date post

    20-Dec-2015
  • Category

    Documents

  • view

    215
  • download

    2

Transcript of Javier A. Sevilla MMF [email protected] FAC Review October 27, 2005 1 Magnetic...

Page 1: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20051

Magnetic Measuring Facility (MMF) Outline

Summary of Facility RequirementsTeamFacility LayoutPre-Construction Activities Construction activities and Status to Date Safety ProgramBudget and Schedule Technical Challenges (Risks)Management ChallengesPath Forward

Page 2: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20052

Site Location Building 081-MMF

LCLS Undulator

HallBTH

PEP Ring Road

NORTH

LINAC

B48-ROB

280

Page 3: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20053

Facility Design Requirements

Technical Note LCLS-TN-041-Z

Space Requirements

Environmental Stability (3 areas)

Space Temperature: ± 0.1 °C short term may go up to 0.3°C if < 1Hr

Relative Humidity: 45%± 5%

Other areas: ±1°C and ±2.5°C

Vibration <0.5 microns-MM Lab

Utility Requirements

Electrical (new 800A, 12.47KV feeder MMFBldg Upgrade)

Other (compressed air and small chiller for User’s equipment)

Page 4: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20054

MMF Facility Uses

Undulator magnet tuning – 2 magnet measuring machine test stands

Aligned with same orientation to Earth’s magnetic field as LCLS Undulator Hall.

Undulator fiducialization – large coordinate measuring machineCradle assembly areaMagnet storage/temperature acclimationWork desks in lab and office space for 2 employees

Page 5: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20055

Resultant Facility Criteria

~4,800 sq. ft. floor space (inc. ~3,000 laboratory space, mech Rm) + mezzanine 1,400 sf (HVAC & Electrical)Locate within an existing building to aid in temperature controlAdequate ceiling height for overhead cranesAccessible for magnet delivery using trucks and forkliftsElectrical service – 800A, 480v, 3Ø (New Feeder to building)

Page 6: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20056

TeamworkFuture Users Magnetic Measurement Facility (MMF)

Robert Ruland – Alignment MgrZachary Wolf – User

Conventional Facilities-WBS 1.09David Saenz – CF Sys ManagerJim Welch – CF Systems PhysicistJavier A. Sevilla-CF Project/CAMK.Chan, K. Yang-CEF UTRRichard Hislop & M. Scharfenstein– Safety & ESHAnita Malahowski –Cost/Schedule

General Contractor and SubsBuilding Occupants (Stores, Transportation, Receiving, Property Jacobs (A&E Title III)

A&EJE

CEF UTR Support

Building Occupants

MMF Users

ConventionalFacilities

GC &Contractors

DOE SSO

Page 7: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20057

Floor Space Allocation-Bldg. 081

SHIPPING & RECEIVING

EQUIPMENT REPAIR

VEHICLE SHOP

Offices

(N) MCC-B081

Front

Rear

(N) Fire Alarm Panel

AP

ReceivingPC

TransportationStores MMF

Page 8: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20058

Building 081 Site Plan Before

Now

Haz Mat

Page 9: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 20059

MMF Ground Floor Plan

Coordinate Measuring

Area~ 1,000 ft. sq.

Cradle Assembly Area~325 ft. sq.

Magnet Loading and Storage~850 ft. sq.

± 2.5°C

± 1°C, 45% RH ±5

Magnet Measuring Lab

~1,800 ft. sq.

± 0.1°C, 45%RH ±5

Rear

Mechanical Room~256 ft. sq.

Page 10: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200510

Mezzanine Floor Plan

Mezzanine for Mechanical/ElectricalEquipment in Conditioned space

4 Air handling Units1 Motor Control Center,X-trmr, Panels,1 small CompressorHVAC Control Panel

Equipment:

Rear

MCC-MMF(on-site)

Page 11: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200511

NORTH

CMM

Test stands

DemisingWall

Page 12: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200512

Pre-Construction Activities

Selection of General Contractor based on specific criteriaReview of subcontractors qualifications (electrical, controls and mechanical)Pre-Construction MeetingReview of Contractor Safety PlanSite mobilizationOrder LLP equipment

Page 13: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200513

General Contractor and Subcontractors

Team

Project Manager: Steve Winslow

Project Superintendent: Gary Meadows

Project Engineer: Kevin Ng

Safety Coordinator: Craig Pancoast

President: Eric Raff

Subs:

AIM

AMS

ASI

SJS

North Star

Blue water

Page 14: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200514

Construction Progress

New Demising Wall Demolition Work

Page 15: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200515

Work Completed and On-GoingDemolition of (e) officesAsbestos AbatementNew demising wall and others wallsExcavationNew concrete footings New fence

Wet Sprinkler SystemSteel FabricationMEP Layout

Page 16: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200516

Work Progress

Footings for Test Stands No. 1 & 2

Footings for Test Stand No. 1

Page 17: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200517

Safety ProgramAlignment of Goals and Objectives

LCLS Environmental,

Safety ad Health Plan

Contractor’s Site Specific Safety

Plan

PM, CEF and LCLS UTR’s

ES&H SMEBuilding Occupants

ZERO ACCIDENTS

DOE SO

Page 18: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200518

Budget & Schedule

Title IIIConstruction $2.5M

(excludes: fire alarm building upgrade B081, roof repair and some stores relocation costs)

Electrical Feeder (12.47KV, Transformer and MCC): 460K$Total TPC: 3.0 M$

Bidding and AwardFirst bids due May 5, 2005Re-bid combined with S20: July 7, 2005.Awarded: July 28, 2005Kick Off meeting: August 22, 2005Mobilization on site: August 29, 2005Beneficial Occupancy, LCLS L4 February, 28 2006

Page 19: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200519

Critical Path Schedule

L4: BO Feb-28-2006

Page 20: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200520

Risks

Internal technical: Not achieving the Temperature and Stability requirements

Plan: Design reviews, constructability and commissioning plan

Internal non-technical: Delays in the BO date Plan: Use Good planning and effective Project Management approach, and select only “qualified” contractors including subs

Internal non-technical: Safety accidentsPlan: Strict implementation of Safety Plans and Procedures

Page 21: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200521

Management Challenges

Schedule and ResourcesSupport form other SLAC’s Departments (ES&H, CEF)

Prioritization of activities

On-Going implementation of new Policies at SLAC (UTR responsibilities, Authority and Oversight)

Page 22: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200522

Path Forward

Continue partnership with ALL stakeholdersContinue to enforce Safety Regulations to All Sub-ContractorsStrict implementation and compliance of drawings and technical specifications to meet User’s requirementsContinue Construction towards Testing and Commissioningo Strict Schedule and Cost Controlso Execute an integrated verification of: operational performance,

testing, complete documentation and training of SLAC personnel, which will operate and maintain this Facility.

Page 23: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200523

Magnetic Measuring Facility (MMF) SUMMARY

Summary of Facility RequirementsTeamFacility LayoutPre-Construction activities to dateConstruction activities and Status to Date Safety ProgramBudget and Schedule Technical Challenges (Risks)Management ChallengesPath Forward

Thanks !

Page 24: Javier A. Sevilla MMF Statussevilla@slac.stanford.edu FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Javier A. Sevilla

MMF Status [email protected]

FAC Review October 27, 200524

END