ITU-BID-04-V1 · integration of SAP to implement the GOS recommendations also taking into account...

15

Transcript of ITU-BID-04-V1 · integration of SAP to implement the GOS recommendations also taking into account...

30/07/2004

BID REFERENCE N° 1142/04

Reference : ITU-BID-THJEH-04-V1

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 2 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

Customer Contacts Mr Arthur LEVIN Mr Raymond CHALINDAR Mr Stephen Geis Chief Coordination, external relation Head of Budget Finance Department IT Management Support and communication units Tel. : 00 41(0)22 730 6113 Tel. : 00 41(0) 22 730 5916 Tel. : 00 41(0)22 730 5337 E-mail : [email protected] E-mail :[email protected] E-mail : [email protected]

IDS Scheer Contacts Responsable commercial CH Thierry Jehotte Ralf Ester Business Development Manager Switzerland Country Manager IDS-Scheer Switzerland Switzerland Tel : 0041 (0)21 625 19 25 Mobile : 0041(0)79 437 97 66 Natel : 0041 (0)79 483 74 13 E-mail : [email protected] E-mail : [email protected] www.ids-scheer.com

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 3 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

Table de matière Introduction…………………………………………………………………………………………………….4 1. Environment……………………………………………………………………………………………………4 2. Scope of Project……………………………………………………………………………………………….4 3. Deliverables…………………………………………………………………………………………………….5 4. Project Calendar……………………………………………………………………………………………….8 5. Sizing……………………………………………………………………………………………………………9 6. Pricing…………………………………………………………………………………………………………12 7. Annexes & Appendix list……………..…………………………………………………………………… 13 8. Notes & Remarks……………………………………………………………………………………………….. 9. Conclusions………………………………………………………………………………………………………

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 4 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

Introduction This Bidding concern a project understanding different elements and different stages. Several specifics needs are expressed:

- A functional usage of SAP, and that, for the next specifics environment:

Controlling, Budgeting and specifically the Results Based Budget - A reengineering of process, and a formalization of these in the framework of the a

structured strategy development - An IT environment analysis for an optimization of this one

This project is spread over different stages including different tasks, needed different solutions and different resources.

But the two principal main lines are:

Improvement of the Controlling and Budgeting systems Reengineering of the processes through a new strategy definition and development

1. Environment

The ITU council decided at its 2004 session (Res. 1216) to appoint a Council Oversight Group (COG) to oversee the implementation of the GOS recommendations.

The ITU secretariat, overseen by COG, will engage a Company with in-depth expertise in integration of SAP to implement the GOS recommendations also taking into account the relevant methodologies described in the Dalberg report Scope of Project.

2. Scope of Project

2.1. Functional Scope: The project should cover the implementation of the relevant GOS recommendations. Principally in the management accounting, controlling, budgetary systems and management

systems. It should also include the definition of ICT strategy and systems integration strategy within the SAP platform and the other systems used by the Union A review should also look for rationalization, uniformisation, and increase of efficiency and reduction of cost.

2.2. Packaged systems selection and/or analysis:

In order to reduce the cost and the time required to carry out the project, the implementation of the GOS recommendations should be made with the current SAP software, with the use of the

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 5 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

suitable version and with additional necessary modules.

3. Deliverables

DEMAND SOLUTION 1.New Budgetary and Cost Management 1.1. Linkage of the structure with

strategic and operational planning (See all details in the bid 3.1.1.) 1.2. Cost allocation structure and

methodology (See all details in the bid 3.1.2.) 1.3. RBB and cost allocation toolbox (See all details in the bid 3.1.3.)

The actual SAP environment in 4.7 version is for us the best basis for the development of the budgetary system and cost management system. This part of analyze must be realized by one of our senior consultant with used of the methodology based on the functional and strategy view of the SAP budgetary and cost management environment. The ASAP Methodology can be used or the PQP A global report which contained all items detailed in the 3.1.1. will be delivered and explained by the consultant. Solutions will also be presented. For the cost management solutions, all the specificities of the SAP controlling tools can be used: CO-CCA ; CO-PCA ; CO-PA ; Internal orders ; ……

The solution consists in the development of the Sub modules of CO in SAP. And the development of a specific Result Based Budget solution. The Result Based Budget is a Budgeting Process developable with the standard tools of SAP Controlling modules Cost allocations and Cost analysis will be developed through the recommendations hoe have to be defined by the business in the workshops, formulated in the BBP by the consultants and validated by Business.

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 6 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

DEMAND

Note:

SOLUTION 1.4 Time Tracking System

The HR environment need a time tracking system. This one can be managed by the CATT solution of SAP

2. Review of ICT Strategy 2.1. Define the ITU ICT Strategy 2.2. Integration and rationalization 2.3. Implementation plan 2.4. Analysis of costs and benefits by

initiative 2.5. Assessment of the information

diffusion strategy 2.6. Requirements definition for

hardware, software and communications. Analyze and Conclusions

2.7. Review of the current applications 2.8. Description of the best practices

for IS department. Procedures and models

2.9. Guide of design of the IT system architecture

For this stage: We need the analyze of a our Senior consultants assist by functional consultant + a technician for technical aspect. This staff has to work with our methodology and trough organized workshops with the business.

3.Business Process reengineering and ICT Strategy Implementation 3.1. Advice and support for: - Re-invigorate existing governance, strategy and org. processes - Develop SLAs with customers - Develop a project management Methodology - Implement an ITU wide information management policy and strategy - Reorganize and rationalize the Services

For this demand and in continuity of the previous one, we propose the installation of the specific tool of Process Management ARIS *See ARIS Documentation The ARIS Process Platform Solutions is composed of different element:

© IDS Scheer AG Business Process Excellence www.ids-scheer .com

ARIS Process Platform

ARIS Web Designer

ARIS Toolset

ARIS EasyDesign

ARIS UML Designer

ARIS Web Publisher

ARIS forHyperwave

ARIS P A

ARIS ABC

ARIS PCA

ARIS Simulation

ARIS BSC

ARIS Integratorfor Vitria

ARISRedocumentation

Scout

ARIS forINTERSHOP

enfinity

ARISProcess Risk

Scout

ARIS formySAP

ARISQualityManagement

Scout

ARISProcess

PerformanceManager

ARISSoftwareEngineering

Scout

ARISOnline Monitoring

ARISProcess Mining

ARISScouts

ARISImplemen-

tationPlatform

ARISControllingPlatform

ARISDesign

Platform

(C) b y IDS Scheer AG. Allrights reserved .

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 7 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

3.2. Implementation of: - Re engineer administrative business process - Update the control framework in place (Objective of decentralization of authority) - Reinforce accountability for performances commensurate (Objective of decentralization of authority) - Increase the footprint of core administrative systems - Extend document management system and roll out E-Collaboration tools - Rationalize the portfolio Applications

Reengineering of Process: Firstly the ARIS Design Tools permit to the company responsible to build the Business Process Design

After The Aris Implementation Platform permit the integration with functional systems like SAP

End The Aris Controlling Platform permit the controlling of the process uding

The information can be spread with

ARIS Web Publisher

ARIS Toolset

ARIS for mySAP

ARIS Process

Performance Manager

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 8 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

- Design new IT infrastructure - Conduct an outsourcing opportunity review - Improve access to information for members, management and staff.

* See all details in documentation A specific BC and IT infrastructure analyze will be realized and proposition suggest in a report with solutions and scenarios After analyze a report will be realized. Different tools and processes can be used. The financial information can be build in BW and send by internal communication system or by web on different types of support. Or, the internal information can be broadcasted by the portal through SAP or ARIS support. To define in the workshops

4. Project Calendar

First stage: From 09/09/2004 to 31/12/2004 Implementation of the: - Result Based Budget

- IT Toolbox

Design and prototype of the: - Time tracking system - New Cost Accounting Methodology Rationalization/Integration of the ICT Strategy Detailed implementation plan of the ICT Strategy and BPR Implementation of ICT Strategy and BPR (stage 1) - Re-invigorate existing governance, strategy and org. processes in IS - Develop a project management methodology - Design a new IT infrastructure architecture - Develop Service Level Agreements (SLAs) with internal users - Implement an ITU wide information management policy and strategy Second stage: From 01/01/2005 to 30/06/2005

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 9 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

Implementation of the: - Time tracking system (we proposed to do it in 2004) - New Cost Accounting System Implementation of ICT Strategy and BPR (stage 2)

- Re-engineer administrative business processes in finance, HR, Procurement and travel - Reinforce accountability for performance commensurate with Decentralization of responsibility

Third stage: Closed for January 1st.2006

Implementation of ICT Strategy and BPR (stage 3) - Simplify and update the control framework currently in place - Increase the footprint of core administrative systems - Extend document management system and roll out e-collaboration tools - Rationalize the applications portofolio in use at ITU - Conduct an outsourcing opportunity review Final stage: closed in 2006 Implementation of ICT Strategy and BPR (stage 4) - Re-organize and rationalize the IT services - Improve access to information for members, management and staff

*See also annexed MPP file

5. Sizing First stage: From 09/09/2004 to 31/12/2004

TASKS SIZING (Working days)

Implementation of the: - Result Based Budget - IT Toolbox

Rule: 1 person full time 1 person part time

from 09/09 to 31/12 80 days

Rule: 25 days for the IT tool. 25 days

Design and prototype of the: - Time tracking system - New Cost Accounting Methodology

Rules: 5 + 15 days

20 days Rule: 1 person part time

from 09/09 to 31/12 50 days

Rationalization/Integration of the ICT Strategy

Rule: 1 pers. 4 weeks 20 days

Detailed implementation plan of the ICT Strategy and BPR

Rule: 1 pers 3 week 15 days

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 10 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

Implementation of ICT Strategy and BPR (stage 1) - Re-invigorate existing governance, strategy and org. processes in IS - Develop a project management methodology - Design a new IT infrastructure architecture - Develop Service Level Agreements (SLAs) with internal users (Optional hypothesis of 4 needed SLAs) - Implement an ITU wide information management policy and strategy

Rule: 1 pers. 3 weeks Rule: 1 pers. 2 weeks Rule: 1 pers 3 weeks Rule: 10 day / SLAs Rule: 1 pers. 4 weeks

120 days

Total of this stage 330 days Second stage: From 01/01/2005 to 30/06/2005

TASKS SIZING (Working days) Implementation of the: - Time tracking system - New Cost Accounting System

Include in 2004 Rule: 1 pers. 4 weeks

20 days Implementation of ICT Strategy and BPR (stage 2) - Re-engineer administrative business processes in finance, HR, Procurement and travel - Reinforce accountability for performance commensurate with decentralization of responsibility

BPM Solution Implementation 140 days

Change Management

Support of a Change Management Consultant part time during the 6 months 140 days

Total of this stage 300 days Third stage: Closed for January 1st.2006

TASKS SIZING (Working days) Implementation of ICT Strategy and BPR (stage 3) - Simplify and update the control framework currently in place - Increase the footprint of core administrative systems - Extend document management system and roll out e-collaboration tools - Rationalize the applications portofolio in use at ITU - Conduct an outsourcing opportunity review

Change Management Support of a Change Management Consultant full time during the 6 months 180 days Functional Consulting Assistance Part Time 60 days

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 11 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

Total of this stage 240 days

Final stage: closed in 2006

TASKS SIZING (Working days)

Implementation of ICT Strategy and BPR (stage 4) - Re-organize and rationalize the IT services - Improve access to information for members, management and staff

For this topic, at this knowledge level let us make an estimated offer linked to the size of a report to establish. Report of 50 pages

40 Days

Development of the SAP Portal for information diffusion. Basis development 60 days After the sizing depend of the needs of diffusion, which kind of information, from where (SAP or not), Which kind of screens (standard or not) This point has to be defined after workshops

Total of this stage 100 days

6. Pricing

6.1. Consulting Rates

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 12 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

6.2. Pricing

STAGE BUDGET STAGE 1 : From 09/09/04 to 31/12/04 660 000 CHf STAGE 2 : From 01/01/05 to 30/06/05 600 000 CHf STAGE 3 : From 01/05/05 to 31/12/05 480 000 CHf STAGE 4 : From 01/01/06 to * Non include the specifics development for Portal

240 000 CHf

TOTAL 1 980 000 CHf 6.3. ARIS Licences

ARIS Toolset 2 Licences 19 840 ARIS Web Designer 10 Licences 40 000 ARIS Web Publisher 800 Licences 38 880 ARIS Business Server 12 160 Sub Total 110 880 Installation Costs + Go Live 6 000 Training Costs 6 000

Daily rates

Function Rates / Day

CHF

1 Project Leader Project Management & Project Lead

2200

2 Functional SAP Consultant

Functional analyse, solution and process integrator

1850

3 Technical Consultant

Architect de solution

1800

4 Technical Consultant

Developer and programmer

1650

5 Strategic Process Analyst 2000

6 Business Process Developer 2000

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 13 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

TOTAL 122 880 Discount 20 % - 24 576

Support and maintenance 20% of this list price per year 6.4. OPTIONS 6.3.1 BW Implementation

1. BW Licences The Licences market and prices are manged by SAP, than we can just delivered a indicative price of licences

See SAP

3. Development

Sizing of a “basic” BW Project developed with the FI, CO, MM, SD, FM, cubes, and with lot of the standard reporting. : 3 month with 2 resources full time

120 Days

Pricing for developement 250 000 CHf

6.3.2 Development of the Specific solution e- Commerce of SAP To take place of “Documentum” Suggestion 6.3.3. Development of the Travel management module of SAP Suggestion

7. Annexes & Appendix list

- Project Flowchart Annex 1 File name : Project Flowchart ITU.doc - Project Planning stage 1 Annex 2 File name : ITU Project1.mpp - Project Planning stage 2 Annex 3 File name : ITU Project2.mpp - Project Planning stage 3 Annex 4 File name : ITU Project3.mpp - Project Planning final stage Annex 5 File name : ITU Project4.mpp - Project Methodology Annex 6 File name : ASAP and Best Practices.ppt - Project Management Annex 7 File name : Validation services.ssm - Project Pricing list Annex 8 File name : Price List for ITU.doc - CV’s

Functional documentation - ARIS Documentation Annex 9 File Name: Image_broschure_en.pdf - IDS Company Documentation: Folder ( Paper documentation )

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 14 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

Appendix - Company Information + Financial data + References - Formal Declaration

8. Notes & Remarks

- The best practices used in the corporations of services and also in the International Institutions are known by IDS-Scheer notably by our interventions within the CIO in Lausanne and the OTAN in Luxembourg - The sizing of the final stage planned in 2006 is not efficient at this stage seen of the

possible evolution before this rationalization period.

9. Conclusions

In conclusion, the scope of project and the needs are based on two principal main lines. The first one concerns a more functional usage of the computer tools and principally the tools of managements and of controlling The second one concerns a reengineering of the organizational process and the development of a new strategy functioning. For the first one ITU use actually SAP. We thought that this is the perfect system for the ITU needs.

Our company is a Global Partner SAP and our staff of consultants is composed from SAP specialists. For the second one our proposition is to implements The ARIS Tools for the reengineering of the process and the strategy.

IDS Scheer is the leader for the supply of BPM solutions (management of the processes) and this with our products ARIS. But our corporation is equally one of the privileged partners of SAP on all type of project, for development and for framing. Especially, IDS Scheer is the alone company offering possibilities of interactivity between the BPM (ARIS) system and the SAP environment. And to close we would be really interested by a long term partnership with ITU.

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 15 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

BID reference 1142 / 04

www.IDS-Scheer.com

Filename:

ITU-BID-04-V1.doc ITU PROJECT Page:

Page 16 Owner:

Thierry Jehotte Date of Creation:

30-07-2004 Modified By:

Date of Modification:

IDS Scheer (Saarbrücken) develops corporate solutions for

business process management. With its ARIS product family, the

company offers a complete portfolio for developing, implementing,

operating and evaluating business processes. IDS Scheer is thus a

provider of both process and IT solutions. IDS Scheer's consultants

support businesses in creating a process organization and

implementing modern application concepts such as e-Business,

Supply Chain Management, Customer Relationship Management

and Enterprise Application Integration. Following its acquisition of

Groupe Expert and the regional companies Plaut CEE and Plaut

North America, IDS Scheer is also able to offer IT & Hosting

Services, lending greater emphasis to its focus on small and

medium enterprises. The PlautWorks and RITS product now

represents a tool that will make rapid SAP introduction a reality for

SME as well. As a part of the ARIS Process Platform, ARIS

Toolset is the number one selling process modeling tool in the

world, and is used by 90 percent of DAX 30 companies. IDS

Scheer was founded in 1984 by Prof. August-Wilhelm Scheer and

now serves about 3,000 customers in over 50 countries through a

network of its own branch offices and partners. In 2002, the 1,450-

strong company earned revenues of over 181 million Euro. In

August 2003, the staff roster grew to about 2000 employees. IDS

Scheer is listed in the TecDAX on the Frankfurt Stock Exchange,

and is thus ranked among the 110 leading companies traded on the

stock exchange, also known as the DAX110. In Germany, IDS

Scheer is among the top 25 IT service providers, in Central and

Eastern Europe, it is recognized as a market leader.

Headquarters: Germany IDS Scheer AG Altenkesseler Straße 17 66115 Saarbrücken Phone: +49 (0)681-210-0 Fax: +49 (0)681-210-1000 E-mail: [email protected] IDS Scheer worldwide: Austria Belgium Czech Republic France Hungary Japan Luxemburg Netherlands North America Poland Singapore Slovakia Slovenia South America Sweden Switzerland United Kingdom www.ids-scheer.com