IsaMill Carbon Presentation BHPB Nov 07

download IsaMill Carbon Presentation BHPB Nov 07

of 56

Transcript of IsaMill Carbon Presentation BHPB Nov 07

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    1/56

    Xstrata Technology

    IsaMill and thePotential for Carbon Credits

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    2/56

    Agenda

    Brief Introduction to Xstrata Technology

    IsaMill Introduction Background

    How it works Advantages including Energy Efficiency IsaMill Case Studies

    Carbon Credit Potential

    Next Steps

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    3/56

    Xstrata Technology

    Small independent group in Xstrata.

    All technologies developed on site, and key to our ownoperations

    Full technology solutions in our areas of expertise

    70 people - strong technical/operations focus

    Deliberately different business model

    A technology transfer group

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    4/56

    Specialist Products in all Areas ofProcessing

    Tankhouse Technologies producing most of the

    worlds refined and EW copper. Expert tankhousedesign.

    ISASMELT high intensity smelting process with lowcapital cost, energy efficient, flexible scale. The newbenchmark in Copper smelting.

    IsaMill step change in grinding technology. Muchhigher energy efficiency. Metallurgy improvementsfrom inert grinding media.

    JAMESON CELL - high intensity flotation. Ideal incombination with conventional flotation for low costcircuit expansions and higher concentrate grades.

    ALBION PROCESS simple, low cost atmosphericleaching for refractory concentrates .

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    5/56

    A deliberately different approach Only market our 5 core technologies

    Aim to be expert in these Each installation should be better than the last

    Provide full package for those products Process design

    Associated engineering (but not EPCM) Equipment supply Process control system Specify and supply associated equipment Training, Commissioning Ongoing support process, spares

    Results in fast start up, successful installations

    Combination of depth and breadth of expertise Grinding, flotation, smelting, leaching, refining

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    6/56

    IsaMill

    3.0MW

    M10,000

    3.5mm ceramic

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    7/56

    Developed for Ultra Fine Grinding

    IsaMill originally developed for UFG duties

    Conventional grinding technology Too energy intensive Media cost too high

    Poor flotation response due to high kg/t steel consumption

    Ultra Fine Grinding needed a step change in technology

    McArthur River

    0 40 micron

    Broken Hill

    0 40 micron

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    8/56

    Concept from Manufacturing Industry

    Solution found in manufacturing industry High value products paint pigments, ink, pharmaceuticals

    Significant testwork programs conducted

    Development program with Netzsch to crossover thetechnology to minerals industry:

    Needed to be much bigger scale

    Needed to be able to use cheap media

    Needed to be easy to maintain

    Needed to be continuous (retain fine low SG media, but passwater and ground slurry)

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    9/56

    Enabling Technology

    IsaMill M3000 1.1MW developed with Netzsch Enabling technology for McArthur River, 1995 Significantly more Energy Efficient than Tower Mills

    Inert grinding environment = selective flotation, high recovery

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    10/56

    Now Developed for Coarse Grinding

    3.0MW M10,000 IsaMill Developed with Anglo Platinum

    Coarse ceramic media developed with Magotteax

    Same benefits for Coarse Grinding Improved energy efficiency

    Process benefits from inert media

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    11/56

    IsaMill: A Step Change in Technology

    Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint

    High Efficiency Fine Media

    Inert Media Downstream Benefits

    Scaleup Maintenance

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    12/56

    IsaMill: Internal Layout

    Grinding chambers in series no short circuiting

    Product separator retains media without fine screens

    Product Separator

    Grinding Discs

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    13/56

    Sharp size distribution

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    14/56

    IsaMill: A Step Change in Technology

    Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint

    High Efficiency Fine Media

    Inert Media Downstream Benefits

    Scaleup Maintenance

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    15/56

    IsaMill A Step Change in Size

    Tower Mill

    Max 1.1MW after 50 years 40kW/m3

    Closed circuit cyclones

    Media handling

    IsaMill M10,000 3.0MW 300kW/m3

    Open circuit no cyclones

    Media under mill platform

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    16/56

    IsaMill A Step Change in Size

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    17/56

    IsaMill: A Step Change in Technology

    Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint

    High Efficiency Fine Media

    Inert Media Downstream Benefits

    Scaleup Maintenance

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    18/56

    IsaMill: A Step Change in Efficiency

    Fine media is key to energy efficiency better transfer ofdrawn energy to slurry

    2,220176,500,0002IsaMill

    370818,00012Tower Mill

    222177,00020Ball Mill

    Surface Area(m2/m3)No. Balls / m3Media Size(mm)

    Results in lower kWhr/t

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    19/56

    IsaMill: A Step Change in Efficiency

    At P80 35um:

    Tower Mill = 32 kWhr/t

    IsaMill = 18kWhr/t

    IsaMill uses up to 45% less power

    F80 = 110um

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    20/56

    IsaMill: A Step Change in Technology

    Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint

    High Efficiency Fine Media

    Inert Media Downstream Benefits

    Scaleup Maintenance

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    21/56

    IsaMill: Inert Media

    Typical Plant Size Recovery Curve

    Momentum

    Surface area / mass

    Surface coatings steel media

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    22/56

    IsaMill: Inert Media

    AMIRA P260

    Improved Recovery

    with ceramic

    Due to higher fines recovery

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    23/56

    IsaMill: Inert Media

    MIM Cu Concentrator

    Grano et al, 1994

    Reduction in surface Fe coatings

    Improvement in Size by SizeRecovery

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    24/56

    IsaMill: A Step Change in Flotation

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    C7 C6 C5/C4 C3-C1 38/53

    75Size fraction

    Z i n c

    R e c o v e r y

    i n s i z e

    f r a c t

    i o n

    %

    0.0%

    5%

    10%

    15%

    20%

    25%

    30%

    35%

    40%

    45%

    50%

    0-4um 4-8um 8-16um 16-38um 38-75um

    Recovery

    Size Dist ribut ion

    MIM Pb/Zn Concentrator IsaMill Stage Grind

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    25/56

    IsaMill: A Step Change in Technology

    Open Circuit, No Cyclones - Sharp PSD

    High Intensity Small Footprint

    High Efficiency Fine Media

    Inert Media Downstream Benefits

    Scaleup

    Maintenance

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    26/56

    IsaMill: Accurate Scaleup 4 10,000L

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    1 00

    0 .1 1 1 0 100 10 00Size (um )

    % P

    a s s

    i n g

    M4 Product - May 2001

    M10,000 Feed - April 2005

    M10,000 Product - April 2005

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    27/56

    IsaMill: A Step Change in Technology

    Open Circuit, No Cyclones - Sharp PSD

    High Intensity Small Footprint

    High Efficiency Fine Media

    Inert Media Downstream Benefits

    Scaleup

    Maintenance

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    28/56

    IsaMill: Maintenance

    Shell slides back formaintenance access

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    29/56

    IsaMill: Maintenance

    Discs removed from shaftusing crane

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    30/56

    IsaMill: Maintenance

    Disposable Shell Liner12 months

    Disposable Disc6-12 months

    Reusable Disc Hub

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    31/56

    IsaMill: A Step Change in Technology

    Open Circuit, No Cyclones - Sharp PSD

    High Intensity Small Footprint

    High Efficiency Fine Media

    Inert Media Downstream Benefits

    Can change the way plants are designed

    Replace tower/ball mills

    Simplify flotation circuits

    Produce higher grades to smelters

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    32/56

    IsaMill Anglo Platinum

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    33/56

    IsaMill Anglo Platinum

    Mainstream Inert Grinding F80 120um to P80 53um grind

    Concentrate Regrinding shift grade

    Production ExpansionShift in Grade has potential to postpone major smelter expansionA fraction of overall energy consumption by grinding than smelting

    22 IsaMills in production / on order

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    34/56

    IsaMill McArthur River

    Rougher

    Cleaning

    Prefloat

    Concentrate

    SAG Mill4MW

    935 kW Tower Mill

    Sand Media

    Current Circuit includes SAG Mill and Tower MillPlan to increase throughput by 30%Testwork conducted and IsaMill selected for expansion

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    35/56

    IsaMill McArthur River

    IsaMill M10,000 treating screened SAG dischargeF80 300um to P80 45umOpen circuit operation

    Rougher

    Cleaning

    Prefloat

    Concentrate

    SAG Mill

    4MW

    7 micron grind

    Tower Mill andcyclones r emoved

    45 micron

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    36/56

    IsaMill BHPB Leinster

    3.5 unit increase in Ni grade

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    37/56

    IsaMill BHPB Leinster

    30% reduction in MgO to concentrate

    Significant implications for smelter performance

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    38/56

    IsaMill BHPB Leinster

    XT anticipate an order in the next couple of months

    Pre work has all been done, prefeasibility, feasibility, etc etc

    First stage of project engineering drawings have alreadybeen provided

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    39/56

    IsaMill Phu Kham

    12-16mtpa Copper Concentrator 2.6MW M10,000 IsaMill replacing Tower Mills

    Relatively coarse primary grind

    Regrind 168tph rougher cons from106 microns to 38 microns in 2.6 MW

    IsaMill

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    40/56

    IsaMill Oxiana Prominent Hill

    8mtpa Copper Concentrator 3.0MW M10,000 IsaMill replacing Tower Mills

    Relatively coarse primary grind

    Regrind 138tph rougher cons from125 microns to 25 microns in 3 MW

    IsaMill

    Single Jameson cell backed

    with conventional cellsSimplified circuit

    Energy efficient

    Small footprint

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    41/56

    IsaMill Growth

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    42/56

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    43/56

    Potential for Carbon Credits (CER)

    IsaMill TM has potential to generate carbon credits under the CleanDevelopment Mechanism (CDM) of Kyoto Protocol

    Under Kyoto Protocol, Annex 1 countries have mandatory targets to reduceGHG emissions by 2012

    Annex 1 countries can offset their domestic emissions with credits (CertifiedEmission Reductions - CERs) earned by investing in non-Annex countries (forexample - Chile)

    Xstrata Technology working with consultant SigmaGlobal to proveaccreditation for IsaMill TM

    Hypothesis : IsaMill - new efficient technology currently not used in Chilereduces power requirements and improves grade / recovery for regrindingcopper

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    44/56

    Annex 1 Countries

    CO 2 Cap

    Carbon Trading Basics

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    45/56

    Annex 1 Countries

    CO 2 Cap

    Increased CO 2Emission

    Offset (CER)

    Required

    Carbon Trading Basics

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    46/56

    CERs

    Non-Annex 1 Countries

    (includes Chile) Annex 1 Countries

    CO 2 Cap

    Increased CO 2Emission

    Offset (CER)

    Required

    Carbon Trading Basics

    CDM Projects

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    47/56

    CERs

    CERs

    CERs

    Non-Annex 1 Countries

    (includes Chile) Annex 1 Countries

    CO 2 Cap

    Increased CO 2Emission

    Offset (CER)

    Required

    Carbon Trading Basics

    CDM Projects

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    48/56

    CDM Market well established and growing

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    49/56

    Breakdown of CDM Projects

    Country Spli t (2006 Projects)

    Project Types (2006 Projects)

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    50/56

    CER Trading

    CER prices increasing

    Growing interest from financial institutions

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    51/56

    Creation of CERs by CDM

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    52/56

    Potential IsaMill Project at BHPBilliton

    Replace 20 Tower Mills @ 1.1MW = 22MW

    With 5 IsaMills @ 3.0 MW = 15MW

    Power Reduction = 7MW

    30% Power Reduction

    Assuming Power Reduction 6.5MW

    Plant Availability (NOT IsaMill) = 90%= 5.85 MW

    Conversion MW to CO 2 Equivalents = 0.59 (Chile)

    = 3.45 t CO 2/hr

    Convert to Annualised CO 2 Tonnage = 30,235 t CO 2/year

    Convert to CER @ $25 AU/T CO 2 = $755,878 AU/year

    Convert to US $ @ 0.86 Exchange = $650,000 US/year for 10 years

    TOTAL CER POTENTIAL = $6.5M US

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    53/56

    Why IsaMills for BHP Billiton in Chile?

    Standard copper regrind circuits (in Chile) use Tower Mills for

    regrinding

    XT perceive there is a barrier to the introduction of IsaMillsinto Chile are none installed yet, and certainly not in copper

    Business as usual is to continue to do the same

    XT understand that there are some issues with BHP Billiton(along with a lot of other companies) and compliance inEurope (an Annex 1 Region)

    PR value one of the first mining projects to get CERs

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    54/56

    To Qualify and Maximise the Benefit

    Consider a project concept Use IsaMills in BHP Billiton ingeneral Copper Circuits or just at Escondida

    Reason for doing it is get carbon credits, which will allow theproject to proceed. If its business as usual then no credits.

    Need to look at the big picture if there is one, to maximisethe benefit. Not just replacing one tower mill with an IsaMill.Doesnt matter if the project falls over, or if you only use 1IsaMill, but to get proposal approved after IsaMills are installedin Chile then would be more difficult

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    55/56

    Some projects already accepted

    Nestle Chile - switching from burning coal to naturalgas in production facility

    Mitsubishi Corporation reduction in N2O gained822,000 CER credits

    Ball mill replacement in Israel

  • 8/13/2019 IsaMill Carbon Presentation BHPB Nov 07

    56/56

    What Next?

    BHP Billiton to decide if this is a goer or not

    If decision is made to proceed then in parallel

    Set up a program to validate the hypothesis

    M20 pilot plant comparison to existing flow sheet Install one IsaMill in parallel with existing Next concentrator to include IsaMills

    Start work with XT and SigmaGlobal on the proposal