Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID...
Transcript of Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID...
![Page 1: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/1.jpg)
Innovative Approachesto Green Roadways
Philadelphia LID SymposiumSeptember 26, 2011
Ross Gordon, PE, CFM, LEED APProject Manager
![Page 2: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/2.jpg)
Presentation Overview
LID in Houston, TX
• State of LID in 2009• Design Contest Overview• Green Roadway Design• Lessons Learned
![Page 3: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/3.jpg)
STATE OF LID IN 2009
![Page 4: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/4.jpg)
State of LID in 2009
• Very few LID projects in Houston
• Developers very confident in their existing business models
• General beliefs:• LID does not work in Houston• LID would cost more• Why should I?
“It’s Different Here!”
![Page 5: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/5.jpg)
LID IMPEDIMENTS IN HOUSTON
• High intensity / volume rainfall• Design Storm:
• 100 yr = 13.2 inches• 2 yr = 5+ inches
Primary considerationis always flood control
• Little experience with separate flood control / water quality features
![Page 6: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/6.jpg)
LID IMPEDIMENTS IN HOUSTON
• Predominantly clay soils• Minimal infiltration capacity• Where does the water go?• Can we use infiltration?
![Page 7: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/7.jpg)
LID IMPEDIMENTS IN HOUSTON
• Strong resistance to changing the development strategy
• No interest in paying more for LID• Who cares about water quality?
• Updated COH Design Manual• Allows LID features but does not
mandate or encourage use• Copied from other design manuals
• Difficult to get LID permitted & approved
![Page 8: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/8.jpg)
![Page 9: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/9.jpg)
LID DESIGN CONTEST
Spur the adoption of LID in the Houston region by educating engineers, developers, and political leaders and by showing
that LID can work in Houston
Green Roadway UrbanRe-development
Suburban Res.Development
![Page 10: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/10.jpg)
LID DESIGN CONTEST
• Design contest initiated Oct. 2009• 23 design teams • 49 firms from across the USA• Over 250 professionals
• Finals event held Jan 2010• Round 1 Judging
• 5 preeminent engineers, architects, and planners in the Houston region
• Round 2 Judging• 20 politicians, developers, regulators, local
government leaders
![Page 11: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/11.jpg)
WHAT HAPPENED?
![Page 12: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/12.jpg)
LID DESIGN CONTEST IMPACTS
• Strong new interest in LID• Developers• Local government• Political leaders
• Rapid increase in LID projects underway
• Harris County LID Design Guide Approved
• Independence Parkway Green Roadway Design named TCEC Eminent Conceptor Award Winner
![Page 13: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/13.jpg)
GREEN ROADWAY DESIGN
![Page 14: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/14.jpg)
DESIGN OVERVIEW
• 13% reduction in construction cost per mile• Approx. 70% reduction in peak discharge• Aesthetically attractive and functional landscapes• A solution tailored to and designed for Houston
Higher Performance - Lower Cost
![Page 15: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/15.jpg)
ROADWAY DESIGN
Green Roadway
Standard Roadway
![Page 16: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/16.jpg)
LANDSCAPING – NATIVE PLANTS
Tripsacum dactyloidesTripsacum dactyloides
Sorghastrum nutans
Sorghastrum nutans
Wedelia texana Wedelia texana
Taxodium distichumTaxodium distichum
Phlox divaricataPhlox divaricata
Wedelia texanaWedelia texana
Panicum virgatumPanicum virgatumAndropogon virginicusAndropogon virginicus
Hibiscus aculeatusHibiscus aculeatus
Chasmanthium latifoliumChasmanthium latifolium
Fraxinus pennsylvanica Fraxinus pennsylvanica
Lobelia cardinalisLobelia cardinalis
ConocliniumcoelestinumConocliniumcoelestinum
![Page 17: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/17.jpg)
LANDSCAPING
![Page 18: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/18.jpg)
STORM WATER STRATEGY
Basic Design• Linear detention concept utilizing
restrictors at cross-over culverts• Maximize detention storage in the ROW• Vegetated swales reduce flow velocities
and filter storm water
100 yr Green WSE Profile
Methodology• Existing, Standard design and Green design all modeled in same manner• Dynamic hydrology and hydraulics using EPA-SWMM• No additional or enhanced infiltration assumed or adjusted CN• Benefits are due to hydraulic attenuation of runoff through the swales /
linear detention
![Page 19: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/19.jpg)
0
10
20
30
40
50
60
70
80
90
100
7:00:00 10:00:00 13:00:00 16:00:00 19:00:00 22:00:00
Flow
(cfs
)
Time
100 yr Existing 2-Lane
100 yr Standard 4-Lane
100 yr Green 4-Lane
STORM WATER BENEFITS
Design Event Scenario Peak
DischargeGreen vs. Standard Percentage of Peak
Green vs. Existing Percentage of Peak
100 yrExisting 2-Lane 76.87
30.4% 34.2%Standard 4-Lane 86.32
Green 4-Lane 26.27
10 yrExisting 2-Lane 42.96
26.8% 40.7%Standard 4-Lane 65.24
Green 4-Lane 17.49
5 yrExisting 2-Lane 30.17
27.2% 43.3%Standard 4-Lane 48.09
Green 4-Lane 13.07
100 Yr. flood is contained inside
the median with no roadway flooding
![Page 20: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/20.jpg)
WATER QUALITY BENEFITS
Significant reductions in highway runoff pollutants• Predicted 84% TSS removal• Predicted 68% metals removal• Predicted 30% pathogen removal
FIRST FLUSHAbility to treat first 1” of storm water runoff
![Page 21: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/21.jpg)
COST OVERVIEW
Cost estimates prepared for both scenarios, with identical unit costs, to facilitate honest cost comparison
13% Reduction in Construction Cost
9% Reduction in Maintenance Cost
Standard / Mile:$4.97 Million
Green / Mile:$4.32 Million
![Page 22: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/22.jpg)
LESSONS LEARNED
![Page 23: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/23.jpg)
LESSONS LEARNED
• Cost and complexity is variable• Simplicity is key when possible• Not just about choosing good BMPs…
• Consistent, defensible analysis is key
• Rely on locally appropriate solutions and methodologies
• Every site is unique and requires a custom solution
• Accept your limitations - don’t fight your constraints
![Page 24: Innovative Approaches to Green Roadways · Innovative Approaches to Green Roadways Philadelphia LID Symposium September 26, 2011 Ross Gordon, PE, CFM, LEED AP Project Manager ross.gordon@aecom.com](https://reader031.fdocuments.us/reader031/viewer/2022013019/5e31612913d1696f9b0ccc53/html5/thumbnails/24.jpg)
LESSONS LEARNED
• It is possible to design dual purpose LID systems• Stretches traditional LID design
specifications
• LID can lead to major cost savings
Understand the hydrologic principles
Understand your client’sgoals and needs