Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

43
INNOVATIONS IN TRENCHLESS REHABILITATION “PRESSURE PIPELINE REHABILITATION USING CIPP LINING- ONSLOW RD STORMWATER UPGRADE” By Raad Dali General Manager Advanced Pipeline Services Ltd. July 2010

Transcript of Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

Page 1: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

INNOVATIONS IN TRENCHLESS REHABILITATION

“PRESSURE PIPELINE REHABILITATION USING CIPP LINING- ONSLOW RD STORMWATER

UPGRADE”

ByRaad Dali

General Manager Advanced Pipeline Services Ltd.

July 2010

Page 2: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

ONSLOW CATCHMENT-WELLINGTON

2

Page 3: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

• Storm water run-off from the Onslow Rd Catchment in Hutt City / Wellington has historically resulted in considerable problems and damage to the road and / or its environment .

• Due to the uncoordinated nature of the upgrading , some of the measures simply transferred the problems to the downstream sections.

• Council Engineers were unwilling to proceed with an further upgrade work until investigation, evaluation, and/or mitigation of the risks of transferring the design flow to the lower sections of the storm water main were completed.

PROJECT BACKGROUND

August 10 3

Page 4: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

The project represented Stage 5 of a 6 Stage upgrade.

This section of the storm water outfall that need to be upgraded runs

beneath Hutt Rd

PROJECT LOCATION

August 10 4

Page 5: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

PROJECT LOCATION

August 10 5

-

The North Island Main Railway line, the Wairarapa Railway line

Page 6: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

PROJECT LOCATION

August 10 6

-

and under Wellington Urban State Highway 1

Page 7: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

PROJECT LOCATION

August 10 7

-

to the sea outfall

Page 8: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

PROJECT DESIGN

August 10 8

-

Conventional upgrade options available included the installation of a larger diameter pipe ( or a duplicate) by open cut or by microtunelling would have been very risky due to the variable ground conditions and the potential for disruptions to the major transportation links serving Wellington City was high.

Preliminary cost estimates for these options run in several million of dollars.

Thinking Innovatively ( both economically and technically) the consultant CPG proposed the alternative of lining the existing pipeline including the manholes with a Cured in Place Pipe ( CIPP liner) to create a continuous pressurized pipeline taking advantage of the upstream gradient and potential hydraulic energy to discharge more water through the existing pipeline.

Page 9: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

PROJECT REQUIREMENTS

August 10 9

-

The technical requirements for the project included the following:

• The CIPP liner should be a fully structural liner capable of withstanding all loads from soil, traffic loads and ground water in its own rights .

• The minimum effective life of the CIPP liner would be 50 years.

• The lining system should not reduce the diameter of the existing pipe by more than 5%

• The CIPP lined section should withstand a test up to 30m

• The curing water should be disposed to an approved site.

Page 10: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

PROJECT CONSTRAINTS

August 10 10

-

Several Lining options are available for the rehabilitation of similar diameter pipelines .However these methods are not suitable in this particular project. Inherent difficulties included :

• The requirement to overcome two transitions in the diameter of the pipeline from 675mm to 750mm, and 750mm to 900mm. Continuous lining through the two transitions in the liner is something not attempted before internationally.

• There are several vertical and horizontal bends in the existing stormwater line.

• Limited access to the installation sites as access points were located in a private property, near a historic trough, in the rail reserve and with one buried manhole located in the middle of the main state highway to Wellington City.

Page 11: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 11

PROJECT CONSTRAINTS

Page 12: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

PROJECT CONSTRAINTS

August 10 12

-

• A Steep installation , there is a significant static head of approx 10m between upstream manhole and down stream sea outlet.

Page 13: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 13

PROJECT PROPOSAL

• Advanced Pipeline Services Ltd proposed the use of Insituform Pressure Pipe Liner (PPL) custom engineered cured in place pipe product. The specific PPL ordered for this project was designed to flexibly negotiate the existing horizontal and vertical bends in the existing pipeline.

Insituform PPL is an advanced, proven and non-disruptive technology that is specially designed to withstand a wide range of system operation conditions, and because it is installed inside the existing main there was no risk of damage or disturbance to adjacent utilities or infrastructures.

As the installation is a fully trenchless technique the process reduces transport and subsequent commercial disruption, site noise, pollution and safety concerns to limited access

Page 14: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 14

PPL LINER

Vinlyester -Epoxy/Fibreglass Structure•Number of Layers dependent on diameter and internal pressure

Vinlyester-Epoxy/Polyester Felt Structure •Provides external load capacity•Layer thickness can be varied depending on the loading conditions

PE coating•Water contact surface•Coating provides water barrier for installation process and impregnation

Page 15: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 15

PPL LINER

DESIGN THICKNESS•The liner was designed according to the ASTM standard F1216-07 with a factor of safety of 1.5 for external loading and a factor of safety of 3 for any vacuum loading.•The design revealed a liner thickness of 12mm

Page 16: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 16

Sketch of liner design showing transitions

Page 17: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 17

DETAIL OF OUTFALL END TO CONTAIN LINER AND CURING WATER

Page 18: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 18

INSTALLATION OF THE PPL LINER-STEP 1 LINER IMPREGNATION

Page 19: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 19

STEP 1-LINER IMPREGNATION

Page 20: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 20

STEP 1-LINER IMPREGNATION

Page 21: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 21

STEP 2- THE LINER IS PACKAGED FOR TRANSPORT TO SITE

Page 22: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 22

STEP 3-LINER INSTALLATION

Page 23: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 23

STEP 3-LINER INSTALLATION

Page 24: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 24

STEP 3- SUPPORTING LINER INSIDE MANHOLE

Page 25: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 25

OUTFALL END

Page 26: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 26

TESTING OF LINER

Page 27: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 27

TESTING OF LINER

Page 28: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 28

END OF PROJECT

Page 29: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

OTHER CIPP LINING PRESSURE APPLICATIONS-INSITUMAIN TM

August 10 29

Page 30: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

InsituMainTM Product Characteristics

August 10 30

ANSI- American National Standards InstituteNSF- National Science Foundation

Page 31: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

InsituMainTM Technical Envelope

August 10 31

Page 32: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

InsituMainTM Applications

August 10 32

Page 33: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

InsituMainTM Design

August 10 33

Page 34: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

InsituMainTM Manufacturing

August 10 34

Page 35: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

Installation Process- Bypass and Pipeline Access

August 10 35

Page 36: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

InsituMainTM Installation

August 10 36

Page 37: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

Service Connection Reinstatement

August 10 37

Page 38: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

Restoring Service

August 10 38

Page 39: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

Future Connections

August 10 39

Page 40: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

Potable Water Case Study

August 10 40

Page 41: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

InsituMainTM Product Benefits

August 10 41

Page 42: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

OTHER NON-POTABLE PROJECTS COMPLETED IN NZ USING PRESSURE LINERS

August 10 42

•Repair of Gulf Harbour-Whangaparaoa Rising main

•640 mm GRP Hobas pipe

•35m repair due to physical damages

•Working pressure 50 psi

•Vinylester- Kevlar reinforced lining system

Page 43: Innovations in Trenchless Rehabilitation “PRESSURE PIPE ...

August 10 43

Mangere Sewage Treatment plant-Watercare Services Ltd.

•250mm Cement lined Steel pipe

•25m repair due to corrosion.

•Working pressure 60 psi

•Testing pressure 90 psi

•Epoxy- Kevlar reinforced lining system

•Installation time 12 hours

OTHER NON-POTABLE PROJECTS COMPLETED IN NZ USING PRESSURE LINERS