IsaMill Carbon Presentation BHPB Nov 07
-
Upload
manuel-leiva-cerda -
Category
Documents
-
view
220 -
download
0
Transcript of IsaMill Carbon Presentation BHPB Nov 07
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
1/56
Xstrata Technology
IsaMill and thePotential for Carbon Credits
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
2/56
Agenda
Brief Introduction to Xstrata Technology
IsaMill Introduction Background
How it works Advantages including Energy Efficiency IsaMill Case Studies
Carbon Credit Potential
Next Steps
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
3/56
Xstrata Technology
Small independent group in Xstrata.
All technologies developed on site, and key to our ownoperations
Full technology solutions in our areas of expertise
70 people - strong technical/operations focus
Deliberately different business model
A technology transfer group
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
4/56
Specialist Products in all Areas ofProcessing
Tankhouse Technologies producing most of the
worlds refined and EW copper. Expert tankhousedesign.
ISASMELT high intensity smelting process with lowcapital cost, energy efficient, flexible scale. The newbenchmark in Copper smelting.
IsaMill step change in grinding technology. Muchhigher energy efficiency. Metallurgy improvementsfrom inert grinding media.
JAMESON CELL - high intensity flotation. Ideal incombination with conventional flotation for low costcircuit expansions and higher concentrate grades.
ALBION PROCESS simple, low cost atmosphericleaching for refractory concentrates .
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
5/56
A deliberately different approach Only market our 5 core technologies
Aim to be expert in these Each installation should be better than the last
Provide full package for those products Process design
Associated engineering (but not EPCM) Equipment supply Process control system Specify and supply associated equipment Training, Commissioning Ongoing support process, spares
Results in fast start up, successful installations
Combination of depth and breadth of expertise Grinding, flotation, smelting, leaching, refining
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
6/56
IsaMill
3.0MW
M10,000
3.5mm ceramic
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
7/56
Developed for Ultra Fine Grinding
IsaMill originally developed for UFG duties
Conventional grinding technology Too energy intensive Media cost too high
Poor flotation response due to high kg/t steel consumption
Ultra Fine Grinding needed a step change in technology
McArthur River
0 40 micron
Broken Hill
0 40 micron
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
8/56
Concept from Manufacturing Industry
Solution found in manufacturing industry High value products paint pigments, ink, pharmaceuticals
Significant testwork programs conducted
Development program with Netzsch to crossover thetechnology to minerals industry:
Needed to be much bigger scale
Needed to be able to use cheap media
Needed to be easy to maintain
Needed to be continuous (retain fine low SG media, but passwater and ground slurry)
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
9/56
Enabling Technology
IsaMill M3000 1.1MW developed with Netzsch Enabling technology for McArthur River, 1995 Significantly more Energy Efficient than Tower Mills
Inert grinding environment = selective flotation, high recovery
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
10/56
Now Developed for Coarse Grinding
3.0MW M10,000 IsaMill Developed with Anglo Platinum
Coarse ceramic media developed with Magotteax
Same benefits for Coarse Grinding Improved energy efficiency
Process benefits from inert media
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
11/56
IsaMill: A Step Change in Technology
Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint
High Efficiency Fine Media
Inert Media Downstream Benefits
Scaleup Maintenance
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
12/56
IsaMill: Internal Layout
Grinding chambers in series no short circuiting
Product separator retains media without fine screens
Product Separator
Grinding Discs
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
13/56
Sharp size distribution
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
14/56
IsaMill: A Step Change in Technology
Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint
High Efficiency Fine Media
Inert Media Downstream Benefits
Scaleup Maintenance
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
15/56
IsaMill A Step Change in Size
Tower Mill
Max 1.1MW after 50 years 40kW/m3
Closed circuit cyclones
Media handling
IsaMill M10,000 3.0MW 300kW/m3
Open circuit no cyclones
Media under mill platform
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
16/56
IsaMill A Step Change in Size
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
17/56
IsaMill: A Step Change in Technology
Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint
High Efficiency Fine Media
Inert Media Downstream Benefits
Scaleup Maintenance
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
18/56
IsaMill: A Step Change in Efficiency
Fine media is key to energy efficiency better transfer ofdrawn energy to slurry
2,220176,500,0002IsaMill
370818,00012Tower Mill
222177,00020Ball Mill
Surface Area(m2/m3)No. Balls / m3Media Size(mm)
Results in lower kWhr/t
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
19/56
IsaMill: A Step Change in Efficiency
At P80 35um:
Tower Mill = 32 kWhr/t
IsaMill = 18kWhr/t
IsaMill uses up to 45% less power
F80 = 110um
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
20/56
IsaMill: A Step Change in Technology
Open Circuit, No Cyclones - Sharp PSD High Intensity Small Footprint
High Efficiency Fine Media
Inert Media Downstream Benefits
Scaleup Maintenance
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
21/56
IsaMill: Inert Media
Typical Plant Size Recovery Curve
Momentum
Surface area / mass
Surface coatings steel media
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
22/56
IsaMill: Inert Media
AMIRA P260
Improved Recovery
with ceramic
Due to higher fines recovery
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
23/56
IsaMill: Inert Media
MIM Cu Concentrator
Grano et al, 1994
Reduction in surface Fe coatings
Improvement in Size by SizeRecovery
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
24/56
IsaMill: A Step Change in Flotation
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
C7 C6 C5/C4 C3-C1 38/53
75Size fraction
Z i n c
R e c o v e r y
i n s i z e
f r a c t
i o n
%
0.0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
0-4um 4-8um 8-16um 16-38um 38-75um
Recovery
Size Dist ribut ion
MIM Pb/Zn Concentrator IsaMill Stage Grind
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
25/56
IsaMill: A Step Change in Technology
Open Circuit, No Cyclones - Sharp PSD
High Intensity Small Footprint
High Efficiency Fine Media
Inert Media Downstream Benefits
Scaleup
Maintenance
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
26/56
IsaMill: Accurate Scaleup 4 10,000L
0
10
20
30
40
50
60
70
80
90
1 00
0 .1 1 1 0 100 10 00Size (um )
% P
a s s
i n g
M4 Product - May 2001
M10,000 Feed - April 2005
M10,000 Product - April 2005
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
27/56
IsaMill: A Step Change in Technology
Open Circuit, No Cyclones - Sharp PSD
High Intensity Small Footprint
High Efficiency Fine Media
Inert Media Downstream Benefits
Scaleup
Maintenance
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
28/56
IsaMill: Maintenance
Shell slides back formaintenance access
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
29/56
IsaMill: Maintenance
Discs removed from shaftusing crane
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
30/56
IsaMill: Maintenance
Disposable Shell Liner12 months
Disposable Disc6-12 months
Reusable Disc Hub
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
31/56
IsaMill: A Step Change in Technology
Open Circuit, No Cyclones - Sharp PSD
High Intensity Small Footprint
High Efficiency Fine Media
Inert Media Downstream Benefits
Can change the way plants are designed
Replace tower/ball mills
Simplify flotation circuits
Produce higher grades to smelters
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
32/56
IsaMill Anglo Platinum
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
33/56
IsaMill Anglo Platinum
Mainstream Inert Grinding F80 120um to P80 53um grind
Concentrate Regrinding shift grade
Production ExpansionShift in Grade has potential to postpone major smelter expansionA fraction of overall energy consumption by grinding than smelting
22 IsaMills in production / on order
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
34/56
IsaMill McArthur River
Rougher
Cleaning
Prefloat
Concentrate
SAG Mill4MW
935 kW Tower Mill
Sand Media
Current Circuit includes SAG Mill and Tower MillPlan to increase throughput by 30%Testwork conducted and IsaMill selected for expansion
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
35/56
IsaMill McArthur River
IsaMill M10,000 treating screened SAG dischargeF80 300um to P80 45umOpen circuit operation
Rougher
Cleaning
Prefloat
Concentrate
SAG Mill
4MW
7 micron grind
Tower Mill andcyclones r emoved
45 micron
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
36/56
IsaMill BHPB Leinster
3.5 unit increase in Ni grade
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
37/56
IsaMill BHPB Leinster
30% reduction in MgO to concentrate
Significant implications for smelter performance
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
38/56
IsaMill BHPB Leinster
XT anticipate an order in the next couple of months
Pre work has all been done, prefeasibility, feasibility, etc etc
First stage of project engineering drawings have alreadybeen provided
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
39/56
IsaMill Phu Kham
12-16mtpa Copper Concentrator 2.6MW M10,000 IsaMill replacing Tower Mills
Relatively coarse primary grind
Regrind 168tph rougher cons from106 microns to 38 microns in 2.6 MW
IsaMill
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
40/56
IsaMill Oxiana Prominent Hill
8mtpa Copper Concentrator 3.0MW M10,000 IsaMill replacing Tower Mills
Relatively coarse primary grind
Regrind 138tph rougher cons from125 microns to 25 microns in 3 MW
IsaMill
Single Jameson cell backed
with conventional cellsSimplified circuit
Energy efficient
Small footprint
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
41/56
IsaMill Growth
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
42/56
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
43/56
Potential for Carbon Credits (CER)
IsaMill TM has potential to generate carbon credits under the CleanDevelopment Mechanism (CDM) of Kyoto Protocol
Under Kyoto Protocol, Annex 1 countries have mandatory targets to reduceGHG emissions by 2012
Annex 1 countries can offset their domestic emissions with credits (CertifiedEmission Reductions - CERs) earned by investing in non-Annex countries (forexample - Chile)
Xstrata Technology working with consultant SigmaGlobal to proveaccreditation for IsaMill TM
Hypothesis : IsaMill - new efficient technology currently not used in Chilereduces power requirements and improves grade / recovery for regrindingcopper
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
44/56
Annex 1 Countries
CO 2 Cap
Carbon Trading Basics
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
45/56
Annex 1 Countries
CO 2 Cap
Increased CO 2Emission
Offset (CER)
Required
Carbon Trading Basics
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
46/56
CERs
Non-Annex 1 Countries
(includes Chile) Annex 1 Countries
CO 2 Cap
Increased CO 2Emission
Offset (CER)
Required
Carbon Trading Basics
CDM Projects
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
47/56
CERs
CERs
CERs
Non-Annex 1 Countries
(includes Chile) Annex 1 Countries
CO 2 Cap
Increased CO 2Emission
Offset (CER)
Required
Carbon Trading Basics
CDM Projects
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
48/56
CDM Market well established and growing
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
49/56
Breakdown of CDM Projects
Country Spli t (2006 Projects)
Project Types (2006 Projects)
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
50/56
CER Trading
CER prices increasing
Growing interest from financial institutions
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
51/56
Creation of CERs by CDM
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
52/56
Potential IsaMill Project at BHPBilliton
Replace 20 Tower Mills @ 1.1MW = 22MW
With 5 IsaMills @ 3.0 MW = 15MW
Power Reduction = 7MW
30% Power Reduction
Assuming Power Reduction 6.5MW
Plant Availability (NOT IsaMill) = 90%= 5.85 MW
Conversion MW to CO 2 Equivalents = 0.59 (Chile)
= 3.45 t CO 2/hr
Convert to Annualised CO 2 Tonnage = 30,235 t CO 2/year
Convert to CER @ $25 AU/T CO 2 = $755,878 AU/year
Convert to US $ @ 0.86 Exchange = $650,000 US/year for 10 years
TOTAL CER POTENTIAL = $6.5M US
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
53/56
Why IsaMills for BHP Billiton in Chile?
Standard copper regrind circuits (in Chile) use Tower Mills for
regrinding
XT perceive there is a barrier to the introduction of IsaMillsinto Chile are none installed yet, and certainly not in copper
Business as usual is to continue to do the same
XT understand that there are some issues with BHP Billiton(along with a lot of other companies) and compliance inEurope (an Annex 1 Region)
PR value one of the first mining projects to get CERs
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
54/56
To Qualify and Maximise the Benefit
Consider a project concept Use IsaMills in BHP Billiton ingeneral Copper Circuits or just at Escondida
Reason for doing it is get carbon credits, which will allow theproject to proceed. If its business as usual then no credits.
Need to look at the big picture if there is one, to maximisethe benefit. Not just replacing one tower mill with an IsaMill.Doesnt matter if the project falls over, or if you only use 1IsaMill, but to get proposal approved after IsaMills are installedin Chile then would be more difficult
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
55/56
Some projects already accepted
Nestle Chile - switching from burning coal to naturalgas in production facility
Mitsubishi Corporation reduction in N2O gained822,000 CER credits
Ball mill replacement in Israel
-
8/13/2019 IsaMill Carbon Presentation BHPB Nov 07
56/56
What Next?
BHP Billiton to decide if this is a goer or not
If decision is made to proceed then in parallel
Set up a program to validate the hypothesis
M20 pilot plant comparison to existing flow sheet Install one IsaMill in parallel with existing Next concentrator to include IsaMills
Start work with XT and SigmaGlobal on the proposal