J3757- Medical Complex Extension at No. 21 Sassoon Road ...

39
Construction Safety Week 2020 Considerate Contractors Site Award Scheme J3757- Medical Complex Extension at No. 21 Sassoon Road for The University of Hong Kong Presented by Cecilia KWOK (Project Manager) November 2020

Transcript of J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Page 1: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Construction Safety Week 2020 Considerate Contractors Site Award Scheme

J3757- Medical Complex Extension at No. 21 Sassoon Road for The University of Hong Kong

Presented by Cecilia KWOK (Project Manager)November 2020

Page 2: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

1. Project Introduction2. Safety Performance3. Environmental Performance4. Caring of Workers & Neighbour5. Innovation & Creativity

2

A Leading Example of Sustainable Alteration & Addition Works

Page 3: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

1.

Project Introduction3

Page 4: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Project Scope

4

1 2

3 4

Page 5: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Work with Existing Operating Campus

5

Villa

Laboratory

Office & Classroom

Noise

High School

Library

Villa

Vibration

Dust

Space

Challenge

Public Safety

Page 6: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Site Layout

6

Page 7: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

2.

Safety Performance

7

Page 8: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Safety Management System

Prior to the commencement of the Project, a Zero Harm Plan was derived from the fundamental concept of Four Layers of Protection.

8

Beyond Contract

Page 9: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Safety Management System

GammonSafety Culture▪ Mindful▪ Inform▪ Learning▪ Fairness▪ Respectful

9

Beyond Contract

Page 10: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Specific Training for Lifting Operation

10

CIC Silver CardA12 - Rigger

On-site Practical TrainingBy Experienced Rigger

Supervisor

Beyond Contract

Page 11: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Site Management

▪ Set up moveable pedestrian walkway for workers and public

11

Beyond Contract

Page 12: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Site Performance

12

Bar Bending Machine Guard CPI Checking

Additional Checking for LG

Charging Station

Beyond Contract

Page 13: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

3.

Environmental Performance

13

Page 14: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Strategy, target Setting and checking

14

Zero waste to landfill- BIM automation, DfMA- 60 % demolition waste recycling

Zero wasted energy- Power planning- Smart energy control office

Zero productivity loss- Digital innovation

Zero wasted water- Waste water recycling

Beyond Contract

- Digital platform to track performance

- Benchmarking performance among projects

Zero Waste Plan Online Dashboard

Page 15: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Power Planning

15

Liaise with HKU for the use of grid electricity to reduce diesel generators

Power from HKE or HKU

Power from generator

Beyond Contract

Reduced carbon emissions and pollutants from diesel combustion

Page 16: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Waste Management

Recycle 600T of broken concrete

Demolition waste recycling rate push up from 30% to 60%

16

Slab cut from existing structure

Transport to pier in Tuen Mun

Concrete is broken down to aggregate

Beyond Contract

Page 17: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Sustainable Construction

17

Beyond Contract

Page 18: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Material Selection - Low Carbon Material

18

- 100% concrete with CIC green product certification (carbon label)

- Material is produced with less environmental impact throughout its life cycle

Beyond Contract

Page 19: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Material Selection - Timber use avoidance with Bondek

19

Bondek structure used as permanent formwork and integrated structure for concreting slab

- Avoids timber consumables and waste

- Avoids sawdust for site tidiness

Beyond Contract

Page 20: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

20

Fish Preservation

Preserve the fish in Fun Pui Garden fish pond before demolition.

Beyond Contract

Page 21: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

4.

Caring of Workers & Neighbour

21

Page 22: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Caring of Existing Campus

22

Using saw cutting machine to cut the exisiting slab to minimize air, noise and vibration impact

Beyond Contract

- Using vacuum cleaner during drilling works

Electric robot to reduce diesel combustion

Page 23: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Caring of Existing Campus

23

Beyond Contract

Page 24: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Additional Monitoring within Campus

24

Real time air quality measurement before hand over- TVOC- PM2.5- Temperature- Relative Humidity

Self-initiated noise measurement in library and theatre

Beyond Contract

Noise barrier for library.

Page 25: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Health Check for workers

25

Beyond Contract

Page 26: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Welfare Facilities

26

Beyond Contract

Page 27: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Promotion Programme for Workers

27

Beyond Contract

Page 28: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Modification of Man Gate

28

Beyond Contract

Page 29: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Care for Others

Volunteer: Home reburbishment for elderly living alone in Island South before Chinese New Year

29

Beyond Contract

Page 30: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Tree Planting

30

Beyond Contract

Page 31: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

5.

Innovation and Creativity

31

Page 32: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Smart Energy Control

32

Office lighting Air conditioner

- Centralize control by smart device- Timer control to reduce energy wastage

Beyond Contract

Page 33: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Design for Manufacturing & Assembly (DfMA)

33

Beyond Contract

- 100% off-site fabricationWaste generationTransportation of components

- 100% bolt and nut connectionEnergy useToxic gas emission from welding

Fabrication scope:Temporary works : 280 tonPermanent works : 1220 ton

- Speed up progress by 1 month

Page 34: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

BIM Automation

34

- BIM design feeds into manufacturing

- 100% off-site fabrication

- Increased accuracy

Controlled wastage < 2%

Beyond Contract

Page 35: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Technology – BIM Monitoring with AR

35

Beyond Contract

▪ BIM for on-site monitoring▪ Increase accuracy▪ Easy to use

Page 36: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Technology – CCTV & Drone Monitoring

36

Beyond Contract

▪ Real-time recording and high resolution ▪ Effective for monitoring different area

Page 37: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Technology – Training by VR Tools

37

Beyond Contract

▪ Good for new comers for experiencing construction activities

Page 38: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

Technology - Inspecto

38

Beyond Contract

Inspecto ▪ Paperless inspection

used by Contractor, Consultant and Client

▪ All parties can respond to latest comments timely

▪ Blockchain technology for verification

Page 39: J3757- Medical Complex Extension at No. 21 Sassoon Road ...

39

Thank you