Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20051
Magnetic Measuring Facility (MMF) Outline
Summary of Facility RequirementsTeamFacility LayoutPre-Construction Activities Construction activities and Status to Date Safety ProgramBudget and Schedule Technical Challenges (Risks)Management ChallengesPath Forward
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20052
Site Location Building 081-MMF
LCLS Undulator
HallBTH
PEP Ring Road
NORTH
LINAC
B48-ROB
280
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20053
Facility Design Requirements
Technical Note LCLS-TN-041-Z
Space Requirements
Environmental Stability (3 areas)
Space Temperature: ± 0.1 °C short term may go up to 0.3°C if < 1Hr
Relative Humidity: 45%± 5%
Other areas: ±1°C and ±2.5°C
Vibration <0.5 microns-MM Lab
Utility Requirements
Electrical (new 800A, 12.47KV feeder MMFBldg Upgrade)
Other (compressed air and small chiller for User’s equipment)
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20054
MMF Facility Uses
Undulator magnet tuning – 2 magnet measuring machine test stands
Aligned with same orientation to Earth’s magnetic field as LCLS Undulator Hall.
Undulator fiducialization – large coordinate measuring machineCradle assembly areaMagnet storage/temperature acclimationWork desks in lab and office space for 2 employees
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20055
Resultant Facility Criteria
~4,800 sq. ft. floor space (inc. ~3,000 laboratory space, mech Rm) + mezzanine 1,400 sf (HVAC & Electrical)Locate within an existing building to aid in temperature controlAdequate ceiling height for overhead cranesAccessible for magnet delivery using trucks and forkliftsElectrical service – 800A, 480v, 3Ø (New Feeder to building)
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20056
TeamworkFuture Users Magnetic Measurement Facility (MMF)
Robert Ruland – Alignment MgrZachary Wolf – User
Conventional Facilities-WBS 1.09David Saenz – CF Sys ManagerJim Welch – CF Systems PhysicistJavier A. Sevilla-CF Project/CAMK.Chan, K. Yang-CEF UTRRichard Hislop & M. Scharfenstein– Safety & ESHAnita Malahowski –Cost/Schedule
General Contractor and SubsBuilding Occupants (Stores, Transportation, Receiving, Property Jacobs (A&E Title III)
A&EJE
CEF UTR Support
Building Occupants
MMF Users
ConventionalFacilities
GC &Contractors
DOE SSO
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20057
Floor Space Allocation-Bldg. 081
SHIPPING & RECEIVING
EQUIPMENT REPAIR
VEHICLE SHOP
Offices
(N) MCC-B081
Front
Rear
(N) Fire Alarm Panel
AP
ReceivingPC
TransportationStores MMF
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20058
Building 081 Site Plan Before
Now
Haz Mat
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 20059
MMF Ground Floor Plan
Coordinate Measuring
Area~ 1,000 ft. sq.
Cradle Assembly Area~325 ft. sq.
Magnet Loading and Storage~850 ft. sq.
± 2.5°C
± 1°C, 45% RH ±5
Magnet Measuring Lab
~1,800 ft. sq.
± 0.1°C, 45%RH ±5
Rear
Mechanical Room~256 ft. sq.
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200510
Mezzanine Floor Plan
Mezzanine for Mechanical/ElectricalEquipment in Conditioned space
4 Air handling Units1 Motor Control Center,X-trmr, Panels,1 small CompressorHVAC Control Panel
Equipment:
Rear
MCC-MMF(on-site)
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200511
NORTH
CMM
Test stands
DemisingWall
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200512
Pre-Construction Activities
Selection of General Contractor based on specific criteriaReview of subcontractors qualifications (electrical, controls and mechanical)Pre-Construction MeetingReview of Contractor Safety PlanSite mobilizationOrder LLP equipment
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200513
General Contractor and Subcontractors
Team
Project Manager: Steve Winslow
Project Superintendent: Gary Meadows
Project Engineer: Kevin Ng
Safety Coordinator: Craig Pancoast
President: Eric Raff
Subs:
AIM
AMS
ASI
SJS
North Star
Blue water
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200514
Construction Progress
New Demising Wall Demolition Work
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200515
Work Completed and On-GoingDemolition of (e) officesAsbestos AbatementNew demising wall and others wallsExcavationNew concrete footings New fence
Wet Sprinkler SystemSteel FabricationMEP Layout
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200516
Work Progress
Footings for Test Stands No. 1 & 2
Footings for Test Stand No. 1
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200517
Safety ProgramAlignment of Goals and Objectives
LCLS Environmental,
Safety ad Health Plan
Contractor’s Site Specific Safety
Plan
PM, CEF and LCLS UTR’s
ES&H SMEBuilding Occupants
ZERO ACCIDENTS
DOE SO
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200518
Budget & Schedule
Title IIIConstruction $2.5M
(excludes: fire alarm building upgrade B081, roof repair and some stores relocation costs)
Electrical Feeder (12.47KV, Transformer and MCC): 460K$Total TPC: 3.0 M$
Bidding and AwardFirst bids due May 5, 2005Re-bid combined with S20: July 7, 2005.Awarded: July 28, 2005Kick Off meeting: August 22, 2005Mobilization on site: August 29, 2005Beneficial Occupancy, LCLS L4 February, 28 2006
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200519
Critical Path Schedule
L4: BO Feb-28-2006
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200520
Risks
Internal technical: Not achieving the Temperature and Stability requirements
Plan: Design reviews, constructability and commissioning plan
Internal non-technical: Delays in the BO date Plan: Use Good planning and effective Project Management approach, and select only “qualified” contractors including subs
Internal non-technical: Safety accidentsPlan: Strict implementation of Safety Plans and Procedures
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200521
Management Challenges
Schedule and ResourcesSupport form other SLAC’s Departments (ES&H, CEF)
Prioritization of activities
On-Going implementation of new Policies at SLAC (UTR responsibilities, Authority and Oversight)
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200522
Path Forward
Continue partnership with ALL stakeholdersContinue to enforce Safety Regulations to All Sub-ContractorsStrict implementation and compliance of drawings and technical specifications to meet User’s requirementsContinue Construction towards Testing and Commissioningo Strict Schedule and Cost Controlso Execute an integrated verification of: operational performance,
testing, complete documentation and training of SLAC personnel, which will operate and maintain this Facility.
Javier A. Sevilla
MMF Status [email protected]
FAC Review October 27, 200523
Magnetic Measuring Facility (MMF) SUMMARY
Summary of Facility RequirementsTeamFacility LayoutPre-Construction activities to dateConstruction activities and Status to Date Safety ProgramBudget and Schedule Technical Challenges (Risks)Management ChallengesPath Forward
Thanks !