INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps,...
Transcript of INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps,...
![Page 1: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/1.jpg)
INTERCHANGE
OPERATIONAL ANALYSIS
REPORT (IOAR)
I-75 at SR 26 (Newberry Road)
Alachua County, Florida
FPID: 437354-1
April 2018 Updated July 2018
![Page 2: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/2.jpg)
INTERCHANGE OPERATIONAL ANALYSIS REPORT
(IOAR)
I-75 at SR 26 (Newberry Road)
FPID: 437354-1
Prepared for:
Florida Department of Transportation - District Two
Alachua County, Florida
April 2018 Updated July 2018
![Page 3: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/3.jpg)
![Page 4: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/4.jpg)
![Page 5: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/5.jpg)
![Page 6: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/6.jpg)
EXECUTIVE SUMMARY I-75 at SR 26 IOAR
EXECUTIVE SUMMARY
The purpose of this study is to determine what short term enhancements can be programmed to
improve traffic operations at the I-75/SR 26 (Newberry Road) interchange. Short term
improvements are aimed at increasing the efficiency of the SR 26 intersections while minimizing
or eliminating right-of-way and bridge impacts.
The primary need for this project is to alleviate existing and future traffic congestion and delay at
the study intersections. If no improvements are made to the ramp terminal intersections and
adjacent intersections, traffic operations within the study area will continue to deteriorate as
traffic continues to grow.
The existing traffic for this Interchange Operational Analysis Report (IOAR) is based on the
Safety Study prepared in October of 2014 by the Florida Department of Transportation (FDOT),
District 2 Traffic Operations Office. The primary basis for the growth rate development, used to
develop the traffic projections in this IOAR, are the historical counts from the 2016 Florida
Traffic Information (FTI) DVD, the latest version of the Gainesville Metropolitan Transportation
Planning Organization (MTPO) Model and Relief Study Model (RSM) developed for the recent
North I-75 Master Plan. The analysis years for this study include Existing Year 2018, Opening
Year 2019 and Design Year 2029. The operational analysis for this study was performed using
the latest version of Synchro and Synchro based results have been reported for all intersections.
Two alternatives were evaluated to address the purpose and needs identified for this project.
These include the No-Build Alternative and the Build Alternative. The Build Alternative, based
on recommendations of the Safety Study, implements improvements to all the study intersections
along SR 26.
SR 26 at I-75 Southbound Ramps
• Westbound direction: provide two left turn lanes
• Northbound direction: provide two right turn lanes and convert the through lane to a
shared through/left turn lane
SR 26 at I-75 Northbound On-Ramp
• Eastbound direction: provide two left turn lanes
• Westbound direction: convert shared through/right turn lane to through lane and add one
right turn lane
SR 26 at NW 69th Terrace
• Eastbound direction: provide two left turn lanes
Based on the evaluations of the No-Build and Build Alternatives, the recommended alternative,
for approval in this study, is the Build Alternative. However by the Design Year 2029, the
![Page 7: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/7.jpg)
EXECUTIVE SUMMARY I-75 at SR 26 IOAR
proposed improvements will not provide acceptable level of service (LOS) at the study
intersections. So, it is recommended that ultimate improvements be analyzed to address future
traffic growth in the study area.
This IOAR has been developed in accordance with the FDOT Policy No. 000-525-015: Approval
of New or Modified Access to Highways on the Strategic Intermodal System (SIS), FDOT
Procedure No. 525-030-160: Approval of New or Modified interchange access to limited access
facilities on SIS, Interchange Access Request User’s Guide (IARUG), and the FDOT Traffic
Forecasting Handbook (Procedure No. 525-030-120).
Compliance with FHWA General Requirements
The following requirements serve as the primary decision criteria used in approval of
interchange access requests. Responses to each of the Federal Highway Administration (FHWA)
two policy points are provided to show that the proposed modification for the I-75 at SR 26
interchange is viable based on the conceptual analysis performed to date.
FHWA Policy Point 1
An operational and safety analysis has concluded that the proposed change in access does not
have a significant adverse impact on the safety and operation of the Interstate facility (which
includes mainline lanes, existing, new, or modified ramps, ramp intersections with crossroad) or
on the local street network based on both the current and the planned future traffic projections.
The analysis should, particularly in urbanized areas, include at least the first adjacent existing
or proposed interchange on either side of the proposed change in access (23 CFR 625.2(a),
655.603(d) and 771.111(f)). The crossroads and the local street network, to at least the first
major intersection on either side of the proposed change in access, should be included in this
analysis to the extent necessary to fully evaluate the safety and operational impacts that the
proposed change in access and other transportation improvements may have on the local street
network (23 CFR 625.2(a) and 655.603(d)). Requests for a proposed change in access should
include a description and assessment of the impacts and ability of the proposed changes to safely
and efficiently collect distribute, and accommodate traffic on the Interstate facility, ramps,
intersection of ramps with crossroad, and local street network (23 CFR 625.2(a) and
655.603(d)). Each request should also include a conceptual plan of the type and location of the
signs proposed to support each design alternative (23 U.S.C. 109(d) and 23 CFR 655.603(d)).
An in‐depth operational and safety analysis was conducted to study the impacts of the proposed
improvements at the I-75/SR 26 interchange. Several performance measures were used to
compare the operations of the existing system under No-Build and Build conditions. Key
measures included delay, Level of Service (LOS) and 95th Percentile Queues for existing and
proposed conditions.
Operational analysis conducted for the short term improvements confirm that the proposed
modifications are not expected to have significant adverse impacts on safety or operations at the
![Page 8: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/8.jpg)
EXECUTIVE SUMMARY I-75 at SR 26 IOAR
I-75/SR 26 interchange and adjacent intersections. When compared to the No-Build Alternative,
the proposed short term improvements will provide up to a 61% reduction in delay at the study
intersections, and will provide up to a 73% reduction in queuing at the study intersections in the
Design Year 2029.
The short term improvements at the study intersections are, also, expected to reduce the number
of collisions at the study intersections, and not have an adverse impact on safety. Using Crash
Modification Factors (CMFs) from the CMF Clearinghouse, a predicted number of crashes was
calculated after the implementation of the improvements. Based on the application of the CMFs
to the study intersections, a 12% reduction in crashes is expected.
The I-75 at SR 26 IOAR will not involve any new mainline access points or change in the
current access locations. The proposed short term improvements are only being applied to the
study intersections. Hence, no analysis was performed for the I-75 mainline, I-75 ramps or
adjacent ramps. Also, the existing signing plan along I-75 and SR 26 will be adequate for the
proposed improvements. A new conceptual signing plan is not required for these improvements.
FHWA Policy Point 2
The proposed access connects to a public road only and will provide for all traffic movements.
Less than “full interchanges” may be considered on a case-by-case basis for applications
requiring special access, such as managed lanes (e.g., transit, HOVs, HOT lanes) or park and
ride lots. The proposed access will be designed to meet or exceed current standards (23 CFR
625.2(a), 625.4(a)(2), and 655.603(d)). In rare instances where all basic movements are not
provided by the proposed design, the report should include a full-interchange option with a
comparison of the operational and safety analyses to the partial-interchange option. The report
should also include the mitigation proposed to compensate for the missing movements, including
wayfinding signage, impacts on local intersections, mitigation of driver expectation leading to
wrong-way movements on ramps, etc. The report should describe whether future provision of a
full interchange is precluded by the proposed design.
The proposed short term improvements to the I-75 at SR 26 interchange and adjacent
intersections will provide full access and cater to all traffic movements from SR 26 to and from
I-75. The proposed modifications are designed to meet current standards for federal-aid projects
on the interstate system and conform to American Association of State Highway and
Transportation Officials (AASHTO) and the FDOT design standards.
![Page 9: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/9.jpg)
TABLE OF CONTENTS I-75 at SR 26 IOAR
Table of Contents
1. INTRODUCTION................................................................................................................. 1
1.1. BACKGROUND ............................................................................................................................................. 1
1.2. PURPOSE AND NEED .................................................................................................................................... 1
1.3. PROJECT LOCATION ..................................................................................................................................... 1
2. METHODOLOGY ............................................................................................................... 3
2.1. AREA OF INFLUENCE ................................................................................................................................... 3
2.2. ANALYSIS YEARS ........................................................................................................................................ 3
2.3. DATA COLLECTION AND SOURCES .............................................................................................................. 3
2.4. TRAVEL DEMAND FORECASTING................................................................................................................. 4
2.5. OPERATIONAL ANALYSIS PROCEDURES ...................................................................................................... 4
2.6. LOS CRITERIA ............................................................................................................................................ 4
3. EXISTING CONDITIONS .................................................................................................. 5
3.1. TYPICAL SECTIONS ...................................................................................................................................... 5
3.2. STUDY INTERCHANGE ................................................................................................................................. 5
3.3. INTERSECTION GEOMETRY .......................................................................................................................... 6
3.4. EXISTING OPERATIONAL PERFORMANCE..................................................................................................... 7
4. NEED ................................................................................................................................... 21
5. FUTURE NO-BUILD CONDITIONS .............................................................................. 22
5.1. FUTURE TRAFFIC FORECAST ..................................................................................................................... 22
5.2. OPERATIONAL ANALYSIS .......................................................................................................................... 23
6. BUILD CONDITIONS ....................................................................................................... 33
6.1. BUILD ALTERNATIVE ................................................................................................................................ 33
6.2. OPERATIONAL ANALYSIS .......................................................................................................................... 34
6.3. PREDICTIVE SAFETY ANALYSIS ................................................................................................................. 43
7. EVALUATON OF ALTERNATIVES .............................................................................. 44
7.1. COMPLIANCE WITH POLICIES AND ENGINEERING STANDARDS .................................................................. 44
7.2. ALTERNATIVES COMPARISON ................................................................................................................... 44
7.3. DESIGN EXCEPTIONS AND VARIATIONS ..................................................................................................... 45
7.4. SUMMARY AND RECOMMENDATIONS ........................................................................................................ 45
8. JUSTIFICATION ............................................................................................................... 46
8.1. COMPLIANCE WITH FHWA GENERAL REQUIREMENTS ............................................................................. 46
9. CONCEPTUAL FUNDING PLAN/CONSTRUCTION SCHEDULE .......................... 48
![Page 10: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/10.jpg)
TABLE OF CONTENTS I-75 at SR 26 IOAR
List of Figures Figure 1-1: Project Location and Area of Influence Map ............................................................... 2
Figure 3-1: I-75 at SR 26 Existing Layout...................................................................................... 5
Figure 3-2: Existing Lane Configuration ...................................................................................... 11
Figure 3-3: Existing Year 2018 Peak Hour Volumes and LOS .................................................... 12
Figure 3-4: SR 26 at NW 75th Street Crash Types (2012-2016) ................................................... 14
Figure 3-5: SR 26 at Southbound Ramps Crash Types (2012-2016) ........................................... 15
Figure 3-6: SR 26 at Northbound Off-Ramp Crash Types (2012-2016) ...................................... 16
Figure 3-7: SR 26 at Northbound On-Ramp Crash Types (2012-2016) ....................................... 18
Figure 3-8: SR 26 at NW 69th Terrace Crash Types (2012-2016) ................................................ 19
Figure 5-1: No-Build Lane Configuration .................................................................................... 30
Figure 5-2: Opening Year 2019 No-Build Peak Hour Volumes and LOS ................................... 31
Figure 5-3: Design Year 2029 No-Build Peak Hour Volumes and LOS ...................................... 32
Figure 6-1: Build Lane Configuration .......................................................................................... 40
Figure 6-2: Opening Year 2019 Build Peak Hour Volumes and LOS ......................................... 41
Figure 6-3: Design Year 2029 Build Peak Hour Volumes and LOS ............................................ 42
List of Tables Table 3-1: Existing Year 2018 Intersection Analysis Results ........................................................ 7
Table 3-2: Existing Year 2018 Signals Queuing Analysis Results .............................................. 10
Table 3-3: SR 26 at NW 75th Street Severity Summary (2012-2016) .......................................... 14
Table 3-4: SR 26 at Southbound Ramps Severity Summary (2012-2016) ................................... 15
Table 3-5: SR 26 at Northbound Off-Ramp Severity Summary (2012-2016) ............................. 17
Table 3-6: SR 26 at Northbound On-Ramp Severity Summary (2012-2016) .............................. 18
Table 3-7: SR 26 at NW 69th Terrace Severity Summary (2012-2016) ....................................... 19
Table 3-8: Study Intersection Crash Summary (2012-2016) ........................................................ 20
Table 5-1: FTI Historic Counts Growth Rate ............................................................................... 22
Table 5-2: Gainesville MTPO Model Growth Rate ...................................................................... 23
Table 5-3: RSM Growth Rate ....................................................................................................... 23
Table 5-4: Opening Year 2019 No-Build Intersection Analysis Results ........................................ 24
Table 5-5: Design Year 2029 No-Build Intersection Analysis Results ....................................... 25
Table 5-6: Opening Year 2019 No-Build Signals Queuing Analysis Results ............................. 27
Table 5-7: Design Year 2029 No-Build Signals Queuing Analysis Results ............................... 29
Table 6-1: Opening Year 2019 Build Intersection Analysis Results .............................................. 34
Table 6-2: Design Year 2029 Build Intersection Analysis Results ............................................. 35
Table 6-3: Opening Year 2019 Build Signals Queuing Analysis Results ................................... 37
Table 6-4: Design Year 2029 Build Signals Queuing Analysis Results ...................................... 39
Table 6-5: Reduction in Crashes .................................................................................................. 43
Table 7-1: Design Year 2029 No-Build and Build Alternatives Intersections Comparison........ 44
![Page 11: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/11.jpg)
TABLE OF CONTENTS I-75 at SR 26 IOAR
List of Appendices
Appendix A: FDOT Safety Study for SR 26 from NW 75th Street to NW 69th Terrace
Appendix B: Existing Year 2018 Alternative Synchro Operational Analysis
Appendix C: Raw Crash Data
Appendix D: 2019 and 2029 No-Build Alternative Synchro Operational Analysis
Appendix E: 2019 and 2029 Build Alternative Synchro Operational Analysis
Appendix F: Build Concept Figure
![Page 12: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/12.jpg)
1.0 INTRODUCTION I-75 at SR 26 IOAR
1
1. INTRODUCTION
1.1. Background The Florida Department of Transportation (FDOT) District Two is requesting approval for the
short term improvements to the I-75 at SR 26 interchange located within the City of Gainesville
in Alachua County. I-75 is a major north-south interstate in the state of Florida. I-75 is a major
commuter, tourist and trucking roadway that results in heavy passenger vehicle and truck traffic
on a daily occurrence. SR 26 (Newberry Road) is a major corridor with many retail, residential
and commercial properties adjacent to it such as the Oaks Mall.
This IOAR has been developed in accordance with the FDOT Policy No. 000-525-015: Approval
of New or Modified Access to Highways on the Strategic Intermodal System (SIS), FDOT
Procedure No. 525-030-160: Approval of New or Modified interchange access to limited access
facilities on SIS, Interchange Access Request User’s Guide (IARUG), and the FDOT Traffic
Forecasting Handbook (Procedure No. 525-030-120).
1.2. Purpose and Need The purpose of this study is to determine what short term enhancements can be programmed to
improve traffic operations, reduce congestion and improve safety at the ramp terminal
intersection and adjacent intersections. Short term improvements are aimed at increasing the
efficiency of the SR 26 intersections while minimizing or eliminating right-of-way and bridge
impacts. A Safety Study was completed by FDOT District 2 Traffic Operations Office in
October 2014 for the study interchange and adjacent intersections. The Safety Study identified
deficiencies at the intersections and recommended improvements aimed at improving operations
and safety.
The primary needs for this project is to improve safety and alleviate existing and future traffic
congestion and delay at the study intersections. If no improvements are made to the ramp
terminal intersections and adjacent intersections, traffic operations within the study area will
continue to deteriorate as traffic continues to grow.
1.3. Project Location The subject interchange is located in Alachua County along I-75 at Milepost 14.5, Section
number 26260000. The I-75 at SR 26 interchange is located between the I-75 at SR 24
interchange to the south and I-75 at SR 222 interchange to the north. The project location and the
study area are shown in Figure 1-1. The study area includes the following interchanges (as
shown in Figure 1-1):
STUDY INTERCHANGE: I-75 at SR 26
![Page 13: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/13.jpg)
!!
!!
!
±
Legend! Study Intersections
Influence Area0 0.07 0.14 0.210.035 Miles
![Page 14: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/14.jpg)
2.0 METHODOLOGY I-75 at SR 26 IOAR
3
2. METHODOLOGY
2.1. Area of Influence
The subject interchange is located in Alachua County’s urbanized area. The following major
interchange has been analyzed.
I-75 at SR 26 is located at milepost 14.5 (Section No. 26260000). I-75 is an Urban
Principal Arterial-Interstate and therefore this interchange is in an urbanized area.
The major study corridor is SR 26:
SR 26 is 5 lanes west of I-75 (3 lanes eastbound and 2 lanes westbound) and 6 lanes east
of I-75. SR 26 is a divided Urban Principal Arterial-Other within the study area and has a
speed limit of 35 miles per hour.
The area of influence includes the intersections associated with all SR 26 ramps. The ramp
terminal and adjacent intersections analyzed within the area of influence are listed below.
Intersections
o SR 26 at NW 75th Street
o SR 26 at Southbound On and Off-Ramps
o SR 26 at Northbound Off-Ramp
o SR 26 at Northbound On-Ramp
o SR 26 at NW 69th Terrace
The area of influence is shown in Figure 1-1.
2.2. Analysis Years The following study years are established for this IOAR:
Existing Year: 2018
Opening Year: 2019
Design Year: 2029
2.3. Data Collection and Sources Existing data was provided in the Safety Study (Appendix A) prepared in October 2014, by the
Florida Department of Transportation (Department), District 2 Traffic Operations Office. The
Safety Study’s purpose was to identify improvements at the study interchange and adjacent
intersections along SR 26 that would improve operations and safety.
Standard K and D factors were not needed for this report because traffic developed for this IOAR
was developed using growth rates applied to the existing traffic from the Safety Study. The
![Page 15: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/15.jpg)
2.0 METHODOLOGY I-75 at SR 26 IOAR
4
design hour truck percentage and peak hour factor were determined based on the traffic counts
performed as part of the 2014 Safety Study.
2.4. Travel Demand Forecasting The February 2014 traffic counts from the Safety Study were obtained for this IOAR and
checked for reasonableness. A growth rate was then applied to the traffic counts to develop
existing year, opening year and design year traffic volumes for the IOAR. The growth rate was
developed based on historic growth trends, the growth from the latest version of the Gainesville
Metropolitan Transportation Planning Organization (MTPO) Model and growth rate from the
Relief Study Model (RSM). Growth rate development and future traffic development are further
discussed in Section 5.
2.5. Operational Analysis Procedures Traffic operational analysis has been conducted for the analysis years for the No-Build and Build
Alternatives. Intersection analysis has been conducted for the study intersections using the most
recent version of Synchro.
2.6. LOS Criteria FDOT Topic No. 525-000-006 provides LOS targets for the State Highway System (SHS). The
term LOS is defined as the system of six designated ranges from “A” (best) to “F” (worst) used
to evaluate roadway facility performance. The FDOT minimum acceptable operating LOS
targets were used for this IOAR. The LOS target for study intersections analyzed in this IOAR
are summarized below:
Signalized Intersections: LOS D
![Page 16: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/16.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
5
3. EXISTING CONDITIONS This Section discusses the existing roadway and traffic conditions at the study interchange of I-
75 at SR 26.
3.1. Typical Sections The I-75 typical section at SR 26 consists of a six lane divided section providing three general
purpose lanes in both directions. I-75 is classified as an Urban Principal Arterial - Interstate. The
SR 26 typical section within the limits of the limited access right-of-way is a five lane urban
divided roadway with a raised landscaped median west of I-75 and a six lane urban divided
roadway with a raised landscaped median to the east of I-75. SR 26 is classified as an Urban
Principal Arterial - Other.
3.2. Study Interchange The study interchange is a partial diamond interchange with a loop ramp in the southwest
quadrant. An aerial of the interchange is provided in Figure 3-1.
Figure 3-1: I-75 at SR 26 Existing Layout
NW
75
th S
tree
t
26
NW
69
th T
erra
ce
Newberry Road
![Page 17: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/17.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
6
3.3. Intersection Geometry The study intersections that will be analyzed as part of this IOAR include:
SR 26 at NW 75th Street
SR 26 at I-75 Southbound Ramps
SR 26 at I-75 Northbound Off-Ramp
SR 26 at I-75 Northbound On-Ramp
SR 26 at NW 69th Terrace
The SR 26 at NW 75th Street intersection is a four-leg signalized intersection. The intersection is
located approximately 1,000 feet west of I-75. The intersection has the following lane
configuration.
Eastbound direction: one left turn lanes, two through lanes and one shared through/right
turn lane
Westbound direction: two left turn lanes, one through lane and one shared through/right
turn lane
Northbound direction: one shared through/left turn lane and two right turn lanes
Southbound direction: one shared left/through/right turn lane
The SR 26 at I-75 Southbound Ramps is a four-leg signalized intersection. This is a ramp
terminal intersection. The intersection has the following lane configuration.
Eastbound direction: one left turn lane, three through lanes and one right turn lane
Westbound direction: one left turn lane, two through lanes and one shared through/right
turn lane
Northbound direction: one left turn lane, one through lane and one right turn lane
Southbound direction: one left turn lane and one shared through/right turn lane
The SR 26 at I-75 Northbound Off-Ramp is a three-leg signalized intersection. This is a ramp
terminal intersection. The intersection has the following lane configuration.
Eastbound direction: three through lanes
Westbound direction: three through lanes
Northbound direction: two left turn lanes and two right turn lanes
The SR 26 at I-75 Northbound On-Ramp is a two-leg signalized intersection. This is a ramp
terminal intersection. The intersection has the following lane configuration.
Eastbound direction: one left turn lane and three through lanes
Westbound direction: two through lanes and one shared through/right turn lane
![Page 18: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/18.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
7
The SR 26 at NW 69th Terrace intersection is a four-leg signalized intersection. The intersection
is located approximately 750 feet east of I-75. The intersection has the following lane
configuration.
Eastbound direction: one left turn lane, two through lanes and one shared through/right
turn lane
Westbound direction: one left turn lane, two through lanes and one shared through/right
turn lane
Northbound direction: one shared through/left turn lane and one right turn lane
Southbound direction: one shared through/left turn lane and one right turn lane
The existing lane configuration is provided in Figure 3-2.
3.4. Existing Operational Performance This section summarizes the existing traffic and operational analysis performed within the area
of influence to assess the mobility conditions. This facility accommodates interstate and regional
mobility for commuter and freight traffic.
3.4.1. Existing Traffic Data
A Safety Study was completed in October 2014 for the study interchange. The Safety Study has
an Existing Year of 2014 and provides traffic volumes for the study intersections. For this
IOAR, the Existing Year 2018 traffic development methodology required a growth rate of 1% be
applied to the Safety Study’s existing year 2014 traffic volumes. Further discussion of the
growth rate development is provided in Section 5.1. The Existing Year 2018 traffic volumes are
provided in Figure 3-3.
3.4.2. Operational Analysis
Existing Year 2018 Intersections Analysis
The results of the intersections analysis for Existing Year 2018 are shown in Figure 3-4 and
Table 3-1. Documentation of the Existing Year analysis is provided in Appendix B.
Table 3-1: Existing Year 2018 Intersection Analysis Results
Intersection
AM Peak Hour PM Peak Hour
Delay
(sec) LOS
Delay
(sec) LOS
SR 26 at NW 75th Street 82.8 F 57.6 E
SR 26 at Southbound Ramps 79.1 E 37.4 D
SR 26 at Northbound Off-Ramp 31.7 C 38.9 D
SR 26 at Northbound On-Ramp 13.9 B 10.7 B
SR 26 at NW 69th Terrace 54.8 D 59.1 E
![Page 19: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/19.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
8
The Existing Year 2018 intersection analysis shows that the Northbound Off-Ramp and
Northbound On-Ramp intersections operate at LOS D or better in the AM and PM peak hours.
The NW 75th Street, Southbound Ramps and NW 69th Terrace intersections operate below LOS
D in the AM and/or PM peak hours. Multiple movements operate at LOS F during the AM
and/or PM peak hours in the existing conditions. The following movements operate at LOS F.
SR 26 at NW 75th Street
o Eastbound left (PM peak hour)
o Eastbound through (AM peak hour)
o Westbound left (AM and PM peak hours)
o Northbound through (AM and PM peak hours)
o Southbound through (AM and PM peak hours)
SR 26 at Southbound Ramps
o Eastbound left (PM peak hour)
o Westbound left (AM and PM peak hours)
o Northbound left (PM peak hour)
o Northbound right (AM peak hour)
SR 26 at Northbound Off-Ramp
o Northbound left (AM and PM peak hours)
o Northbound right (AM and PM peak hours)
SR 26 at Northbound On-Ramp
o Eastbound left (PM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM and PM peak hours)
o Westbound through (AM peak hour)
o Southbound through (AM peak hour)
o Southbound right (PM peak hour)
![Page 20: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/20.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
9
Existing Year 2018 Queuing Analysis
Table 3-2 summarizes the results of the study intersections 95th percentile queue analysis for the
AM and PM peak hours. In order to provide operationally efficient and safe conditions, queuing
needs to be within the provided storage. The following movement’s queues are beyond the
available storage:
SR 26 at NW 75th Street
o Eastbound through (AM and PM peak hours)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
SR 26 at Southbound Ramps
o Eastbound through (AM peak hour)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
o Northbound left (AM and PM peak hours)
o Northbound right (AM peak hour)
SR 26 at Northbound On-Ramp
o Eastbound left (PM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM peak hour)
o Eastbound through (AM peak hour)
o Westbound through (PM peak hour)
o Southbound right (PM peak hour)
No queues at the ramp terminals back up to the I-75 mainline.
![Page 21: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/21.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
10
Table 3-2: Existing Year 2018 Signals Queuing Analysis Results
Intersection Time
Period
Eastbound Westbound Northbound Southbound
Left Through Right Left Through Right Left Through Right Left Through Right
SR 26 at
NW 75th
Street
AM
Peak 29 #765 #569 127 #375 #814 96
PM
Peak 80 476 #577 #1167 #620 133 139
Existing
Storage
(feet)
240 415 415 500 650 650 670 - - 150
SR 26 at
Southbound
Ramps
AM
Peak m25 m774 m0 #381 m191 #293 25 #965 41 31
PM
Peak m16 204 m18 m#728 m434 #278 11 59 28 54
Existing
Storage
(feet)
250 670 600 160 420 420 150 - 150 85 85
SR 26 at
Northbound
Off-Ramp
AM
Peak m118 53 #309 #437
PM
Peak 145 61 #581 #340
Existing
Storage
(feet)
- 420 - - 250 - 930 - 1,200 - - -
SR 26 at
Northbound
On-Ramp
AM
Peak m136 m0 m105
PM
Peak 325 m0 m168
Existing
Storage
(feet)
240 - - - 225 225 - - - - - -
SR 26 at
NW 69th
Terrace
AM
Peak #788 782 48 #558 76 0 139 47
PM
Peak #169 477 145 890 171 53 195 #752
Existing
Storage
(feet)
250 520 520 185 740 740 190 190 190 - - 265
# 95th percentile volume exceeds capacity, queue may be longer.
m - Queue is metered by the upstream intersection.
![Page 22: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/22.jpg)
Legend:
Exis ng Lanes
Study Intersec on
SR 26
NW 75th St.
Figure 3‐2 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off Ra
mps
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
SR 26
NW 69th Terr.
Exis ng Lane Configura on
![Page 23: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/23.jpg)
198 (205) 1,555 (829)
157 (266
)
2,963 (1,649)
Delay: 82.8 (57.6)
LOS: F (E)
Legend:
XXX (XXX): 2018 AM (PM) Volumes
Delay: Seconds per vehicle
LOS: A‐F
: Study Intersec on
SR 26
NW 75th St.
Figure 3‐3 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
NW 69th Terr.
Exis ng Year 2018 Peak Hour Volumes and LOS
7 (8)
1,23
9 (827
)
9 (34)
157 (261)
2 (14)
31 (3
7)
17 (2
7)
620 (1,564) 22 (50)
734 (875)
2,374 (1,500)
26 (1
00)
11 (2
) 7 (98)
550 (85)
35 (79)
76 (1
14)
1,148 (2,296) 186 (39)
18 (81)
2 (4)
122 (371
)
1,068 (2,106)
239 (583)
354 (641
) 46
7 (337
)
1,058 (2,119)
2,718 (1,547)
1,157 (2,340)
170 (351)
2,165 (1,240)
677 (437)
168 (180
) 7 (2)
554 (285
)
Delay: 13.9 (10.7)
LOS: B (B)
Delay: 31.7 (38.9)
LOS: C (D)
Delay: 54.8 (59.1)
LOS: D (E)
23 (10) 11
(3)
5 (20)
19 (1
1)
25 (32)
Delay: 79.1 (37.4)
LOS: E (D)
![Page 24: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/24.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
13
3.4.3. Crash and Safety Information
Vehicular crash data along SR 26 was obtained from the FDOT State Safety Office Map Based
Query Tool (SSOGis). SSOGis is a database maintained annually by FDOT for crashes reported
along state highway facilities. The database provides information on various characteristics
associated with each crash including: collision type, severity, weather conditions, road surface
conditions and date/time information. The crash data was collected for the most recent five years
available (2012-2016). The crashes were analyzed to make an assessment of safety conditions at
the intersections within the project limits. The existing crash analysis performed for this IOAR is
consistent with the methods outlined in the Highway Safety Manual 1st Edition (HSM). In this
section, the existing crash analysis will be broken down between the study intersections. The raw
crash data is provided in Appendix C.
The existing crashes were first segmented based on intersection segmentation outlined in Chapter
12 of the HSM. After segmenting the study intersections, the crash frequency and crash rate were
calculated for each intersection. The ‘Average Crash Rate Method’ of crash analysis, based on
AADT and number of crashes occurred, was used for calculating actual crash rate for the
roadway segments. The actual crash rate for the study corridors from year 2012 to 2016 was
compared with the statewide average crash rate for the same type of facility. All the study
intersections in the study area have a crash rate higher than the statewide average except at the
SR 26 at Northbound On-Ramp intersection.
SR 26 at NW 75th Street
The crash analysis results reveal that there was a total of 114 crashes at the SR 26/NW 75th Street
intersection during the five study years (2012-2016). Of these 114 crashes, front to rear (rear
end) were the most common type of crash accounting for 47% of total crashes followed by angle
crashes accounting for 26% of total crashes at this intersection. There were 46 total injuries and
no fatalities. The average crash rate for this intersection is higher than the statewide average
crash rate for similar facilities. Summaries of the crash analysis are provided in Figure 3-4,
Table 3-3 and Table 3-8.
![Page 25: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/25.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
14
Figure 3-4: SR 26 at NW 75th Street Crash Types (2012-2016)
Table 3-3: SR 26 at NW 75th Street Severity Summary (2012-2016)
Injury Type 2012 2013 2014 2015 2016 Total Percent
of Total
Number of
Property
Damage Only
Crashes
13 21 22 13 9 78 68%
Number of
Crashes
with Injuries
5 7 9 5 10 36 32%
Number of
Crashes
with Fatalities
0 0 0 0 0 0 0%
Total 18 28 31 18 19 114 100%
Number of
Injuries 7 7 11 9 12 46
Number of
Fatalities 0 0 0 0 0 0
SR 26 at Southbound Ramps
The crash analysis results reveal that there was a total of 106 crashes at the SR 26/Southbound
Ramps intersection during the five study years (2012-2016). Of these 106 crashes, front to rear
(rear end) were the most common type of crash accounting for 49% of total crashes followed by
angle crashes accounting for 30% of total crashes at this intersection. There were 73 total injuries
47%
4%
26%
14%
1%
2%0%
6%
0%
Crash Type at NW 75th Street
Front to Rear (Rear End)
Front to Front
Angle
Sideswipe, same direction
Sideswipe, opposite direction
Rear to Side
Rear to Rear
Other
Unknown
![Page 26: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/26.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
15
and no fatalities. The average crash rate for this intersection is higher than the statewide average
crash rate for similar facilities. Summaries of the crash analysis are provided in Figure 3-5,
Table 3-4 and Table 3-8.
Figure 3-5: SR 26 at Southbound Ramps Crash Types (2012-2016)
Table 3-4: SR 26 at Southbound Ramps Severity Summary (2012-2016)
Injury Type 2012 2013 2014 2015 2016 Total Percent
of Total
Number of
Property
Damage Only
Crashes
17 5 13 16 9 60 57%
Number of
Crashes
with Injuries
14 4 5 14 9 46 43%
Number of
Crashes
with Fatalities
0 0 0 0 0 0 0%
Total 31 9 18 30 18 106 100%
Number of
Injuries 20 6 9 27 11 73
Number of
Fatalities 0 0 0 0 0 0
49%
2%
30%
9%
2%0% 0%
8%
0%
Crash Type at Southbound Ramps
Front to Rear (Rear End)
Front to Front
Angle
Sideswipe, same direction
Sideswipe, opposite direction
Rear to Side
Rear to Rear
Other
Unknown
![Page 27: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/27.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
16
SR 26 at Northbound Off-Ramp
The crash analysis results reveal that there was a total of 125 crashes at the SR 26/Northbound
Off-Ramp intersection during the five study years (2012-2016). Of these 125 crashes, front to
rear (rear end) were the most common type of crash accounting for 54% of total crashes followed
by angle crashes accounting for 19% of total crashes at this intersection. There were 62 total
injuries and no fatalities. The average crash rate for this intersection is higher than the statewide
average crash rate for similar facilities. Summaries of the crash analysis are provided in Figure
3-6, Table 3-5 and Table 3-8.
Figure 3-6: SR 26 at Northbound Off-Ramp Crash Types (2012-2016)
54%
0%
19%
18%
0%
0%
0%9%
0%
Crash Type at Northbound Off-Ramp
Front to Rear (Rear End)
Front to Front
Angle
Sideswipe, same direction
Sideswipe, opposite direction
Rear to Side
Rear to Rear
Other
Unknown
![Page 28: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/28.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
17
Table 3-5: SR 26 at Northbound Off-Ramp Severity Summary (2012-2016)
Injury Type 2012 2013 2014 2015 2016 Total Percent
of Total
Number of
Property
Damage Only
Crashes
18 15 8 17 29 87 70%
Number of
Crashes
with Injuries
8 9 4 9 8 38 30%
Number of
Crashes
with Fatalities
0 0 0 0 0 0 0%
Total 26 24 12 26 37 125 100%
Number of
Injuries 12 18 9 12 11 62
Number of
Fatalities 0 0 0 0 0 0
SR 26 at Northbound On-Ramp
The crash analysis results reveal that there was a total of 23 crashes at the SR 26/Northbound
On-Ramp intersection during the five study years (2012-2016). Of these 23 crashes, front to rear
(rear end) were the most common type of crash accounting for 44% of total crashes followed by
angle crashes accounting for 22% of total crashes at this intersection. There were 10 total injuries
and no fatalities. The average crash rate for this intersection is not higher than the statewide
average crash rate for similar facilities. Summaries of the crash analysis are provided in Figure
3-7, Table 3-6 and Table 3-8.
![Page 29: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/29.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
18
Figure 3-7: SR 26 at Northbound On-Ramp Crash Types (2012-2016)
Table 3-6: SR 26 at Northbound On-Ramp Severity Summary (2012-2016)
Injury Type 2012 2013 2014 2015 2016 Total Percent
of Total
Number of
Property
Damage Only
Crashes
2 5 0 2 5 14 61%
Number of
Crashes
with Injuries
4 0 0 2 3 9 39%
Number of
Crashes
with Fatalities
0 0 0 0 0 0 0%
Total 6 5 0 4 8 23 100%
Number of
Injuries 4 0 0 2 4 10
Number of
Fatalities 0 0 0 0 0 0
SR 26 at NW 69th Terrace
The crash analysis results reveal that there was a total of 114 crashes at the SR 26/NW 69th
Terrace intersection during the five study years (2012-2016). Of these 114 crashes, front to rear
(rear end) were the most common type of crash accounting for 48% of total crashes followed by
angle crashes accounting for 24% of total crashes at this intersection. There were 76 total injuries
44%
0%
22%
17%
0%
0% 0%
17%
0%
Crash Type at Northbound On-Ramp
Front to Rear (Rear End)
Front to Front
Angle
Sideswipe, same direction
Sideswipe, opposite direction
Rear to Side
Rear to Rear
Other
Unknown
![Page 30: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/30.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
19
and no fatalities. The average crash rate for this intersection is higher than the statewide average
crash rate for similar facilities. Summaries of the crash analysis are provided in Figure 3-8,
Table 3-7 and Table 3-8.
Figure 3-8: SR 26 at NW 69th Terrace Crash Types (2012-2016)
Table 3-7: SR 26 at NW 69th Terrace Severity Summary (2012-2016)
Injury Type 2012 2013 2014 2015 2016 Total Percent
of Total
Number of
Property
Damage Only
Crashes
20 12 10 31 4 77 68%
Number of
Crashes
with Injuries
15 7 5 7 3 37 32%
Number of
Crashes
with Fatalities
0 0 0 0 0 0 0%
Total 35 19 15 38 7 114 100%
Number of
Injuries 27 23 5 13 8 76
Number of
Fatalities 0 0 0 0 0 0
Table 3-8 further summarizes the existing crash data, and provides the crash frequency and rate
at each of the study intersections.
48%
2%
24%
18%
0%
1%1%
6%
0%
Crash Type at NW 69th Terrace
Front to Rear (Rear End)
Front to Front
Angle
Sideswipe, same direction
Sideswipe, opposite direction
Rear to Side
Rear to Rear
Other
Unknown
![Page 31: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/31.jpg)
3.0 EXISTING CONDITIONS I-75 at SR 26 IMR
20
Table 3-8: Study Intersection Crash Summary (2012-2016)
Intersection
Number
of
Crashes
Daily
Entering
(AADT)1
Crash
Frequency
Cash Rate
(crashes/million entering)
Statewide
Average
Crash
Rate
SR 26 at NW 75th
Street 114 34,737 22.8 1.798 0.799
SR 26 at Southbound
Ramps 106 39,477 21.2 1.471 0.484
SR 26 at Northbound
Off-Ramp 125 38,927 25.0 1.760 0.484
SR 26 at Northbound
On-Ramp 23 47,587 4.6 0.265 0.484
SR 26 at NW 69th
Terrace 114 49,048 22.8 1.274 0.799
1 – Average of the AADT based on location provided in Raw Crash Data
3.4.4. Consistency with Master Plans, LRTP and DRIs
The latest adopted transportation programs and plans available were reviewed and are consistent
with the IOAR.
FDOT Five-Year Work Program
Local Government Comprehensive Plans
FDOT’s Strategic Intermodal System Plans
Any other studies or Master Plans
![Page 32: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/32.jpg)
4.0 NEED I-75 at SR 26 IOAR
21
4. NEED The I-75 at SR 26 interchange is an important connection for commuters, dining and retail in the
region.
The goal of this project is to improve traffic operations and safety at the study intersections
through implementation of operational and capacity improvements that will maintain and
improve mobility, support existing and future development and enhance emergency evacuation
and response times.
The need for the project is based on the following factors:
Transportation Capacity
Currently, the I-75 at SR 26 interchange is the major access point for the City of Gainesville. It
currently experiences heavy congestion and due to this, queues form at the off ramps and
between intersections at the study interchange.
As a result, future traffic demand on this major arterial will need to be addressed.
Existing Safety Concerns
The study intersections have been a prime safety concern to FDOT for some time. A review of
the Department’s High Crash intersection and segment lists was conducted as part of this IMR.
The high crash location lists do not go beyond the year 2013. The segment list indicated that SR
26 was identified as a high crash segment from 2010-2013. Also, all of the study intersections
were listed as high crash intersections from 2011-2013. In order to address these major safety
concerns along SR 26 and at the study intersections, a Safety Study was performed in October of
2014. Since the Safety Study was completed, safety has continued to be a major concern along
SR 26 and at the study intersections.
As a result, improvements to the SR 26 arterial need to be implemented to address the existing
safety concerns.
Emergency Evacuation and Response Times
I‐75 serves as part of the emergency evacuation route network designated by the Florida Division
of Emergency Management. As designated evacuation facility this roadway is critical in
facilitating traffic flow during emergency evacuation periods.
![Page 33: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/33.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
22
5. FUTURE NO-BUILD CONDITIONS This section documents the future conditions within the I-75 at SR 26 interchange area of
influence for the No-Build Alternative. The No-Build Alternative assumes the existing plus
committed roadway network. At this time, there are no committed roadway projects, so, the No-
Build will match existing conditions.
The No-Build lane configuration is provided in Figure 5-1.
The analysis years considered under the No-Build Alternative are Opening Year 2019 and
Design Year 2029. The operational analysis includes the future year peak hour traffic forecasts
for the area of influence. The primary objective of this analysis was to establish the No-Build
operational conditions at the study interchange and intersections.
5.1. Future Traffic Forecast In order to develop future volumes, a compound annual growth rate for the entire project area
was developed. The growth rates from the FTI historical counts, Gainesville MTPO model and
the RSM were summarized and compared. The RSM was developed as part of the recently
completed North I-75 Master Plan. The RSM is based on the latest socio-economic data obtained
from the local Metropolitan Planning Organizations (MPOs). The final growth rate was based on
the comparison of these sources. The final growth rate was decided because it provided the best
representation of the traffic trends in the area. A compound annual growth rate of 1.0% was
applied to the Existing Year traffic to develop the 2019 and 2029 traffic. Table 5-1, Table 5-2
and Table 5-3 provide a summary of the growth rate development.
Table 5-1: FTI Historic Counts Growth Rate
Description 2014 AADT 2016 AADT CAGR1
SR 26 W of I-75 49,500 51,000 1.5%
SR 26 E of I-75 50,000 49,500 -0.5%
SR 26 E of NW 69th Terrace - - -
I-75 SB On-Ramp 8,100 7,000 -7.0%
I-75 NB Off-Ramp 8,500 9,000 2.9%
I-75 SB Off-Ramp 5,300 4,800 -4.8%
I-75 NB On-Ramp 5,300 5,500 1.9% 1. CAGR = Compound Annual Growth Rate
![Page 34: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/34.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
23
Table 5-2: Gainesville MTPO Model Growth Rate
Description 2010 AADT 2040 AADT CAGR1
SR 26 W of I-75 59,889 67,761 0.4%
SR 26 E of I-75 59,037 67,686 0.5%
SR 26 E of NW 69th Terrace 52,307 60,099 0.5%
I-75 SB On-Ramp 9,458 8,985 -0.2%
I-75 NB Off-Ramp 8,988 8,496 -0.2%
I-75 SB Off-Ramp 8,799 9,700 0.3%
I-75 NB On-Ramp 8,613 9,998 0.5% 1. CAGR = Compound Annual Growth Rate
Table 5-3: RSM Growth Rate
Description 2015 AADT 2040 AADT CAGR1
I-75 N of I-10 74,400 106,600 1.4%
Ramps N of I-10 15,200 19,500 1.0%
Ramps S of I-10 20,400 32,900 1.9%
I-75 S of I-10 79,600 120,000 1.7% 1. CAGR = Compound Annual Growth Rate
The percentage splits in future years were kept same as existing. The final 2019 and 2029 traffic
was balanced and checked for reasonableness.
Opening Year 2019 and Design Year 2029 traffic is shown in Figure 5-2 and Figure 5-3
respectively.
5.2. Operational Analysis Opening Year 2019 and Design Year 2029 No-Build Intersections Analysis
Intersection analysis was performed for Opening Year 2019 and Design Year 2029 using the
latest version of Synchro. Intersection analysis was performed for the study intersections. All the
study intersections are signalized. Delay and LOS were reported for the intersections as
Measures of Effectiveness (MOEs) used in evaluation. The results of the intersection analysis for
Opening Year 2019 and Design Year 2029 are shown in Figure 5-2 and Figure 5-3 and Table 5-
4 and Table 5-5 respectively. Documentation of the No-Build Alternative analysis is provided in
Appendix D.
![Page 35: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/35.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
24
Table 5-4: Opening Year 2019 No-Build Intersection Analysis Results
Intersection
AM Peak Hour PM Peak Hour
Delay
(sec) LOS
Delay
(sec) LOS
SR 26 at NW 75th Street 83.7 F 76.0 E
SR 26 at Southbound Ramps 80.4 F 46.2 D
SR 26 at Northbound Off-Ramp 32.8 C 39.1 D
SR 26 at Northbound On-Ramp 17.3 B 23.1 C
SR 26 at NW 69th Terrace 56.7 E 61.8 E
The Opening Year 2019 intersection analysis shows that the Northbound Off-Ramp and
Northbound On-Ramp intersections operate at LOS D or better in the AM and PM peak hours.
The NW 75th Street, Southbound Ramps and NW 69th Terrace intersections operate below LOS
D in the AM and/or PM peak hours. Multiple movements operate at LOS F during the AM
and/or PM peak hours with the existing conditions; the following movements operate at LOS F.
SR 26 at NW 75th Street
o Eastbound left (PM peak hour)
o Eastbound through (AM peak hour)
o Westbound left (AM and PM peak hours)
o Northbound through (PM peak hour)
o Southbound through (AM and PM peak hours)
SR 26 at Southbound Ramps
o Eastbound left (PM peak hour)
o Westbound left (AM and PM peak hours)
o Northbound left (PM peak hour)
o Northbound right (AM peak hour)
SR 26 at Northbound Off-Ramp
o Northbound left (AM and PM peak hours)
o Northbound right (AM and PM peak hours)
SR 26 at Northbound On-Ramp
o Eastbound left (PM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM and PM peak hours)
o Westbound through (AM peak hour)
o Northbound through (PM peak hour)
o Southbound through (AM peak hour)
o Southbound right (PM peak hour)
![Page 36: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/36.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
25
Table 5-5: Design Year 2029 No-Build Intersection Analysis Results
Intersection
AM Peak Hour PM Peak Hour
Delay
(sec) LOS
Delay
(sec) LOS
SR 26 at NW 75th Street 102.7 F 92.1 F
SR 26 at Southbound Ramps 90.1 F 64.9 E
SR 26 at Northbound Off-Ramp 42.1 D 48.5 D
SR 26 at Northbound On-Ramp 35.8 D 30.2 C
SR 26 at NW 69th Terrace 81.3 F 76.6 E
The Design Year 2029 intersection analysis shows that the Northbound Off-Ramp and
Northbound On-Ramp intersections operate at LOS D or better in the AM and PM peak hours.
The NW 75th Street, Southbound Ramps and NW 69th Terrace intersections operate below LOS
D in the AM and/or PM peak hours. Multiple movements operate at LOS F during the AM
and/or PM peak hours with the existing conditions; the following movements operate at LOS F.
SR 26 at NW 75th Street
o Eastbound left (PM peak hour)
o Eastbound through (AM peak hour)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
o Northbound through (AM and PM peak hours)
o Northbound right (AM peak hour)
o Southbound through (AM and PM peak hours)
SR 26 at Southbound Ramps
o Eastbound left (PM peak hour)
o Westbound left (AM and PM peak hours)
o Northbound left (PM peak hour)
o Northbound right (AM peak hour)
SR 26 at Northbound Off-Ramp
o Northbound left (AM and PM peak hours)
o Northbound right (AM and PM peak hours)
SR 26 at Northbound On-Ramp
o Eastbound left (PM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM and PM peak hours)
o Westbound through (AM peak hour)
o Northbound through (PM peak hour)
o Southbound through (AM peak hour)
o Southbound right (PM peak hour)
![Page 37: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/37.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
26
Opening Year 2019 and Design Year 2029 No-Build Queuing Analysis
Table 5-6 and Table 5-7 summarizes the results of the study intersections 95th percentile queue
analysis for the AM and PM peak hours. In order to provide operationally efficient and safe
conditions queuing needs to be within the provided storage. The following movement’s queues
are beyond the available storage in Opening Year 2019:
SR 26 at NW 75th Street
o Eastbound through (AM and PM peak hours)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
SR 26 at Southbound Ramps
o Eastbound through (AM peak hour)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
o Northbound left (AM and PM peak hours)
o Northbound right (AM peak hour)
SR 26 at Northbound On-Ramp
o Eastbound left (PM peak hour)
o Westbound through (PM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM peak hour)
o Eastbound through (AM and PM peak hours)
o Westbound through (PM peak hour)
o Southbound right (PM peak hour)
No queues at the ramp terminals back up to the I-75 mainline. However, there are queues along
SR 26 that will back up into adjacent intersections affecting operations at adjacent intersections
such as the eastbound left queue at NW 69th Terrace.
![Page 38: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/38.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
27
Table 5-6: Opening Year 2019 No-Build Signals Queuing Analysis Results
Intersection Time
Period
Eastbound Westbound Northbound Southbound
Left Through Right Left Through Right Left Through Right Left Through Right
SR 26 at
NW 75th
Street
AM
Peak 29 #801 #606 118 #328 #764 96
PM
Peak 78 449 #671 #1208 #583 148 137
Existing
Storage
(feet)
240 415 415 500 650 650 670 - - 150
SR 26 at
Southbound
Ramps
AM
Peak m26 m858 m0 #374 m328 #286 25 #957 40 31
PM
Peak m15 284 14 m#734 m760 #277 11 58 28 53
Existing
Storage
(feet)
250 670 600 160 420 420 150 - 150 85 85
SR 26 at
Northbound
Off-Ramp
AM
Peak m110 53 #313 #443
PM
Peak 410 63 #561 #328
Existing
Storage
(feet)
- 420 - - 250 - 930 - 1,200 - - -
SR 26 at
Northbound
On-Ramp
AM
Peak m125 m0 m105
PM
Peak 324 m0 m282
Existing
Storage
(feet)
240 - - - 225 225 - - - - - -
SR 26 at
NW 69th
Terrace
AM
Peak #835 831 48 #569 76 0 142 48
PM
Peak #184 686 145 881 170 53 195 #753
Existing
Storage
(feet)
250 520 520 185 740 740 190 190 190 - - 265
# 95th percentile volume exceeds capacity, queue may be longer.
m - Queue is metered by the upstream intersection.
![Page 39: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/39.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
28
The following movement’s 95th percentile queues are beyond the available storage in Design
Year 2029:
SR 26 at NW 75th Street
o Eastbound through (AM and PM peak hours)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
SR 26 at Southbound Ramps
o Eastbound through (AM peak hour)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
o Northbound left (AM and PM peak hours)
o Northbound right (AM peak hour)
SR 26 at Northbound On-Ramp
o Eastbound left (PM peak hour)
o Westbound through (PM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM peak hour)
o Eastbound through (AM and PM peak hours)
o Westbound through (PM peak hour)
o Southbound right (PM peak hour)
No queues at the ramp terminals back up to the I-75 mainline. However, there are queues along
SR 26 that will back up into adjacent intersections affecting operations at adjacent intersections.
![Page 40: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/40.jpg)
5.0 FUTURE NO-BUILD CONDITIONS I-75 at SR 26 IOAR
29
Table 5-7: Design Year 2029 No-Build Signals Queuing Analysis Results
Intersection Time
Period
Eastbound Westbound Northbound Southbound
Left Through Right Left Through Right Left Through Right Left Through Right
SR 26 at
NW 75th
Street
AM
Peak 33 #919 #675 171 #422 #1001 102
PM
Peak 84 #575 m#694 m#1372 #701 196 148
Existing
Storage
(feet)
240 415 415 500 650 650 670 - - 150
SR 26 at
Southbound
Ramps
AM
Peak m25 m857 m0 #412 m324 #275 27 #1089 45 34
PM
Peak m16 m245 m8 m#804 m854 #333 11 61 30 57
Existing
Storage
(feet)
250 670 600 160 420 420 150 - 150 85 85
SR 26 at
Northbound
Off-Ramp
AM
Peak m237 53 #348 #500
PM
Peak 409 m66 #641 #380
Existing
Storage
(feet)
- 420 - - 250 - 930 - 1,200 - - -
SR 26 at
Northbound
On-Ramp
AM
Peak m127 m0 m146
PM
Peak 354 m0 m227
Existing
Storage
(feet)
240 - - - 225 225 - - - - - -
SR 26 at
NW 69th
Terrace
AM
Peak m#1099 #1247 52 #632 80 0 152 63
PM
Peak #213 749 #173 #1163 190 56 #219 #845
Existing
Storage
(feet)
250 520 520 185 740 740 190 190 190 - - 265
# 95th percentile volume exceeds capacity, queue may be longer.
m - Queue is metered by the upstream intersection.
![Page 41: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/41.jpg)
Legend:
Exis ng Lanes
Study Intersec on
SR 26
NW 75th St.
Figure 5‐1 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off Ra
mps
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
SR 26
NW 69th Terr.
No‐Build Lane Configura on
![Page 42: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/42.jpg)
200 (207) 1,571 (837)
159 (269
)
2,993 (1,665)
Delay: 83.7 (76.0)
LOS: F (E)
Legend:
XXX (XXX): 2019 AM (PM) Volumes
Delay: Seconds per vehicle
LOS: A‐F
: Study Intersec on
SR 26
NW 75th St.
Figure 5‐2 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
NW 69th Terr.
Opening Year 2019 No‐Build Peak Hour Volumes and LOS
7 (8)
1,25
1 (835
)
9 (34)
159 (264)
2 (14)
31 (3
7)
17 (2
7)
626 (1,580) 22 (51)
741 (884)
2,398 (1,515)
26 (1
01)
11 (2
) 7 (99)
556 (86)
35 (80)
77 (1
15)
1,159 (2,319) 188 (39)
18 (82)
2 (4)
123 (375
)
1,079 (2,127)
241 (589)
358 (647
) 47
2 (340
)
1,069 (2,140)
2,745 (1,562)
1,169 (2,363)
172 (355)
2,187 (1,252)
684 (441)
170 (182
) 7 (2)
560 (288
)
Delay: 17.3 (23.1)
LOS: B (C)
Delay: 32.8 (39.1)
LOS: C (D)
Delay: 56.7 (61.8)
LOS: E (E)
23 (10) 11
(3)
5 (20)
19 (1
1)
25 (32)
Delay: 80.4 (46.2)
LOS: F (D)
![Page 43: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/43.jpg)
221 (229) 1,735 (925)
176 (297
)
3,306 (1,839)
Delay: 102.7 (92.1)
LOS: F (F)
Legend:
XXX (XXX): 2029 AM (PM) Volumes
Delay: Seconds per vehicle
LOS: A‐F
: Study Intersec on
SR 26
NW 75th St.
Figure 5‐3 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
NW 69th Terr.
Design Year 2029 No‐Build Peak Hour Volumes and LOS
8 (9)
1,38
2 (922
)
10 (38)
176 (292)
2 (15)
34 (4
1)
19 (3
0)
691 (1,745) 24 (56)
819 (976)
2,649 (1,674)
29 (1
12)
12 (2
) 8 (109
)
614 (95)
39 (88)
85 (1
27)
1,280 (2,562) 208 (43)
20 (91)
2 (4)
136 (414
)
1,192 (2,350)
266 (651)
395 (715
) 52
1 (376
)
1,181 (2,364)
3,032 (1,725)
1,291 (2,610)
190 (392)
2,416 (1,383)
756 (487)
188 (201
) 8 (2)
619 (318
)
Delay: 35.8 (30.2)
LOS: D (C)
Delay: 42.1 (48.5)
LOS: D (D)
Delay: 81.3 (76.6)
LOS: F (E)
25 (11) 12
(3)
6 (22)
21 (1
2)
28 (35)
Delay: 90.1 (64.9)
LOS: F (E)
![Page 44: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/44.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
33
6. BUILD CONDITIONS
6.1. Build Alternative
The Build Alternative incorporates the following short term roadway improvements
recommended in this IOAR:
SR 26 at I-75 Southbound Ramps
Westbound direction: provide two left turn lanes
Northbound direction: provide two right turn lanes and convert the through lane to a
shared through/left turn lane
SR 26 at I-75 Northbound On-Ramp
Eastbound direction: provide two left turn lanes
Westbound direction: convert the shared through/right turn lane to through lane and add
one right turn lane
SR 26 at NW 69th Terrace
Eastbound direction: provide two left turn lanes
As part of the Build Alternative, all signals timings were optimized, and the yellow and all red
clearance intervals were increased per the current FDOT standards.
The Build Alternative lane configuration figure with all improvements shown in red is provided
in Figure 6-1. The travel demand forecast for the project assumes that the above improvements
would not impact overall future traffic flow patterns within the study. Therefore, the future year
peak hour turning movement volume forecasts for the No-Build Alternative are also evaluated
for the Build Alternative. Opening Year 2019 and Design Year 2029 traffic is shown in Figure
6-2 and Figure 6-3 respectively. The Build Alternative concept design is provided in Appendix
F.
![Page 45: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/45.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
34
6.2. Operational Analysis Opening Year 2019 and Design Year 2029 Build Intersections Analysis
The results of the intersections analysis for Opening Year 2019 and Design Year 2029 are shown
in Figure 6-2 and Figure 6-3 and Table 6-1 and Table 6-2 respectively. Documentation of the
Build Alternative analysis is provided in Appendix E.
Table 6-1: Opening Year 2019 Build Intersection Analysis Results
Intersection
AM Peak Hour PM Peak Hour
Delay
(sec) LOS
Delay
(sec) LOS
SR 26 at NW 75th Street 68.9 E 74.6 E
SR 26 at Southbound Ramps 26.5 C 26.2 C
SR 26 at Northbound Off-Ramp 22.8 C 34.8 C
SR 26 at Northbound On-Ramp 5.4 A 7.4 A
SR 26 at NW 69th Terrace 33.7 C 36.2 D
The Opening Year 2019 intersection analysis shows that all intersections operate at LOS D or
better in the AM and PM peak hours except the NW 75th Street intersection. However, there are
multiple movements operate at LOS F during the AM and/or PM peak hours with the proposed
improvements; the following movements operate at LOS F.
SR 26 at NW 75th Street
o Eastbound left (AM and PM peak hours)
o Eastbound through (AM peak hour)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
o Northbound through (AM and PM peak hours)
o Southbound through (AM and PM peak hours)
SR 26 at Southbound Ramps
o Eastbound left (PM peak hour)
o Westbound left (AM peak hour)
o Northbound left (PM peak hour)
o Northbound through (PM peak hour)
o Southbound Left (AM peak hour)
SR 26 at Northbound Off-Ramp
o Northbound left (PM peak hour)
o Northbound right (PM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM and PM peak hours)
o Westbound left (AM peak hour)
![Page 46: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/46.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
35
o Southbound through (AM peak hour)
o Southbound right (PM peak hour)
Table 6-2: Design Year 2029 Build Intersection Analysis Results
Intersection
AM Peak Hour PM Peak Hour
Delay
(sec) LOS
Delay
(sec) LOS
SR 26 at NW 75th Street 99.5 F 89.8 F
SR 26 at Southbound Ramps 53.2 D 41.5 D
SR 26 at Northbound Off-Ramp 36.9 D 44.1 D
SR 26 at Northbound On-Ramp 13.9 B 11.9 B
SR 26 at NW 69th Terrace 46.5 D 46.6 D
The Design Year 2029 intersection analysis shows that all intersections operate at LOS D or
better in the AM and PM peak hours except the NW 75th Street intersection. The LOS at the
Southbound Ramps and NW 69th Terrace intersections improve to LOS D versus LOS F for the
No-Build Alternative. Also, the delay and LOS improve at all study intersections compared to
the No-Build. Even with these improvements, there are multiple movements operate at LOS F
during the AM and/or PM peak hours with the proposed improvements; the following
movements operate at LOS F.
SR 26 at NW 75th Street
o Eastbound left (AM and PM peak hours)
o Eastbound through (AM and PM peak hour)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
o Northbound through (AM and PM peak hours)
o Southbound through (AM and PM peak hours)
SR 26 at Southbound Ramps
o Eastbound left (PM peak hour)
o Westbound left (AM peak hour)
o Northbound left (PM peak hour)
o Northbound through (PM peak hour)
o Southbound Left (AM peak hour)
SR 26 at Northbound Off-Ramp
o Northbound left (PM peak hour)
o Northbound right (AM and PM peak hours)
SR 26 at NW 69th Terrace
o Eastbound left (AM and PM peak hours)
o Westbound left (AM peak hour)
![Page 47: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/47.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
36
o Southbound through (AM peak hour)
o Southbound right (PM peak hour)
Opening Year 2019 and Design Year 2029 Build Queuing Analysis
Table 6-3 and Table 6-4 summarizes the results of the study intersections’ 95th percentile queue
analysis for the AM and PM peak hours. In order to provide operationally efficient and safe
conditions queuing needs to be within the provided storage. The following movements’ queues
are beyond the available storage in Opening Year 2019:
SR 26 at NW 75th Street
o Eastbound through (AM and PM peak hours)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
SR 26 at Southbound Ramps
o Westbound left (PM peak hour)
o Westbound through (PM peak hour)
o Northbound left (AM and PM peak hours)
o Northbound right (AM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM peak hour)
o Eastbound through (AM and PM peak hours)
o Westbound through (PM peak hour)
o Southbound right (PM peak hour)
No queues at the ramp terminals back up to the I-75 mainline. However, there are queues along
SR 26 that will back up into adjacent intersections affecting operations at adjacent intersections.
![Page 48: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/48.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
37
Table 6-3: Opening Year 2019 Build Signals Queuing Analysis Results
Intersection Time
Period
Eastbound Westbound Northbound Southbound
Left Through Right Left Through Right Left Through Right Left Through Right
SR 26 at
NW 75th
Street
AM
Peak 30 #892 #538 194 #360 #782 101
PM
Peak 78 #528 #522 #1171 #624 112 137
Existing
Storage
(feet)
240 415 415 500 650 650 670 - - 150
SR 26 at
Southbound
Ramps
AM
Peak m19 m543 m101 150 223 155 156 221 53 34
PM
Peak 33 355 52 #334 866 168 166 49 35 54
Existing
Storage
(feet)
250 670 600 160 420 420 150 - 150 85 85
SR 26 at
Northbound
Off-Ramp
AM
Peak 316 14 257 #377
PM
Peak 282 56 #561 #328
Existing
Storage
(feet)
- 420 - - 250 - 930 - 1,200 - - -
SR 26 at
Northbound
On-Ramp
AM
Peak m89 0 130 29
PM
Peak 167 m0 m177 m43
Existing
Storage
(feet)
240 - - - 225 225 - - - - - -
SR 26 at
NW 69th
Terrace
AM
Peak 361 765 #68 522 80 0 149 58
PM
Peak 80 528 145 881 170 53 195 #504
Existing
Storage
(feet)
250 520 520 185 740 740 190 190 190 - - 265
# 95th percentile volume exceeds capacity, queue may be longer.
m - Queue is metered by the upstream intersection.
![Page 49: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/49.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
38
Ramp queue lengths at the Southbound Ramps and Northbound Off-Ramp intersections reduce
compared to the No-Build Alternative. Left turning movement queues at the ramp terminals and
NW 69th Terrace also reduce. However, there are still movements that exceed the existing
storage. The following movements are beyond the available storage in Design Year 2029:
SR 26 at NW 75th Street
o Eastbound through (AM and PM peak hours)
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
SR 26 at Southbound Ramps
o Westbound left (AM and PM peak hours)
o Westbound through (PM peak hour)
o Northbound left (AM and PM peak hours)
o Northbound right (AM peak hour)
SR 26 at NW 69th Terrace
o Eastbound left (AM peak hour)
o Eastbound through (AM and PM peak hours)
o Westbound through (PM peak hour)
o Southbound right (PM peak hour)
No queues at the ramp terminals back up to the I-75 mainline. However, there are queues along
SR 26 that will back up into adjacent intersections affecting operations at adjacent intersections.
![Page 50: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/50.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
39
Table 6-4: Design Year 2029 Build Signals Queuing Analysis Results
Intersection Time
Period
Eastbound Westbound Northbound Southbound
Left Through Right Left Through Right Left Through Right Left Through Right
SR 26 at
NW 75th
Street
AM
Peak 34 #1041 #638 298 #416 #965 107
PM
Peak 84 #628 #630 #1376 #711 163 148
Existing
Storage
(feet)
240 415 415 500 650 650 670 - - 150
SR 26 at
Southbound
Ramps
AM
Peak m21 m561 m115 #211 244 168 168 #431 #72 37
PM
Peak 35 407 53 #381 #1168 180 184 51 37 58
Existing
Storage
(feet)
250 670 600 160 420 420 150 - 150 85 85
SR 26 at
Northbound
Off-Ramp
AM
Peak m293 38 285 #447
PM
Peak 331 61 #641 #380
Existing
Storage
(feet)
- 420 - - 250 - 930 - 1,200 - - -
SR 26 at
Northbound
On-Ramp
AM
Peak m89 m0 39 m1
PM
Peak 182 m0 m187 m55
Existing
Storage
(feet)
240 - - - 225 225 - - - - - -
SR 26 at
NW 69th
Terrace
AM
Peak m#422 #546 #75 #651 84 0 159 67
PM
Peak 87 565 #173 #1163 190 56 #219 #600
Existing
Storage
(feet)
250 520 520 185 740 740 190 190 190 - - 265
# 95th percentile volume exceeds capacity, queue may be longer.
m - Queue is metered by the upstream intersection.
![Page 51: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/51.jpg)
Legend:
Exis ng Lanes
Build Lanes
S Study Intersec on
SR 26
NW 75th St.
Figure 6‐1 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off Ra
mps
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
SR 26
NW 69th Terr.
Build Lane Configura on
![Page 52: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/52.jpg)
200 (207) 1,571 (837)
159 (269
)
2,993 (1,665)
Delay: 68.9 (74.6)
LOS: E (E)
Legend:
XXX (XXX): 2019 AM (PM) Volumes
Delay: Seconds per vehicle
LOS: A‐F
: Study Intersec on
SR 26
NW 75th St.
Figure 6‐2 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
NW 69th Terr.
Opening Year 2019 Build Peak Hour Volumes and LOS
7 (8)
1,25
1 (835
)
9 (34)
159 (264)
2 (14)
31 (3
7)
17 (2
7)
626 (1,580) 22 (51)
741 (884)
2,398 (1,515)
26 (1
01)
11 (2
) 7 (99)
556 (86)
35 (80)
77 (1
15)
1,159 (2,319) 188 (39)
18 (82)
2 (4)
123 (375
)
1,079 (2,127)
241 (589)
358 (647
) 47
2 (340
)
1,069 (2,140)
2,745 (1,562)
1,169 (2,363)
172 (355)
2,187 (1,252)
684 (441)
170 (182
) 7 (2)
560 (288
)
Delay: 5.4 (7.4)
LOS: A (A)
Delay: 22.8 (34.8)
LOS: C (C)
Delay: 33.7 (36.2)
LOS: C (D)
23 (10) 11
(3)
5 (20)
19 (1
1)
25 (32)
Delay: 26.5 (26.2)
LOS: C (C)
![Page 53: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/53.jpg)
221 (229) 1,735 (925)
176 (297
)
3,306 (1,839)
Delay: 99.5 (89.8)
LOS: F (F)
Legend:
XXX (XXX): 2029 AM (PM) Volumes
Delay: Seconds per vehicle
LOS: A‐F
: Study Intersec on
SR 26
NW 75th St.
Figure 6‐3 I‐75 at SR 26 (Newberry Road) IOAR
I‐75 SB
On/Off
I‐75 NB Off Ra
mp
I‐75 NB On Ra
mp
NW 69th Terr.
Design Year 2029 Build Peak Hour Volumes and LOS
8 (9)
1,38
2 (922
)
10 (38)
176 (292)
2 (15)
34 (4
1)
19 (3
0)
691 (1,745) 24 (56)
819 (976)
2,649 (1,674)
29 (1
12)
12 (2
) 8 (109
)
614 (95)
39 (88)
85 (1
27)
1,280 (2,562) 208 (43)
20 (91)
2 (4)
136 (414
)
1,192 (2,350)
266 (651)
395 (715
) 52
1 (376
)
1,181 (2,364)
3,032 (1,725)
1,291 (2,610)
190 (392)
2,416 (1,383)
756 (487)
188 (201
) 8 (2)
619 (318
)
Delay: 13.9 (11.9)
LOS: B (B)
Delay: 36.9 (44.1)
LOS: D (D)
Delay: 46.5 (46.6)
LOS: D (D)
25 (11) 12
(3)
6 (22)
21 (1
2)
28 (35)
Delay: 53.2 (41.5)
LOS: D (D)
![Page 54: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/54.jpg)
6.0 BUILD CONDITIONS I-75 at SR 26 IOAR
43
6.3. Predictive Safety Analysis A predictive quantitative safety analysis was performed to determine if the proposed
improvements addressed the existing safety concern. The safety analysis performed follows the
guidelines developed in the 2018 IARUG for an IOAR.
Table 6-5 shows the existing number of crashes, reduction in crashes and the total number of
predicted crashes if the Build Alternative is implemented. Crash modification factors (CMF) that
were available were used to help predict the reduction in crashes.
The CMFs for this analysis were determined using the CMF Clearinghouse funded by FHWA. If
more than one CMF was used at an intersection, the CMFs were multiplied together to get one
CMF for the study intersection. Not every improvement recommended has a CMF that correlates
with it. Due to this, quantitative safety analysis can only be performed for specific
improvements, described below. A qualitative safety analysis can then be performed for all other
recommendations. The three CMFs used to quantify the benefits of the project include:
Clearinghouse CMF 4203: Increase yellow interval and all red interval = 0.99 (applied to
all intersections)
Clearinghouse CMF 288: Provide right-turn lane on one major-road approach = 0.91
(applied to SR 26 at NW 75th Street intersection)
Clearinghouse CMF 340: Change from permitted-protected to protected on major
approach (applied to SR 26 at Southbound Ramps intersection)
Table 6-5: Reduction in Crashes
Intersection Existing
Crashes CMF 1 CMF 2 CMF
Predicted
Crashes
Reduction
in Crashes
SR 26 at NW 75th Street 114 0.99 0.91 0.90 103 11
SR 26 at Southbound Ramps 106 0.99 0.58 0.57 61 45
SR 26 at Northbound Off-Ramp 125 0.99 - 0.99 124 1
SR 26 at Northbound On-Ramp 23 0.99 - 0.99 23 0
SR 26 at NW 69th Terrace 114 0.99 - 0.99 113 1
Total 482 - - - 423 59
By implementing the proposed modifications, a total expected crash reduction of 59 crashes a
year is expected.
In addition, some of the proposed improvements cannot be analyzed as part of a quantitative
safety analysis, but based on the safety analysis performed and the reduction in delay and queues
safety should improve with all the recommended improvements.
![Page 55: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/55.jpg)
7.0 EVALUATION OF ALTERNATIVES I-75 at SR 26 IOAR
44
7. EVALUATON OF ALTERNATIVES This section discusses the analysis of alternatives based on safety, engineering and operational.
The No-Build Alternative was evaluated in Section 5 and the Build Alternative in Section 6. A
comparison of the No-Build and the Build Alternative is also provided in this section. The
evaluation criteria are described as follows:
Compliance with FHWA Requirements
Traffic Operational Performance
7.1. Compliance with Policies and Engineering Standards The design criteria for this project is based on design parameters outlined in the FDOT Florida
Design Manual, the FDOT Manual of Uniform Minimum Standards for Design, Construction
and Maintenance for Streets and Highways and AASHTO’s A Policy on Geometric Design of
Highway and Streets published in 2011.
7.2. Alternatives Comparison The No-Build Alternative and the Build Alternative were compared and a summary is provided
in the sections below.
7.2.1. Operational Comparison
Based on the analysis, the Build Alternative provides significant improvements over the No-
Build condition at the ramp terminals and NW 69th Terrace intersections. A comparison of the
Design Year 2029 No-Build and Build results are provided in Table 7-1.
Table 7-1: Design Year 2029 No-Build and Build Alternatives Intersections
Comparison
Intersection
2029 No-Build 2029 Build
AM Peak Hour PM Peak Hour AM Peak Hour PM Peak Hour
Delay
(sec) LOS
Delay
(sec) LOS
Delay
(sec) LOS
Delay
(sec) LOS
SR 26 at NW 75th Street 102.7 F 92.1 F 99.5 F 89.8 F
SR 26 at Southbound Ramps 90.1 F 64.9 E 53.2 D 41.5 D
SR 26 at Northbound Off-Ramp 42.1 D 48.5 D 36.9 D 44.1 D
SR 26 at Northbound On-Ramp 35.8 D 30.2 C 13.9 B 11.9 B
SR 26 at NW 69th Terrace 81.3 F 76.6 E 46.5 D 46.6 D
![Page 56: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/56.jpg)
7.0 EVALUATION OF ALTERNATIVES I-75 at SR 26 IOAR
45
The Build Alternative will improve the delay at all the study intersections. The biggest
improvements in delay and LOS occur at the Southbound Ramps, Northbound On-Ramp and
NW 69th Terrace intersections. The delay at the Southbound Ramps is reduced by 36.9 seconds
and 23.4 seconds during the AM and PM peak hours, respectively. The delay at the Northbound
On-Ramp is reduced by 21.9 seconds and 18.3 seconds during the AM and PM peak hours,
respectively. The delay at NW 69th Terrace is reduced by 34.8 seconds and 30.0 seconds during
the AM and PM peak hours, respectively.
The Build Alternative will also improve the queues at the study intersections compared to the
No-Build Alternative. One major improvement was the ramp queues at the ramp terminals. For
example, the queues along the ramps at the Southbound Ramps intersection reduce by up to 658
feet with the Build Alternative. The queues along the ramps at the Northbound Off-Ramp
intersection reduce by up to 63 feet with the Build Alternative. Another major improvement is
the queueing between the study intersections. For example, in the No-Build Alternative the
eastbound movements at NW 69th Terrace would queue back to the Northbound On-Ramp. With
the Build Alternative improvements, the eastbound movement queues will reduce by 701 feet.
7.3. Design Exceptions and Variations Implementation of the proposed improvements will not require any design exceptions or
variations.
7.4. Summary and Recommendations The proposed short term improvements will provide up to a 61% reduction in delay at the study
intersections, and will provide up to a 73% reduction in queuing at the study intersections in the
Design Year 2029.
The proposed short term improvements will also provide a safer transportation facility. Based on
the proposed improvements, it is predicted there will be a reduction of 59 crashes per year within
the study area.
Based upon this analysis, the recommendation is to implement the Build Alternative due to the
improved operations and safety compared to the No-Build Alternative. However, the Build
Alternative will have movements that operate a LOS F by Design Year 2029; so it is
recommended that ultimate improvements be analyzed to address the future traffic demand within
the study area.
![Page 57: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/57.jpg)
8.0 JUSTIFICATION I-75 at SR 26 IOAR
46
8. JUSTIFICATION
8.1. Compliance with FHWA General Requirements The following requirements serve as the primary decision criteria used in approval of interchange
access requests. Responses to each of the Federal Highway Administration (FHWA) two policy
points are provided to show that the proposed modification for the I-75 at SR 26 interchange is
viable based on the conceptual analysis performed to date.
8.1.1. FHWA Policy Point 1
An operational and safety analysis has concluded that the proposed change in access does not
have a significant adverse impact on the safety and operation of the Interstate facility (which
includes mainline lanes, existing, new, or modified ramps, ramp intersections with crossroad) or
on the local street network based on both the current and the planned future traffic projections.
The analysis should, particularly in urbanized areas, include at least the first adjacent existing
or proposed interchange on either side of the proposed change in access (23 CFR 625.2(a),
655.603(d) and 771.111(f)). The crossroads and the local street network, to at least the first
major intersection on either side of the proposed change in access, should be included in this
analysis to the extent necessary to fully evaluate the safety and operational impacts that the
proposed change in access and other transportation improvements may have on the local street
network (23 CFR 625.2(a) and 655.603(d)). Requests for a proposed change in access should
include a description and assessment of the impacts and ability of the proposed changes to safely
and efficiently collect distribute, and accommodate traffic on the Interstate facility, ramps,
intersection of ramps with crossroad, and local street network (23 CFR 625.2(a) and
655.603(d)). Each request should also include a conceptual plan of the type and location of the
signs proposed to support each design alternative (23 U.S.C. 109(d) and 23 CFR 655.603(d)).
An in‐depth operational and safety analysis was conducted to study the impacts of the proposed
improvements at the I-75/SR 26 interchange. Several performance measures were used to
compare the operations of the existing system under No-Build and Build conditions. Key
measures included delay, Level of Service (LOS) and 95th Percentile Queues for existing and
proposed conditions.
Operational analysis conducted for the short term improvements confirm that the proposed
modifications are not expected to have significant adverse impacts on safety or operations at the
I-75/SR 26 interchange and adjacent intersections. When compared to the No-Build Alternative,
the proposed short term improvements will provide up to a 61% reduction in delay at the study
intersections, and will provide up to a 73% reduction in queuing at the study intersections in the
Design Year 2029.
The short term improvements at the study intersections are, also, expected to reduce the number
of collisions at the study intersections, and not have an adverse impact on safety or operations.
![Page 58: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/58.jpg)
8.0 JUSTIFICATION I-75 at SR 26 IOAR
47
Using Crash Modification Factors (CMFs) from the CMF Clearinghouse, a predicted number of
crashes was calculated after the implementation of the improvements. Based on the application
of the CMFs to the study intersections, a 12% reduction in crashes is expected.
The proposed I-75 at SR 26 IOAR will not involve any new mainline access points or change in
the current access locations. The proposed short term improvements are only being applied to the
study intersections. Hence, no analysis was performed for the I-75 mainline, I-75 ramps or
adjacent ramps. Also, the existing signing plan along I-75 and SR 26 will be adequate for the
proposed improvements. A new conceptual signing plan is not required for these improvements.
8.1.2. FHWA Policy Point 2
The proposed access connects to a public road only and will provide for all traffic movements.
Less than “full interchanges” may be considered on a case-by-case basis for applications
requiring special access, such as managed lanes (e.g., transit, HOVs, HOT lanes) or park and
ride lots. The proposed access will be designed to meet or exceed current standards (23 CFR
625.2(a), 625.4(a)(2), and 655.603(d)). In rare instances where all basic movements are not
provided by the proposed design, the report should include a full-interchange option with a
comparison of the operational and safety analyses to the partial-interchange option. The report
should also include the mitigation proposed to compensate for the missing movements, including
wayfinding signage, impacts on local intersections, mitigation of driver expectation leading to
wrong-way movements on ramps, etc. The report should describe whether future provision of a
full interchange is precluded by the proposed design.
The proposed short term improvements to the I-75 at SR 26 interchange and adjacent
intersections will provide full access and cater to all traffic movements from SR 26 to and from
I-75. The proposed modifications are designed to meet current standards for federal-aid projects
on the interstate system and conform to American Association of State Highway and
Transportation Officials (AASHTO) and the FDOT design standards.
![Page 59: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/59.jpg)
9.0 CONCEPTUAL FUNDING PLAN/CONSTRUCTION SCHEDULE I-75 at SR 26 IOAR
48
9. CONCEPTUAL FUNDING PLAN/CONSTRUCTION SCHEDULE
A preliminary cost estimate was prepared for this project as part of the FDOT Safety Study. The
preliminary cost estimate is provided as part of the Safety Study in Appendix A.
The improvements proposed as part of the Build Alternative at the I-75 at SR 26 interchange are
performed under the Programmatic Agreement with FHWA. Therefore, FDOT Central Office
will conduct necessary review and assessment of the justification for the proposed
improvements. The IOAR and design of this project are currently funded under FDOT Work
Program as Financial Project Identification Number (FIN) 437354-1. The Design and
Construction of the improvements are funded for year 2019.
![Page 60: INTERCHANGE OPERATIONAL ANALYSIS REPORT (IOAR) · 2020. 3. 20. · wrong-way movements on ramps, etc. The report should describe whether future provision of a full interchange is](https://reader033.fdocuments.us/reader033/viewer/2022051906/5ff8491638e34d1f7253e49f/html5/thumbnails/60.jpg)
APPENDIX I-75 at SR 26 IOAR
List of Appendices
Appendix A: FDOT Safety Study for SR 26 from NW 75th Street to NW 69th Terrace
Appendix B: Existing Year 2018 Alternative Synchro Operational Analysis
Appendix C: Raw Crash Data
Appendix D: 2019 and 2029 No-Build Alternative Synchro Operational Analysis
Appendix E: 2019 and 2029 Build Alternative Synchro Operational Analysis
Appendix F: Build Concept Figure