Item ____IPP03_______ - REPORTS -______04/05/2016_________
N O R T H S Y D N E Y C O U N C I L R E P O R T S
NSIPP MEETING HELD ON 04/05/2016
Attachments: Plans
1. Site Plan
2. Plans and Elevations
ADDRESS/WARD: 22-28 Albany Street, St Leonards (Y)
APPLICATION No: DA13/15/3
PROPOSAL: To modify Development Consent DA13/15 for various
modifications including minor increase in building heights,
inclusion of substation and amended louver detail
PLANS REF:
Plan
No.
Issue Title Drawn by Dated Received
A102 R Level 1 & 2 Plans PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A150 N South and North Elevations PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A151 L East Elevation PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A152 K West Elevation PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A160 K Section A-A PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A161 K Section B-B PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A162 K Section C-C PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A163 K Section D-D PD Mayoh Ptd Ltd 1/2/2016 2/2/2016
OWNER: Peades Properties Pty Ltd
APPLICANT: P.D. Mayoh Pty Ltd
AUTHOR: Lara Huckstepp, Executive Planner
DATE OF REPORT: 28 April 2016
DATE LODGED: 2 February 2016
AMENDED: 26 April 2016
RECOMMENDATION: Approval
Report of Lara Huckstepp, Executive Planner Page 2
Re: 22-28 Albany Street, St Leonards
EXECUTIVE SUMMARY
This development application seeks approval to modify DA013/15 which allowed the
construction of a mixed use building at No.22-28 Albany Street, St Leonards. The modifications
seek to raise the approved height by 850mm and the applicant advises the need has arisen due to
building construction requirements. Various other modifications are proposed.
The modification is reported to North Sydney Independent Planning Panel for determination
given the further increase in Building Height. Notification of the proposal has attracted two (2)
submissions raising particular concerns about view loss and building height. The assessment has
considered these concerns as well as the performance of the application against Council’s
planning requirements.
Following this assessment the modification application is considered to be reasonable in the
circumstances and is recommended for approval subject to conditions.
LOCATION MAP
SERGEAN
TS
CHR
ISTIE STREET
RESER
VE
LANE
CHRISTIE STR
EET ATCHISON
ATCHISON
MITCHELL STREET
PLAZA
MI T
CH
E LL
ST
REE
T
CLARKE
ALBANY
ALBANY
STREET
POLE
STR
E ET
OX L
E Y
CLARKE
HUME STREETPARK
LANE
STREET
LANE
STR
E ET
HU
ME
LANE
ING
RAM
RO
A D
ZIG
LAN
E
LANE
HUM
E
LANE
CHANDOS
PACIFIC
STREET
567
563
545
402-42
0
521
511
34
38
(3/4
1)
(4/4
1)
28-34
22-26
20
(14)
(36
)
(1/3
6)
(2/3
6)
36
61
63
59
55
53
51
43
49
45-4
73
94
13
53
1-3
3
(11
6)
63
65
67
69
71
66
68
75 (3)
70
72
76
74
80
78
82
86
90
77
88
94
96
98
79 (
81)
10
21
00
10
41
06
108
83
110
-112
114
(98
A)
(82)
85
(84)
(114
)
657
10
0
655
81-8
37
7-7
97
5
1
621
2
11 19
619
21 23
10
33
601
35-37
20
39-41
22
599
43
30
1
45
5
38
7
51
575-597
9
55
48
63-65
15
22
67-69
1
26 (28)
50
21
71-73
23
30
75
52-56
7-9
25
79-81
58
27
83-85
38-46
60
31
11
87
62
33-35
89
64
48
51
91
37
50-52
93
66
39
70
95 97
41
23
72
45
74
54-60
99-101
76
47
78
49
25-27
103-105
80-82
62
51
64
53
66
55
68
107
65
70
57
96
10
11
03-1
11
11
31
13A
117
119
123
12
712
9
15
013
61
60
16
416
8
80
76
(59)
33
111-115
31
74
84-90
134
99
13
2
97
13
0
95
12
6-1
28
93
72
91
(91A
)8
9
11
8-1
24
87
29
SP 54033
SP 90263
A
570425
B374468
Sec 8
24SP 71539
SP 77606
28724
1148
728437
2
617114
2872 20
25
Sec 4
216893 1
D 1
6
Sec 4
2872
SP 52547 S
ec 6
126
5
341
46
923722 1
2923723A 1
193399
B 1
SP 30953 387489 A 455938
3 2549551
(sp
lit f
or V
alu
atio
np
ur p
ose
s o
nly
)
9 (split for Valuationpurposes only)Sec 4
28729001321100
14
52
115
1
B
Sec 6
126566713330
4
(spl
i t fo
r V
alu
ati
on
pur p
oses
on l
y)
SP 80874
394320 A
Kelly's PlaceChildrens Centre
SP 33062 311
Se
c 4
2872
655677
20
799
7
(Lease - split for Valuationpurposes only)
B
132 436217 A
312011
1Sec 4
132872
12
11116778228
72
Sec 4 B
627992
1096359
A3905571
21
302454
1SP 76699
733
52
8
1083469
10
3
2
917989
Pt 1
1
564685
(Lease - for Valuation purposes only)
2
12
229804
2281761
SP32797
8141891
4559371
SP 69051SP 69052
SP 72241
Pt 3
1
19
66
09
66
102
28
81
1
SP
229
97
57
70
70
Pt 3
1
1
1216746
2
33991
Pt 3
6
749690
71
7
740017
1
771311
8
564606
120
28
72
17
Sec 11
17
SP
54
43
8
2872
Sec 10
SP
83
145
SP 92232
20
SP
907
38
SP 71980
A
17
249
9
C
SP 88056
431687
1
927
407
10
660453
1
SP 72517SP 75764
SP 72519
772247
1
1
10
481
6
SP 70012SP 70013
2
A
131586S
P 5
71
19
443072
1
B
1096026
SP 73937
C
7
26
1
90
09
98
SP 77654
1
115
58
1
SP 44485
28
455
93
9
Sec 11
2872
2872
1
(Le
ase
- s
plit
for
Va
lua
tion
purp
ose
s o
nly
)
1160762
(Le
ase
- f
or V
alu
atio
npu
rpo
ses
on
ly)
11
(split for Valuationpurposes only) 1
7
Hume Street Carpark &North Sydney Indoor Sports Centre
287
2
Sec 4
369939
(in stratum)
7284
37
11
491147
A
728437
(sp
lit f
or
Va
lua
tion
purp
ose
s o
nly
)
1838
SP 74219SP 74218 H
( Le
ase
- f
or
Va
lua
tio n
purp
ose
s o
nly)
(Le
ase
- s
plit f
or V
al u
atio
npu
rpo
ses
on
ly)
24
0831 564218 55
93
67
2 F
748270
5D
Sec 7 Sec 4 315327 21
93
09
22
57
24
79
56
36
90
2408
3
287
2
2872 551757SP 45213
61
SP
90
61
4
62
1741 11113 AS
ec 4
2872 23
Sec 81265
1
110B1 212 A 8
SP
367
88
SP 60857SP 73656
SP
600
04
SP 21397
287
2
10
13
802
503
37
0
59
77
86
442
085
Sec 5
20
4
771
247
1001
7
28 291 2 21A32
28
72
2
Sec 6
SP 61242 SP 74974SP 6199628722872
12
20
562
4
31
32
64
97
Sec 644
31
66
5
Sec 11
4 1265
1Sec 6
SP
92
63
9
437
33
0
102
98
39
A
44
016
5
2872SP 91359
2
SP 197051265
811A
519221
B2 A1
718988
B
Sec 9
1
933485B
516684287
2
1
Sec 6
Sec 9
2
1
7
1
9270751
1
A
29
1
2B 323 2431 321
88
332
7
SP
79
88
4
SP
158
27
87
37
00
807
81
0
2872
28
72
Sec 5
608
40
0
399283
566
48
0
Sec 5Sec 10
22
2
Re: Page 3
Property/Applicant Submittors - Properties Notified
22-28 Albany Street, St Leonards - DA 13/15/3
Report of Lara Huckstepp, Executive Planner Page 4
Re: 22-28 Albany Street, St Leonards
DESCRIPTION OF PROPOSAL
The proposal involves the modification of an approved shop top housing development. The
approved development comprises the demolition of an existing commercial building and
construction of a 13 storey mixed use building comprising retail / commercial space, 47
apartments and basement car parking. In detail, the approved development allows:-
Ground and part first floor commercial
Provision of 47 apartments over 12 levels including:
o 14 Studio apartments
o 12 x 1 bedroom apartments
o 18 x 2 bedroom apartments
o 3 x 3+ bedroom apartments
Common area of level 13 inlcuding an internal area and northern terrace;
Three levels of basement car parking including 40 car parking spaces, bicycle parking and
storage;
A through site link between Albany Street and Albany Lane;
A loading bay is proposed on Albany Lane
The modifications proposed are described by the applicant as:
1. Building Height – The building height is required to be raised due to the transfer levels
in the structural design:
The Level 4 terrace has increased by 570mm to RL101.410 (Previously RL100.840). The
eastern privacy wall height has also increased by 570mm.
The Level 7 terrace has increase by 850mm to RL110.840 (Previously RL109.990).
The Common Room has increased by 795mm to RL129.085 (Previously RL128.290).
The roof and plant area on Level 8 has been raised by 820mm to RL113.860 (Previously
RL113.040).
The Roof has increased by 995mm to RL132.085 (Previously RL131.09)
2. The inclusion of a substation on Level 1 as per Ausgrids requirements.
3. Amendments to louvre types on the Southern Façade.
4. Amendment to conditions to including staging of consent
CHECKING OF PLANS
This application has been checked to ensure that the changes being sought are the only changes
included in the submitted plans.
STATUTORY CONTROLS
North Sydney LEP 2013
Zoning – B4 Mixed Use
Item of Heritage - No
In Vicinity of Item of Heritage - No
Report of Lara Huckstepp, Executive Planner Page 5
Re: 22-28 Albany Street, St Leonards
Conservation Area - No
S94 Contribution
Environmental Planning & Assessment Act 1979
SEPP No. 55 - Contaminated Lands
SEPP 65 – Design quality of residential flat development
SREP (2005)
Local Development
POLICY CONTROLS
DCP 2013
DESCRIPTION OF LOCALITY
The subject site comprises two existing commercial buildings with a total site area of 731sqm.
The site is located on the northern side of Albany Street. No.22 Albany Street is an existing four
storey commercial building and No.26-28 Albany Street is an existing two storey commercial
building.
Subject site viewed from Albany Street
22 Albany
Report of Lara Huckstepp, Executive Planner Page 6
Re: 22-28 Albany Street, St Leonards
Subject site Albany Street frontage
Adjacent development to the east at No.30 Albany Street (The Encore) is an existing 6 storey
mixed use building (approximate building height of 20m) as can be seen below:
Adjacent building to the east at No.30 Albany Street
22 Albany 26-28 Albany
30 Albany
Report of Lara Huckstepp, Executive Planner Page 7
Re: 22-28 Albany Street, St Leonards
Adjacent development to the west is an existing mixed use building (The Abode) which has a
height of approximately 40m on its eastern end, and 60m on its western end.
Albany Street elevation
599 Pacific
Highway Subject site
Report of Lara Huckstepp, Executive Planner Page 8
Re: 22-28 Albany Street, St Leonards
Site context
Development on the southern side of Albany Street comprises an existing 9 storey mixed use
building at No.1-5 Albany Street, and a part 5 / part 13 storey mixed use development is currently
under construction at No.7-19 Albany Street.
To the north of the subject site on the northern side of the Laneway is an existing 40m mixed use
building (The Nexus Building).
Albany Lane Elevation
Subject site
599 Pacific Hwy
(The Abode)
30
Albany
Street
15
Atchison
Street
Subject site
30 Albany
Street
Report of Lara Huckstepp, Executive Planner Page 9
Re: 22-28 Albany Street, St Leonards
RELEVANT HISTORY
Development Application DA13/15 was approved by the North Sydney Independent Planning
Panel at its meeting held on 5 August 2015.
A Modification Application DA13/15/2was approved under delegated authority on 25
November 2015 which allowed various modifications to apartments, changes to glazing, vergolas
and plant area on the roof.
The subject Modification Application DA13/15/3 was submitted to Council 2 February 2016.
Concern was raised by Council during the process that the additional height would result in the
podium on Albany Street not matching the adjoining podium. The applicant submitted amended
plans on 26 April 2016 to lower the solid podium elements along this elevation and provide a
glass balustrade behind, which maintains the visual appearance of the podium.
REFERRALS
Building
The development application has not been specifically assessed in relation to compliance with the
Building Code of Australia. If the development application is unable to achieve compliance with
the BCA, an additional Section 96 Application may be lodged.
SUBMISSIONS
Adjoining properties and the Holtermann Precinct were notified of the proposed development
between 19 February – 4 March 2016. A Notice was placed in the Mosman Daily on 18 February
2016. Two submissions were received with the main issues raised summarised as follows:-
Report of Lara Huckstepp, Executive Planner Page 10
Re: 22-28 Albany Street, St Leonards
Basis of Submissions
We are writing to submit our objection against the increased height of the proposed
development.
Our apartment is at one level above the east tower of the ABODE. The proposed
development will be completely blocking the eastern view that we currently enjoy.
The proposed development exceeds the current Local Environmental Plan (LEP) limit for
that location, even from its original proposal;
It is unfair for people who used the LEP as a reference, to buy their properties;
If the proposed development is approved, it will depreciate the value of our apartment.
You will see that I objected to the earlier Application for this site, which was to contravene
Council’s height restictions.
I now note that the Developer is requesting approval for a design that would increase that
contravention even more, and this is not a ‘minor increase in building height’ as noted in
your circular. It is incremental over what already contravenes Council height limits.
My original objection remains, and in fact, is now even louder. Council must stay with its
proclaimed restrictions, otherwise why have them.
The amended plans received on 26 April 2016 proposing the lower the solid elements on the
Albany Street podium were not required to be notified as they lowered the solid elements to the
generally match those approved and resulted in no additional impacts.
CONSIDERATION
The proposal is required to be assessed having regard to the following matters.
Section 96(2) of the Environmental Planning and Assessment Act 1979 enables a consent authority to
modify a development consent upon application being sought by the applicant or any person entitled
to act on the consent, provided that the consent authority:
is satisfied that the development to which the consent as modified relates is substantially the
same development;
has consulted the relevant Minister, public authority or approval body in respect of a condition
imposed as a requirement of a concurrence to the consent or in accordance with the general
terms of an approval proposed to be granted by the approval body and that Minister, authority
or body has not, within 21 days after being consulted, objected to the modification of that
consent;
has notified the application in accordance with the regulations and has considered any
submissions made concerning the proposed modification; and
in determining the application for modification, has taken into consideration such matters
referred to under Section 79C(1) as are relevant.
Therefore, Council’s assessment of the application to modify the subject development consent must
consider the following issues:
1. Is the proposed development as modified substantially the same development approved by
the NSIPP?
The proposed development is considered to be substantially the same as the development approved by
NSIPP. The proposed development will result in generally the same yield as approved. Those new
elements that have been increased in height are assessed as not resulting in any material impacts to
adjoining properties. The proposed development is considered to continue to result in an acceptable
level of residential amenity for its occupants and has an acceptable appearance.
Report of Lara Huckstepp, Executive Planner Page 11
Re: 22-28 Albany Street, St Leonards
2. Whether the application required the concurrence of the relevant Minister, public
authority or approval body and any comments submitted by these bodies?
No concurrence is required.
3. Whether any submissions were made concerning the proposed modification.
Two submissions have been received. Issues raised have been outlined and a planning response
required within this report.
4. Any relevant considerations under Section 79C(1) of the Environmental Planning and
Assessment Act 1979.
The provisions of any environmental planning instrument or draft environmental
planning instrument that is or has been placed on public exhibition and details of
which have been notified to the consent authority.
NORTH SYDNEY LEP 2013
Permissibility within the zone: The subject site is zoned B4 Mixed Use pursuant to LEP2013.
Development for the purpose of ‘Shop top housing’ is permissible with the consent of Council.
Objectives of the zone: The particular objectives of the Mixed Use zone are to:
To provide a mixture of compatible land uses.
To integrate suitable business, office, residential, retail and other development in
accessible locations so as to maximise public transport patronage and encourage
walking and cycling.
To create interesting and vibrant mixed use centres with safe, high quality urban
environments with residential amenity.
To maintain existing commercial space and allow for residential development in mixed
use buildings, with non-residential uses on the lower levels and residential uses above
those levels.
The proposed modified development will be consistent with the objectives of the zone.
Principal Development Standards – North Sydney Local Environmental Plan 2013
Site Area - 731m² Approved Proposed Control Complies
Clause 4.3 – Heights of
Building
43m
40m (balconies)
22.8m (level 7
structures)
43.82m
40.8m
(balconies)
23.3m (level 7
structures)
40m (No. 22)
20m (No.26-28)
No
Clause 4.4a – Non residential
FSR
0.42:1 (over entire
site)
0.40 (over
entire site)
0.75:1 (over
No.22)
0.6:1 (over
No.26-28)
No
Report of Lara Huckstepp, Executive Planner Page 12
Re: 22-28 Albany Street, St Leonards
Building Height
Clause 4.3 LEP2013 sets a maximum building height of 40m on the western portion of the site
over No.22 Albany Street, and a maximum building height of 20m on the eastern portion of the
site over No.26-28 Albany Street. A Clause 4.6 Objection was considered and supported for the
approved development. Those new elements proposed that are in breach in the building height
control include:
The Level 4 terrace has increased by 570mm to RL101.410 (Previously RL100.840). The
eastern privacy wall height has also increased by 570mm.
The Level 7 terrace has increase by 850mm to RL110.840 (Previously RL109.990).
The Common Room has increased by 795mm to RL129.085 (Previously RL128.290).
The roof and plant area on Level 8 has been raised by 820mm to RL113.860 (Previously
RL113.040).
The Roof has increased by 995mm to RL132.085 (Previously RL131.09).
Council raised concerns with that the building height would result in the podium that is located
above that of the adjoining property at No.599 Pacific Highway, St Leonards. The applicant
submitted amended plans on 26 April 2016 which reduced the solid elements of the Albany
Street podium to generally match that approved, providing instead a glass balustrade. This is
considered to improve the appearance of the podium and is acceptable. The modification can be
seen below:
A Clause 4.6 Objection is not required for a Section 96 Modification Notwithstanding this, the
proposal is considered against the objectives of the controls as follows:-
To promote development that conforms to and reflects natural landforms, by stepping
development on sloping land to follow the natural gradient – The proposed additional
height continues to be acceptable. Those elements proposed above the building height
control over the 40m building height comprise mostly common area and plant and the
like. Those elements proposed above the building height control over the 20m building
height comprise part of habitable residential level No.7 with the use of the roof permitted
as an outdoor terrace. Despite the additional height 850mm in height, this is considered to
continue to provide a transitional step and is supported. The form of the building is
considered to be contextual.
(b) To promote the retention and, if appropriate, sharing of existing views – The proposed
new elements have been considered with regards to view loss as follows:
Common room and lift over run additional height -
Existing surrounding properties other than the Abode have a building height of 40m or
lower. As such, the additional height would be unlikely to remove any important exisitng
views.
The Abode apartments enjoy their outlook mostly to the north and south, with views to
the east being mostly secondarly from the eastern tower. Existing properties within the
western tower
Report of Lara Huckstepp, Executive Planner Page 13
Re: 22-28 Albany Street, St Leonards
Rooftop plant – The proposed rooftop plant will be located to the south of the approved
rooftop structures and at a lower height. In any case, existing surrounding development is
generally at a similar or lower height and therefore views from surrounding properties
have been generally removed by those components of the building that comply with the
building height control.
Properties located within No.599 Pacific Highway (The Abode) enjoy eastern views
across the site that will be removed by the approved development. The height of the
adjoining building is generally consistent with the height of the Abode where it adjoins
the subject site. As such, the roof plant would be located the level of residential
apartments that immediately adjoin it. The Abode building also has a higher tower on its
western side. Any more distant views lost by these residential apartments, or any
surrounding apartments are considered to be a generally expected outcome of
development on this site. The majority of surrounding buildings, including the Abode,
have rooftop plant structures and it is therefore considered to be characteristic. There is
no known material view loss that arises from the addition of the roof plant adjacent to the
approved roof plant.
Vergola on Level 7 roof terrace – The proposed vergola would be lightweight and have
a height of 1m above the approved balustrading. Existing views across the site are
predominantly from No.15 Atchison Street and No.48 Atchison Street. Any loss of
outlook from these properties would be generally onto adjacent buildings, rather than any
iconic or important views. There is no known material view loss that arises from the
proposed vergola.
As such, those elements in breach of the Building Height Control are not considered to
result in the material loss of views from surrounding properties.
(c) To maintain solar access to existing dwellings, public reserves and streets, and to
promote solar access for future development – The proposed new elements above the
building height limit would not result in any material additional overshadowing to
surrounding properties.
(d) To maintain privacy for residents of existing dwellings and to promote privacy for
residents of new buildings – Those components that are non-compliant with the building
height control including:
Roof top plant – No privacy impacts.
Level 7 Vergola – No privacy impacts given the vergola is located over an
approved balcony.
(e) to ensure compatibility between development, particularly at zone boundaries – The
building form is considered to be compatible with surrounding development and is
considered to be a generally expected outcome of development on the site. Adjoining
sites are also zoned B4 mixed use.
(f) to encourage an appropriate scale and density of development that is in accordance
with, and promotes the character of, an area – The proposed development continues to
be considered to be consistent with the desired character of the area as expressed within
Council’s controls.
Report of Lara Huckstepp, Executive Planner Page 14
Re: 22-28 Albany Street, St Leonards
It is concluded that despite the additional breach to Clause 4.3 NSLEP, the modifications meet
the objectives of the control and the breach can be supported in this instance.
Clause 2(c) LEP2013 sets out that:
„Despite subclause (2), development consent may be granted to development on land identified as
“land in St Leonards‟ on the Exceptions to Development Standards Map if the height of a
building (excluding plant rooms and other similar structures) will exceed the maximum height
shown for the land on the Height of Buildings Map by no more than 3 metres”.
In this instance, the plant and vergola are considered to be ancillary structures with no new
habitable residential space proposed under the subject modification application. Notwithstanding
the above, it is noted that the above clause had a sunset clause that has now expired.
St Leonards / Crows Nest Planning Study Precinct 2 & 3 - Council has now adopted the
St Leonards Planning Study that aims to develop new strategies and initiatives that will provide
for a number of outcomes across the Precinct including improved urban design outcomes. The
study identifies the subject site as having the potential for 40m across the entire site, subject to
other design considerations which could be carried through in a planning proposal for
consideration. This study has not however been relied upon for the subject modification
application.
Non-residential floor space ratio ranges
Clause 4.4A LEP 2013 requires a minimum non-residential FSR of 0.75:1 over No.22 Albany
Street; and 0.6:1 over 26-28 Albany Street. The approved development allowed a breach
providing 0.4.2:1 which was supported on the basis that a through site link was provided. The
modification application proposes a further reduction of 22sqm to provide for the proposed
substation, reducing the non-residential floorspace to 0.40:1. The substation is an essential
element and there is considered to be no reasonable location to increase non-residential floor
space on the site. It is noted that the original non-compliance was supported given that the
through site link was provided over two levels, in accordance with Council’s controls. Should
this area have been provided as non-residential floorspace instead, the proposed development
would have complied with minimum non-residential FSR controls.
NORTH SYDNEY DCP2013
DEVELOPMENT CONTROL PLAN 2013 – Part B Section 2- Commercial and Mixed Use
Development
complies Comments
2.2 Function
Diversity of Activities Yes Despite the further non-compliance with the non-residential
floor space, the proposal continues to provide for an
appropriate variety of uses. The retail spaces adequately
activate both the Albany Street and Albany Lane frontages.
Mixed Residential Population Yes No change is proposed to the number or mix of dwellings.
2.3 Environmental Criteria
Views Ye.
The proposed development is considered to result in a
reasonable impact of views. Refer to discussion following
the DCP table.
Report of Lara Huckstepp, Executive Planner Page 15
Re: 22-28 Albany Street, St Leonards
Visual Privacy Yes Change in louvres on northern elevation – The proposed
change in louvres on the southern elevation will continue to
provide adequate privacy.
2.4 Quality built form
Setback – Side Yes No change to setbacks are proposed
Setback - Rear Yes No change is proposed to the approved 1.5m whole of
building setback.
Podiums Yes The additional height resulted in the podium height also
being increased. Concern was raised that the podium would
no longer match the adjoining podium at No.599 Pacific
Highway. To address this issue, the applicant modified the
podium to provide a glass balustrade to replace the solid
balustrade, to provide a more consistent façade. The
amended façade can be seen below and is assessed as being
acceptable.
Albany Street facade
Building Design Yes No change is proposed to the building design.
Skyline Yes The proposed development will result in a reasonable skyline
appearance.
2.5 Quality Urban Environment High Quality Residential
Accommodation
Yes No change is proposed to the approved number and mix of
dwellings.
Car Parking Yes No change is proposed to the basement level
2.6 Efficient Use of Resources Energy Efficiency Yes An amended BASIX Certificate has been submitted.
Staging of consent
The applicant has sought to amend the conditions to allow the staging of development consent.
Council has adopted a standard condition to allow for the staging of large scale developments to
enable the demolition works and excavation works to be carried on a separate CC to the above-ground
works.
The applicant seeks to modify the development consent as follows:
Report of Lara Huckstepp, Executive Planner Page 16
Re: 22-28 Albany Street, St Leonards
The above-mentioned staging is considered acceptable with the exception of the additional CC
required prior to structures on the roof. This is not supported, and all other conditions will be required
to be complied with prior to above-ground works being undertaken.
It is noted that those conditions required to be complied prior to any demolition include construction
management plan (B1), dilapidation reports (C5, C6 and C7), Structural adequacy & Geotechnical
(C9, C10, C11) all bonds and Section 94 Contributions (C27, C41 & 42).
A new condition is recommended to be added in this regard.
Section 94 Contributions
No change in Section 94 Contributions are required as no change to the number of configuration of
apartments is proposed.
The proposed modifications do not alter the approved development scheme's compliance with the
requirements of any relevant State Plan or Policy. The proposed development is considered to
continue to the consistent with the provisions of the NSLEP 2013 and NSDCP 2013.
(b) The likely impacts of that development, including environmental impacts on both the
natural and built environments, and social and economic impacts in the locality.
All likely impacts of the proposed modification are considered to have been addressed in this
report.
(c) The suitability of the site for the development.
The subject site is suitable for the proposed development.
(d) Any submissions made in accordance with this Act or the regulations.
Two submissions have been received and are considered within this report.
(e) The public interest.
The proposed development is considered to be in the public’s interest.
Report of Lara Huckstepp, Executive Planner Page 17
Re: 22-28 Albany Street, St Leonards
ALL LIKELY IMPACTS OF THE DEVELOPMENT
All likely impacts of the proposed development have been considered within the context of this
report.
ENVIRONMENTAL APPRAISAL CONSIDERED
1. Statutory Controls Yes
2. Policy Controls Yes
3. Design in relation to existing building and Yes
natural environment
4. Landscaping/Open Space Provision Yes
5. Traffic generation and Carparking provision Yes
6. Loading and Servicing facilities Yes
7. Physical relationship to and impact upon adjoining Yes
development (Views, privacy, overshadowing, etc.)
8. Site Management Issues Yes
9. All relevant S79C considerations of
Environmental Planning and Assessment (Amendment) Act 1979
SUBMITTORS CONCERNS
Issues raised by submittors relate to view loss which has been considered in detail within this
report.
CONCLUSION
The proposed modification is considered to be substantially the same as the approved
development is recommended for approval subject to the following conditions.
RECOMMENDATION
PURSUANT TO SECTION 80 OF ENVIRONMENTAL PLANNING AND ASSESSMENT
ACT 1979 (AS AMENDED)
THAT the North Sydney Independent Planning Panel, as delegate of the General Manager, as the
consent authority, resolve to modify its Development Consent dated 5/8/2015 in respect of a proposal
for the construction of a mixed use building at 22-28 Albany Street, St Leonards under the provisions
of Section 96 of the Environmental Planning and Assessment Act only insofar as will provide for the
following:
1. To amend Condition A1 as follows:
Report of Lara Huckstepp, Executive Planner Page 18
Re: 22-28 Albany Street, St Leonards
Development in Accordance with Plans/documentation
A1. The development must be carried out in accordance with the following drawings and
documentation and endorsed with Council’s approval stamp,
Plan
No.
Issue Title Drawn By Received
A.001 F Cover Sheet and Schedules PD Mayoh Pty Ltd 23 June 2015
A.010 B Demolition Plan PD Mayoh Pty Ltd 23 June 2015
A.100 G Basement 3 & Basement 2 PD Mayoh Pty Ltd 23 June 2015
A101 G Basement 1 & Ground Floor PD Mayoh Pty Ltd 23 June 2015
A102 G Level 1 & 2-3 Plans PD Mayoh Pty Ltd 23 June 2015
A103 F Level 4 & 5 PD Mayoh Pty Ltd 23 June 2015
A103-1 A Level 6 PD Mayoh Pty Ltd 23 June 2015
A104 F Level 7 & 8-12 PD Mayoh Pty Ltd 23 June 2015
A105 E Roof Plan PD Mayoh Pty Ltd 23 June 2015
A160 E Section A-A PD Mayoh Pty Ltd 23 June 2015
A161 D Section B-B PD Mayoh Pty Ltd 23 June 2015
A162 E Section C-C PD Mayoh Pty Ltd 23 June 2015
A163 D Section D-D PD Mayoh Pty Ltd 23 June 2015
A400 C Adaptable Units PD Mayoh Pty Ltd 23 June 2015
A401 C Adaptable Units PD Mayoh Ptd Ltd 23 June 2015
Except as modified by the modifications shown in colour on:
Plan No. Issue Title Drawn by Dated Received
A.001 G Cover Sheet & Schedules PD Mayoh Ptd Ltd 2/9/2015 8/9/2015
A.100 H Basement 3 and Basement 2 Plans PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.101 H Basement 1 & Ground Floor Plans PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.102 H Level 1 & 2-3 Plans PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.103 G Level 4 & 5 Plans PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.103-1 B Level 6 Plans PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.104 G Level 7 & 8 -11 Plans PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.105 F Level 12 & Roof Plans PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.150 H South and North Elevations PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.151 G East Elevation PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.152 F West Elevation PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.160 F Section A-A PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.161 E Section B-B PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.162 F Section C-C PD Mayoh Pty Ltd 2/9/2015 8/9/2015
A.163 E Section D-D PD Mayoh Pty Ltd 2/9/2015 8/9/2015
And except as further modified by the modifications shown in colour on:
Plan
No.
Issue Title Drawn by Dated Received
A102 R Level 1 & 2 Plans PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A150 N South and North Elevations PD Mayoh Pty Ltd 1/2/2016 26/4/2016
A151 L East Elevation PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A152 K West Elevation PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A160 K Section A-A PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A161 K Section B-B PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A162 K Section C-C PD Mayoh Pty Ltd 1/2/2016 2/2/2016
A163 K Section D-D PD Mayoh Ptd Ltd 1/2/2016 2/2/2016
- Level 4 Podium Parapet
Height reduction
PD Mayoh Pty Ltd 26/4/2016 26/4/2016
Except where amended by the following conditions of this consent.
Report of Lara Huckstepp, Executive Planner Page 19
Re: 22-28 Albany Street, St Leonards
(Reason: To ensure that the form of the development undertaken is in
accordance with the determination of Council, Public Information)
2. To add new Condition C50:
Staged Construction
C50. The works may be carried out in stages with the relevant conditions being
satisfied prior to the issue of a Construction Certificate for each stage as follows:-
Stage Conditions to be satisfied
Prior to demolition of existing building –
CC1
B1, C5, C6, C7, C9, C10, C11, C13, C18,
C27, C30, C37, C41, C42, C45, D1, D3, D4
Prior to bulk excavation of the site and below
ground structure CC2
C8, C12, C19, C22, C39
Balance of works – CC4 C1, C2, C3, C4, C14, C15, C16, C17, C20,
C21, C23, C24, C25, C26, C28, C31, C44,
C46, C29, C32, C33, C34, C35, C36, C40,
C43, C47, C48, C49 (Noted as C48
DA13/15/2), C50 (Noted as C49 DA13/15,
D2
Unless identified above, a condition that must be satisfied prior to the issue of a construction
certificate must be satisfied prior to the first construction certificate.
(Reason: To enable the consent to be reasonably enacted upon)
3. To amend Condition A1 as follows:
Condition G14 is amended as follows:
Height
G14. Upon completion of the works and prior to the issue of any Occupation Certificate an
appropriately qualified and practising surveyor shall certify the development as compliant
with the maximum approved levels being RL133.085 measured at the highest point of the
lift over run. This survey and certification must be submitted to the Certifying Authority
with the application for an Occupation Certificate and a copy provided to Council (if it is
not the Certifying Authority).
(Reason: To ensure compliance with the terms of this development consent)
Lara Huckstepp Stephen Beattie
A/MANAGER DEVELOPMENT SERVICES A/DIRECTOR CITY STRATEGY
90
90
90
90
80
90
80
80
76.8
82.8
76.7
80.0
98.3
81.4
92.6
89.6
90.5
92.2
100.1
99.5
83.0
83.6
82.1
83.0
84.0
95.9
121.5
84.3
99.098.0
98.2
102.5
89.0
102.8
97.1102.1
95.2
91.1
94.7
95.5
98.6
91.5
99.4
93.0
95.1
102.4
91.1
101.6
92.2
157.5
110.8
92.2
123.9
91.0
91.7
87.3
120.5
91.0
87.3
103.9
98.1
100.1 102.5
87.7
110.9
110.9
98.4
95.395.094.4 96.994.2102.3 99.4101.7104.997.299.8
93.9111.0
98.1101.598.1
110.9
96.6
96.1
102.4100.2 99.3
92.1
97.197.394.5
97.5
95.898.6
111.9
101.3
102.2
99.9
111.5
97.6
95.9
97.7
99.2
95.9
94.3
104.5
91.5
90.3
95.2
93.9
92.6
95.4
107.9
105.1101.5
95.7 94.3
92.8
93.3
104.0
96.9
100.9
99.8
99.8
90.1 90.1
95.9
97.1
96.1
91.5
96.7
94.2
95.3
94.0
93.7
92.7
95.1
92.1
94.0
86.6
84.093.6 83.4
96.9
83.3
84.7
83.5
84.3
95.5
97.2
92.3
89.1
88.2
94.5
86.2
85.285.7
85.1
86.6
85.7
90.8
82.7
83.3
81.781.7
84.6
84.3 84.3
82.0
85.787.5
82.5
82.0
81.7
84.6
85.0
83.5
84.9
83.5
84.7
86.0
84.8
83.3
86.4
83.0
84.4
82.8
ATCHISON
ATCHISON
MITCHELL STREET
PLAZA
MIT
CH
E LL
ST
RE E
T
NICHOLSON
STREET ROAD
CLOSURE
NICHOLSONCLARKE
ALBANY
ALBANY
STREET
POLE
STR
E ET
OXL
EY
CLARKE
STREET
HUME STREETPARK
LANE
STREET
LANE
S TR
EET
HU
ME
LANE
LAN
EH U
ME
LANE
OXLEY
CHANDOS
PACIFIC
STREET
29
27
32- 3
6
27
23-2
5
21
24
22
20
18
16A
16
14
12
10
8
567
35-514-6
563
545
33
31
402-42029
521
400
390
388
511
34
38
382
378
507-509
503
(3/4
1)
(4/4
1)
501
28-34
376
374
497
372
370
368
366
22-26
495
20479
(14)477
(36)
(1/3
6)
(2/ 3
6)
36
61
63
59
55
53
51
43
49
45-4
73
94
13
53
1-3
3
10-12
118
4
(2D) (2C)
1
621
2
11 19
619
21 23
10
33
601
35-37
20
39-41
22
599
43
30
1
45
5
38
7
51
575-597
9
55
48
63-65
15
22
67-69
1
26 (28)
50
21
71-73
23
30
75
52-56
7-9
25
79-81
58
27
83-85
38-46
60
31
11
87
62
33-35
89
64
48
51
91
37
50-52
93
66
39
70
95 97
41
23
72
45
74
54-60
99-101
76
47
78
49
25-27
103-105
80-82
62
51
64
53
66
55
68
107
65
70
57
96
80
76
(59)
33
111-115
31
74
84-90
72
29
151
152 812179
SP 13897
1
SP 21942
SP 48306
168787
SP
30197
220608
419382
1
513450
2
A
403932
B
1
385256
2
A
DRAINAG
E
RESERVE
B
SP 20454
A
B
SP 30607
SP 54033
SP 90263
1
172
4930
1
925872
7
705550
940853
A101
656452
177051
573543
663560
1
1
570425
4320
B4
Sec 3
2
374468
577047
5
1
Sec 8
24SP 71539
SP 77606
2872222601
14
114872
8437
6
455153 600579
100
901161
Se
c 3
2
747672
101 393260
1
SP 72806
SP 83220
A
442804
SP 62905 3
375
882
617114
2872
305810
25
Sec 4
24
216893
D Sec 4
SP 52547
Sec 4
34
14
6
923722
923723A
SP 30953 387489
(sp
lit f
or
Val
ua
tion
purp
oses
on
ly)
Sec 4900132110
01
45
211
51
575046
66713330S
P 80874
394320
Kelly's PlaceChildrens Centre
SP 33062
Sec 4
655677
(Lease - split for Valuationpurposes only)
1
32 436217
Sec 4
1167782287
2
Sec 4
627992
1096359
3905571
213
1
564685
(Lease - for Valuation purposes only)
2
12
229804
2281761
SP32797
8141891
4559371
SP 69051SP 69052
SP 72241
Pt 3
1
19
660
966
10
22
881
1
SP
229
97
57
70
70
Pt 3
1
1
1216746
2
33991
Pt 3
6
749690
71
7
740017
1
771311
8
564606
120
28
72
17
Sec 11
17
SP
54
43
8
2872
Sec 10
SP
83
14
5
SP 92232
20
SP
90
738
SP 71980
A
17
24
99
C
SP 88056431687
1
927
40
7
10
660453
1
SP 72517SP 75764
SP 72519
772247
1
1
10
48
16
SP 70012SP 70013
2
A
131586S
P 5
71
19
443072
1
B
1096026
SP 73937
C
7
26
1
90
09
98
SP 77654
1
115
58
1
SP 44485
28
45
59
39
Sec 11
2872
2872
1
(Le
ase
- s
plit
for V
alu
atio
npu
rpo
ses
on
ly)
( Le
ase
- f
or
Va
lua
ti on
purp
ose
s o
nly
)
(split for Valuationpurposes only)
Hume Street Carpark &North Sydney Indoor Sports Centre
Sec 4
(in stratum)
72
843
71
14
91147728437
(sp
lit f
or V
alu
atio
np
urp
ose
s o
nly)
38
SP 74219SP 74218 (L
eas
e -
for V
alu
atio
np
urp
ose
s o
nl y
)
(Le
ase
- s
plit
for
Va
lua
tion
purp
ose
s o
nly
)
1 564218 559
36
7
Sec 7 Sec 4 315327930
92
2
572
47
9
563
69
0
28
72
2872 551757SP 45213
SP
906
1417
41 11113
Sec 4
2872
110B1 212 A 8
SP 60857SP 73656
SP
600
04
SP 21397
287
2
101
380
2
50
337
0
597
78
6
442
08
5
Sec 5
28 291 2 21A32
28
72
Sec 6
SP 61242 SP 74974SP 6199628722872
20
56
24
31
32
64
97
Sec 644
31
66
Sec 11
Sec 6
43
73
30
10
298
39
A
44
01
65
2872SP 91359 SP 19705
811A B2 A1 B
B
287
2
Sec 6
11
1
A
29
2B 323 2431 321
88
33
27
SP
798
84
SP
15
82
7
87
37
00
80
78
10
2872
287
2
Sec 5
60
84
00
399283
56
64
80
Sec 5Sec 10
22
2
North Sydney CouncilCopyright:
Copyright © North Sydney Council - No part of this map may be reproducedwithout permission. Commercial decisions should not be made based on information contained in this map without first checking details held by the responsible Government authority.
Further details can be obtained by calling (02) 9936 8100 or e-mail [email protected].
ATTACHMENT TO IPP03 - 04/05/2016 Page 20
GITIÉI OVÉRRUIRL ì33 385
RqoFRt t32 B5
UÉf OVËRRURL t33 3!5
Rt J208i
COMMONSPACERr l2? 08i
rElEr l2RL 125 990
ÉYnÈL 2't924
cYEt r0RL I tt 9C0
LEVEL 9'RL ó 880
TEVETEit J8ó0
.rEyEr 7
Rt 084
\r,/ nLralv LaleÆ NOR]H ELEVATTON
COORDINATION ISSUE
o -,.. ".," c-,ñ\,,.., .,{¡,.,¡¡,o.,.*'*oo@oo
oo
@o@
oo
o
oo
DD,IAIOU Þlt LID
FcopesFopurc5Py td
SOUTH & NORIH ELEVATIONS
MIXFD !SE DEVETOPMENT
22.28 ALEANY STRE€IST LEONARDS - NsW
NA t50
t+\þ
il
I
@
(,
@
ilr6r-Tl
l
¡tlo
ll oi
@
=
@
o
ll
aò
ELEVATION
SiREEI
ATTACHMENT TO IPP03 - 04/05/2016 Page 21
(Ð @ (¡) (Ð (Ð COORDINATION ISSUE
NOIES
ROOFRt 132 @5
COMMONSPACE
piII Rr ìæ6
EAST ELEVAIION
æML FIÑßHES GÊEND.LEVil 12RL ì6.990 o
o
o&Éh4ú!cútr51.fu LÌw^br
@(D
CÐ
LilEL ì I
il t29n
LEVil ìORrìt9ræ
IEVET9ós0RL
k¡ o@TD
o(iloCr@@(D
rryEr8RL Iì3M
TEVELZRL tì0ru
TRELóRL t07 m
IryEL5Rr t040
TEVELlRt l0t ¡ì0
LEVil3RL98ã
s4
nr*,**,*,,*""*"-
¡Eù.¡e'@o'oBla @uo
(9)
LEVEL 2R195ru
ATBANY LoneLfVil IRLt2 ìæ
ilP6oÞetProæniesPly Lld
tuù¡qhußINSW æ10
EAST ELEVATIONATBANY STREET]
GROUND
BÆÉMENT IRL&S.94
MIXED USE OEVELOPMENT22,28 ALBANY SIREflSI LEONARDS - NSW
ATBANY LANE
hN, t$J
*-rrruxjli'i'l
o@
¡
(
(Ð
(ù
í1r
.;i
,it
. 1/,¡-
û
(tI
i' CÐ
,rò-1"(i)
(t
(c)
iI
@
(Ð
Pl'l ri r
A.t5t
ATTACHMENT TO IPP03 - 04/05/2016 Page 22
L ,:l- g flio
ilro fllo
l Lr@ r-@
¡4¡eeN1 ¡o¡9,
o
rd @-"r i,l
rdo
o
UÍOYERUNRt ìss-R0oFRL t32Æ
COWONSPÂÇfRL ì?.M
EVEL I 2RI IãJ9O
uvaìttut29n
wa ì0ÊL tì9.Ð
LryR 8RLlt3¡&
trva7nL ¡10,ru
8EL¿RL 107.ø
LM{5RL I&O
at4lL tbl.lro
r¡vEr3RL'8ru
rÉvfl 2RL'5 M
@Arq¡sEf,oN NoEs
COORDINATION ISSUE
ô 4rùcæhf.fu'o4sÀ
o@
Ooo@o
@ oñ'úÞ!û'@
o@o@@@o@o@
k¡¿É@ñ@sc6b
Poæ tooFtu Pry. tE
M€hud NWÐ10
r**,**'**I"***.",***,
PD NAION DTI LTD
bq¡¡¡v_ùnçqlWEST ELEVATION
sr. tEoNARos - Nsw
MIXED USE OEVELOPMENT22.28 ALBANY SIREEI
lø iio." -* lm
iqy¡1.pt¡ to*r¡.inurl
K
ffitRL'z æ
A. ì52
ATTACHMENT TO IPP03 - 04/05/2016 Page 23
_\EX SILNG FOOTPATN\
,-P\ 'A\.tnJ, \.tov,'-a
1. 2 3 4)fiå)'a
tt- /,(,åì <tl\2 r .-- \--(1) (6
(nì",t
@¡ tuþl þ-zse,2BED SÌUDTO qrUDtO
trao4lI BED
STLDIO
u t02
(a)(.)B P"
LOGGI^
* tii
LOGGq
lxltrÍl
"¿4
.^.^11 \
,4.lól,
,r\..¿ !'\\ì ós, I
ã ilÉcL.3MwúlkaFEiroas)
ltT oqNM€R4 e'N'-
raì Æas* ôm{w*'
FLffi FINISHES LEGEND. R€FËR fO A 60I
: DrE(w{rr*F.Rroa s)
Mhghußt NSw 2010
:
r.r)
(Ð
(.c)
(¡r.)
I
4"+ 4,>(. t.)
(¿)
rt)
ON
LOæA
r eðldroLtqùd6ñù¡dìrivd6
Ñ ¡*'i*UV
K)
sfuDlo
u. rq5.
.Ð '{""" (e (;
LEVEL] &2PLANS
MIXED IISE DEVELOPMENT
STUDIO
iC Loli(Adopfoble)
STUD]O
!-,!L-ì BED
iu!4
$r
STUDIO StUDtO
þ@ U?qóì(Adoploble) {Adoploble)
(#,1
22-28 ALBANY SIREETST TEONARDS - NSW
(t';-¡ú ìS3
,o*] ll PM MKLÆì\ LEVEL I PLAN /6À LEVEL 2 PLAN
t-.R
ô
DN KI
"!lLOPG A
LIVLV
locc^""1
KTotN
LV
ü
1
îcorñnc¡L
TOADING BAY
ô
i
l"], B
.([ON
|OGGA
Lq
Ufl2
!flt
orN
' tål!æGIA
2 BED
ru.æq-
A t02
ATTACHMENT TO IPP03 - 04/05/2016 Page 24
I
-1
EALC
ROOtRL ì326
COMMONSPACERt ì29 ffis
LEVA ì2RL r259m
TEVEL I I
Rr ì22 9æ
iEVEI ìO
Rlll99æ
wÉ19RL I ìóru
LEVELSRL ]]3EO
LEVEL 7RL tì0m
LEVEL¿RL ì07¿æ
------l
COORDINAIION ISSUE
ELEVAÌION å SECIION NOES
o(t
pì
'3)
o ^,Êh-.1*'."trN ds'l
(,oaa,,
(,oe)@
olr)Gr@(,G)ul@(¡)
@)
t--t
ffi--*^*.^"**-'ru*"*^'*.^,.-"
-t
-1
I
I
I
-lI
I
I
I
I
t-
-BALC
f-
I
t--J
r
LEVEL5RL ì04 óæ
LilEL 4RL l0ì.¡t0
NWilllRL RL&.?¡O
BNEMES2RLæ2S
Nffi3È 7g&
LryEL3R1984
LEVEL ]
RL 92 tþ
LEVEL2R195.ru t l)D,rAlotlptÌ tlt)
ALBANY LoNCALBANY STREET'
GROUND
PeopesProperEsPlY Ltd
Mæhûßl Nw 20ìQ
SECTION A-A
MIXED ISE DEVELOPMENT
22 28 ALEANY STREflsl LrcNARDS. NsW
I
-)li *
-
cÂÊE/REfAURANI
!N[7@ -f
uN[ 902
UNI æ2
uNtT I 102
-uñr ó05 |
ustuEÑr
NEN1ENI2
BAENlENI:PÆKNG
SU6STAIION
UNI ?OI
UNT
!ñtT90r
uN[80ì
UNI
6A5EMEÑI ]
PAiKNG
!N[201
ùNLl40ì
SALC
BALC.
COLDWAIERP!MP ROòM
A.tó0
ATTACHMENT TO IPP03 - 04/05/2016 Page 25
t. _-
ROOF
Rt t3208s
COMMON
RL t29 0S
LEVEL I 2RL t259t0
EVEL I
RL ìU 920
IEVEL IORLtì99æ
IEVEL9RL iló.æ0
TEVELSRL I r3 8ó0
LWEI7Fr lr0M
LEVEL 5RL 104 é@
LEVEL 1RL 10t.4 0
LFIEL3Rrt&2æ
LEVEI2RL95@
UNI
;----.!t-f{l¿il r
TÉF----E-11 !ñ ll :
uN[ t0]
:¡3FAffING
Il
uN[ I ¡02
uNt ìæ2
UNI M2
CrBov
;8ì UnrcYER
HÊICHI
HELGfiI,/¡\
-l
-t
I
I
I
I
I-lI
-l
ouNlf4ø c i-D
I BALC
COORDINATION ISSUE
ELEVAI¡ON ¿ SECIION NOIES
Ë|ryÈ4ffi"]f?iftHriffi ,r*.hläåPl-cl9lh
Häüå,#fifflfrrHffiffiffiä1.ä'
lg
c)oo@arl(t(Ð
.:,(,-,)
()oooG)GolD(t)(i)
4 rdúc.oorñßdr . Èrù4
ru* .***""*-,*."**
ffi
EXIêRN FINISHES LEGNDI
t, baú!h6cEd!ñ
(Ð b!tuùGÞM(Ìtury
PæpdProFliciFy Ltd
Dodnehußr NSw æt0
o)
(Ð
(i)
(Ðl
tt .-
(Ð
IçVEL IRft2.r30
GROUNO
RLæ,fr
SÊCTION B-B
_,r,,, ,.-MIXED USE DEVELOPMENI22.28 ALBANY SlREflSÏ TEÔNARDS . NsW
!ÆfuENT ìFL Rl85.9ð
8AEMENI21L¡22S
. _,..i,t, ,r,:i ,1.: , . .;1+b,M t333
t1-l l- - ìic"*'ú Ptr ] ù-" il pM MK
'i KA.tól
ATTACHMENT TO IPP03 - 04/05/2016 Page 26
COORDINAIION ISSUEuflovmR!ñRL ì33SRæFRL ì32N
LEVEL 12RL tã9rc
LEVEL ì ìRL ì229æ
LWEL 'RL IIó@
,
i
)
I)II
iI
)
I
t:,
, ,2-2¡ Át¡ANY 5tRlÉl0onç sr'.ion irngl,
Ì -----I
I
lI
I
1
I
I
I
l
I
I
ì
I
COMMONSPACERL I29.N
EVEI IORt I t9.9æ
tot9 ñeG)
G)(q.)
"i.a-Ðî@
(roaÐ
ooe)(4r
o)@
o
(ì(loo@(t0)(t(Ð(Ð
G)(o(Ð (,.
/6ì\f-7-lI
Â(q)
.
(1r
(Ð
G)
(r)6)rf',
LEVEISRt ì r3.M
LryEL7RL lì0.ð{
LEVELó
RL ì07.óÐ
LEVELSRL r04.m
LEVEL ¡RL l0r.1t0
LEVET 3RL98220
IryEL2R195.ru
BALC
!,
i
:tt,l.
hd&dio¡úôùqq¡ù (!!
DD,tAl()lDlt tD
ALBANY Lone
(, @)(?)LOÀOINGBAY LEVEL I
RL'2 æCo
PeopesFropel€sPlv Lld
tulinghußt Nsw 2010
AL8ANY STREEI i
(.u
SECTION D-D
MIXED IJSE DEVELOPMENT22-28 ALBANY STREET
ST LEONARDS - NSW
sN, 1333
KA tó3
N!M8JI3.fr /¡.ófl
: .:.', .: ,l
. ,.,: .,. .,.
:
I
luN[702I
r.1N r 40ó
I
L
l
BÆilENI I
PARKING
BASEMENI2
8^SilENl3P^RKINC
uN[ æ8
UNIru
uNiT4ì
uNt70tI
UNIT
UNISI
8NilEÑI3SIORAGEARA
!T
$
BASEMENIPARKING
BAEMENI2PARKNG
K
a
s2
ATTACHMENT TO IPP03 - 04/05/2016 Page 27
\OO
LOGGIA
LOGGIA
LEVEL 5RL r 04.ó00
(,^)
REDUCED PARAPET HEIGHÏWITH FRAMED GLASS BALUSTRADEBEHIND
ssOLEVEL 4RL l0l .410
REDUCED GLAZING LEVEL 4TO RETAIN PODIUM SURROUNDPROPORTION
N)5OO
LEVEL 3RL 98.220
LÇwv+ FþDrutl ?AlAfvç +lglbHrßúO w¡t a Fr envrùØlÞ +Aaa N
lb z?-?år¡,uA}(r¡r w nÁYoÞt
oooBALC.
I
UNIT 208
BALC.UNIT 505
UNIT 40ó
UNIT 308
ATTACHMENT TO IPP03 - 04/05/2016 Page 28