Internship Final Report Design and Analysis of Commercial ... · Design and Analysis of Commercial...
Transcript of Internship Final Report Design and Analysis of Commercial ... · Design and Analysis of Commercial...
Internship Final Report
Design and Analysis of Commercial
Photovoltaic Systems
Prepared By Lee Joo Shen
Jan 2014
Design and Analysis of Commercial Photovoltaic Systems and Components
1
I. Abstract
Renewable energy industry has been booming since 8 years ago and has been growing
exponentially since 2010 since the production costs of PV systems have greatly reduced
due to technological advancements. Balance Utility Solutions (BUS) was established in
2011 to cope with the growing market for embedded generation. BUS has completed
multiple energy generation projects over Australia and Asia over 2013.
BUS is a member of the Balance Services Group, alongside with our client Barclay
Engineering (BE), the client for the 9.04kWp grid-connected PV install.
The initial aim of the project was to acquire the related system approvals, design and
procurement and implement the system before the end of the contract. This would
serve not only as a investment to our client, but also a facility to train BUS personnel for
rack assembly and also serve as a test facility for future developments. Along the way 2
minor projects were also undertaken and included as minor projects.
It was later discovered that alongside the 4kW of PV modules that BE had also bought
battery banks, a standalone inverter its associated balance of system which could then
be implemented and designed to operate like dedicated UPS systems that are available
on the market. Fundamental operational specification also documented as part of the
future plans for the project.
Minor project 1 was an involvement in other document preparation including a tender
document for a 150kWp PV system for a wastewater plant. This involved planning and
documenting the project delivery; acquiring quotes for components and understanding
and complying with the scope that is required by the client. PV systems above 100kW are
uncommon in WA, and require protection relays to be integrated and approved by
Western Power.
Minor project 2 was the small test of the Sun Power PV modules and their degradation
when modules are operational for two years and stored for an additional year. Results
were then used to locate the module that has suffered the most degradation and omit it
from the design. Results are discussed in section 12.
Design and Analysis of Commercial Photovoltaic Systems and Components
2
II. Disclaimer
I declare that this thesis is my own account of my research and contains as its main content work, which has not previously been submitted for a degree at any tertiary education institution.
.................................... (Your name)
In the case of a re-submitted thesis the wording of the declaration should be as follows:
I declare that this thesis is my own account of my research. .................................... (Your name)
Design and Analysis of Commercial Photovoltaic Systems and Components
3
III. Acknowledgements
This project was in courtesy of Balance Utility Solutions (BUS), for which I would like to thank for
giving the chance to taste the engineering world. It would not have been possible, without their
guidance and experience in their industry. First and foremost, I would like to express my deepest
appreciation to Mr Mike Laughton-Smith (CEO), who is a well-established electrical engineer himself,
for welcoming me to the industry, showing great leadership, offering me help with assembling my first
work desk and keeping the workplace sanity with his uncanny humour.
It was an honour to have worked with my industry supervisor, Dr. James Darbyshire, who I would like
to thank for selflessly sharing his knowledge and technical knowledge, which is amongst the best of
the industry.
I would also like to extend my sincere gratitude to Mr. Alessio Ricchiardi, who always took time off his
busy schedule to guide me throughout my placement with BUS with enthusiasm.
Special thanks must also be given to my university supervisors Dr. Gareth Lee who answered every
query I had for Murdoch’s internship program and Dr. Sujeewa Hettiwatte, who answered every query
in such a timely manner.
I am also greatly indebted to all my university colleagues, in particularly Ms. Tanvi Gupta, and Mr.
Daniel Allison. For their immense moral support and invaluable assistance, which pointed me in the
right path and complete my work.
Last but not least, I would like to thank my parents for their unconditional love, care and support
towards me when it was most important.
Design and Analysis of Commercial Photovoltaic Systems and Components
4
IV. Glossary
The following acronyms are used throughout this document
Acronym Meaning
AC Alternating Current Active conductor Conductor not directly connected to earth BE Barclay Engineering BUS Balance Utility Solutions BOS Balance of System, wiring, CB etc. to complete the
electrical system
CAG Competing application group CB Circuit breaker, means for disconnection when over
current occurs CEC Clean Energy Council DC Direct Current ETAC Electricity transfer access contract Grid connected PV system that is connected to the electrical grid
through an inverter and does not have a storage system
IP Ratings Ingress Protection IWC Interconnection works contract Inverter Power converter, it is also referred to as the inverter LGC Large generation certificate MEN Multiple Earth to Neutral MPPT Maximum power point tracking PCE Power converter equipment, referring to the inverter POA Point of approval PV Photo Voltaic PV cell Electronic device to convert solar energy to electrical
energy
PV module A combination of PV cells connected in series to increase the voltage output
PV string A combination of PV modules connected in series PV system System comprising PV array, inverter and associated
equipment
Racking The framework of the PV modules REBS Renewable energy buyback scheme REC Renewable Energy Certificates SPD Device to protect an electrical system from the danger
of high voltage spikes
SLD Single Line Drawing STC Small technology certificates SWIS South-Western Interconnected grid UPS Uninterruptable power supply WP Western Power
Design and Analysis of Commercial Photovoltaic Systems and Components
5
Table of contents
I. ABSTRACT ................................................................................................................ 1
II. DISCLAIMER ............................................................................................................. 2
III. ACKNOWLEDGEMENTS ............................................................................................ 3
IV. GLOSSARY ................................................................................................................ 4
1 INTRODUCTION ....................................................................................................... 9
1.1 PROJECT OBJECTIVE ....................................................................................................... 11
1.2 LAYOUT OF PV ............................................................................................................. 12
1.3 COMPANY HISTORY ....................................................................................................... 13
2 SIMULATION TOOLS ............................................................................................... 14
2.1 HOMER ....................................................................................................................... 14
2.2 TRIMBLE SKETCH UP ...................................................................................................... 14
3 PRELIMINARY AUTHORIZATION .............................................................................. 15
3.1 INTRODUCTION ............................................................................................................. 15
3.2 THE SOUTH WEST INTERCONNECTED SYSTEM (SWIS) ........................................................ 15
3.3 ADDITIONAL PROCESS OF PV INSTALLATIONS IN THE SWIS NETWORK .................................... 16
3.3.1 Synergy Application ........................................................................................... 17
3.3.2 Western Power Application (Less or equal to 30kVA) ....................................... 18
3.3.3 Renewable Energy Certificates (RECs) ............................................................... 18
3.4 SUMMARY ................................................................................................................... 19
4 FEASIBILITY STUDIES .............................................................................................. 20
4.1 INTRODUCTION ............................................................................................................. 20
4.1 RESOURCE ANALYSIS ..................................................................................................... 21
4.2 FINANCIAL ANALYSIS ..................................................................................................... 22
4.3 CAPITAL COSTS ............................................................................................................. 25
4.4 SUMMARY ................................................................................................................... 26
5 DESIGN .................................................................................................................. 27
5.1 INTRODUCTION ............................................................................................................. 27
5.2 IMPORTANT PROPERTIES OF PV SYSTEMS ......................................................................... 28
5.2.1 Ingress protection .............................................................................................. 28
5.2.2 Maximum Power Point Tracking (MPPT) ........................................................... 29
5.2.3 BI – Directional Meter ........................................................................................ 29
5.3 CHOOSING AN INVERTER ................................................................................................ 30
5.4 DESIGN 1 (1 INVERTER) .................................................................................................. 31
5.4.1 Issues and Solutions to design error .................................................................. 32
5.5 DESIGN 2 (3 INVERTER) .................................................................................................. 33
5.6 CABLE CALCULATIONS: ................................................................................................... 34
5.7 CIRCUIT BREAKER/ENCLOSURE ........................................................................................ 39
5.8 CABLE ROUTING AND CABLE TYPES ................................................................................... 40
5.9 LIGHTNING PROTECTION SYSTEMS (LPS) .......................................................................... 41
5.9.1 External Lightning Protection ............................................................................ 41
Design and Analysis of Commercial Photovoltaic Systems and Components
6
5.9.2 Internal Lightning Protection ............................................................................. 43
5.10 LIGHTNING PROTECTION RISK ASSESSMENT .................................................................... 45
5.11 EARTHING ................................................................................................................. 46
5.12 CONNECTORS ............................................................................................................. 48
5.13 SUMMARY ................................................................................................................. 49
6 PROCUREMENT ...................................................................................................... 50
6.1 INTRODUCTION ............................................................................................................. 50
6.2 ITEMS TO BE PROCURED ................................................................................................ 50
6.3 SUMMARY ................................................................................................................... 51
7 IMPLEMENTATION ................................................................................................. 52
7.1 INTRODUCTION ............................................................................................................. 52
7.2 FENCING OPTIONS ........................................................................................................ 53
7.3 GROUND-MOUNTED RACKING SYSTEM: ............................................................................ 55
7.4 SYSTEM SECURITY ......................................................................................................... 57
7.4.1 Recommendation for Security of the System ..................................................... 57
7.5 SUMMARY ................................................................................................................... 58
8 COMMISSIONING ................................................................................................... 59
8.1 INTRODUCTION ............................................................................................................. 59
8.2 QUALITY ASSURANCE TESTING ........................................................................................ 60
8.3 COMMISSIONING TEST INSTRUCTIONS AND TEST SHEETS ..................................................... 61
8.4 SUMMARY ................................................................................................................... 61
9 FUTURE PLANS AND RECOMMENDATIONS ............................................................. 62
9.1 INTRODUCTION ............................................................................................................. 62
9.2 SUNNY ISLAND 5048 ..................................................................................................... 63
9.3 UPS SYSTEMS .............................................................................................................. 64
9.3.1 Operation of UPS systems .................................................................................. 65
9.4 SUMMARY ................................................................................................................... 66
10 MINOR PROJECT 1 – TECHNICAL DESIGN OF 150KW SYSTEM ................................... 67
10.1 DEMONSTRATED UNDERSTANDING OF THE SCOPE OF WORK: .............................................. 68
10.2 PROCESS OF DELIVERY OF GOODS AND SERVICES ............................................................... 69
10.3 APPROVALS FOR THE SYSTEM ........................................................................................ 71
11 MINOR PROJECT 2 – TESTING OF SUN POWER MODULES ........................................ 85
11.1 INTRODUCTION........................................................................................................... 85
11.2 OBJECTIVE OF TESTING ................................................................................................ 85
11.3 BACKGROUND ............................................................................................................ 86
11.4 METHOD ................................................................................................................... 88
11.4.1 Data Processing ............................................................................................... 88
11.5 RESULTS .................................................................................................................... 89
11.6 SUMMARY ................................................................................................................. 92
12 OVERALL CONCLUSION ........................................................................................... 93
13 LEARNING EXPERIENCES ......................................................................................... 93
Design and Analysis of Commercial Photovoltaic Systems and Components
7
14 ANNOTATED BIBLIOGRAPHY .................................................................................. 95
15 REFERENCE ............................................................................................................ 96
16 APPENDICES........................................................................................................... 99
16.1 A1: SYNERGY BI-DIRECTIONAL METERING GENERATION ..................................................... 99
16.2 A2 : WESTERN POWER APPLICATION ............................................................................. 99
16.3 A3: SYNERGY APPROVAL.............................................................................................. 99
16.4 A4: WESTERN POWER APPROVAL ................................................................................. 99
16.5 A5: SMA SB2500-TL DATA SHEET ............................................................................... 99
16.6 A6: STP 5000TL-20 DATA SHEET ................................................................................. 99
16.7 A7: FRONIUS IG15 DATA SHEET .................................................................................... 99
16.8 A8: KYOCERA KD315GX-LPB DATASHEET ..................................................................... 99
16.9 A9: SUN POWER SPR-200-BLK DATASHEET ................................................................... 99
16.10 A10: SINGLE LINE DIAGRAM OF 9.04KW SYSTEM ......................................................... 99
16.11 A11: BOS COMPONENT LIST ...................................................................................... 99
16.12 A12: APPROVED LOCATIONS FOR PV ........................................................................... 99
16.13 A13: SPR-200-BLK TEST RESULTS ............................................................................. 99
16.14 A14: BE COMMISSIONING INSTRUCTIONS AND TEST SHEETS ........................................... 99
16.15 A15: FENCING OPTION A .......................................................................................... 99
16.16 A16: FENCING OPTION B .......................................................................................... 99
16.17 A17: FENCING OPTION C .......................................................................................... 99
16.18 A18: EMAIL CORRESPONDENCE WITH FRONTIER RACK ................................................... 99
16.19 A19: EMAIL CORRESPONDENCE WITH FRONTIER RACK ................................................... 99
16.20 A20: LOW LEVEL GANTT CHART FOR MINOR PROJECT .................................................... 99
16.21 A21: LIGHTNING RISK ASSESSMENT ............................................................................ 99
16.22 A22: CABLE LOSS CALCULATIONS ( ................................................................ 99
16.23 A23: CABLE LOSS CALCULATIONS ( ) ................................................................... 99
16.24 A24: SUNNY ISLAND 5048 DATASHEET ........................................................................ 99
16.25 A25: PROJECT PLAN (24/01/2014) ........................................................................... 99
Design and Analysis of Commercial Photovoltaic Systems and Components
8
LIST OF FIGURES
FIGURE 1: AERIAL VIEW OF SITE ................................................................................................................... 10 FIGURE 2: LAYOUT OF PV AT BARCLAY ENGINEERING ....................................................................................... 12 FIGURE 3: BI-DIRECTIONAL METER INSTALLED ................................................................................................ 17 FIGURE 4: SOLAR RESOURCE (HTTPS://EOSWEB.LARC.NASA.GOV/SSE/) .............................................................. 21 FIGURE 5: OVERVIEW OF SYSTEM ................................................................................................................. 37 FIGURE 6: SLD AND BREAKER SPECIFICATIONS ................................................................................................ 38 FIGURE 7: MAIN DISTRIBUTION BOARD ......................................................................................................... 40 FIGURE 8: PREVENTION OF WIRING LOOPS IN CIRCUITS [26] ............................................................................ 42 FIGURE 9: EARTHING CONDUCTOR SELECTION [29] ......................................................................................... 47 FIGURE 10: SHADING FROM FENCE .............................................................................................................. 53 FIGURE 11: DESIRED FENCING OPTION ......................................................................................................... 54 FIGURE 12: BEFORE PREPARATION ............................................................................................................... 56 FIGURE 13: THICKNESS OF CONCRETE .......................................................................................................... 56 FIGURE 14: FLOW OF APPLICATION FOR GENERATOR UP TO 150KVA .................................................................. 72 FIGURE 16: CONCRETE FOOTINGS ................................................................................................................ 74 FIGURE 17: SITE LAYOUT ............................................................................................................................ 75 FIGURE 18: SWITCH ROOM LAYOUT .............................................................................................................. 76
List of Tables:
TABLE 1: ENERGY ANALYSIS (HTTPS://EOSWEB.LARC.NASA.GOV/SSE/) ............................................................... 22 TABLE 2: OFF PEAK AND PEAK SAVINGS ......................................................................................................... 23 TABLE 3: ENERGY CONSUMPTION ................................................................................................................ 23 TABLE 4: OFF PEAK AND ON PEAK SAVINGS ................................................................................................... 24 TABLE 5: INGRESS PROTECTION OF INVERTERS ................................................................................................ 28 TABLE 6: INVERTER COMBINATIONS .............................................................................................................. 30 TABLE 7: SERIES AND PARALLEL CONFIGURATIONS (1 INVERTER) ........................................................................ 31 TABLE 8: DC ANALYSIS OF 3-INVERTER SYSTEM .............................................................................................. 33 TABLE 9: MODULE TO THEIR RESPECTIVE INVERTER ......................................................................................... 35 TABLE 10: INVERTER TO COMBINER BOX ....................................................................................................... 35 TABLE 11: CURRENT AT THE COMBINER BOX .................................................................................................. 36 TABLE 12: VOLTAGE DROPS FROM PCE TO THE MAIN DISTRIBUTION BOARD ....................................................... 36 TABLE 13: LIGHTNING RISK ASSESSMENT ....................................................................................................... 45 TABLE 14: VOLTAGE DROP CALCULATIONS (MINOR PROJECT 1) ........................................................................ 78 TABLE 17: TEST RESULTS OF SUN POWER MODULES ....................................................................................... 90 TABLE 18: DEGRADATION OF MODULES ........................................................................................................ 91
Design and Analysis of Commercial Photovoltaic Systems and Components
9
1 Introduction
The proposed site is located at Catalano Road, Canning Vale as indicated in Figure 1. The
proposed grid connected system will utilize both roof and ground mounting systems,
which will be illustrated in Figure 2. The final design consists of the following PV
equipment:
Modules:
5.04kW of Kyocera KD315GX-LPB on ground area (16 X 315W)
4kW of Sun power SPR-200-BlK on roof area (20 X 200W)
Inverters:
1 X SMA STP 5000Tl-20
1 X Fronius IG15
1 X SMA SB2500-TL
This 9.04kWp design will utilize all available PV modules to produce maximum amount of
power. The layout of PV and the inverters are illustrated in figure 2. Inverters are
strategically placed behind the walls and hidden away from the general public due to
security reasons.
There will be 4kW of Sun Power (SPR-200-BLK) modules placed on the roof of BE and
5kW (Kyocera KD315GX-LPB) modules on the BE barbeque area will house the ground-
mounted Kyocera modules.
Design and Analysis of Commercial Photovoltaic Systems and Components
10
Figure 1: Aerial view of site
Design and Analysis of Commercial Photovoltaic Systems and Components
11
1.1 Project Objective
The objective of the project is to acquire approvals, design, procure, implement and
commission the 9.04kWp before the end of the internship placement.
Besides giving our client the chance to take advantage of the REC scheme [31] and
provide monetary savings backed up by green energy, the ground mounted system will
also facilitate the rack assembly ground and act as a team building experience of Balance
Services Group over the course of implementation.
Design and Analysis of Commercial Photovoltaic Systems and Components
12
1.2 Layout of PV
There will be 2 arrays as indicated in a drawn to scale drawing as indicated in Figure 2.
4kWp of Sun Power SPR-200-BLK located on the roof of BE and 5.04kWp drawn to scale
of Kyocera LPB 315-GX modules located on the outdoor barbeque area at BE. The
enlarged diagram on the right side of figure 2 indicates the location of the poles of the
racking system. Total system peak capacity is 9.04kWp DC and is handled by the 3
inverters mentioned in the introduction.
Figure 2: Layout of PV at Barclay Engineering
Design and Analysis of Commercial Photovoltaic Systems and Components
13
1.3 Company History
Balance Utilities Solution (BUS) is part of the Balance Services Group, along with Barclay
Engineering and Ugen to operate on the purpose for providing better platforms for
power generation solutions to enable more productive activity, with greater social
benefit, whilst being friendly to the environment.
In 2011[16], during a time where a growing need in the market for sustainable and
integrated energy was required, Balance Utilities Solutions was formed.
Direct experience where both manufacturers and customers showed their frustration
when service projects are not brought together to meet expectations. Balance Utility
Solutions, with its three principals (Rod Hayes, Terry Barclay and Mike Laughton-Smith)
has over 80 years of combined experience in utilities management, infrastructure
development, energy project management and delivery, and equipment fabrication and
installation, believe that a viable yet sustainable solution can be integrated into
genuinely sustainable long term solutions [16].
In 2012, Balance Services Group brought Barclay Engineering along with its industry
leading 35+ year track record project delivery of mechanical engineering and fabrication
[16], acting as a key contractor for the group.
As of 2013, Balance Utility Solutions stands with its industry leading engineering and
expertise in renewable energy. Expert knowledge of the system dynamics, covering the
lifecycle from design and approvals, procurement, implementation and commissioning
of diesel, gas, solar and wind generation, control systems, energy storage and water
treatment systems allows customers to define their expectations and be given a turn-
key solution [16].
Design and Analysis of Commercial Photovoltaic Systems and Components
14
2 Simulation tools
2.1 Homer
Homer is a useful software package [32] for feasibility studies but is only compatible
with Microsoft Windows and has the options to simulate and optimize systems capital
costs by using surface conditions from NASA surface meteorology.
It has a friendly user interface that incorporates sensitivity analysis towards capital and
operational and maintenance costs for Wind, PV, diesel, hydro and also hybrid systems in
both standalone and grid connected forms.
It also has the capability to include economic factors such as inflation, discount rates and
input current fuel prices for diesel or electricity charges to simulate the system
according to the users tariff of choice, making the simulation results resemble real life
situations to a very high level.
2.2 Trimble Sketch up
This is a useful software package [33] for doing site drawings and electrical drawings
due its interface with Google Maps. It is a capable program with many usable functions
that can enable the user to draw to scale 3D drawings and animation of shadings
depending on site location.
Design and Analysis of Commercial Photovoltaic Systems and Components
15
3 Preliminary Authorization
3.1 Introduction
Preliminary authorization is the formality of getting approvals from the electricity
retailer (Synergy) and the electricity transporter (Western Power) especially if system is
to be grid-connected. The two applications that are required for a system to be
connected to the SWIS network will be discussed over in this chapter. A third
application form will need to be completed to claim the RECs available when the system
is completed.
3.2 The South West Interconnected System (SWIS)
The SWIS interconnected system is the utility network that provides electricity to all end
users of the network; Suitable application forms must be completed and approved to
gain authorization before additional generation can be connected to the grid.
There are two types of tariffs that electricity consumer’s fall under:
1. Contestable: electricity consumption of more than 50MWh per year -
consumers are then able to choose their electricity retailers;
2. Non-contestable: electricity consumption of less than 50MWh per year -
consumers are not able to choose their retailers.
BE is situated in Canning Vale in Western Australia, with coordinates (32.06S, 115,902E)
and is situated in the SWIS network. With an annual consumption of more than 50MWh
per year, it falls under the medium to large business tariff. Suitable application forms for
embedded generation are attached in the Appendix A3 and Appendix A4.
It was essential to complete the following two applications simultaneously along with
preliminary designs of the projects. The two authorizations that were completed and
approved during the second month of the project (October 2013) are:
1. Synergy: Non contestable bi-directional metering and embedded generation
service application;
2. Western Power: connect embedded generation to the Western Power network
Design and Analysis of Commercial Photovoltaic Systems and Components
16
3.3 Additional process of PV installations in the SWIS network
The following are the processes that were undertaken during the design. It is important
to do the design in the correct sequence. If there are no means for achieving a
satisfactory outcome of a particular step, the step before it has to be reviewed. The
following are the design steps with reference to WP guidelines.
1. Check if site is in WP approved list of suburbs (Appendix A12);
2. Choose modules to suit the application;
3. Choose inverter;
4. Check if inverter is in WP approved list
Design and Analysis of Commercial Photovoltaic Systems and Components
17
3.3.1 Synergy Application
As a requirement of a complete PV system, a bi- directional meter [21] must be installed
prior to system being grid connected. This is an essential step, because electricity will be
exported to the grid when it is not consumed. This step is also essential as part of the
WP application. Upon approval, the customer is issued a reference number. Application
can be found in Appendix A1. As stated by the retailer, an import/export sign will be put
on the new bi-directional meter once it is installed. Figure 3 is the actual site photo of the
bi-directional meter installed.
Figure 3: Bi-Directional Meter Installed
Design and Analysis of Commercial Photovoltaic Systems and Components
18
3.3.2 Western Power Application (Less or equal to 30kVA)
High level of technical information like cable sizing is also required as part of a
application. To simplify the process and make it more illustrative, a single line diagram of
the system was created via Trimble Sketch up [33] and cable loss calculations had to be
done as conductor size and lengths had to be chosen. During the application a single line
drawing was created (Appendix A10), and the final application is attached in Appendix
A2
3.3.3 Renewable Energy Certificates (RECs)
Early during the design phase, it is important to ensure that the PV equipment, PV
modules and inverter are in the clean energy council (CEC) component list, only
components that are new and listed in the CEC are eligible for RECs.
Under the jurisdiction of the Australian Federal Government, new PV systems have to be
certified by a CEC accredited designer and installer to be eligible for a small technology
certificates (STCs). STCs vary in price on a daily basis, and will also depend on the
location and date of the install. Module and inverter also have to be on the CEC
approved list of products if STCs are to be claimed [2][3].
The current market rate for subsidy is approximately $36.00 per STC (correct on 13 Jan
2014). This ground-mounted system has a capacity of 5.04kW and will be eligible for 104
STCs. The amount of eligible STCs is calculated from the Australian Government Clean
Energy Regulator [31]. Solar companies will usually implement this as a point of sale
discount to customers, or sell them at an open market.
Design and Analysis of Commercial Photovoltaic Systems and Components
19
3.4 Summary
The three main applications for a system as such a that were completed for the grid
connected 9.04kWp system was the synergy embedded generation application, WP
embedded generation application and also the ENVIROBANK application which is
required for the claiming of RECs. The ENVIROBANK application was not completed, as it
requires a fully completed and commissioned project that is signed off by a CEC
accredited installer.
The first application that was completed successfully was the Synergy bi-directional
metering application. This application is essential for the WP embedded generation
application because upon approval the applicant is supplied with a customer reference
number as shown in Appendix A3. This application took 5 working days to be approved
and the reference number that was given in the approval letter stays valid for 60 days.
The WP embedded generation application was a slightly more complex application to fill
out as it involves basic design information in an aerial view of the site as attached in
Appendix A2.
Location
Capacity of inverters
Cable lengths
Cable diameters
The application was completed with reference to the application examples provided on
the WP site and was approved upon submission within 28 days after the application was
lodged. Upon approval the application stays valid for a period of 1 year till connection,
which is well within the expected finish date of the project.
Design and Analysis of Commercial Photovoltaic Systems and Components
20
4 Feasibility Studies
4.1 Introduction
Feasibility studies must be supported with facts and the latest financial information that
contributes to the value of engineering. This information also contributes to good
project management where taxations and legislation are considered. There will also be
estimates for costs, selection of components for optimisation of costs to meet
requirements and also the project’s impact on the environment [15].
Each feasibility assessment is to deterministic for the cost effectiveness in multiple
circumstances, and each risk is identified in during this phase of the planning. Ultimately
reflecting on the profitability and the total amount of payback years.
Energy outputs of the PV arrays and total amount of savings generated from the system
are shown in the models in this chapter. Simulation data will ultimately affect the
payback period of the project. Payback period is calculated by the capital injected and
the amount of the revenue projected. PV projects require maintenance steps such as
clearing of vegetation and cleaning the modules. Output tests once a year if the system
is functioning properly, these can be eradicated from the program if a monitoring
system is installed.
Design and Analysis of Commercial Photovoltaic Systems and Components
21
4.1 Resource Analysis
Sites with 5 kWh/ /d solar resource and above are generally regarded as a suitable for
PV installations. The calculated average daily radiation of the site 5.5 kWh/ /d, shows
that the solar resource is well suited for PV installation.
Clearness index is the amount of solar radiation that makes it to the surface and ranges
from 0-1 (fully overcast – Clear skies). BE has an annual clearness index of 0.633 which
Indicates that skies are relatively clear. Clearness index peaks in January at 0.708. The
range between the highest and lowest clearness index months are 0.184, and varies
between clear skies and slight overcast [18], which is well suited for PV systems. Figure 4
attached below is the HOMER solar resource inputs according to the latitude and
longitude as selected by the user.
Figure 4: Solar Resource (https://eosweb.larc.nasa.gov/sse/)
Design and Analysis of Commercial Photovoltaic Systems and Components
22
4.2 Financial Analysis
The Analysis is based on the data over the past 12 months (Aug 2012 – Aug 2013). Solar
resource data is acquired from HOMER and the total savings that can be generated from
the 9.04kW system is modelled with all modules facing true north and tilted uniformly at
30°. The tables and charts below graphically demonstrate the benefits of having the PV
modules installed. The simulation assume that all PV generated is consumed.
Table 1 below is the energy generation data that shows the energy reduction of the
system when installed; Table 2 is the table of monetary savings of on peak and off peak
tariffs. Graphical data is shown in Table 3; results show that the 9.04kWp system will
have an annual energy reduction of 8.39%. Table 4 is a graphical translation of on and off
peak savings that can be generated from the system.
This study is based on the Synergy p1 contestable business tariff; peak and off-peak
periods are as follows:
Peak (8am-10pm) weekdays: $0.39 per unit (kWh)
Off peak (10pm-8am weekdays; Saturday, Sunday): $0.10 per unit (kWh)
Table 1: Energy Analysis (https://eosweb.larc.nasa.gov/sse/)
Month PV
Generation (kWh)
Grid Energy Consumption
(kWh)
Grid Energy Consumption
With PV (kWh)
Energy Reduction
Nov-12 1539.83 11422.41 9882.58 13.40% Dec-12 1600.05 18589.44 16989.4 8.61% Jan-13 1634.44 15205.78 13571.34 10.75% Feb-13 1609.87 15925.41 14315.54 10.11% Mar-13 1458.78 16807.7 15348.92 8.68% Apr-13 1214.37 16183.9 14969.53 7.50% May-13 959.06 15486.28 14527.22 6.19% Jun-13 846.49 17454.68 16608.19 4.85% Jul-13 881.28 16073.3 15192.01 5.48%
Aug-13 1079.88 21297.75 20217.87 5.07% Sep-13 1284.28 16807.87 15523.59 7.64% Oct-13 1457.42 11781.8 10324.38 12.37%
Total 15565.75 Average
Reduction 8.39%
Design and Analysis of Commercial Photovoltaic Systems and Components
23
Table 2: Off peak and Peak Savings
Month Off Peak Off Peak + PV On Peak On Peak + PV
Nov-12 $380.26 $327.96 $2,526.80 $2,123.54 Dec-12 $638.48 $589.79 $4,048.43 $3,587.11 Jan-13 $603.48 $557.78 $3,047.37 $2,562.18 Feb-13 $488.63 $444.64 $4,082.12 $3,661.70 Mar-13 $517.89 $470.65 $4,217.94 $3,807.85 Apr-13 $487.40 $453.97 $1,406.67 $1,058.71 May-13 $512.73 $486.93 $4,181.52 $3,891.95 Jun-13 $654.12 $618.73 $4,422.31 $4,225.55 Jul-13 $459.24 $441.22 $3,741.50 $3,453.87
Aug-13 $761.18 $731.05 $5,578.68 $5,256.72 Sep-13 $488.63 $453.32 $4,082.12 $3,713.98 Oct-13 $402.82 $359.69 $3,345.49 $2,920.51
Savings Summary:
Off peak savings: $459.12
Peak savings: $4417.27
Savings per year: $4876.39
Table 3: Energy Consumption
0.00
5000.00
10000.00
15000.00
20000.00
25000.00
Ene
rgy
(kW
h)
Grid Energy Consumption
Before PV(kWh) After PV (kWh)
Design and Analysis of Commercial Photovoltaic Systems and Components
24
Table 4: Off Peak and On Peak Savings
$0.00
$1,000.00
$2,000.00
$3,000.00
$4,000.00
$5,000.00
$6,000.00D
olle
rs (
$)
Monthly Savings Breakdown
Off peak Off peak + PV On peak On peak + PV
Design and Analysis of Commercial Photovoltaic Systems and Components
25
4.3 Capital Costs
Under the jurisdiction of the Australian Federal Government, new PV systems have to be
certified by a CEC accredited designer and installer to be eligible for a small technology
certificates (STCs). STCs vary in price on a daily basis, and will also depend on the
location and date of the install [34].
The current market rate for subsidy is approximately $36.00 per STC (correct on 13 Jan
2014) [35]. This ground-mounted system will be eligible for 104 STCs [34], which will be
sold to an STC trader. The rebate from the STC will be passed on to BE as a discount to
the payment to BUS. The following is the itemized breakdown of the scope of BUS and
the client. This section is included in the business proposal; prices of the following items
shall not be disclosed due to the confidential nature of business.
Capital cost of the proposed system includes the following two sections:
1. Breakdown of design and equipment:
Engineering design
STP 5000TL-20-inverter
Balance racking system
Kyocera PV modules
STC Rebate
2. Breakdown of client payment:
Synergy Meter Upgrade
Balance of System (BOS)
Construction labour (50 hours)
Most of the balance of system (BOS) is already available at BE. The component list for
the balance of system is attached in Appendix A11.
The system lifetime is 20 years or more and will generate a total annual savings of
$4876.12; this however is subjected to increase as the electricity prices increases. Over
the projected lifetime of 20 years, the system will generate $87,768 ($4876.39 X 20
years) or more worth of savings.
Design and Analysis of Commercial Photovoltaic Systems and Components
26
4.4 Summary
This chapter was completed with simulation data with the aid of simulation outputs
from HOMER, which is a tool highly recommended due to its ease of use and the ability
to include economic data into the user interface. System capital costs are not included
in the report because of privacy issues, however it is an inaccurate way to value the
system and calculating payback periods because part of the system was bought second
hand and not eligible for STCs.
BE is situated in Perth, and being in the southern hemisphere and experiencing four
seasons in a year has an expected average solar resource of 5.5 kWh/ /d with its peak
months during the summer period and lowest solar resource during the winter months
(June). Clearness index is a relatively high at 0.633 with little variation throughout the
year, indicating that solar generation will be consistent and not be interrupted due to
overcast conditions throughout the year. The suitability for PV installs that are of such
size because BE is locked into the non-exporting business tariff, making it very beneficial
if all generation is consumed within the facility.
Electricity costs ever rising and the STC multiplier, for a certain location, the solar credit
multiplier, which was X4 in 2011, has now been changed to X1 for systems installed post
June 2013. In the near future, when PV is accepted as another form of “conventional
electricity generation” as the costs for production is lowered, REC schemes for PV
installs are also expected to be removed, making now a high time for the system to be
installed.
Design and Analysis of Commercial Photovoltaic Systems and Components
27
5 Design
5.1 Introduction
The original design proposed used a single 10kW 3 phase inverter, however due to the
design complications caused by the updates to clause 3.1 of the AS/NZS 5033:2012 where
string voltage should not exceed 600V, the design of the system was modified.
The final design documented from section 5.5 onwards included the use of two existing
single-phase inverters. To comply with the WP rule of having a phase difference of not
more than 2.5kVA, a 3-phase, 5kW inverter (STP-5000Tl-20) was included in the design,
which resulted the final design to be an unbalanced 3-phase system.
BE has already procured a 4kW set up comprising of 20X200W modules, and two single
phase inverters (SMA SB2500TL, Fronius IG15) inverters to support. The remaining
5.04kW of Kyocera modules will require a new inverter for the system to be connected.
Section 5.4 will discuss these issues and how the design did not conform to the
specifications of the inverter and Australian standards, particularly clause 3.1 of the
AS5033: 2012. The rest of the chapter (Section 5.5-5.10) discusses the approach to how
the final design was reached and the BOS sheet finalized.
Design and Analysis of Commercial Photovoltaic Systems and Components
28
5.2 Important Properties of PV Systems
5.2.1 Ingress protection
Ingress protection ratings (IP ratings) are important factors to consider when doing
electrical installations. Appliances that are to be used outdoors (Isolator box, junction
box, combine r boxes) all need to be IP55 or an IP55 rated enclosure needs to be used.
In reference to the AS60529, the IP rating is the specification of durability when exposed
to solid, liquid and mechanical objects to the electronic device. The equipment
manufacturers determine IP ratings after performing multiple tests [24].
The following are the interpretations of the IP rating:
First digit: Enclosure protection against solid objects [24]
Second digit: Enclosure protection against liquids [24]
Third digit: Enclosure protection against mechanical stress [24]
As a result of inverters not exposed to mechanical stress during their lifetime, the third
digit generally is not required for PV components because once the system is
commissioned; it is advisable not place items on top or near the components
IP 65: Totally protected from ingress of dust, can be hosed from all directions.
IP45: Access probe of not more than 10mm shall not penetrate can be hosed
from all directions.
IP ratings of 45 and 65 makes it an equipment which is quite versatile to weather
conditions however the inverters shall be placed in a shaded area where it would not be
under direct sunlight. Table 5 is the summary of the ingress protection ratings of the
inverters to be used in the install.
Table 5: Ingress Protection of Inverters
Inverter Ingress rating
SMA STP5000-TL-20 IP65
SMA SB2500TL IP65
Fronius IG15 IP45
Design and Analysis of Commercial Photovoltaic Systems and Components
29
5.2.2 Maximum Power Point Tracking (MPPT)
MPPT tracking is the electronic tracking of the best match between the supply and load
for optimizing power delivery. Without MPPT trackers, PV systems are only limited to
the loads which the system is connected to. The two common types of topology of the
inverter used in PV systems are the DC--DC buck or buck or boost converter or the DC-DC
converter [23] used only at the DC side for MPPT and having a transformer on the AC
side.
In a PV application, the mismatching conditions caused by partial shading or mix
matching of PV modules linked to the same input can be partially fixed by MPPT device
in the inverter by altering the DC input voltage of the inverter to provide the optimum
energy available from the system [22].
5.2.3 BI – Directional Meter
The Bi-Directional electrical meter enables the electricity retailer to monitor the usage
and charge the end user according to how much electricity is exported and imported.
This bi-directional meter for this project is installed by Synergy after the application has
been approved. The sticker on the main supply (Figure 3) of the site will have a sign
indicating that the Bi-Directional meter has been installed.
The client has to have the bi-directional meter installed because of the different tariffs
for import and exports for electricity [21]. Without the new meter installed, existing
analogue meters may spin backwards and give an inaccurate reading for the correct
amount to be paid [21].
Design and Analysis of Commercial Photovoltaic Systems and Components
30
5.3 Choosing an Inverter
Matching inverters and solar modules are important so that the power generated from
the modules is matched to the inverter and its operating voltage window. Cable is
selected through a process followed closely to the Australian Standards. Voltage drops
from the source and load to PCE of less than 3% [29].
The original approach (design 1) was to use a 1-inverter system, the Aurora PVi-10-OUTD
inverter was chosen because it requires less amount of space, if a monitoring system
was to be implemented, this would be a more viable option because only a single
monitoring system would be required. This option also is discussed in section 5.4.
Section 5.4.1 addresses the problems that were associated with the design as it
exceeded the maximum allowable Vdc of 600V in the AS5033 clause 3.1.
The Final design (design 2) utilizes 3 inverters. This was the most viable option as 2 out of
the 3 inverters were already available on site. A single 3-phase inverter SMA STP 5000TL-
20 was included in the design to accommodate the 5.04kWp ground-mounted system.
Refer to table 6 for a clearer view.
Table 6: Inverter Combinations
3 inverter
OR
2 inverter
OR
1 inverter
SB2500TL(available) STP 5000TL-20 Aurora PVI-10-OUTD
Fronius IG15 (available) SMA SB4000
STP 5000TL-20
Design and Analysis of Commercial Photovoltaic Systems and Components
31
5.4 Design 1 (1 inverter)
The single inverter was chosen, however to comply with AS5033: 2012 clause 3.1, the
system needed to be secluded from the general public. This was not a favourable choice
to our client due to the extra costs that may be associated to isolate the system. Table 9
indicates the string voltages of the systems in series and in an attempt to lower the
string voltage a parallel configuration was also considered.
In series configuration, the maximum string voltage of MPPT1 exceeds the upper limit of
MPPT1 and MPPT2. In parallel configuration, minimum string voltage of the rooftop
modules is 17.3V short of reaching the minimum operating range of MPPT1; string
current is also 0.4 A above the tolerable limit of the current rating of MPPT2. Table 7 is
the summary of the string voltages and currents for the entire system.
Table 7: Series and Parallel Configurations (1 inverter)
Design and Analysis of Commercial Photovoltaic Systems and Components
32
5.4.1 Issues and Solutions to design error
Issue:
After analysing the design in accordance with the inverter data sheets, it was found that
that string voltages were not within the MPPT range of the inverter specifications for
both MPPT 1 and MPPT2. When placed in a parallel configuration, minimum voltage was
out of the MPPT voltage window, which further confirms the need for a different design.
Possible Solutions:
1. Put strings in parallel to reduce voltage;
2. Exclude modules from the design to reduce string voltage;
3. Choose another inverter
As the string voltage was too high, the parallel combination had induced a nominal
current that was too high for many inverters in the market. A new 3-phase inverter (SMA
STP5000Tl-20) was included in the design along with the Fronius IG15 and SMA
SB2500TL.
Design and Analysis of Commercial Photovoltaic Systems and Components
33
5.5 Design 2 (3 inverter)
Because the BE is connected to a 3 phase grid supply, the SMA STP5000TL-20 is a 3
phase inverter and the Fronius IG15 and SMA SB25000-TL are both single phase
inverters. According to the WP requirement there should not be a difference of more
than 2.5kVA. This requirement is fulfilled with the current design, the 5kW inverter
relates to 1.67kVA per phase. Apparent power difference between the highest and
lowest phase has a difference of 0.83kVA. Table 8 is the DC analysis of the final design
and incorporates the temperature coefficients to a minimum of 5°C and a maximum
temperature of 65°C.
Table 8: DC Analysis of 3-Inverter System
Design and Analysis of Commercial Photovoltaic Systems and Components
34
5.6 Cable Calculations:
4 cables were used from the modules to the inverter. Cable lengths are illustrated
in Figure 5. The voltage drops were of less than 1% for each string to inverter, detailed
cable calculations for the DC side and AC sides can be found in Appendix A22. The
following are the formulas that were used for majority of the calculations:
Line to line current equation:
√
Using the formula above the line current of the Fronius IG15 and SMA 25000TL single-
phase inverters are found and added with phase a and phase b at the combiner box.
Step 1:
Step 2:
Step 3:
The AS5033: 2012 states that the total voltage drop of the system cannot exceed 3%.
Because of the complexity of the system the tables will be split into the following
sections, starting from the DC side of the system to the AC side of the system. Cable
calculations will be done from the modules to the inverter, inverter to the AC combiner
box and lastly, then from the AC combiner box to the main distribution board. These
tables illustrate the summarized data of the calculations that determine the size of the
cables that are to be used.
Table 9: Modules to their respective inverters
Table 10 Inverter to Combiner Boxes
Table 11: Combining the outputs of the single phase inverters to the three
phase
Table 12: Voltage drops from the PCE to the main distribution board
Design and Analysis of Commercial Photovoltaic Systems and Components
35
Table 9: Module to their Respective Inverter
Modules to inverter
DC cable Length (m) Cable diameter ( ) Voltage drop %
Kyocera 5.04kW 5 4 0.01
Sun Power 1.5kW 15 4 0.08
Sun Power 2.5kW 25 4 0.24
Table 10: Inverter to Combiner Box
Inverter to AC Combiner Box
Inverter Length (m) Cable diameter ( ) Voltage drop %
SMA STP 5000TL-20 5 4 0.246
Fronius IG15 5 4 0.005
SMA SB2500-TL 5 4 0.202
Design and Analysis of Commercial Photovoltaic Systems and Components
36
Table 11: Current at the Combiner Box
At the combiner Box
Phase Voltage (V) Current (A)
a 240 22.138
b 240 18.805
c 240 12.138
Table 12: Voltage Drops from PCE to the Main Distribution Board
Combiner Box to Main Distribution Board AC Cable
Length (m) Cable diameter ( ) Phase Voltage drop %
40 10 a 1.670%
b 1.210%
c 0.623%
According to the (AS3008:2009, clause 4.6), it is a safety measure to consider the
heaviest load when considering voltage drops and over current protection. Protection
on the phases with lower currents will leave the system without an appropriate buffer
for starting up currents and cause nuisance tripping on all the other 3 phases.
The 9.04kWp system contributes to the grid as a generator. Phase a carries the most
amount of current, therefore should be connected to the line that carries the most load
in BE. Phase b shall be connected to the line that carries the second highest amount of
current. Phase c as shown in table 13, carries the least amount of current and therefore
can be connected to the line with the lowest current. Figure 5 below is an illustration of
the distances of cable runs that were used for the cable loss calculations. It should also
be noted that the SMA STP5000TL-20 inverter is a 3-phase inverter, the outputs of the
other 2 single phase inverters are combined together as an unbalance 3-phase system.
Figure 6 is the single line diagram that was used to attain electrical quotes on the
system.
Design and Analysis of Commercial Photovoltaic Systems and Components
37
Figure 5: Overview of system
CombinerBox
Drawingisforillustra vepurposes,andisnottoscale
Kyocera5kW
SunPower1.5kW
SunPower2.5kW
FroniusIG15
SMASB2500TL
SMASTP5000Tl
Distribu onBoard
25m
15m
5m
5m
5m
40m5m
Design and Analysis of Commercial Photovoltaic Systems and Components
38
Figure 6: SLD and Breaker Specifications
Design and Analysis of Commercial Photovoltaic Systems and Components
39
5.7 Circuit breaker/Enclosure
Overcurrent protection measures used will be in the form a circuit breaker (CB). Each CB
shall be rated differently as this is a more complex system compared to the conventional
single or three phase PV installations. Components exposed to outdoor conditions are
to be at least IP 54 complaint or be put into IP 54 rated enclosures. All of the CBs with
the exception of the one at the main distribution board will require being in IP 65
enclosures.
As per AS5033, CBs are rated to 25% more than the Isc (maximum current that the array
experiences). The formula used to rate the CBs is as the following:
[29]
Because this is a combination of a three phase and two single-phase systems, the
protection CB at the combiner box must be rated in accordance to its highest line
current to accommodate. Fault protection devices to be used are all rated differently
and are to be indicated in the SLD in Figure 6.
Due to the cable lengths of the system from device to device, isolations points are
required whenever the inverter is not within sight. The roof-mounted system has
breakers included in the design (B1, B2) to comply with this standard.
Design and Analysis of Commercial Photovoltaic Systems and Components
40
5.8 Cable Routing and cable types
All 3 inverters are located behind the fence as shown in Figure 2. The reason for the
inverters being located there is due to possible future development of the site.
Copper cables are used as DC cables from the rooftop array and ground-mounted array,
adhering to AS5033 (clause 4.3.6.3.1). Isolation points (B1, B2) on the rooftop are
required and are shown in the SLD in Figure 6. Enclosures are to be located at a highly
accessible area and to be IP65 rated for the system to comply with the standards. All
exposed wires of the system shall be in a UV stabilized conduit. Cable diameter is
justified in section 5.6.
The distance from the inverters to the AC combiner box (IP65) is an estimated 5m
XLPE 3+1 core cable [8] per inverter prior connection to the AC combiner box (IP65, 6
poles). From the AC combiner box to the main switchboard, the distance will cover 40m
(estimated) and shall utilize cable no less than in diameter; slightly thicker
conduit (32 ) is used for the application. Cables are to be run along the fence line
and into the rooftop of the BE office, and into an empty port on the BE main distribution
board as illustrated in Figure 7.
Figure 7: Main Distribution Board
Design and Analysis of Commercial Photovoltaic Systems and Components
41
5.9 Lightning Protection Systems (LPS)
BE is located in an industrial area in Canning Vale, the area surrounding the installation
site consists of other factories and business without significant high-rise buildings or tall
trees. This leaves the array a potential lightning strike target. However, to determine
whether or not the building required LPS systems, a risk assessment must be done.
It is important to consider lightning protection systems (LPS) for PV installs. Areas with
higher lightning densities such as office buildings, schools and power utilities will include
both internal and external protection if there are high volumes of human traffic and
expensive electrical components.
5.9.1 External Lightning Protection
LPS systems are used to attract and direct the charge to its circuit rather than having
the lightning strike cause mechanical or thermal damage to its structure by providing a
low resistance path to ground where it gets terminated. External methods of
overvoltage protection are discussed briefly in the overvoltage protection section in
AS5033: 2012 clause 3.5.2 and Appendix F5 in the AS5033 [29]. External methods can
consist of earthing and bonding, magnetic shielding and cable/conductor routing; and
SPD protection [26]. Figure 8 below is also a method of wiring the modules as it
decreases the amount of loops in the cables, providing an alternative path for the
current to flow, protecting the modules against lightning [26].
If there are no means of external lightning protection at the site, internal protection
methods such as the appropriate placement of internal LPS can be used.
Design and Analysis of Commercial Photovoltaic Systems and Components
42
Figure 8: Prevention Of Wiring Loops in Circuits [26]
Design and Analysis of Commercial Photovoltaic Systems and Components
43
5.9.2 Internal Lightning Protection
The two forms of internal lightning protection that will be discussed are:
Equipotential Bonding
Surge Protection Devices (SPD)
Equipotential bonding is the bonding of all the ground to the same multiple earth
neutral connection (MEN connection). This will work by making all the equipment
bonded together have the same electrical potential. This enables the human being to be
able to touch two items with the same reference because it eliminates the potential
difference between them [27].
Design and Analysis of Commercial Photovoltaic Systems and Components
44
Surge protection is referenced to ground and provides an alternative route for the
current to flow to the ground. It operates by having two pathways for the current to
flow. During normal operating conditions, the flow of current goes to the load while the
other pathway is blocked by a bad conductive metal, which only conducts when a higher
voltage than average voltage is received (during overvoltage).
There are 3 protection levels in SPDs (Type I, Type II, Type III). Protection levels are in
descending order with Type I as the highest order of protection. While most inverters
already have a type II inverter within its internal circuit, surges can still pass through due
to the high operating currents of PV systems. SPDs shall be connected before and after
the inverter for overall protection of the inverter and BOS, details on where SPDs should
be installed and the range (10m) it protects can be found in the appendix of AS5033.
Although the final design does not include SPDs, it is recommended that the system
have the following protection installed:
DC side:
Type II SPD intercepts the circuit after the PV array and also at the point before inverter
for the rooftop arrays. Ground array only requires SPD at the point at the inverter as the
distance is between the PV modules and inverter is less than 10 metres.
AC side:
Type II SPD intercepts the circuit before the entrance of the building and also at the
point of the inverters.
Design and Analysis of Commercial Photovoltaic Systems and Components
45
5.10 Lightning Protection Risk Assessment
A lightning protection risk assessment has been conducted according to the lightning
man guideline. This guideline is a replicated version according to AS1768 which is
available online. The risk assessment incorporated the risk of the site where power
utilities are involved and human lives are at risk during a case where lightning strikes.
Risk to human life loss is low and a dedicated external LPS system is not required.
Factors considered in the lighting risk assessment are shown below in Table 13.
Table 13: Lightning Risk Assessment
Assessment Type of Structure
or use
Type of
Construction
Height of
structure
Prevalence/
Thunder
days
Situation
Description
Structure with
contents of fair
importance, e.g.
Water tower,
Shop with
valuable
contents, office,
factory or
residential
building
Reinforced
concrete or
steel frame
structure
with a
ferrous
metallic roof
Exceeding
6m but not
exceeding
11m
Exceeding 8
but not
exceeding 15
On the flat,
at any
elevation
Value of
index score 2 1 2 3 0
Total score 8
This risk assessment gives a total score of 8, which indicates that risk involved is
negligible and therefore LPS systems are not required. SPDs should still be included in
the final design if the budget is permissible. The full lightning assessment is attached in
Appendix A21.
Design and Analysis of Commercial Photovoltaic Systems and Components
46
5.11 Earthing
Earthing of the system is an important safety precaution that needs to be addressed for
onsite personnel and maintenance personnel; all conductive equipment must be
equipotential bonded; this included the racking of the system. The human perception of
an electric shock is 0.5mA [19]. A study at Murdoch University [19] recorded 0.6mA of
leakage current from a 2.25kWp array in its racking system, which further enforces the
need for the racking system to be earthed to prevent accidents from happening.
Earth Lugs are included in each individual rack to prevent the electric shock when a well-
earthed person touches the racking system. The flow chart in Figure 9 is a map to how
the earth conductor is chosen and implemented as shown in the SLD, in Figure 6.
All conductive material is to be linked to the same earth bar as the MEN connection of
BE. By doing so, all components will be equipotential bonded; this leads to the potential
difference between a well-earthed person and the ground to be of a much smaller
magnitude.
Design and Analysis of Commercial Photovoltaic Systems and Components
47
Figure 9: Earthing Conductor Selection [29]
Design and Analysis of Commercial Photovoltaic Systems and Components
48
5.12 Connectors
Connection points of the PV array and the inverters have to be lockable and only
separable when force is applied. Most new modules on the market today (MC4, Tyco,
Amphenol Helios H4) are lockable [29]. The ground mounted Kyocera modules already
come equipped with MC4 connections points from the junction boxes. The Sun Power
modules had MC3 connectors which are non-lockable and therefore needs to be
replaced. 20 male and 20 female MC4 connectors for the Sun Power modules are listed
in the balance of system sheet with a crimp tool to make the connections are included in
the BOS sheet as attached in Appendix A11.
Design and Analysis of Commercial Photovoltaic Systems and Components
49
5.13 Summary
This chapter takes into considerations of the installation guidelines of AS5033 and
regulations set out by WP for embedded generation. Voltage drop for the largest phase
was 1.69% while using a 10 cable from the combiner box to the main distribution
board (40m), a 6 cable was initially considered and had an voltage drop of 2.8%,
however it was avoided because the distance of 40m was a estimation and using the
6 cable would allow for no margin for error. Cable is to be routed from module to
the distribution board in conduit.
Initially there were a few design problems as indicated in section 5.4. However the
problems faced were overcome by changing the design of the system to utilize 3
inverters instead of 1 inverter. During this stage, the availability of the SMA STP 5000TL-
20 was also sourced from various distributors to get quotes on the cheapest price.
A lightning risk assessment was done for the site and the risk assessment is attached in
Appendix A21. The site is exposed to a mild risk of lightning strikes and therefore does
not need any form of external lightning protection. Internet protection like
equipotential bonding of the racking and the use of surge protection can be offered as
an option but are not required.
After completion of the design, a list of components that is required to complete the
system was finalized and the balance of system was formulated and passed on to the
on-site electrician for quote on the final pricing on the components. This was followed
by the preparation of a business proposal to our client, indicating the benefits and
system capital costs involved in implementing the grid connected PV system.
Design and Analysis of Commercial Photovoltaic Systems and Components
50
6 Procurement
6.1 Introduction
Procurement usually takes place after the detailed design is discussed and approved. It
is an important skill that project managers must have to increase the cost effectiveness
of the project.
When procurement is taking place, some important factors to consider are:
Are the items large in size?
When is the item required?
Will items obstruct workflow when they arrive on site?
Are the items sensitive to environmental issues (rain/ hail/ sunlight)?
What are the payment methods?
An example that can be used is given in minor project in minor project 1. This is a good
example because the arrival of PV modules should only arrive after site clean-up, ground
works are completed. Arrival of components, which are not required during the stage,
obstructs the flow of work that takes place and may cause delays. If component are
sensitive to exposure to environment, they will incur storage fees, which can all be
avoided if arrival of the materials are well timed.
6.2 Items To Be Procured
The following are the components that need to be procured:
SMA STP5000-Tl-20
New Roof Racking
Contractor for Concrete Cutting
Concrete for foundations of the system
Labour
CEC accredited installer sign off
Design and Analysis of Commercial Photovoltaic Systems and Components
51
6.3 Summary
This project did not proceed to the procurement stage of the project because of the
financial terms of the project have not been met.
Sub-contractors and the lead times associated for the components to arrive on site have
been acquired and implemented on the Gantt Chart for reference.
This phase of the project required prior knowledge of a systematic approach for the
project to flow smoothly. If well timed and planned can lower project overhead and
avoid delays.
Design and Analysis of Commercial Photovoltaic Systems and Components
52
7 Implementation
7.1 Introduction
This chapter involves the process of getting the installation crew to get started and the
job safety assessments (JSA) plans for the job to proceed. Site visits were mandatory, to
make sure of the availability of space. Trimble sketch up was a very good indicator for
area estimation however from the aerial view of the site as shown in figure 1, the shade
sails had been a problem when estimating points of where the lines of fencing is
situated.
During the site visit, the measurement of the area further affirms that fencing had to be
removed for the system to operate efficiently. Total required area for the site for the
installation of the system was 24.72 .
Consideration have also been given to the 4kW on the roof, however after the design
had been done, roof renovation commenced which may impose delays on the project.
Design and Analysis of Commercial Photovoltaic Systems and Components
53
7.2 Fencing Options
This section applies to the ground-mounted array, which has fencing to the north of the
system as illustrated in Figure 2. An estimated 30% of the cells will be shaded from direct
sunlight, during noon as illustrated in a not to scale drawing in figure 10. Current
technologies within the inverter, such as MPPT tracking and bypass diodes in the
modules are insufficient to enable the system from reaping the full benefits of a PV
install, ultimately decreasing the system efficiency and monetary value in savings.
As seen in Figure 10, the ground-mounted array will fit onto the proposed site with only
the removal of the fencing on the east. However due to the partial shading caused by
the 1.85m fence line to the north of the array, it is essential that this part of the fence be
removed for an optimized performance of the system; hence increasing the monetary
value of the system.
Figure 10: Shading From Fence
As part of the business proposal to BE, the client had to be notified that the fencing was
required to be removed for the ground-mounted system to be installed. The fencing is
1.85m high as shown in Figure 10 and will impose significant amounts of shadings to the
ground-mounted PV array. Three separate site layouts and possible restructure of the
Design and Analysis of Commercial Photovoltaic Systems and Components
54
barbeque area with their benefits and function listed was discussed among BUS
internally.
A PowerPoint presentation was prepared for the different fencing options available and
will be included in the Appendix 15-17, and the final decision was to leave most of the
fence intact and remove fencing on the north of the PV array that can cause shading as
indicated in Figure 11.
Figure 11: Desired Fencing Option
Design and Analysis of Commercial Photovoltaic Systems and Components
55
7.3 Ground-mounted racking system:
The floor of the installation site for the 5.04kW ground mounted system had concrete
set on it as it was an outdoor barbeque area for BE (Figure 12), the ground on the east is
paved by bricks and the allocated site for the piling the support beams of the 5.04kW
system had to be piled 1.5m into the ground as per installation manual of the racking
system.
In order for the installation to proceed, the vertical axis of the racking system (H beam),
had to be installed on the concrete part as indicated on Figure 12. The concrete is 85mm
(refer to Figure 13) at its thickest point, sand beneath. For small piles such as the poles
for the ground-mounted system, concrete squares of 0.2mX0.2m have to be cut out
with a circular saw before installation of the piles. A small excavator with a vibrator can
be used to vibrate the poles into the ground. An excavator can also use its bucket to
knock the poles into the ground however will cause damage to the tops of the poles and
cause issues with connecting the pole top and pole top connector.
Numerous piling contractors were contacted and due to the small scale of the job, many
established local piling contractors were not willing to accept the job, or gave very
expensive quotes. The cheaper solution of getting the foundations as shown in Figure 15
was to have the 85mm thick concrete cut out square blocks, the next step was
to manually dig the hole 1.5m deep and fill it with 0.5m of rapid set concrete.
Density of concrete = 2400kg/
Volume per base anchor =
Weight per anchor (kg) =
The base anchorage is approximately 48kg per pot. A total of 4 pots equalling 192kg of
concrete have to be used for the foundations of the racking system. Installation advice
on the improvised foundation was proposed, and recognized by the manufacturer.
Email correspondence with manufacturer is found in Appendix A19.
Design and Analysis of Commercial Photovoltaic Systems and Components
56
Figure 12: Before preparation
Figure 13: Thickness of Concrete
Design and Analysis of Commercial Photovoltaic Systems and Components
57
7.4 System Security
Security becomes an issue when the PV system is exposed to the public. There are
multiple solutions to prevent this from happening; however the modules are still
subjected to vandalism.
The following are the suggested methods that can be included as part of the package to
enhance security of the system:
1. Have motion sensor lights that cover the area of the modules
2. Have locks and chains at the back of the modules to decrease accessibility
3. Have security cables of the modules that trigger a security alarm when the
modules are moved
4. Secure the modules with one way security bolts
5. Insurance coverage for theft and burglary
7.4.1 Recommendation for Security of the System
It is recommended the stakeholder utilizes multiple security measures as mentioned
above. There are one way security nuts that can be replacements of the M8 bolts that
are attached to end clamps that hold the modules to the frame. This will be the most
crucial step to secure the system because this makes it impossible to remove the
modules individually without the use of a specific tool provided in the kit.
Design and Analysis of Commercial Photovoltaic Systems and Components
58
7.5 Summary
All stages of the implementation were sourced including quotes from external
contractors for the foundations of the racking system.
Currently the site has concrete flooring; it is not possible for the piling as recommended
by the manufacturers to be done, a different approach on how the foundations would
be set was suggested and approved by the manufacturers of the system.
Job safety is of high priority and standard industry safety protocols are implanted by JSA
plans. The assembly team consists of individuals from BE and BUS. Procedures for JSA
was acquired from the production manager at BE. Instructions are to be followed by all
members of the assembly team.
Security of the system is documented in section 7.4 and is highly recommended for the
ground mounted system and should be implemented because the design of ground
mounted system is assessable to general public.
Design and Analysis of Commercial Photovoltaic Systems and Components
59
8 Commissioning
8.1 Introduction
Commissioning is set to take place when implementation of the system has been
completed. It is the procedure of “final checks” of the system to ensure that all
components are installed appropriately not only by the information provided by the
manufacturer, but also complies to the Australian Standards on PV installation.
Commissioning tests also act as an indicator to ensure that all components are
functioning to satisfactory levels and safety hazard issues are all rectified before the
project is handed over to the client.
Commissioning tests are to be performed by the CEC accredited PV designer, using the
commissioning equipment available at BUS and will be split into four main sections and
also its step-by-step instructions that is required to perform the commissioning.
1. Mechanical and structural inspection
2. DC Commissioning
3. AC Commissioning
4. Safety tests
The following documentation presents the commissioning procedure for the BE grid
connected PV system. The commissioning procedure is sectioned into two phases. The
first phase is a physical and mechanical inspection of the array and surrounding
components. The second phase is the electrical site acceptance testing of the PV
system.
The mechanical inspections includes the following:
Inspection of PV array installation;
1. Concrete foundation location;
2. General Site Arrangement;
Inspection of inverter enclosure.
Design and Analysis of Commercial Photovoltaic Systems and Components
60
The electrical testing includes the following:
Testing of each PV string at the Junction Box;
1. Earth/Ground Continuity Test;
2. Open voltage test, short circuit test;
Testing of each inverter;
Testing of AC connection at combiner box;
Testing of complete power system at the main distribution board.
8.2 Quality Assurance Testing
1. Factory assessment testing (FAT)
Factory assessment testing is the procedure that manufacturers put their products
through before it rolls out of the production floor (e.g. flash testing on solar modules)
2. Site assessment testing (SAT)
On site testing for function as described by manufacturer, there are different
procedures in completing this test. This is determined by the assembly team/contractor
(e.g. on-site physical inspection of equipment)
3. Commissioning
This is the last stage of quality checks which is done by the CEC accredited PV designer
and the installer. Mechanical and electrical testing of a fully functioning system is tested
before it is connected to the grid.
Design and Analysis of Commercial Photovoltaic Systems and Components
61
8.3 Commissioning Test Instructions and Test Sheets
The Commissioning Test instructions and Test Sheets are located in Appendix A14.
8.4 Summary
Commissioning of the system was not possible during the timeframe of the internship
project. However the commissioning test instructions and test sheets have been
formulated and ready for when the commissioning is to be done on the system. This will
only be possible once a financial agreement has been made with the client and the
system has been completed.
Implementation of the system is due to be started by February and is due to be
commissioned by the end of the Feb 2014. Completed commissioning test data will then
be handed over to the client for early detection of an underperforming system.
Design and Analysis of Commercial Photovoltaic Systems and Components
62
9 Future Plans and Recommendations
9.1 Introduction
Considering the standalone inverter SMA Sunny Island 5048 (SI), battery banks have
been pre acquired together with other PV equipment, further development of the site
for UPS capability can be done with low capital costs.
BE has an onsite back-up generator that currently needs to be manually switched on
during blackouts. Blackouts can occur without notice and can cause valuable
information to be lost and business operations to come to a halt while waiting for the
generator to come online. An integrated system with battery banks and a backup
generator can be implemented using an uninterruptable power supply (UPS) system.
A conceptual design of the standalone/ grid connected hybrid system is documented in
this chapter.
Design and Analysis of Commercial Photovoltaic Systems and Components
63
9.2 Sunny Island 5048
The SI is a much more sophisticated inverter when compared to the grid connected ones
that are used in the main project. The inverter alone has multiple functions that are
listed below (Appendix A24):
Grid monitoring
Grid forming
Control of frequency and voltage
AC to DC conversion for battery charging
DC to AC conversion for load supply
Load and energy source control
Generator control capability
202V - 253V AC voltage
Under WP connection rules, standalone inverters such as the SI cannot be grid
connected; this is due to the non anti-islanding capabilities of the inverter. When the
grid is online, the SI acts strictly as a charger for the batteries from the supply of the grid
while not supplying any loads; its internal programmable logic control (PLC) can also be
configured to operate the utility grid and generator mutually exclusively with
coordination settings for a seamless transition between utility grid and back up
generation.
Design and Analysis of Commercial Photovoltaic Systems and Components
64
9.3 UPS Systems
UPS systems are widely used to provide temporary power supply for the system when
there are power shortages or blackouts. Their support time is limited to the capacity of
the battery. UPS systems are usually wired in to telecommunication systems or network
server pc, as they are the most important in organizations in scale, data processing
machines to provide ample time to back up devices and prepare for downtime.
Generators and UPS systems are forms of back up for existing power systems; the big
difference is the continuity of the power. The internal PLC within the Sunny Island 5048
can provide control during blackouts and can direct the site to receive power supply
from the generator and PV supply.
During the transitional period of normal operating conditions and stand-by generation,
usually by diesel generators, there will be a down time as opposed to UPS systems. This
is because generators are manually started or have electrical starters with its associated
PLC signal. During an unexpected power shortage event, dedicated loads can receive
supply from the batteries while the generator becomes a substitute for the grid. The
switching period is 16ms [30], which is less than a cycle of Australian electric power
network frequency of 50 HZ. This is sufficient for a seamless switching of supply.
Design and Analysis of Commercial Photovoltaic Systems and Components
65
9.3.1 Operation of UPS systems
The proposed UPS system consists of a dedicated UPS load, standalone island inverter
and battery banks and a voltage rectifier/charger and PLCs with its input sensors getting
feed from the grid. The following are the statuses and operations of the main
components (generator, PV and utility grid of the UPS system) during normal operation,
during a blackout and grid reconnection [30].
Before switching:
During normal operation, the load and UPS both receive supply from the grid while the
grid charges the battery bank via the SI.
During Switching: transient period
During downtime, the microprocessor of the SI detects a no signal from the grid and
diverts to backup supply (battery) while it signals the generator to be started up.
During Blackout
During the blackout, the utility grid is disconnected and the facility is islanded. The
facility is running from the generator supply and PV if available. Charging the battery can
be optional, depending on the generator capacity and the load required. The SI
continues to monitor to the grid for a signal.
Grid Reconnection:
When the PLC detects the availability of the grid, it will signal the generator to ramp
down its output while it matches the grid voltage. Once the grid is reconnected the
generator can go into standby mode and later on be turned off.
Design and Analysis of Commercial Photovoltaic Systems and Components
66
9.4 Summary
With most of the expensive components already procured by BE, the development of a
test bench will only inflict a low capital cost to BE. The majority of the costs that BE will
incur will be for the detailed engineering design, and testing of the existing components
such as Sunny Island 5048, 1MW load, battery banks and design involved. Due to the
lengthy period of which the battery has been left without charge, there is a possibility
that the battery banks will need replacement.
Developing a UPS system that supports the two main components of a business;
telecommunications and the main PC for business operation can be very beneficial. This
enables the business to receive enquiries, process payments during blackouts, making
this a very feasible option for the completeness in power supply of the facility. A
monitoring system is highly recommended to provide more efficient fault finding.
Advanced systems that are available in the industry also support SCADA interfaces.
Design and Analysis of Commercial Photovoltaic Systems and Components
67
10 Minor project 1 – Technical design of 150kW system
Having worked on the technical design of a 150kW wastewater treatment plant PV
project that is due to be completed during May 2014. Due to a last minute decision to
prepare the tender document for the project, a tight timeframe of 5 days was given to
complete the document.
A first meeting was held to distribute the workload and the author picked up section
“demonstrated understanding” which consists of the fundamentals of technical design,
project delivery and the materials used. Skills that were learned from my internship so
far were truly tested in the level of detail and consideration that is required for the
tender document to be completed. Two versions of the Gantt Chart (high level and low
level) were also implemented over the course of the minor project. The high level
version submitted together with the tender, while the low level version were attached
in Appendix A20.
The scope that was covered during the tender documentation is as follows, and further
details will be provided over the following chapter documented in the sections as listed
below [7]:
1. Demonstrated understanding of the scope of work
2. The process of delivery of goods and services
3. Various approvals for the system
4. How did the products meet the specific requirements of the project?
Design and Analysis of Commercial Photovoltaic Systems and Components
68
10.1 Demonstrated understanding of the scope of work:
Balance Utility Solutions will be undertaking the following scope of works for the 150kW
PV System consists of the following components.
Supply of quality power components including:
o Photovoltaic (PV) modules
o PV inverters
o Racking and ground mount structures
o Balance of system (Including cables, cable tray, switches, protection
devices, junction and combiner boxes)
o Communication gear
o Power protection relay gear (Balance Grid Integration Box)
o Switch room ancillary components (including air-conditioning
components)
Detailed electrical engineering design for the commercial PV System;
Site inspections and grid connection application;
Site leveling and clearing;
Installation of ground mounted PV racking system (North Facing);
Securing of the PV modules to the racking system;
Connection of DC cable and cable tray installation;
Installation of PV Inverters in switch room;
Installation of air-conditioning within switch room;
Installation of communication gear;
Installation of ancillary boxes (DC Junction box and AC Combiner Box);
Interconnection of AC Cable from Combiner box with existing switch board;
Installation of main solar supply switch;
Commissioning of PV system;
Commissioning of communication system;
Application of initial Large Generation Certificates (LGCs);
Operator Training and Assistance.
Design and Analysis of Commercial Photovoltaic Systems and Components
69
10.2 Process of delivery of goods and services
This section involved a detailed consideration of all aspects of the project, which was
categorized in the following 4 steps:
Step 1: Engineering design and approvals
Resource evaluation
Performance evaluation
Cost of equipment
System design
Components of BOS
Complying to principle expectation
Western Power grid connection application
Safety induction training
Step 2: Procurement
7 X Aurora TRIO-20.0-TL-OUTD-S2-400
1 X Aurora PVi-10-Tl-OUTD
Cable tray
Inverter mounting plate
Concrete footings
Racking system
600 X 255W HanWha SolarOne HSL6060p6-PB-1-255E PV modules
Hiring out of site equipment
Making of concrete blocks
Step 3: Implementation
Site provided free and clear of scrub
Site surveyed for placement of blocks
Placement of concrete blocks
Installation of cable trays
Assembly of racking system
Installation of PV modules
Design and Analysis of Commercial Photovoltaic Systems and Components
70
Electrical cable installation
Installation of Inverters
Installation of GIB
Installation of control and monitoring equipment
Clearing of site
Step 4: Commissioning
Civil ITP (Inspection and Test Procedure)
Structural ITP
Electrical ITP
PV DC Commissioning
Inverter Commissioning
Control Commissioning
Monitoring Commissioning
CEC PV system sign-off
Training and Handover
Design and Analysis of Commercial Photovoltaic Systems and Components
71
10.3 Approvals for the system
The application process is for connecting transmission loads and large generators to the
WP Network. The Process involves 6 stages and is done with collaboration with WP; the
following are the 6 stages and a brief description of theirs tasks and application
components that need to be submitted are indicated. This magnitude of generation
(above 30kVA) requires depth of detail during the application and involves mandatory
protection relays as part of the design requirement. Figure 14 is a more illustrative view
of the application stages that are required.
1. Enquiry
Identify suitable network connection point and feasibility, a submission of
lodgement fee is also due.
2. Project initiation
Identify network constraints and its options to modify network. Submission of
the corrected application and technical data with lodgement fee is required.
3. Project Scoping
Selecting final technical solution to be implemented. Adhering to technical and
safety requirements of the SWIS network. Preliminary designs such as computer
models, environmental assessments and project planning definition are
included. Identifying the CAG solution is mandatory at this stage. Submission of a
preliminary access offer is required.
4. Project Planning
This step Involves project planning, business cases and estimates of the project,
and also submission of the final technical solution to modify the network.
Statutory approvals are finalized. Submission of Access offer is required.
5. Construction & commissioning
The IWC (Interconnection works contract) then constructs and commissioned by
Western Power. Checking against the compliancy regulations for performance
verification and model validation.
Design and Analysis of Commercial Photovoltaic Systems and Components
72
6. Operation
Once constructed, the new and modified connection assets become the
property of Western Power. Assets can now begin operating under the terms of
the electricity transfer access contract (ETAC), which is a operation to facilitate
the construction of a connection or technical compliance [36].
Figure 14: Flow of Application for generator up to 150kVA
Design and Analysis of Commercial Photovoltaic Systems and Components
73
Competing Applications group (CAG)
For systems upwards of 30kVA, the network has to be upgraded to accommodate the
change. The Competing Applications group (CAG) is a network solution that involves all
consenting parties to pay processing fee, which covers the following [28]:
Developing the shared network solution;
Preparing a preliminary design and cost estimate for the solution;
Undertaking system studies (such as load flow and dynamic studies);
Undertaking a regulatory test (where applicable);
Conducting a net benefits assessment (where applicable); and
Developing a project schedule and the likely costs to implement the solution if it
is accepted.
Terms and conditions for the applicants of the CAG [28]:
Preliminary offer is an upfront payments for the applicants in a CAG, the
acceptance fee is non refundable unless WP does not make an access offer.
Once sufficient funds are received, access offers will be created.
When the POA is being developed, any fees paid will not be refunded to the
applicant and will contribute towards overall costs to develop the POA of the
CAG.
If there is insufficient response and access offers are not issued, WP will proceed
and use the funds for development and refund the remaining after the rework.
POA offers will include technical information and costs for all the CAG
participants, information such as land acquisition; planning and environmental
issues are included.
Design and Analysis of Commercial Photovoltaic Systems and Components
74
4. How did the products meet the specific requirements of the project?
Design:
Inverter:
7 X Aurora TRIO 20KW-TL
1 X Aurora PVI-10kW-TL-OUTD
Racking system:
Figure 15: Concrete Footings
The ground mounted racking systems are custom made for every system and are
designed to comply with the following standards as shown in Figure 16:
1. AS1170.2 Structural design actions – Wind loads
2. AS1664.1 – Aluminium Structures
3. AS4600 – Cold Formed Steel Structures
4. AS3798-2007 – Guidelines on earthworks and commercial and residential
developments
PV modules:
255W modules will be utilized for the ease of installation and transportation. Associated
requirements as per request to tender document.
Configuration:
There are 15 rows of modules that resemble Figure 4, All modules are in portrait form,
containing 20 columns of 2 rows. The total amount of modules is 600. A total of 602
modules will be bought, however 2 will be used as spares.
This is designing with respect to the Vmax of the inverter; the inverters are rated to 1000V
per input string. However there is an option if the site has to allow for public access, the
configuration has to be changed to allow string voltage to go below 600V as per
AS5033, clause 3.1
Design and Analysis of Commercial Photovoltaic Systems and Components
75
Monitoring system components:
Aurora Enviro Sensors Entry
AuroraMAX Logger
Aurora Hand Held Display
a) Proposed installed location;
Trimble sketch up was used to draw the site location and the switch room layout. There
were two options that were given by principle on where the locations of the inverters
and combiner boxes were to be located: in the switch room or out in the field. The
option of having the PV equipment in the switch room was the preferred method of
install, however as space was a constraint for the set up, test fitting of the 8 inverters,
the BUS designed grid integration box (GIB), air conditioner was also considered to
compensate for the heat dissipated from the inverters.
Benefit of having equipment in the switch room:
Lowering of capital costs by eliminating the need for inverter enclosures;
Site layout
The tilt angle is 25 degrees and the space in between rows of modules is 1.35m. The PV
array takes up a total of 1276 , including the space in between each row of modules.
Beside both sides of the array, there is also space in excess of 8m, which allows for easy
access for service vehicles. Actual site drawing is located in figure 17.
Figure 16: Site layout
Design and Analysis of Commercial Photovoltaic Systems and Components
76
The wall layout on the 13m by 2.7m wall in the switch room has the following layout: a
new 3.5kW air conditioning unit is placed in the middle of all equipment to compensate
for the amount of heat dissipated from the inverters. The switch room layout is
illustrated in Figure 18, with the inclusion of a 3.5kW air conditioning unit to dissipate
heat.
Figure 17: Switch room layout
Design and Analysis of Commercial Photovoltaic Systems and Components
77
f. Wiring losses;
As Option 1 is chosen as the BUS preferred method of install for optimized performance.
The calculations are done from the furthest end of the PV array to the back of the switch
room, covering a total distance of 80m, voltage drop and power loss calculations for a
6mm2 Copper tinned cable with a resistance value of 3.11 Ω/km. String voltage of 616V
and nominal current of 8A is applied for the calculations shown on Table 14.
Design and Analysis of Commercial Photovoltaic Systems and Components
78
Table 14: Voltage Drop Calculations (Minor Project 1)
Strings Inverter Length (m) Cable Power Loss Power Loss % Volt Drop Volt Drop %
1 1 50 0.1555 19.904 0.20% 2.488 0.40%
2 1 50 0.1555 19.904 0.20% 2.488 0.40%
3 1 58 0.18038 23.08864 0.23% 2.88608 0.47%
4 1 58 0.18038 23.08864 0.23% 2.88608 0.47%
5 2 64 0.19904 25.47712 0.25% 3.18464 0.52%
6 2 64 0.19904 25.47712 0.25% 3.18464 0.52%
7 2 72 0.22392 28.66176 0.28% 3.58272 0.58%
8 2 72 0.22392 28.66176 0.28% 3.58272 0.58%
9 3 80 0.2488 31.8464 0.31% 3.9808 0.65%
10 3 80 0.2488 31.8464 0.31% 3.9808 0.65%
11 3 88 0.27368 35.03104 0.34% 4.37888 0.71%
12 3 88 0.27368 35.03104 0.34% 4.37888 0.71%
13 4 96 0.29856 38.21568 0.37% 4.77696 0.78%
14 4 96 0.29856 38.21568 0.37% 4.77696 0.78%
15 4 102 0.31722 40.60416 0.40% 5.07552 0.82%
16 4 102 0.31722 40.60416 0.40% 5.07552 0.82%
17 5 110 0.3421 43.7888 0.43% 5.4736 0.89%
18 5 110 0.3421 43.7888 0.43% 5.4736 0.89%
19 6 120 0.3732 47.7696 0.47% 5.9712 0.97%
20 6 120 0.3732 47.7696 0.47% 5.9712 0.97%
21 6 128 0.39808 50.95424 0.50% 6.36928 1.03%
22 6 128 0.39808 50.95424 0.50% 6.36928 1.03%
23 7 136 0.42296 54.13888 0.53% 6.76736 1.10%
24 7 136 0.42296 54.13888 0.53% 6.76736 1.10%
25 7 144 0.44784 57.32352 0.56% 7.16544 1.16%
26 7 144 0.44784 57.32352 0.56% 7.16544 1.16%
27 8 152 0.47272 60.50816 0.59% 7.56352 1.23%
28 8 152 0.47272 60.50816 0.59% 7.56352 1.23%
29 8 160 0.4976 63.6928 0.62% 7.9616 1.29%
30 8 160 0.4976 63.6928 0.62% 7.9616 1.29%
Summary
Power Loss 1242.01W
Power loss (%) 0.81%
Average Volt drop 0.84%
Design and Analysis of Commercial Photovoltaic Systems and Components
79
Potential issues associated with the specific project and how they will overcome.
Issue:
Delays in Western Power Approval
Solution:
Application for Western Power grid connection shall be completed and submitted one week
from the date of when the tender is deemed successful. Previous projects and experience
will enable Balance Utility Solutions to gain approval for the application in a fast and efficient
manner.
Issue:
Illness
Solution:
Balance Services Group is the parent company of Balance Utility Solutions, along with Barclay
Engineering and Balance infrastructure. With capabilities for all aspects of the project to be
done in house. Project continuity will not be affected and personnel’s with multiple skill sets
can easily be arranged within the group.
Design and Analysis of Commercial Photovoltaic Systems and Components
80
10.4 A project schedule/timeline
This aspect of the tender document greatly relied on the lead times associated with the
logistics of the equipment. All aspects of the project have to be considered in detail for
an accurate project handover date to be estimated. Suppliers and manufacturers were
contacted for numerous aspects of the system for an accurate estimate of lead times
Involved for equipment to arrive on site. Two Gantt Charts were created; a summarized
version was included in the tender document, and the detailed version, which will be
handed over to BUS for future project management duties. The high level Gantt Chart is
attached to this document as Table 15.
The low-level Gantt Chart involved the internal meetings, site visits, dates for booking of
flights and arrival of the site engineers and installation team. The low-level Gantt Chart is
also attached on Appendix A20 created a more realistic estimation of time required for
tasks to be done, yet enhancing the level of accuracy compared to the final cost of the
project
Design and Analysis of Commercial 84 Photovoltaic Systems and Components
Table 15: High Level Gantt Chart of Minor Project 1
Design and Analysis of Commercial 85 Photovoltaic Systems and Components
11 Minor project 2 – Testing of Sun Power Modules
11.1 Introduction
The Sun Power modules that were to be installed on the rooftop of BE were purchased
second hand from a company that was liquidizing in WA. These modules have been
operational for 3 years and put in storage in BE for another 2 years.
The Sun Power modules SPR-200-BLK (Appendix A9) were very high-end PV modules.
With breakthrough technology and industry leading module efficiencies of 16.1%. There
are a total of 21 modules to be tested and the objectives of testing is listed in section
11.2.
11.2 Objective of Testing
The main objectives of the testing are:
Familiarization of commissioning gear for future use
Compare the degradation of the modules against published results
Find the 20 best performing modules to include in the design
Study of degradation when in Australian climate
Design and Analysis of Commercial 86 Photovoltaic Systems and Components
11.3 Background
A study of degradation rates of PV technologies done by National Renewable Energy
Laboratory (NREL) shows a mean degradation rate of 0.8% per year [20] and 78% of data
points from a sample size of 2000 indicate a degradation rate of less than 1% per year
[20]. From the study alone, it is perceivable that not only climate will have an effect on
the degradation rates of the modules and system and also to take into consideration the
components used and installation location.
Studies from the NREL indicate that the degradation rates can vary from close to 0% in
(Vulcana, Italy) to 1% per year when placed in the desert in Libya [20], which shows the
sensitivity to climate conditions. Table 16 below is a study done by the NREL on the
average degradation rate on different cell technologies.
Performance output warranties allow for a power output degradation of 10% for 12 years
and 20% for a period of 25 years.
Design and Analysis of Commercial 87 Photovoltaic Systems and Components
Table 16: Test Results of Sun Power Modules
Design and Analysis of Commercial 88 Photovoltaic Systems and Components
11.4 Method
The testing of the modules is a straightforward process and can easily be done by using
a conventional multimeter. The following are the steps that I followed to achieve the
test results.
Before executing tests on the PV modules, all of the instruction videos on how to
perform the commissioning tests were viewed and notes taken on how to operate the
Seaward PV150 and Seaward 200R commissioning gear.
1. Locate a site to test the modules (non obstructing to operations of BE, exposed
to sufficient sunlight)
2. Wipe down access dust and effects of long storage periods
3. Create boundary on where the modules shall be placed
4. Record serial number of all 21 modules
5. Sync the Seaward PV150 and Survey 200R modules
6. Align the Survey 200R with the modules using the extension bracket provided
7. Record ambient temperature and module temperature
8. Connect the MC connector clips to the rear of the modules outputs (Red to
positive and black to negative)
9. Record Isc and Voc as shown in the Seaward PV150
10. Put the modules back into storage
11.4.1 Data Processing
1. Sets up tables with data in excel
2. Using ratios, Bring the outputs of Isc and Voc in reference to STC
3. Include Isc and Voc temperature coefficients to the measured ambient
temperature
4. Calculate the Power output of the modules by using the formula
5. Make an assumption that all modules have a 200W output
6. Calculate degradation of the modules
Design and Analysis of Commercial 89 Photovoltaic Systems and Components
11.5 Results
There was only enough room for 5 modules to be lined up in a row as the testing was
conducted outside the storage area of BE. Results were acquired at 36°C on the 7th of
November 2013, according to the method mentioned in secti0n 11.3. Irradiance levels
were recorded periodically during the swapping of modules. A slight overcast condition
when testing modules 17-21, which caused irradiance levels to lower. The test data with
the Voc and Isc along with the testing conditions are recorded in Table 17. Table 18 shows
the degradation rates for 18 out of the 21 modules.
Note: Degradation rates for modules 2,3 and 8 could not be calculated because they had
broken connectors and was dangerous because of the high current levels.
Design and Analysis of Commercial 90 Photovoltaic Systems and Components
Table 17: Test Results of Sun Power Modules
Irradiance level 932,944,900,880 (refer below) W/m²
Outdoor conditions Sunny, partly cloudy
Ambient/module temperature
36, 39 °C
Test equipment Seaward pv150, Survey 200R
Notes:
- Modules are tested at the following irradiance levels: - Modules (1-4): 932 W/m²; - Modules (5-12): 944 W/m² ; - Modules (13-16): 900 W/m - Modules (17-21): 880 W/m²; Modules 2 and 3 had broken connectors
Module Type Sun Power Date: 7/11/2013
SPR-200_BlK
Module number Serial number Isc (A) Voc (V)
1 C42j00256521 4.5 A 41 V
2 C43j00261609 - 41 V
3 C34j00220294 - 42 V
4 C07joo101467 4.8 A 41 V
5 C33j00215116 4.2 A 43 V
6 C38j00244946 4.3 A 43 V
7 C04j00094525 4.3 A 43 V
8 C46j00280987 - 43 V
9 C42j00256520 4.0 A 43 V
10 C43j00261613 4.1 A 44 V
11 C38j00244947 4.2 A 43 V
12 C42j00256524 4.2 A 43 V
13 C06j00097598 3.7 A 43 V
14 C42j00256522 4.0 A 41 V
15 C38j00244943 4.2 A 43 V
16 C33j00215124 4.1 A 42 V
17 C43j00261614 3.6 A 42 V
18 C38j00244944 3.8 A 42 V
19 C36j00230469 3.7 A 43 V
20 C07j00101478 3.6 A 43 V
21 C44j00271411 3.8 A 42 V
Design and Analysis of Commercial 91 Photovoltaic Systems and Components
Table 18: Degradation of Modules
Each module is 200W
Module Delta Isc Delta Voc Power Degradation
( A ) ( V ) Degraded (W) Percentage
1 0.54 4.88 2.642060435 1.321%
2 4.88
3 3.88
4 0.22 4.88 1.06969992 0.535%
5 0.92 2.88 2.654152906 1.327%
6 0.81 2.88 2.348559685 1.174%
7 0.81 2.88 2.348559685 1.174%
8 2.88
9 1.13 2.88 3.265339346 1.633%
10 1.03 1.88 1.933766465 0.967%
11 0.92 2.88 2.654152906 1.327%
12 0.92 2.88 2.654152906 1.327%
13 1.26 2.88 3.629334827 1.815%
14 0.92 4.88 4.517245938 2.259%
15 0.70 2.88 2.02666816 1.013%
16 0.81 3.88 3.160845938 1.580%
17 1.28 3.88 4.965904524 2.483%
18 1.05 3.88 4.082995433 2.041%
19 1.16 2.88 3.359795433 1.680%
20 1.28 2.88 3.687613615 1.844%
21 1.05 3.88 4.082995433 2.041%
Average 1.530%
Minimum 0.535%
Maximum 2.483%
Design and Analysis of Commercial 92 Photovoltaic Systems and Components
11.6 Summary
Monocrystaline-Si modules have been in used since the 1970’s and the amount of data
samples shown on Table 16 shows the amount of data points pre and post year 2000.
The degradation of the Sun Power modules has been calculated based on the
assumption that all modules are exactly 200W.
The key findings of the testing are:
Modules 2,3,8 cannot be tested due to having missing connectors (possibly
detached during de-commissioning);
Degradation rates were 0.02% higher than the NREL study;
Module 17 has the highest degradation at 2.483%;
Module 4 has the lowest degradation at 0.535%;
Average degradation of the 18 modules is 0.38%
The possibilities for the substandard degradation rate can be due to the following:
Power tolerances were not included in the calculation;
Dust was present on the surface of the modules;
Light induced degradation is highest during the first year of exposure
Design and Analysis of Commercial 93 Photovoltaic Systems and Components
12 Overall Conclusion
There are numerous official standards and applications for PV installation. Both the
major and minor projects have been designed and handled with care, and the final
designs were very cost effective. This is due to the use of second hand and new
components in the overall system.
Over the course of this internship, there have been numerous experiences with
corresponding with contractors, broadening my professional network while also
deepening my understanding of the Australian standards used in the solar industry.
Due to the short timeframe and 100kW project commissioning in Guam and the
commencement 6MVA back up generation at Perth Market Authority (PMA), this
project is up to the procurement stage and once the client accepts the quote,
construction of the site can commence.
13 Learning Experiences
This internship project was collaboration between Murdoch University and Balance
Utility Solutions to design and project manage 9.04kWp PV system for Barclay
Engineering. There were other tasks such as preparing of tender documentation and
also soil resistivity testing of Perth Market Authority (PMA) and projects involved with
provided a very insightful experience on how versatile professional electrical engineers
must be.
Many valuable experiences have been gained from this internship project including the
familiarization of PV authorization approvals for PV systems of less than 30kVA and also
the application of PV installs up to 150kVA, which fall under the LGC scheme.
Liaising with contractors and getting quotations for items has enabled one to build a
professional network outside of university. Participating in tender documentation of the
minor project in tight time frames has truly let me experience working in a team under
pressure to meet deadlines of projects.
Design and Analysis of Commercial 94 Photovoltaic Systems and Components
It is also learnt that for a system to be Clean Energy Council (CEC) approved, the design
has to be certified by a CEC accredited PV designer, and the installation must be
supervised or installed by a CEC accredited installer.
Design and Analysis of Commercial 95 Photovoltaic Systems and Components
14 Annotated Bibliography
1. Australia, Standards. “As5033 Installation and Safety Requirements for
Photovoltaic (PV) Arrays.” (2012).
This is the standards for installation and safety requirements for photovoltaic (PV)
arrays. It covers issues for safety requirements and safety gear that is required for the
PV install.
2. Australia, Standards. “Electrical Installation” In Part 1.1: Cables for alternating
voltages up to and including 0.6/1 kV - Typical Australian installation conditions. Sai
Global Limited, 2009.
This standard has examples of LV cables cable selection for Australian installs. This
standard also has cable routing options and suitability of conductor for its respective
use.
3. Dirk C, J, and S R. Kurtz. "Photovoltaic Degradation Rates - an Analytical
Review." Progress in Photovoltaics, no. Research and Applications (2012).
This journal enlightens about the different cell technologies and how different
technologies can affect the degradation rate of the modules.
4. “Horizon Power, Western Power” Western Australian Distribution Connections
Manual.” 2013.
This connection manual provides a touch of every aspect of the Western Australian
distribution network. It also created a link for installers and consumers. WADCM
contains typical circuit diagrams for a clearer vision of the circuit.
5. Paskulich, John. Photovoltaic Grid Connect Systems Design. Central Institute of
Technology, 2011.
This book contains all the factors that need to be considered when designing a grid
connected PV system. However its limitations are that pre-acquired knowledge was
required. A guideline on preliminary system design is included.
Design and Analysis of Commercial 96 Photovoltaic Systems and Components
15 Reference
[1] “Can I choose my retailer?,” Economic regulation authority – Online
http://ret.cleanenergyregulator.gov.au/Certificates/Large-scale-Generation-
Certificates/about-lgcs [Accessed 16/11/2013]
[2] CEC, approved inverter, PCE list, November 2013- pg54 [Accessed 17/11/2013]
[3] CEC, Approved module, PCE list, November 2013- Pg55 [Accessed 17/11/2013]
[4] Paraskevadaki, E.V.; Papathanassiou, S.A., "Evaluation of MPP Voltage and Power of
mc-Si PV Modules in Partial Shading Conditions," Energy Conversion, IEEE Transactions
on , vol.26, no.3, pp.923,932, Sept. 2011 [Accessed 08/12/2013]
[5] England, B. (2012). An investigation into Arc Detection and fire safety aspects of
photovoltaic installations. School of Engineering and Energy Murdoch university.
[Accessed 17/08/2013]
[6] Paskulich, John. Photovoltaic Grid Connect Systems Design. Central Institute of
Technology, 2011. [Accessed 09/109/2013]
[7] K, City of K. "Request to Tender ." 2013. [Accessed 15/11/2013] [8] Olex. "The Handbook." 2012. [Accessed 09/09/2013] [9] Horizon Power, Western Power. "Western Australian Distribution Connections
Manual." 2013. [Accessed 10/10/2013] [10]Lee Joo Shen, Tanvi Gupta, Daniel Allison. "Eng 421: Electrical Design 2." Murdoch
University, 2013. [Accessed 23/08/2013] [11]Australia, Standards. "As 1768: Lightning Protection." Standards Australia, GPO Box
476, Sydney. NSW 2001 and Standards New Zealand, Priate Bag 2439, Wellington 6020, 2007. [Accessed 12/12/2013]
[12] Council, Clean Energy. "Approved Inverter List." 2013. [Accessed 15/08/2013] [13] Council, Clean Energy. "Approved Module List" 2013. [Accessed 15/08/2013] [14] Overton, Rodney. "Feasibility Studies Made Simple." Martin Books,
http://www.murdoch.eblib.com.au/patron/FullRecord.aspx?p=306614&echo=1&userid=21159c59ed13b928d835b6d64cd2b2a1&tstamp=1386296168&id=449c78797688a6ee524dff95d4cd6533. [Accessed 01/01/2014]
[15] "Engineering Feasibility Studies." HRL technology,
http://www.hrlt.com.au/engineering-feasibility-studies/w4/i1039651/. [Accessed 01/01/2014]
Design and Analysis of Commercial 97 Photovoltaic Systems and Components
[16] "Balance Services Group." http://www.balanceservicesgroup.com.au/?page_id=1623. [Accessed 14/01/2014]
[17] Krishnan, G., and D. N. Gaonkar. "Control of Grid Connected and Islanding
Operations of Distributed Generation Systems with Seamless Transfer between Modes." Paper presented at the Control Applications (CCA), 2013 IEEE International Conference on, 28-30 Aug. 2013 2013. [Accessed 16/01/2014]
[18] E.C Okogbue, J.A. Adedokun, B Holmgren. "Hourly and Daily Clearness Index and
Diffuse Fraction at a Tropical Station, Ile-Lfe, Nigeria." INTERNATIONAL JOURNAL OF CLIMATOLOGY (2008). [Accessed 03/01/2014]
[19] M Calais, A Ruscoe, M Dymond. "Transformerless Pv Inverter Issues Revisited - Are
Australian Standards Adeqate?" In 47th ANZSES Annual Conference. Townville, Queensland, Australia, 2009. [Accessed 10/01/2014]
[20] Dirk C, J, and S R. Kurtz. "Photovoltaic Degradation Rates - an Analytical Review."
Progress in Photovoltaics, no. Research and Applications (2012). [Accessed 11/01/2014]
[21] . Synergy- ONLINE http://www.synergy.net.au/at_home/how_can_i_read_my_meter.xhtml. [Accessed
12/01/2014] [22] Balato, M., and M. Vitelli. "A Hybrid Mppt Technique Based on the Fast Estimate of
the Maximum Power Voltages in Pv Applications." Paper presented at the Ecological Vehicles and Renewable Energies (EVER), 2013 8th International Conference and Exhibition on, 27-30 March 2013 2013. [Accessed 23/12/2013]
[23] A, Ricciardi. "Improved Maximum Power Point Tracking with Partially Shaded
Photovoltaic System." Curtin University, 2012. [Accessed 13/01/2014] [24]"Degrees of Protection Provided by Enclosures (Ip Code)." In AS 60529 - 2004.
Standards Australia International: Standards Australia International Ltd, 2004. [Accessed 23/08/2013]
[25] Abidin, H. Z., and R. Ibrahim. "Thunderstorm Day and Ground Flash Density in
Malaysia." Paper presented at the Power Engineering Conference, 2003. PECon 2003. Proceedings. National, 15-16 Dec. 2003 2003. [Accessed 14/01/2014]
[26] Australia, Standards. "As 5033 Installation and Safety Requirements for
Photovoltaic (Pv) Arrays." 2012. [Accessed 17/01/2014] [27] SÖHNE, DEHN +. "Lighitning Protection Guide Revised 2nd Edition." DEHN + SÖHNE,
2012. [Accessed 20/01/2014] [28] "Connecting Transmission Loads and Large Generators to the Western Power
Network." http://www.westernpower.com.au/documents/business/generators/WP_connection_process_maps_CAG.pdf. [Accessed 28/12/2013]
Design and Analysis of Commercial 98 Photovoltaic Systems and Components
[29] Australia, Standards. "As 5033 Installation and Safety Requirements for Photovoltaic (Pv) Arrays." 2012. [Accessed 20/01/2014]
[30] Australia, SMA. "Sunny Island 5048u Product Training." edited by SMA Australia.
SMA. [Accessed 23/01/2014] [31] “Australian Government Clean Energy Regulator”-Online
https://www.rec-registry.gov.au/home.shtml [Accessed 2/02/2014]
[32] "About Homer Energy." http://homerenergy.com/index.html.[Accessed 11/02/2014]
[33] "About Sketch Up." http://www.sketchup.com/about/sketchup-story. [Accessed 11/02/2014]
[34] "Small Generation Unit Stc Calculator." Australian Government, https://www.rec-registry.gov.au/sguCalculatorInit.shtml. [Accessed 11/02/2014]
[35] "Green Energy Trading." http://greenenergytrading.com.au/.[Accessed 11/02/2014]
[36] Power, Western. "Access Arrangement Information." In Standard Access Contract Demonstration of Code Compliance: Western Power. [Accessed 11/02/2014]
Design and Analysis of Commercial 99 Photovoltaic Systems and Components
16 Appendices
16.1 A1: Synergy bi-directional metering generation
16.2 A2 : Western Power application
16.3 A3: Synergy Approval
16.4 A4: Western Power Approval
16.5 A5: SMA SB2500-TL data sheet
16.6 A6: STP 5000TL-20 data sheet
16.7 A7: Fronius IG15 data sheet
16.8 A8: Kyocera KD315GX-LPB datasheet
16.9 A9: Sun Power SPR-200-BLK datasheet
16.10 A10: Single Line Diagram of 9.04kW system
16.11 A11: BOS component list
16.12 A12: Approved locations for PV
16.13 A13: SPR-200-BLK Test Results
16.14 A14: BE Commissioning Instructions and Test Sheets
16.15 A15: Fencing Option A
16.16 A16: Fencing Option B
16.17 A17: Fencing Option C
16.18 A18: Email Correspondence With Frontier rack
16.19 A19: Email Correspondence with Frontier Rack
16.20 A20: Low Level Gantt Chart for Minor project
16.21 A21: Lightning Risk Assessment
16.22 A22: Cable Loss Calculations (
16.23 A23: Cable Loss calculations ( )
16.24 A24: Sunny island 5048 datasheet
16.25 A25: Project plan (24/01/2014)