Jabari 2015

download Jabari 2015

of 13

Transcript of Jabari 2015

  • 7/26/2019 Jabari 2015

    1/13

    Large-scale power system controlled islanding based on Backward

    Elimination Method and Primary Maximum Expansion Areas

    considering static voltage stability

    Farkhondeh Jabari a,, Heresh Seyedi a, Sajad Najafi Ravadanegh b

    a Faculty of Electrical and Computer Engineering, University of Tabriz, Tabriz, Iranb Smart Distribution Grid Research Lab, Department of Electrical Engineering, Azarbaijan Shahid Madani University, Tabriz, Iran

    a r t i c l e i n f o

    Article history:

    Received 21 September 2014

    Received in revised form 26 November 2014

    Accepted 1 December 2014

    Keywords:

    Backward Elimination Method (BEM)

    Binary Imperialistic Competitive Algorithm

    (BICA)

    Boundary network

    Primary Maximum Expansion Area (PMEA)

    Slow coherency

    Static voltage stability

    a b s t r a c t

    This paper proposes a novel approach for separation of bulk power system into several stable subsystems

    following a severe disturbance. An interconnected power system may become unstable due to wide area

    contingency when it is operated close to the stability boundaries as a result of increased demand, power

    industry restructuring and competition in the deregulated electricity markets. Meanwhile, large-scale

    power system controlled splitting is the last resort to prevent catastrophic cascading outages and wide

    area blackout. The proposed method of this paper reduces the huge initial search space of the islanding

    strategy to only interface boundary network by clustering the coherent generators and simplifying the

    network graph. Then, Backward Elimination Method (BEM) based on Primary Maximum Expansion Areas

    (PMEAs) has been proposed to generate all proper islanding scenarios in the simplified graph. The New-

    tonRaphson power flow method and QV modal analysis have been used to evaluate the steady state

    stability of the islands in each generated scenario. Binary Imperialistic Competitive Algorithm (BICA)

    has then been applied to minimize total load-generation mismatch considering no-isolated bus, voltage

    permitted range and static voltage stability constraints. Comprehensive discussions have been provided

    using the simulations on NPCC 68-bus test system. The results demonstrate the speed, effectiveness andcapability of the proposed strategy to generate fast feasible splitting solutions considering static and

    dynamic stability.

    2014 Elsevier Ltd. All rights reserved.

    Introduction

    Power industry restructuring and competition in the deregu-

    lated electricity markets in order to provide increased consump-

    tion causes operation of large power systems close to their

    stability margins. Although an interconnected power system may

    be stable against small disturbances, wide area contingencies

    may cause the system to lose stability and lead to the catastrophic

    wide area blackouts. Hence, splitting is the final action to preventcascading failures. Power system islanding procedures will have to

    determine two important issues[1]:

    1. When to split

    Islanding starts exactly after separating detection. In recent

    years, many different techniques have been proposed to detect

    the interconnected power system splitting.

    2. Where to split

    Many wide area blackouts such as 2003 Italy [2], 2003 Sweden

    Denmark[3], 2003 United States and Canada [4], 2005 JavaBali

    [5], 2009 Brazil and Paraguay [6], July 2012 India blackout [7]

    may have been prevented and load-generation mismatch may

    have been reduced by fast, accurate, feasible controlled splitting

    strategies[811]. Controlled intentional islanding separates a bulk

    power system into a number of stable islands by tripping selectedtransmission lines according to the minimum load-generation mis-

    match [12]. Hence, once separation is detected, the most important

    step is to find the optimal splitting points. In the literature, several

    approaches have been proposed to split a large power system into

    several stable sections following a wide area contingency. These

    procedures can be divided into two general categories. The first

    one is based on the coherent generators clustering and the second

    one is based on the network graph theory.

    http://dx.doi.org/10.1016/j.ijepes.2014.12.008

    0142-0615/ 2014 Elsevier Ltd. All rights reserved.

    Corresponding author. Tel.: +98 41 33393732.

    E-mail addresses: [email protected] (F. Jabari), [email protected]

    (H. Seyedi),[email protected](S. Najafi Ravadanegh).

    Electrical Power and Energy Systems 67 (2015) 368380

    Contents lists available at ScienceDirect

    Electrical Power and Energy Systems

    j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m / l o c a t e / i j e p e s

    http://dx.doi.org/10.1016/j.ijepes.2014.12.008mailto:[email protected]:[email protected]:[email protected]://dx.doi.org/10.1016/j.ijepes.2014.12.008http://www.sciencedirect.com/science/journal/01420615http://www.elsevier.com/locate/ijepeshttp://www.elsevier.com/locate/ijepeshttp://www.sciencedirect.com/science/journal/01420615http://dx.doi.org/10.1016/j.ijepes.2014.12.008mailto:[email protected]:[email protected]:[email protected]://dx.doi.org/10.1016/j.ijepes.2014.12.008http://crossmark.crossref.org/dialog/?doi=10.1016/j.ijepes.2014.12.008&domain=pdf
  • 7/26/2019 Jabari 2015

    2/13

    Islanding based on coherent generators clustering

    In the literature, there are mainly two clustering methodology:

    The first one identifies coherent machines through a time-domain

    simulation according to the dynamic behavior of each generator

    due to specific disturbance. Hence, the machines with similar rotor

    angle or speed curves are assumed to be coherent. Slow coherency

    theory as a two-time-scale method is a driven force behind the first

    procedure. It is based on the power system oscillations which can

    be classified into two modes; local or intra-area modes in the 1

    3 Hz range and inter-area modes less than 1 Hz [13]. The machines

    with the same inter-area mode swing together and they are called

    coherent in the selected inter-area modes[14]. In[15], the coher-

    ent groups are determined through the Empirical Mode Decompo-

    sition (EMD) and Stochastic Subspace Identification (SSI) method.

    In this method, the generator rotor speed prepared from the Wide

    Area Measurement System (WAMS) is only used to cluster the

    coherent machines. In[16], a novel approach based on the correla-

    tion characteristics of the generator rotor angle oscillation is pre-

    sented to identify the coherent machines. In proposed scheme,

    the correlation coefficients of generators are assessed by online

    measurement of rotor angle oscillations. In[1720], a slow coher-

    ency method has been applied to cluster the coherent generators of

    an interconnected power network. The mathematical background

    of slow coherency theory and selective modal analysis can be

    found in[21].

    In[12], the slow coherency theory is used to obtain the desired

    generator groups. Angle Modulated Particle Swarm Optimization

    (AMPSO) is then used to find a number of candidate scenarios that

    provide optimal static and dynamic characteristics. In[2123], the

    coherent machines have been clustered by the slow coherency the-

    ory. A spanning tree based Breadth First Search (BFS) algorithm is

    then used to find all proper islanding scenarios. This method

    reduces the large initial search space of the integrated power sys-

    tems islanding to the boundary branches. The proposed islanding

    strategy determines the best separating points according to the

    minimum load shedding. In[25,26],the Krylov projection methodhas been used to cluster the coherent machines. A spanning tree

    based Depth First Search (DFS) algorithm has then been used to

    find all candidate solutions in reduced search space. In [27], the

    slow coherency based grouping is used to provide the primary

    dynamic criteria. An automatic islanding program is then applied

    to find the optimal cutsets to form the isolated stable islands con-

    sidering minimum load-generation mismatch. All generators clus-

    tering techniques reduce the large search space of the islanding

    from the entire system to the boundary interface network signifi-

    cantly. The slow coherency based islanding has two important

    advantages [2124,27].

    1. Slow coherency based clustering is independent of the size,

    type and location of the disturbance. Hence, it is possible todesign a defensive splitting strategy before a wide area

    disturbance.

    2. Slow coherency based clustering is independent of the genera-

    tor model details. So, the classical model can be used.

    Islanding based on network graph theory

    An interconnected power system can be interpreted as a simple

    two-dimensional graph. The inputs are nodes and branches. In real

    power system,the numberof nodes andbranches increaseconsider-

    ably. Hence, the bulk power system splitting will have a large initial

    search space. In some literature, the scenario reduction techniques

    based on graph simplification have been proposed. In [1], Source

    Node Expansion (SNE) algorithm based on slowcoherency has beenproposed to split a simplified power network. The SNE initiates

    expansion from a source node to the connect loads until desired

    power balance be met. When all sources were expanded, optimal

    cutsets can be determined using the adjacency matrix. In[28], an

    OBDD-based three-phase method has been proposed to find proper

    islanding solutions of interconnected power systems. A time-based

    layered structure has then been introduced to demonstrate the

    capability of the proposed strategy. The feasibility of this method

    has been studied by means of power system transient simulations

    in [29]. In [30], a novel approach based on the minimal cutsets with

    minimum net flow has been proposed to split the large power sys-

    tem into several stable sections following a severe disturbance. In

    [31],a three-phase multilevel partitioning scheme has been used

    to split the entire network graph. The Greedy growing and KL algo-

    rithm have then been applied to find the optimal scenario. In[32],

    the slow coherency algorithm has been applied to cluster coherent

    generators. Then, a multi-level graph partitioning has been pro-

    posed to split the reduced network graph into desired islands with

    minimum generation-load mismatch. In [33], an Ant SearchMecha-

    nism (ASM) based on linear programming and DC power flow has

    been proposed to identify proper splitting pointsconsidering power

    balance and line overloading constraints. In[34], a Mixed Integer

    Linear Programming (MILP) algorithm has been proposed to deter-

    mine optimal islanding scenario. The steady-state DC power flow

    equations and operating limits such as line losses, transmission

    capacity constraint and generation limits have been considered to

    minimize total load shedding. Then, an AC optimal load shedding

    problem has been solved in islanded system to provide a scenario

    that satisfies AC power flow.

    To achieve a fast practical islanding solution which satisfies all

    the steady state and dynamic constraints within the islands is an

    arduous challenge. A fast scenario generator algorithm is necessary

    due to the inherent real-time application of islanding strategies in

    which a feasible solution is needed to guarantee the stable opera-

    tion of islands. In the literature, there are remarkable efforts on

    defensive separating of power systems. However, there are still

    some unsolved problems to satisfy the static and dynamic voltage

    stabilities of islands and reduce the risk of their partial blackouts.This paper develops a real-time strategy for fast, proper, accurate

    and feasible islanding decision making which can guarantee the

    voltage security margin, steady state and dynamic stabilities of

    islands and prevent their partial blackout. Another unique feature

    of proposed scenario generator algorithm is its capability of ana-

    lyzing the steady state stability of each island independent of the

    other islands, since the PMEA of each island has been considered

    in primary line and bus data matrices. Therefore, if there are N

    coherent independent clusters, it will be possible to break one

    complex optimization process into N computationally efficient

    problems and reduce the average calculation time, significantly.

    In the current paper, the large initial search space of the sepa-

    rating strategy has been reduced to only smaller interface network

    by aggregating the coherent machines and simplifying the networkgraph. Backward Elimination Method (BEM) based on Primary

    Maximum Expansion Areas (PMEAs) is then proposed to generate

    all proper islanding scenarios in the simplified power network.

    The NewtonRaphson power flow and QV modal analysis have

    been used to assess the steady state stability of the islands in each

    generated scenario. Binary Imperialistic Competitive Algorithm

    (BICA) is applied to minimize total load-generation mismatch con-

    sidering integrity, voltage permitted range and static voltage sta-

    bility constraints.

    The rest of the current paper is organized as follows: Section

    Problem formulation presents the problem formulation. The pro-

    posed splitting strategy has been provided in Section Proposed

    controlled islanding strategy. Section Simulation results and dis-

    cussions contains the simulation results and discussion. Finally,conclusion appears in Section Conclusion.

    F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380 369

    http://-/?-http://-/?-
  • 7/26/2019 Jabari 2015

    3/13

    Problem formulation

    Objective function

    The amount of power mismatch affects the network frequency.

    If active generation increases, the frequency will be increased else

    if active load increases, the frequency will be decreased. It will be

    necessary to maintain the islands frequency in an acceptable limitby minimizing the active power imbalance between load and gen-

    eration. Hence, the following objective function is defined to min-

    imize total load-generation mismatch.

    Objective Function MinXnislandi1

    PGisland i PLisland i ! 1

    where PGislandi is the total active generation of ith island, PLislandi

    the total active load ofith island and nislandis the number of islands.

    PGisland i XNGim1

    PGim 2

    PLisland i XNLin1

    PLin 3

    In relations (2) and (3), PGi m and PLi n are the active generation of

    themth machine and the active consumption of thenth load inith

    island, respectively.

    Constraints

    The criteria for finding proper stable islanding scenarios can be

    summarized as follows [12,33].

    No-isolated bus (integrity)

    The islanding process must not eliminate any bus from primary

    integrated power system. All buses inside each island must be con-

    nected to each other to form some integrated areas.

    Voltage permitted range

    The voltage magnitude must be limited in an acceptable range

    as following relation:

    Vmini

  • 7/26/2019 Jabari 2015

    4/13

    magnitude of the sensitivity cannot evaluate the voltage security

    margin and stability degree. Hence, the QV modal analysis is used

    to determine the voltage stability indices. Therefore:

    JR nKg 10

    In (10),nand g are the right and left eigenvector matrices of theJR, respectively. The K matrix consists of the eigenvalues of the

    reduced Jacobian matrix. From Eq.(10):

    J1R nK1g 11

    Substituting in Eq. (9), the relation between incremental change

    in bus voltage magnitude and incremental change in bus reactive

    power injection can be rewritten as(12) and (13):

    DV nK1gDQ 12

    And

    DVXi

    nigiki

    DQ 13

    In(13),k i is theith eigenvalue, ni is the ith column of the right

    eigenvector matrix and gi is the ith row of the left eigenvectormatrix. Since:

    g n1 14

    Therefore:

    gDV K1gDQ 15

    The vectors of the modal voltage variation and the modal reac-

    tive power variation are defined as(16) and (17), respectively:

    v gDV 16

    q gDQ 17

    Eq.(18)can be written as:

    vi qi=ki 18

    Ifk i > 0, the voltage and the reactive power variation of the ith

    PQ bus are along the same direction and the system is stable. If

    ki < 0, the voltage and the reactive power variation of the ith PQ

    bus are along opposite directions and the system is unstable. If

    ki 0, theith modal voltage collapses.

    Coherency criterion

    All machines in each island should remain in synchronism to

    increase the dynamic stability of the created islands. Two non-

    coherent generators must not be connected to each other. As

    shown inFig. 1, two independent coherent groups should be iso-

    lated by trippingij transmission line.

    Proposed controlled islanding strategy

    Coherent generators grouping

    In this paper, the slow coherency based aggregating has been

    applied on NPCC 68-bus test system to guarantee the dynamic

    Fig. 4. Concepts of Primary Maximum Expansion Areas in New England 39-bus test system.

    F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380 371

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/26/2019 Jabari 2015

    5/13

    stability of the created islands following a severe disturbance.

    Coherency analysis as a scenario reduction technique can reduce

    the computational burden of the stability studies and limit the

    huge initial search space of the intentional separating to only smal-

    ler interface network.

    Proposed network graph simplification

    In an interconnected power system with thousands of busesand branches, the islanding search space grows exponentially.

    However, the graph simplification without losing the useful infor-

    mation can reduce the calculation time, significantly. In graph the-

    ory, the degree of a bus is the number of the branches connected to

    it. The bus type can be classified into three categories; load bus,

    generation bus and transfer bus. The bus with load and no gener-

    ator is called load bus. The bus with generator and no load is called

    generation bus and the bus with no load and generator is called

    transfer bus. As shown inFig. 2, C is a degree two transfer bus. If

    AC transmission line is closed, x(i) will be equal to 1, else, it will

    be zero. Similarly, if C-B transmission line is closed, x(j) will be

    equal to 1, else, it will be zero. The number of islanding scenarios

    can be reduced by consideringx(i) =x(j).

    As shown in Fig. 3, the binary states of the parallel transmissionlines between A and B can be considered to be identical. In other

    words, all parallel branches between A and B are either connected

    (1) or disconnected (0).

    Determination of interface boundary network

    Following the aggregation of the coherent machines and the

    simplification of the network graph, it is important to determine

    the types of the branches and buses to obtain the interface bound-

    ary network and limit the search space from entire system to the

    boundaries. The interface network between each area with other

    adjacent areas is called boundary or probabilistic network which

    consists of boundary or probabilistic branches and buses. Hence,

    the branches or buses that are not boundary are called non-bound-

    ary or deterministic branches or buses, respectively. In a large

    power network, the branches and buses are classified into two cat-

    egories as fallows:

    Deterministic or non-boundary areas

    The branches which connect coherent generators should be

    closed. In other words, the islanding strategy is not allowed toopen these branches. If multiple trajectories exist to connect two

    coherent machines, a path will be selected that none of its

    branches can be considered as a boundary line. If the generators

    Gi andGj are not coherent, the ij branch must be opened. Also,

    the faulted transmission lines must be tripped. These branches

    have non-boundary or deterministic states in power system islan-

    ding studies. The buses connected to non-boundary lines are called

    deterministic buses.

    Probabilistic or boundary area

    All of the branches which are not deterministic are called prob-

    abilistic branches. The buses that are connected to the probabilistic

    lines are called boundary buses.

    Principles of proposed Backward Elimination Method

    In this section, a novel probabilistic search strategy denoted as

    Backward Elimination Method based on Primary Maximum Expan-

    sion Areas is proposed for generating all proper separating scenar-

    ios according to coherent groups and simplified network graph.

    The NewtonRaphson power flow method and QV modal analysis

    have been used to evaluate the steady-state stability of the islands

    in each generated scenario. Binary Imperialistic Competitive Algo-

    rithm is then applied to minimize the load-generation active

    power mismatch considering integrity; voltage permitted range

    and static voltage stability as optimization problem constraints.

    Fig. 5. PMEAs of three islands and boundary branches in New England 39-bus test system.

    372 F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380

  • 7/26/2019 Jabari 2015

    6/13

    In order to apply the BEM based on PMEAs as a defensive islanding

    strategy, the following steps should be carried out sequentially.

    Determination of the Primary Maximum Expansion Areas

    The Primary Maximum Expansion Area of the island A consistsof deterministic buses of island A, deterministic branches of island

    A and boundary network considering isolated islands constraint.

    As shown in Fig. 4, there are three coherent groups named A, B

    and C and colored by red, blue and green, respectively. The bound-

    ary or probabilistic interface network has been shown with purple.

    The Primary Maximum Expansion Area of the island A has been

    determined as a gray area by considering the islands

    independence.

    Formation of the probabilistic line and bus data matrices considering

    PMEAs

    The primary line data matrices of the islands will have probabi-

    listic nature due to the boundary transmission lines. After number-

    ing all buses and determining the slack bus in each island (Theslack bus must not belong to the set of the boundary buses)

    considering PMEAs of the islands, the primary probabilistic line

    data matrix will be formed for each island as follows. For the kth

    boundary branch connectingith andjth buses of island A, we can

    use:

    Zi;j 1 xkMZ0i;j 19

    xk 0 if thekth boundary branch has been opened

    1 if thekth boundary branch has been closed

    20

    Z0i;j Ri;j jXi;j 21

    Z(i,j) is the impedance of the transmission line i to j in primary

    probabilistic line data matrix of island A. Mis a sufficiently large

    constant. Z0(i,j), R(i,j) and X(i,j) are the impedance, resistance

    and reactance of ij transmission line in per unit, respectively.

    According to (20), x(k) shows the state of the kth probabilistic

    branch. In a generated scenario, the primary probabilistic line datamatrix can be updated as follows. If x(k) = 0, the kth boundary

    Fig. 6. The flowchart of the proposed optimal defensive islanding strategy.

    F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380 373

    http://-/?-http://-/?-http://-/?-
  • 7/26/2019 Jabari 2015

    7/13

    branch is opened andZ(i,j) ffi M. Ifx(k) = 1 thekth boundary branch

    is closed and Z(i,j) =Z0(i,j).

    Once all buses of each island have been numbered and the slack

    buses of the islands have been determined (The slack bus must not

    belong to the set of the boundary buses), the probabilistic bus data

    matrix will be formed for each island according to PMEA of island.

    In order to generate proper splitting solutions, it is necessary to

    update the probabilistic bus data matrices of the islands in eachgenerated scenario. Hence, if the ith bus of the island A (that is a

    boundary bus) is removed from island A to island B, the ith bus

    of island A will be eliminated from the probabilistic bus data

    matrix of this island through a Bus-Trajectory matrix. In other

    words, for each generated scenario, the probabilistic bus datamatrix which is formed based on the PMEA of the island A will

    be updated across the Bus-Trajectory matrix of this island. The

    Bus-Trajectory matrix of the island A can be formed as follows. If

    the ith bus of the island A is a deterministic or non-boundary

    bus, the ith row of the Bus-Trajectory matrix of island A will be

    equal to 1. In other words, BTAi 1. If the ith bus of island A is

    a probabilistic or boundary bus, the ith row of the Bus-Trajectory

    matrix of island A can be calculated via the following steps.

    1. All probabilistic trajectories which connect theith probabilistic

    bus of island A to the deterministic network of this island

    should be determined.

    2. A trajectory which connects theith bus of island A to the deter-

    ministic network of this island through boundary branches can

    be considered as the multiplication of the binary states of these

    probabilistic branches.

    Table 1

    All modes, frequency and damping of NPCC 68-bus system.

    No Modes Freq (Hz) Damping Inter-area modes No Modes Freq (Hz) Damping Inter-area modes

    1 0.0001 0 1 Yes 17 0.2500 7.1908i 1.1444 0.0347 No

    2 0.8203 0 1 Yes 18 0.2500 + 7.1908i 1.1444 0.0347 No

    3 0.3591 2.3868i 0.3799 0.1488 Yes 19 0.2500 7.6827i 1.2227 0.0325 No

    4 0.3591 + 2.3868i 0.3799 0.1488 Yes 20 0.2500 + 7.6827i 1.2227 0.0325 No

    5 0.3801 3.0739i 0.4892 0.1227 Yes 21 0.2517 7.8977i 1.2570 0.0319 No

    6 0.3801 + 3.0739i 0.4892 0.1227 Yes 22 0.2517 + 7.8977i 1.2570 0.0319 No7 0.3617 3.9378i 0.6267 0.0915 Yes 23 0.2500 8.4151i 1.3393 0.0297 No

    8 0.3617 + 3.9378i 0.6267 0.0915 Yes 24 0.2500 + 8.4151i 1.3393 0.0297 No

    9 0.4302 4.9073i 0.7810 0.0873 Yes 25 0.2500 9.2183i 1.4671 0.0271 No

    10 0.4302 + 4.9073i 0.7810 0.0873 Yes 26 0.2500 + 9.2183i 1.4671 0.0271 No

    11 0.2500 5.9666i 0.9496 0.0419 Yes 27 0.2500 9.4569i 1.5051 0.0264 No

    12 0.2500 + 5.9666i 0.9496 0.0419 Yes 28 0.2500 + 9.4569i 1.5051 0.0264 No

    13 0.2550 6.4568i 1.0276 0.0395 No 29 0.2520 10.9986i 1.7505 0.0229 No

    14 0.2550 + 6.4568i 1.0276 0.0395 No 30 0.2520 + 10.9986i 1.7505 0.0229 No

    15 0.2906 7.0406i 1.1205 0.0412 No 31 0.2500 14.3598i 2.2854 0.0174 No

    16 0.2906 + 7.0406i 1.1205 0.0412 No 32 0.2500 + 14.3598i 2.2854 0.0174 No

    Table 2

    Inter-area modes, frequency and damping of NPCC 68-bus system.

    No Modes Freq (Hz) Damping

    1 0.8203 0 1.0000

    2 0.3591 2.3868i 0.3799 0.1488

    3 0.3801 3.0739i 0.4892 0.1227

    4 0.3617 3.9378i 0.6267 0.0915

    5 0.4302 4.9073i 0.7810 0.0873

    6 0.2500 5.9666i 0.9496 0.0419

    Fig. 8. Voltage profile under given disturbances.

    0.2

    0.4

    0.6

    0.8

    1

    30

    210

    60

    240

    90

    270

    120

    300

    150

    330

    180 0

    G14 rotor angle

    0.05

    0.1

    0.15

    0.2

    30

    210

    60

    240

    90

    270

    120

    300

    150

    330

    180 0

    G15 rotor angle

    0.2

    0.4

    0.6

    0.8

    1

    30

    210

    60

    240

    90

    270

    120

    300

    150

    330

    180 0

    G16 rotor angle

    0.1

    0.2

    0.3

    30

    210

    60

    240

    90

    270

    120

    300

    150

    330

    180 0

    G10,G11,G12,G13 rotor angles

    0.05

    0.1

    0.15

    0.2

    0.25

    30

    210

    60

    240

    90

    270

    120

    300

    150

    330

    180 0

    G1,G2,G3,G4,G5,G6,G7,G8,G9 rotor angles

    Fig. 7. Compass plot of rotor angle terms of 3rd inter-area mode eigenvector.

    374 F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380

  • 7/26/2019 Jabari 2015

    8/13

    3. The sum of the obtained expressions for all of the probabilistic

    trajectories in previous step (which connect the ith probabilistic

    bus of island A to the deterministic network of this island) is

    calculated as theith row of the Bus-Trajectory matrix of island

    A.

    InFig. 5, there are three coherent groups named A, B and C. The3rd and 7th buses of island C are deterministic and probabilistic

    buses, respectively. Therefore, the 3rd and 7th rows of Bus-

    Trajectory matrix of island C will be equal to 1 and

    x4 x6zfflfflfflfflfflfflfflffl}|fflfflfflfflfflfflfflffl{

    T1

    x4 x5 x7 x8zfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflffl}|fflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflffl{

    T2

    x4 x5 x7 x9zfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflffl}|fflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflfflffl{

    T3

    ,

    respectively. The primary probabilistic bus data matrix of island A

    can be updated as fallows. IfBTA(i) = 0, theith bus of island A will

    be removed from this island. IfBTA(i) 0, the ith bus of island A

    will belong to this island.

    BEM, PMEAs and BICA based optimization

    The BEM, PMEAs and BICA based optimization program is

    applied to minimize total load-generation mismatch. The steadystate stability can be evaluated in each island using Newton

    Raphson power flow program and QV modal analysis for each

    generated scenario. The integrity, voltage permitted range andsteady-state voltage stability constraints have been considered in

    the optimization process.

    The coherent generators should be clustered based on the slow

    coherency theory. The proposed graph simplification is then

    performed. The deterministic areas and the interface boundary

    network have then been determined according to the coherent

    machines, deterministic and probabilistic buses and branches.

    The PMEAs of the islands can be determined to form the

    primary probabilistic line and bus data matrices. For each

    generated scenario, the primary probabilistic line and bus data

    matrices are updated through the Bus-Trajectory matrices. Then,

    NewtonRaphson power flow and QV modal analysis have been

    performed based on the updated line and bus data matrices in each

    island. All of the controlled islanding constraints are then checked.If one of them is not met, the new scenario will be generated;

    otherwise the load-generation power mismatch will be calculated

    to find the best solution vector. The flowchart of the proposed opti-

    mal intentional islanding strategy has been shown inFig. 6.

    Simulation results and discussions

    In order to demonstrate the speed, effectiveness and capability

    of the proposed strategy, the NPCC 68-bus test system is used. One

    line diagram and initial operating point of this system has been

    given in[37].

    The NewtonRaphson power flow has been performed undernormal operating condition. Total active load and generation are

    Fig. 9. Simplified graph and boundary network of NPCC 68-bus test system.

    Table 3Best scenario for islanding of NPCC 68-bus test system.

    x(1) x(2) x(3) x(4) x(5) x(6) x(7) x(8) x(9) x(10) x(11)

    1 1 0 1 1 1 1 1 0 0 1

    x(12) x(13) x(14) x(15) x(16) x(17) x(18) x(19) x(20) x(21)

    1 1 1 0 0 1 1 1 1 1

    F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380 375

    http://-/?-http://-/?-http://-/?-
  • 7/26/2019 Jabari 2015

    9/13

    equal to 184.0873 and 182.3390 per unit, respectively. The simula-

    tion results consist of three sections.

    Slow coherency based clustering

    Under normal operating condition, the coherent generators can

    be identified based on the slow coherency scheme. InTable 1, all

    modes, frequency and damping of the NPCC 68-bus system have

    been shown. According toTable 2, there are five inter-area modes

    in this system.

    A compass plot of the rotor angle terms of the eigenvectors in

    the 3rd inter-area mode is shown in Fig. 7. According to rotor angle

    terms, five coherent groups {G1,G2,G3,G4,G5,G6,G7,G8,G9},

    {G10,G11,G12,G13}, {G14}, {G15}, {G16}, have been formed.

    Graph simplification and determination of interface boundary network

    A solid three-phase fault occurs on one of transmission lines

    connecting bus 930 close to bus 9 at t= 1.0 s and is cleared after

    0.3 s by removing the transmission lines 930. Another contin-

    gency is occurred on the branch 127 at t= 1.3 s and this branch

    will be opened. The voltage profile following given contingencies

    and the simplified network graph with boundary network have

    been shown inFigs. 8 and 9, respectively.

    BEM, PMEA and BICA based optimization

    The search space will have 221 = 2, 097, 152 possible solutions.

    The best solution vector and load-generation mismatch in five

    areas have been reported in Tables 3 and 4, respectively. According

    to Table 4, the total generation (201.207 per unit) is larger than the

    total load (182.689 per unit), thus load shedding is not necessary.

    The total minimum power mismatch is 18.5188 per unit which lost

    in transmission systems. The optimal islanded NPCC 68-bus power

    system has been shown inFig. 10.

    Voltage profiles of five islands have been shown inFigs. 11 and

    12. The static voltage stability indices of islands have been shown

    Fig. 10. Optimal islanded NPCC 68-bus test system.

    Table 4

    Load, generation and power mismatch of islands in per unit.

    Active power in per unit Area 1 Area 2 Area 3 Area 4 Area 5 Total

    Total active generation 17.4697 11.5000 33.1888 81.6431 57.4062 201.2078

    Total active load 13.0683 11.5000 32.2170 74.1237 51.7800 182.689

    Total active imbalance 4.4014 0.000 0.9718 7.5194 5.6262 18.5188

    376 F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380

  • 7/26/2019 Jabari 2015

    10/13

    Fig. 12. Voltage profile in island 4 and 5.

    Fig. 13. Voltage stability indices in island 1 and 3.

    Fig. 14. Voltage stability indices in island 4 and 5.

    Fig. 11. Voltage profile in island 1, 2 and 3.

    F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380 377

    http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/26/2019 Jabari 2015

    11/13

    in Figs.13and14. Basedon the optimalscenario,the5th,6thand 7th

    busesof area 1 whichare similar to the 22nd, 21st and 20thbuses of

    area 4 and 39th, 38thand42ndbusesof area 5,belongto the island 4.

    The 3rd, 4th,5th and 6th buses ofthe area3 which are similarto the

    26th, 25th, 28th and 27th buses of the area 4 belongto the island 3.

    The 17th, 18th and 19th buses of the area 4 which are similar

    to the 37th, 36th and 35th buses of the area 5 belong to the

    island 5. According to Fig. 9, the PQ buses in island 1, 3, 4, 5

    are {3, 4, 5, 6, 7}, {3, 4, 5, 6}, {4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 15, 17, 18,

    19, 20, 21, 22, 23, 24, 25, 26, 27, 28} and {3, 6, 7, 9, 10, 11, 12, 13,

    14, 15, 16, 17, 19, 21, 22, 23, 24, 25, 26, 28, 29, 30, 31, 33, 35, 36, 37,

    38, 39, 40, 41, 42}, respectively. All stabilityindicesare positive and

    the static voltage stability has been satisfied in each island.

    As mentioned in the introduction section, the optimum separat-

    ing points can be found by solving four optimization problems in

    islands 1, 3, 4 and 5, sequentially or simultaneously. In this study,

    the sequential method has been applied as follows.

    The PMEA of the island 1 has been shown in Fig. 15. There are

    five probabilistic branches and 32 scenarios in optimization pro-

    cess of island 1. Therefore, the number of required initial countries,

    imperialists and decades of the BICA and calculation time will be

    decreased. In the obtained best scenario shown inFig. 15, the volt-

    age permitted range and SVS criteria have not been satisfied for the

    5th, 6th and 7th buses of the island 1. Hence, they are transferred

    from island 1 to area 4. If in optimization process of area 4, the

    voltage constraints are not satisfied for 20th, 21st and 22nd buses,they will again be transferred from island 4 to area 5.

    The PMEA and the optimum separating point of the area 3 with

    16 solutions have been shown inFig. 16. It is not necessary to trip

    any boundary branch for optimal isolation of Section Proposed

    controlled islanding strategy. According to the best solutions of

    the islands 1 and 3, the reduced interface network of the subsys-

    tem 4 will have 256 possible solutions. As shown in Fig. 17,it will

    optimally become an isolated area by tripping the 217 transmis-

    sion lines based on the obtained optimal solution. Finally, the 5th

    island will have 32 possible scenarios. Based on the obtained best

    scenario shown in Fig. 18, it is not necessary to trip any probabilis-

    tic branch for defensive separation of Section Conclusion. All con-

    straints in the optimization process of the island 5 have been met.

    Hence, the optimization problems have been implemented in avery short time as a result of the fast convergence of each process

    within first iteration.

    As shown inFigs. 1518, total search space will have 336 pos-

    sible scenarios in five optimization problems. In order to prove

    the practicability of the proposed fast strategy, the calculation time

    has been compared with OBDD, ASM and ST-BFS methods in

    Table 5.

    According to above table, the proposed algorithm is computa-

    tionally efficient and fast.

    Similar to the previous scheme, the four optimization programs

    can be implemented considering Primary Maximum Expansion

    Areas of islands instead of their reduced interface boundary net-

    works in simultaneous method. There are 32, 16, 214 = 16,384

    and 210

    = 1024 scenarios in four splitting search spaces,respectively.

    Fig. 15. PMEA of island 1.

    Fig. 16. PMEA of island 3.

    Fig. 17. Reduced interface network of island 4.

    378 F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380

  • 7/26/2019 Jabari 2015

    12/13

    Conclusion

    Power industry restructuring and competition in the deregu-lated electricity markets in order to provide increased consump-

    tion causes operation of large power systems close to their

    stability margins. If there is no emergency corrective control to

    resynchronize all generators and prevent fault spreading, occur-

    rence of large disturbance may cause the system to lose stability

    and even lead to the wide area blackout. Hence, defensive

    Separation of bulk power system as a comprehensive real-time

    decision making is the last defense line against passive collapse

    of system.

    This paper introduces a novel strategy for separation of inter-

    connected power systems following severe disturbances. In this

    paper, the slow coherency based aggregation and graph simplifica-

    tion as two scenario reduction techniques have been used to

    reduce the large initial search space of the islanding strategy from

    entire network to only smaller interface boundary network. Then,

    Backward Elimination Method (BEM) based on Primary Maximum

    Expansion Areas (PMEAs) has been proposed to generate all fast,

    proper and feasible islanding scenarios in the simplified systemby transferring some of the boundary buses in one island to

    another island such that total mismatch is minimized. The New-

    tonRaphson power flow method and QV modal analysis have

    been used to evaluate the steady-state stability of the islands in

    each generated scenario. The Binary Imperialistic Competitive

    Algorithm (BICA) has then been applied to minimize total load-

    generation mismatch considering integrity, voltage permitted

    range and static voltage stability constraints. The proposed sce-

    nario generator algorithm generates each possible islanding solu-

    tion in an average calculation time less than 0.1 s and evaluates

    the static voltage stability of the PQ buses based on QV modal

    analysis in each generated solution. The results demonstrate the

    speed, effectiveness and capability of the proposed scheme to gen-

    erate fast practical splitting solutions considering static and

    dynamic stability.

    Fig. 18. Reduced interface network of island 5.

    Table 5

    Calculation times of fast strategies.

    Calculation time PMEAs, BEM and BICA based optimization(on a Lenovo with 2.10 GHz CPU, 4 GB RAM)

    OBDD (on a PC Pentium IV-1.4GCPU and 256M DDRAM)

    ASM (PC with 2.26GHzCPU, 2 GB RAM, 3 MB

    Cache)

    ST-BFS

    For finding each

    scenario

  • 7/26/2019 Jabari 2015

    13/13

    References

    [1]Ibrahim I. Source node expansion algorithm for coherency based islanding of

    power systems master of sciences dissertation. Ontario, Canada: University of

    Windsor; 2011.

    [2] UCTE. Final report of the investigation committee on the 28 September 2003

    blackout in Italy. . April 2004.

    [3] Larsson S, Danell A. The black-out in southern Sweden and eastern Denmark,

    September 23, 2003. In: IEEE power systems conference and exposition; Oct.29Nov. 1 2006. p. 30913.

    [4] USCanada power system outage task force. Final report on the August 14,

    2003 blackout in the United States and Canada causes and recommendations.

    Final report ; 2004.

    [5] http://en.wikinews.org/wiki/Indonesian_blackout_caused_by_lack_of_gener-

    ation_capaciy.

    [6] http://en.wikipedia.org/wiki/2009_Brazil_and_Paraguay_blackout.

    [7] http://www.cercind.gov.in/2012/orders/Final_Report_Grid_Disturbance.pdf.

    [8] UCTE. Final report on the disturbances of 4 November 2006. ; Jan. 2007.

    [9] Andersson G, Donalek P, Farmer R, Hatziargyriou N, Kamwa I, Kundur P. Causes

    of the 2003 major grid blackouts in north America and Europe, and

    recommended means to improve system dynamic performance. IEEE Trans

    Power Syst 2005;20(4):19228.

    [10] Yang B, Vittal V, Heydt GT. Slow-coherency-based controlled islanding a

    demonstration of the approach on the August 14, 2003 blackout scenario. IEEE

    Trans Power Syst 2006;21(4):18407.

    [11] Wang X, Shao W, Vittal V. Adaptive corrective control strategies for preventing

    power system blackouts. In: Presented at the 15th power systemscomputation conference. Lige (Belgium); 2226 August 2005.

    [12] Liu Li, Liu W, Cartes DA, Chung Il-Yop. Slow coherency and angle modulated

    particle swarm optimization based islanding of large-scale power systems.

    Adv Eng Inform 2009;23(1):4556.

    [13] Chaudhuri B. Robust control in power systems. .

    [14] Wang X. Slow coherency grouping based islanding using minimal cutsets and

    generator coherency index tracing using the continuation method [Ph.D.

    dissertation]. Iowa State University; 2005. p. 1132.

    [15] Cai G, Zhang J, Deyou Y, Chan KW. The identification of coherent generator

    groups via EMD and SSI. In: International conference on power system

    technology; 2428 Oct. 2010. p. 15.

    [16] Aghamohammadi MR, Tabandeh SM. Online coherency identification based on

    correlation characteristics of generator rotor angles. In: IEEE international

    conference on power and energy (PECon); 25 Dec. 2012. p. 499504.

    [17] Chow JH, KokotovicPV, Thomas RJ. Slow coherency aggregation of large power

    system in Eigen-analysis and frequency domain methods for system dynamic

    performance. In: IEEE publications 90TH0292-3-PWR; 1990. p. 5060.

    [18] Date RA, Chow JH. Aggregation properties of linearized two-time-scale power

    networks. IEEE Trans Circ Syst 1991;38(7):72030.

    [19] Chow JH, Date R. A nodal aggregation algorithm for linearized two-time-scale

    power networks. In: IEEE international symposium on circuits and systems;

    1988. p. 66972.

    [20] Chow JH, Galarza R, Accari P, Price WW. Inertial and slow coherency

    aggregation algorithms for power system dynamic model reduction. IEEE

    Trans Power Syst 1995;10(2):6805.

    [21] Najafi SR, Hosseinian SH, Abedi M. A novel strategy for stability evaluation of

    islanded power systems. Iran J Electr Comput Eng 2010;9(1) .

    [22] Najafi SR. A strategy for frequency stability of islanded power systems. In:

    Power and energy conference; 13 Dec. 2008. p. 1126.

    [23] Najafi SR. An early warning mechanism to encounter interconnected powersystems catastrophic failures. Int J Tech Phys Prob Eng (IJTPE)

    2013;5(17):10512.

    [24] Najafi S, Hosseinian SH, Abedi M. Evaluation of interconnected power systems

    splitting. Electr Power Compon Syst 2010;38(11):124868.

    [25] Najafi S, Hosseinian SH, Abedi M. Proper splitting of interconnected power

    systems. IEEJ Trans Electr Electron Eng 2010;5(2):21120.

    [26] Najafi S. Evaluation of interconnected power systems controlled islanding. In:

    IEEE bucharest power tech conference. Bucharest (Romania); June 28thJuly

    2nd, 2009. p. 18.

    [27] You H, Vittal V, Xiaoming W. Slow coherency-based islanding. IEEE Trans

    Power Syst Nov. 2004;19(4):48391.

    [28] Sun K, ZhengDZ, Lu Q. Splittingstrategies forislanding operation of large-scale

    power systems using OBDD-based methods. IEEE Trans Power Syst

    2004;18(2):91223.

    [29] Sun K, Zheng DZ, Lu Q. A simulation study of OBDD-based proper splitting

    strategies for power systems under consideration of transient stability. IEEE

    Trans Power Syst 2005;20(1):38999.

    [30] Wang X, Vittal V. System islanding using minimal cutsets with minimum net

    flow. In: Proc. IEEEpower systems conference and exposition. New York; 2004.

    p. 379384.

    [31] Tian Z, Miao W, Hongjie J, Zhou J. Multilevel partitioning algorithm for power

    system splitting control. In: IEEE innovative smart grid technologies Asia

    (ISGT Asia); 2124 May 2012. p. 16.

    [32] Yang B, Vittal V, Heydt GT, Sen A. A novel slow coherency based graph

    theoretic islanding strategy. In: IEEE power engineering society general

    meeting; 2428 June 2007. p. 17.

    [33] Aghamohammadi MR, Shahmohammadi A. Intentional islanding using a new

    algorithm based on ant search mechanism. Int J Electr Power Energy Syst

    2012;35(1):13847.

    [34] Trodden PA. MILP formulation for controlled islanding of power networks. Int J

    Electr Power Energy Syst 2013;45(1):5018.

    [35] Kundur P. Power system stability and control. New York: McGraw-Hill Inc.;

    1994.

    [36] Kothari DP, Dhillon JS. Power system optimization. 2nd ed. Prentice-Hall of

    India; 2004.

    [37] http://www.eps.ee.kth.se/personal/vanfretti/pst/Power_System_Toolbox_

    Webpage/Downloads.html.

    380 F. Jabari et al. / Electrical Power and Energy Systems 67 (2015) 368380

    http://refhub.elsevier.com/S0142-0615(14)00735-2/h0005http://refhub.elsevier.com/S0142-0615(14)00735-2/h0005http://refhub.elsevier.com/S0142-0615(14)00735-2/h0005http://refhub.elsevier.com/S0142-0615(14)00735-2/h0005https://www.entsoe.eu/fileadmin/user_upload/_library/publications/ce/otherreports/20040427_UCTE_IC_Final_report.pdfhttps://www.entsoe.eu/fileadmin/user_upload/_library/publications/ce/otherreports/20040427_UCTE_IC_Final_report.pdfhttp://reports.energy.gov/http://en.wikinews.org/wiki/Indonesian_blackout_caused_by_lack_of_generation_capaciyhttp://en.wikinews.org/wiki/Indonesian_blackout_caused_by_lack_of_generation_capaciyhttp://en.wikinews.org/wiki/Indonesian_blackout_caused_by_lack_of_generation_capaciyhttp://en.wikipedia.org/wiki/2009_Brazil_and_Paraguay_blackouthttp://www.cercind.gov.in/2012/orders/Final_Report_Grid_Disturbance.pdfhttp://www.ucte.org/_library/otherreports/Final-Report-20070130.pdfhttp://www.ucte.org/_library/otherreports/Final-Report-20070130.pdfhttp://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://refhub.elsevier.com/S0142-0615(14)00735-2/h0050http://refhub.elsevier.com/S0142-0615(14)00735-2/h0050http://refhub.elsevier.com/S0142-0615(14)00735-2/h0050http://refhub.elsevier.com/S0142-0615(14)00735-2/h0060http://refhub.elsevier.com/S0142-0615(14)00735-2/h0060http://refhub.elsevier.com/S0142-0615(14)00735-2/h0060http://www.springer.com/978-0-387-25949-9http://www.springer.com/978-0-387-25949-9http://refhub.elsevier.com/S0142-0615(14)00735-2/h0090http://refhub.elsevier.com/S0142-0615(14)00735-2/h0090http://refhub.elsevier.com/S0142-0615(14)00735-2/h0100http://refhub.elsevier.com/S0142-0615(14)00735-2/h0100http://refhub.elsevier.com/S0142-0615(14)00735-2/h0100http://refhub.elsevier.com/S0142-0615(14)00735-2/h0105http://refhub.elsevier.com/S0142-0615(14)00735-2/h0105http://refhub.elsevier.com/S0142-0615(14)00735-2/h0115http://refhub.elsevier.com/S0142-0615(14)00735-2/h0115http://refhub.elsevier.com/S0142-0615(14)00735-2/h0115http://refhub.elsevier.com/S0142-0615(14)00735-2/h0120http://refhub.elsevier.com/S0142-0615(14)00735-2/h0120http://refhub.elsevier.com/S0142-0615(14)00735-2/h0120http://refhub.elsevier.com/S0142-0615(14)00735-2/h0125http://refhub.elsevier.com/S0142-0615(14)00735-2/h0125http://refhub.elsevier.com/S0142-0615(14)00735-2/h0135http://refhub.elsevier.com/S0142-0615(14)00735-2/h0135http://refhub.elsevier.com/S0142-0615(14)00735-2/h0140http://refhub.elsevier.com/S0142-0615(14)00735-2/h0140http://refhub.elsevier.com/S0142-0615(14)00735-2/h0140http://refhub.elsevier.com/S0142-0615(14)00735-2/h0145http://refhub.elsevier.com/S0142-0615(14)00735-2/h0145http://refhub.elsevier.com/S0142-0615(14)00735-2/h0145http://refhub.elsevier.com/S0142-0615(14)00735-2/h0165http://refhub.elsevier.com/S0142-0615(14)00735-2/h0165http://refhub.elsevier.com/S0142-0615(14)00735-2/h0165http://refhub.elsevier.com/S0142-0615(14)00735-2/h0170http://refhub.elsevier.com/S0142-0615(14)00735-2/h0170http://refhub.elsevier.com/S0142-0615(14)00735-2/h0175http://refhub.elsevier.com/S0142-0615(14)00735-2/h0175http://refhub.elsevier.com/S0142-0615(14)00735-2/h0180http://refhub.elsevier.com/S0142-0615(14)00735-2/h0180http://refhub.elsevier.com/S0142-0615(14)00735-2/h0180http://www.eps.ee.kth.se/personal/vanfretti/pst/Power_System_Toolbox_Webpage/Downloads.htmlhttp://www.eps.ee.kth.se/personal/vanfretti/pst/Power_System_Toolbox_Webpage/Downloads.htmlhttp://www.eps.ee.kth.se/personal/vanfretti/pst/Power_System_Toolbox_Webpage/Downloads.htmlhttp://www.eps.ee.kth.se/personal/vanfretti/pst/Power_System_Toolbox_Webpage/Downloads.htmlhttp://refhub.elsevier.com/S0142-0615(14)00735-2/h0180http://refhub.elsevier.com/S0142-0615(14)00735-2/h0180http://refhub.elsevier.com/S0142-0615(14)00735-2/h0175http://refhub.elsevier.com/S0142-0615(14)00735-2/h0175http://refhub.elsevier.com/S0142-0615(14)00735-2/h0170http://refhub.elsevier.com/S0142-0615(14)00735-2/h0170http://refhub.elsevier.com/S0142-0615(14)00735-2/h0165http://refhub.elsevier.com/S0142-0615(14)00735-2/h0165http://refhub.elsevier.com/S0142-0615(14)00735-2/h0165http://refhub.elsevier.com/S0142-0615(14)00735-2/h0145http://refhub.elsevier.com/S0142-0615(14)00735-2/h0145http://refhub.elsevier.com/S0142-0615(14)00735-2/h0145http://refhub.elsevier.com/S0142-0615(14)00735-2/h0140http://refhub.elsevier.com/S0142-0615(14)00735-2/h0140http://refhub.elsevier.com/S0142-0615(14)00735-2/h0140http://refhub.elsevier.com/S0142-0615(14)00735-2/h0135http://refhub.elsevier.com/S0142-0615(14)00735-2/h0135http://refhub.elsevier.com/S0142-0615(14)00735-2/h0125http://refhub.elsevier.com/S0142-0615(14)00735-2/h0125http://refhub.elsevier.com/S0142-0615(14)00735-2/h0120http://refhub.elsevier.com/S0142-0615(14)00735-2/h0120http://refhub.elsevier.com/S0142-0615(14)00735-2/h0115http://refhub.elsevier.com/S0142-0615(14)00735-2/h0115http://refhub.elsevier.com/S0142-0615(14)00735-2/h0115http://refhub.elsevier.com/S0142-0615(14)00735-2/h0105http://refhub.elsevier.com/S0142-0615(14)00735-2/h0105http://refhub.elsevier.com/S0142-0615(14)00735-2/h0100http://refhub.elsevier.com/S0142-0615(14)00735-2/h0100http://refhub.elsevier.com/S0142-0615(14)00735-2/h0100http://refhub.elsevier.com/S0142-0615(14)00735-2/h0090http://refhub.elsevier.com/S0142-0615(14)00735-2/h0090http://www.springer.com/978-0-387-25949-9http://www.springer.com/978-0-387-25949-9http://refhub.elsevier.com/S0142-0615(14)00735-2/h0060http://refhub.elsevier.com/S0142-0615(14)00735-2/h0060http://refhub.elsevier.com/S0142-0615(14)00735-2/h0060http://refhub.elsevier.com/S0142-0615(14)00735-2/h0050http://refhub.elsevier.com/S0142-0615(14)00735-2/h0050http://refhub.elsevier.com/S0142-0615(14)00735-2/h0050http://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://refhub.elsevier.com/S0142-0615(14)00735-2/h0045http://www.ucte.org/_library/otherreports/Final-Report-20070130.pdfhttp://www.ucte.org/_library/otherreports/Final-Report-20070130.pdfhttp://www.cercind.gov.in/2012/orders/Final_Report_Grid_Disturbance.pdfhttp://en.wikipedia.org/wiki/2009_Brazil_and_Paraguay_blackouthttp://en.wikinews.org/wiki/Indonesian_blackout_caused_by_lack_of_generation_capaciyhttp://en.wikinews.org/wiki/Indonesian_blackout_caused_by_lack_of_generation_capaciyhttp://reports.energy.gov/https://www.entsoe.eu/fileadmin/user_upload/_library/publications/ce/otherreports/20040427_UCTE_IC_Final_report.pdfhttps://www.entsoe.eu/fileadmin/user_upload/_library/publications/ce/otherreports/20040427_UCTE_IC_Final_report.pdfhttp://refhub.elsevier.com/S0142-0615(14)00735-2/h0005http://refhub.elsevier.com/S0142-0615(14)00735-2/h0005http://refhub.elsevier.com/S0142-0615(14)00735-2/h0005