Indian Highways Vol.41 5 May 13

download Indian Highways Vol.41 5 May 13

of 43

Transcript of Indian Highways Vol.41 5 May 13

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    1/100

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    2/100

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    3/100

    The Indian Roads Congress

    E-mail: [email protected]/[email protected]

    Founded : December 1934

    IRC Website: www.irc.org.inJamnagar House, Shahjahan Road,

     New Delhi - 110 011

    Tel : Secretary General: +91 (11) 2338 6486

    Sectt. : (11) 2338 5395, 2338 7140, 2338 4543, 2338 6274

    Fax : +91 (11) 2338 1649

    Kama Koti Marg, Sector 6, R.K. Puram

     New Delhi - 110 022

    Tel : Secretary General : +91 (11) 2618 5303

    Sectt. : (11) 2618 5273, 2617 1548, 2671 6778,

    2618 5315, 2618 5319, Fax : +91 (11) 2618 3669

     No part of this publication may be reproduced by any means without prior written permission from the Secretary General, IRC.

    Edited and Published by Shri Vishnu Shankar Prasad on behalf of the Indian Roads Congress (IRC), New Delhi. The responsibility of the

    contents and the opinions expressed in Indian Highways is exclusively of the author/s concerned. IRC and the Editor disclaim responsibility

    and liability for any statement or opinion, originality of contents and of any copyright violations by the authors. The opinions expressed in the

     papers and contents published in the Indian Highways do not necessarily represent the views of the Editor or IRC.

      VOLUME 41 NUMBER 5 MAY 2013

      CONTENTS ISSN 0376-7256

    LIST OF ADVERTISERS

    ICT Pvt. Ltd. - Inside Front Cover 

    AE&C - Inside Back Cover 

    Bentley Systems Pvt. Ltd. - Outside Back Cover 

    10 Metal Engineering & Treatment Co. Pvt. Ltd.

    11 Rettenmaier India Pvt. Ltd.

    12 BASF

    13 Tiki Tar Industries India Ltd.

    14 Alchemist Touchnology Ltd.

    15 IRF-India Chapter 

    16 Advertisement Tarrif 

    23 Primax Equipment Pvt. Ltd.

    24 Gloster Limited 

    39 Casta Engineers Pvt. Ltd.

    40 Poly Flex

    65 Perma Construction Aids Pvt. Ltd.

    65 Arun Soil Lab Pvt. Ltd.

    66 Coir Board 

    75 Redecon (India) Pvt. Ltd.

    92 Alexis Enterprises Pvt. Ltd.

    93 Techfab India

    94 Halcrow Consulting India Pvt. Ltd.

    95 Jalnidhi Bitumen Specialities Pvt. Ltd.

    96 New/Revised Publications Now Available on Sale

    INDIAN HIGHWAYSA REVIEW OF ROAD AND ROAD TRANSPORT DEVELOPMENT

     Page

    2-3 From the Editor’s Desk

    4-9 Glimpses of First Collaborative Endeavour of IRC with

    Educational Institutions

    17 Inuence of Environmental Factors on TemperatureDifferential in High Performance Cement Concrete

    Pavements

    K.S. Suresh Kumar, M.S. Amarnath and G.B. Avinash

    25 Quality Audit for Concrete Constructions

    C.V. Kand 

    41 Sustainability Challenges & Opportunities in Bridge

    Building

    V. N. Heggade

    57 Inuence of Skew Angle in the Design of Grids  Madhavi N, Baskar K, Natarajan C and Rajaraman A.R.

    67 Experiences from Investigation of Expansion Joints and

    Bearings in Concrete Bridges

    S.K. Sharma, Lakshmy Parameswaran, Rajeev Goel and

    Sushil Kumar 

    76-88 Amendments to IRC:6-2010 and IRC:78-2000

    89-90 Circulars Issued by MORT&H

    91 Tender Notice of NHs Kanpur 

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    4/100

      2 INDIAN HIGHWAYS, MAY 2013

    Dear Readers,

    The visionary decision taken by the Government for getting highway projects executed through

    Engineering Procurement and Construction (EPC) mode in place of traditional mode of item rate

    contracts may provide the much needed relief to the road sector players. In the current scenario of

    global economic downtrend with symptoms of economic contraction, the execution of highway sector

     projects through EPC mode may allow much needed breather both to the Contractors & Financers, as

    EPC contracts are public funding cash contracts. This may also allow much needed consolidation in the

    sector which may help in strengthening the foundation for achieving greater pace of progressiveness

    in the coming years.

    As normally happens, the introduction of new system/mode comes with some apprehensions and

    reservations among the different stakeholders. There is a need to demystify the EPC benets, processand procedures. This may require a concerted efforts as well as collaborative approach from all the

    stakeholders. However, the visionary action of the government of introducing EPC in highway sector

    is clearly a step towards building a climate perceivable to be friendly to enterprises, investment and

    expeditious development in the road building activities which will have enormous positive linkages to

    the overall economic development.

    The EPC mode provides an opportunity as well as exibility to the Contractor(s) to introduce cuttingedge technologies, techniques, instrumentation, new materials, etc. This may help him in not only in

    improving the efciency but may also help in improving overall durability as well as bringing downthe cost of the project(s).

    The EPC entrepreneur(s) may also have the scope to make use of emerging concept of “frugal”

    engineering which implies lean engineering methodology or process that involves optimum use of

    resource(s) at hand. 

    Similarly, the various approvals/permissions to be provided by the client road authorities within the

    stipulated time frame augurs well for all stakeholders including public, as system of implementation of

     projects becomes a well-dened and transparent process. However, this may result in added pressureon the cliental road authorities to meet the stipulated deadlines for different activities especially related

    to handing over the land, environmental clearances, General Arrangement Drawings (GAD), etc. There

    may be some possibilities of augmenting the human resource in certain domain areas of the cliental

    road authorities coupled with upgrading the skill of existing manpower.

    From the Editor’s Desk

    EPC IN HIGHWAY – WIN-WIN FOR ALL

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    5/100

    EDITORIAL

      INDIAN HIGHWAYS, MAY 2013 3

    The explicit provision of damages payable to the Contractors on account of non-availability of the

    stipulated clearances, etc. clearly reects towards the transformation of role of the government –moving away from the command and control economy/development of earlier days towards ensuring

    good governance and an effective system to incentivize innovation(s) and removal of inefciency. Thisis also reected in provisions related to payment of bonus for early completion of the project(s).

    The EPC mode in highway sector also throws open more opportunities for job creation and

    employment in the road sector including entrepreneurship in the domain areas of consultancy services

    in project preparation, survey & investigations, road safety, quality control, etc. This is adequately

    reected in the enabling provision of 70% of work which can be outsourced by the EPC Contractor.Possibly EPC may prove to be a game changer in road sector in the coming years.

    Perceptible benets of the EPC in road sector may be many but of course best practices suitingdifferent category of projects needs to be evolved, which may get evolved over a time period and

    feedback based there on from different implementing agencies. In the process of transition to new

    concepts and systems, it is always preferable to remember the wise words of Osho:- “Knowledge

    makes you learned, but wisdom makes you innocent. Knowledge is ego fullling but wisdom kills ego.Wisdom is simply wisdom. It is truth. Wisdom cannot be true or untrue”. 

    Place: New Delhi Vishnu Shankar Prasad 

    Dated: 22nd  April, 2013 Secretary General

     ————— 

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    6/100

    HIGHLIGHTS

      4 INDIAN HIGHWAYS, MAY 2013

    As a new initiative of widening the reach of IRC,

    a collaborative approach with technical institutions

    has been initiated by IRC. In the rst of the series,a National Event “Transport Infrastructure Congress

    and Expo-2013 (TICE-2013)” has been organized as

     joint endeavour by the Malaviya National Institute

    of Technology (MNIT) Jaipur & IRC from March 7,

    2013 to March 9, 2013 as a part of Golden Jubilee

    Celebrations of MNIT Jaipur.

    The event generated a lot of interest from all the

    stakeholders including the private sector and

     particularly the student community of the

    engineering colleges. It is heartening to

    mention that 25 Engineering Colleges/Universities participated in this event from the States of

    Rajasthan, Gujarat, Uttar Pradesh, Orissa,

    Karnataka & Tamil Nadu. Besides students and

    faculties of these colleges, a large number of

     professionals/engineers/scientists from the

    Central Government, State Government,

    Public Sector Units, Research Institutions, etc.

     participated in the deliberations. The

    engineering students for the rst time were given a

    unique opportunity of having interaction with the practising professionals & experts in the eld of

    GLIMPSES OF FIRST COLLABORATIVE ENDEAVOUR OF

    IRC WITH EDUCATIONAL INSTITUTIONS

    road & road transport sector. The students were

    exposed to the wisdom of the experts, thereby

     preparing them to meet the challenges in future in

     better way. The engineering students showcased

    their talent and capabilities through the working

    models and posters on the real life issues in the

    road and road transport sector.

    The major features of the event were:-

    1. Two day National Workshop/ Conference.

    2. Three day Technical Exhibition on

    Transportation technologies and materials.

    3. Student Research Model Exhibition/

    Competition.4. Three days Career Counselling Session

    over job opportunities in Transport Sector/

    Engineering.

    The State Government of Rajasthan extended full

    support to the event. Shri Shanti Dhaliwal, Hon’ble

    Minister of Urban Development, Government of

    Rajasthan inaugurated the event. The inaugural event

    was also attended by Shri Gajendra Haldea, Advisor

    to DCH (Infrastructure) Planning Commission, Govt.

    of India as Guest of Honour besides other dignitariesfrom the Central and State Government.

    Glimpses of Inaugural Session

    Shri Shanti Dahliwal, Hon’ble Minister Urban Development, Govt. of Rajasthan

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    7/100

    HIGHLIGHTS

      INDIAN HIGHWAYS, MAY 2013 5

    Shri Gajendra Haldea, Advisor to DCH (Infrastructure)

    Planning Commission

    Shri G.S. Sandhu, Additional Chief Secretary,

    Government of Rajasthan

    View of Audience

    During the event the Experts/Speakers made presentation on the following topics.

    1. “Design of Noise Barrier for Elevated Highway

    Infrastructure” by M. Parida, Professor IIT

    Roorkee.

    2. “Transit Oriented Sustainable Urban

    Development” by S.L. Dhingra, Professor IIT

    Bombay.

    3. “Road Drainage A case Study of Panipat City” by S.N. Sachdeva, Professor NIT Kurukshetra

    4. “Enabling New Policy Initiatives of MoRTH

    to Promote Innovation and Road Safety” by

    S.K. Nirmal, MoRTH, New Delhi

    5. “New Materials & Technology in Roads” by

    P.K. Jain, Head Flexible, Pavement Division,

    CRRI

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    8/100

    HIGHLIGHTS

      6 INDIAN HIGHWAYS, MAY 2013

    6. “Review of Bituminous Mixes Used in India”

     by Prof. P.S. Kandhal, Associate Director

    Emeritus, National Center for Asphalt

    Technology, USA

    7. “Remote Sensing & GIS application for RouteAlignment ” by P K Garg, Professor IIT

    Roorkee

    8. “Trafc Infrastructure Projects for Jaipur city” by Shri Kuldeep Ranka, Jaipur Development

    Commissioner 

    A Panel Discussion was also held. The students/researchers were given an exclusive opportunityto have rst-hand interaction with the expertsof various issues relating to the road transport

    sector. The Panelist were Shri Vishnu ShankarPrasad, Secretary General, IRC, Professor P.S.Kandhal, M Parida, Prof. IIT Roorkee, S L Dh-ingra, Prof. IIT Bombay, Dr. I.K. Bhatt, DirectorMNIT Jaipur, Prof B L Swami MNIT Jaipur andDr. Arun Gaur MNIT Jaipur.The innovative feature of this event was the exhi- bition of research models/posters on the theme oftransport infrastructure by the students. The stu-dent showcased the solutions to various problemsand current issues & situations in the road sec-tor. Prizes were distributed to encourage students.The models & posters were evaluated by a groupof experts under categories namely (i) Electronics(ii) Architecture (iii) Civil & (iv) Posters. Thewinners under four categories were as under:-

    1. Electronics Category

    (i) Shri Akhil Jain, 3rd   Year B.Tech

    Electronics & Communication

    Engineering, MNIT Jaipur on an

    embedded system which is used for

    tracking and positioning of any vehicle by

    using Global Positioning System (GPS) &

    GSM.

    (ii) Team of S/Shri Utkarsh Verma, Shayam

    Sunder, Vipin Kumar Choube & Saurabh

    Jain (VII SEM, VIT-EAST, ECT) on

    Multi Storeyed Automatic Parking;

    (iii) Team of S/Shri Gaurav Upadhyay

    & Hitendra Singh Rathore, 3rd   Year

    B.Tech (Electrical Enginnering),

    Poornima Institute of Engineering &

    Technology, Jaipur (PIET) on sendingtimely information to the train drivers

    regarding signals, boards and approaching

    trains.

    2. Architecture Category

    (i) Team of Shri Kamal Tahilramani,

    Shri Prateek Parashar, Shri Deepak

    Kumar, Shri Samarth Patel, Ms Umang

    Jain & Shri Tushar Sharma (Ayojan

    School of Architecture) on Elevated

    Road Over The Tonk Road, Jaipur with

    a underpass crossing on B2 Bypass and

    Provision of Suspended Monorail.

    (ii) Team of S/Shri Saptarshi Kapri, Mitesh

    Jatolia, Preet Kanwar Singh, Kartik

    Paturkar & Vipul Raj (Ayojan School of

    Architecture) on Metro Station Design.

    3. Civil Engineering

    (i) Team of S/Shri Mukesh A. Patel (Ganpat

    University, Meshana, Gujarat) ShriGautam Dadhich (PDPU, Gandhinagar,

    Gujarat) & Dr. H.S. Patel (LDCE,

    Ahmedabad) on Modied Dynamic ConePenetrometer (DCPM) and Modied StateCone Penetrometer (SCPM).

    4. Poster 

    (i) Team of Mukesh A. Patel (Ganpat

    University, Meshana, Gujarat), Gautam

    Dadhich (PDPU, Gandhinagar, Gujarat &

    Dr. Rakesh Kumar (Associate Professor,

    SVNIT, Surat.

    The list of the educational institutions which

     participated in the event organized at MNIT

    Jaipur is as under:-

    •  Arya College of Engg. & Research Center,

    Jaipur 

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    9/100

    HIGHLIGHTS

      INDIAN HIGHWAYS, MAY 2013 7

    •  Aayojan School of Architecture, Jaipur 

    •  Amity School of Engineering and Technology

    •  Baldev Ram Mirdha Institute of Technology,

    Jaipur •  CBS Group of College

    •  Ganpat University, Meshana, Gujarat

    •  Global Institute of Technology, Jaipur 

    •  Government Engineering College, Jhalawar 

    •  Gyan Vihar University, Jaipur 

    •  IIT Roorkee

    •  Jaipur Institute of Technology, Group of

    Institutions, Jaipur 

    •  JECRC, Jaipur 

    •  Kautilya Institute of Technology &

    Engineering, Sitapura, Jaipur 

    •  L. D. College of Engineering, Ahemdabad 

    •  NIET (NIMS University), Jaipur 

    •  P. I. E. T. Jaipur 

    •  Pandit Deendayal Petroleum University,

    Gandhinagar, Gujarat

      PEC University of Technology•  Poornima Group of Institutions, Jaipur 

    •  Poornima Institute of Engineer and

    Technology, Jaipur 

    •  Sri Balaji College of Engg. & Tech., Jaipur 

    •  Sri Shakti Institute of Engineering and

    Technology

    •  BMS College of Engineering, Bangalore

      Orissa College of Engineering, Bhubaneswar •  NIT, Surat

    The new materials/equipment/instruments

    accredited by IRC were also displayed in the

    Technical Exhibition. It helped the students

    to get an exposure of the emerging materials/

    technology/techniques in the road sector.

    Glimpses of Prize Distribution & Winning Models

    Winner Civil Category (Modied Cone Penetrometer (DCPM) and Modied Static Cone Penetrometer (SCPM)

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    10/100

    HIGHLIGHTS

      8 INDIAN HIGHWAYS, MAY 2013

    Architecture Category (Elevated Road) Winner (Joint) Electronics Category (Timely information given

    to train driver regarding signals, board and approaching trains)

    Winner Electronics Category (Tracking and Positioning of any vehicle by using GPS & GSM)

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    11/100

    HIGHLIGHTS

      INDIAN HIGHWAYS, MAY 2013 9

       W   i  n  n  e  r   (   J  o   i  n   t   )   E   l  e  c   t  r  o  n   i  c  s   C  a   t  e  g  o  r  y

       (   M  u

       l   t   i   S   t  o  r  e  y  e   d   A  u   t  o  m  a   t   i  c   P  a  r   k   i  n  g   S  y  s   t  e  m   )

       P  r   i  z  e   D   i  s   t  r   i   b  u   t   i  o  n   b  y   S  e  c  r  e   t  a  r  y   G  e  n  e  r  a   l ,

       I   R   C

       &   D   i  r  e  c   t  o  r   M   N   I   T ,   J  a   i  p  u  r

       W   i  n  n  e  r  o   f   A

      r  c   h   i   t  e  c   t  u  r  e   C  a   t  e  g  o  r  y   (   M  e   t  r  o   S   t  a   t   i  o  n   D  e  s   i  g  n   )

       W   i  n  n  e  r  o   f   P  o  s   t  e  r   C  a   t  e  g  o  r  y   (   M   i  c  r  o  s  u  r   f  a  c   i  n  g  :   A  n   I  n  n  o  v  a   t   i  v  e

       T  e  c   h  n  o   l  o  g  y   f  o  r   P

      a  v  e  m  e  n   t   P  r  e  v  e  n   t   i  v  e   M  a   i  n   t  e  n  a  n  c  e   )

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    12/100

      10 INDIAN HIGHWAYS, MAY 2013

     

     

     

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    13/100

      INDIAN HIGHWAYS, MAY 2013 11

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    14/100

      12 INDIAN HIGHWAYS, MAY 2013

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    15/100

      INDIAN HIGHWAYS, MAY 2013 13

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    16/100

      14 INDIAN HIGHWAYS, MAY 2013

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    17/100

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    18/100

      16 INDIAN HIGHWAYS, MAY 2013

    INDIAN ROADS CONGRESS, NEW DELHI

    ADVERTISEMENT TARIFF FOR “INDIAN HIGHWAYS” - A MONTHLY MAGAZINE

    Position of page Rates for

    regular issue

    (b/w)per page

    Rates for

    Annual /Special

    Number (b/w)per page

    Rates for

    regular issue

    (4-Color)per page

    Rates for Annual/ 

    Special Number

    (4-Color) perpage

    Annual Charges for

    12 issues i.e. after

    10% discount

    Outside Back Cover - - Rs.24,000/- Rs.30,000/- Rs.2,59,200/-

    Inside Front/ Inside Back Covers - - Rs.23,000/- Rs.29,000/- Rs.2,48,400/-

    Full page Rs.7000/- Rs.8000/- Rs.20,000/- Rs.25,000/- Rs.75,600/- (b/w)

    Rs.2,16,000/- (color)

    Half page Rs.4000/- Rs.4500/- Rs.12000/- Rs.15000/- Rs.43,200/- (b/w)

    Rs.1,29,600/- (color)

    Quarter page Rs.2500/- Rs.3000/- - - Rs.27,000/-

    Tender Notice Rs.9,000/- Rs.9,000/- - - -

    ADVERTISEMENT TARIFF FOR “JOURNAL OF THE INDIAN ROADS CONGRESS” A QUARTERLY JOURNAL

    Position of page Rates per page (b/w) Rates per page

    (4-Color)

    Annual Charges for

    4 issues i.e. after 10% discount

    Outside Back Cover - Rs.24,000/- Rs.86,400/-

    Inside Front/ Inside Back Covers - Rs.23,000/- Rs.82,800/-

    Full page Rs.7000/- Rs.20,000/- Rs.25,200/- (b/w)

    Rs.72,000/- (color)

    Half page Rs.4000/- Rs.12000/- Rs.14,400/- (b/w)

    Rs.43,200/- (color)

    MECHANICAL DATA

      Advertisement print size 24 cm x 19 cm for full page & Tender Notice  11.5 cm x 19 cm for half page

      11.5 cm x 7.5 cm for quarter page

    TERMS & CONDITIONS

    1. 10 per cent Agency commission will be allowed to Advertising Agents only on the advertisements received through them.2. 10 per cent discount will be allowed to advertisers if space is booked for all the 12 issues of Indian Highways or 4 issue of

    Journal of the Indian Roads Congress.3. No discount will be allowed for advertisements received directly for less than 12 issues in the case of Indian Highways and

    4 issues in case of Journal of the Indian Roads Congress.4. Only one voucher copy of the issue will be supplied free to an Advertiser for each advertisement. A copy of the printed

    advertisement will be supplied to Agents.5. All payments are to be made in advance. This is applicable to advertising agents also. Demand Drafts/Cheques may be drawn

    in favour of the Secretary General, Indian Roads Congress, New Delhi.6. Indian Highways is printed one month in advance as such all materials received by the 18th of the preceding month would

     be included in the issue to which it pertains.

    Release orders may be sent to:

    D. Sam Singh

    Under Secretary,

    Indian Roads Congress,

    Kama Koti Marg, Sector-6, R.K. Puram,

     New Delhi – 110 022Tel: +91 11 2618 5315,19/Extn. 203, 2618 5273

    E-mail: [email protected]

    ADVERTISEMENT TARIFF

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    19/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 17

    ABSTRACT

    Daily and seasonal variations in temperature and moisture

    are important factors inuencing the functioning of concrete pavements. In addition to temperature, other environmental

    factors that affect rigid pavement performance include humidity,

     precipitation, amount of solar radiation etc. This paper is part of

    a comprehensive study on High Performance Cement Concrete

    Pavements (HPCCPs) conducted at Bangalore University.

    Amongst the HPCs, an approach is made in this paper to

    determine the realistic temperature differential in High Volume

    Fly Ash Concrete (HVFAC). Durability tests such as abrasion,

    water absorption and exural fatigue were conducted on HVFAC

    in addition to compressive and static exural strength tests. Thetest results show that the HVFAC is a high performance concrete.A HVFAC concrete slab is instrumented with thermocouples, for

    monitoring temperature at three regions, interior, edge and corner.

    Thermocouples are inserted at top, middle and bottom of the slab.

    The variation in pavement temperature is recorded every hour for

    seven days. The inuence of climatic conditions such as humidityand number of solar radiation hours on daily and seasonal variations

    (summer, winter and monsoon) of temperature differential through

    the slab thickness is investigated. The minimum top temperatures

    during summer, winter and monsoon seasons were 22.8˚C, 21.30ºCand 21.10ºC respectively. The maximum top temperatures duringsummer, winter and monsoon seasons were 53.9ºC, 42.30ºC and38.60ºC respectively. The maximum temperature differentials

    observed during summer, winter and monsoon season were 13.5ºC,13ºC and 8.80ºC respectively. Taking into account the localenvironmental factors and the material properties, temperature

    differential prediction models for HVFAC slabs are suggested

    in this paper. The temperature differential at any location in

    India can be obtained by developing similar prediction models

    and substituting values of the environmental parameters in the

     prediction models. The values of these parameters are available

    from Indian Meteorological Department. Temperature stresses are

    evaluated by using the classic Westergaard equations.

    1 INTRODUCTION

    Temperature is an important factor inuencingthe performance of cement concrete pavements.

    The temperature differential is a function of the

    heat transfer mechanisms of thermal conduction,

    convection and solar radiation. Liu Wei 2005 reports

    that environmental factors like humidity, wind,

     precipitation, frost etc. also cause variations in

    temperature. The cement concrete pavement response

    to temperature differences through the slab thickness

    is recognized as curling. A positive temperature

    difference between the top and bottom surfaces of the

    concrete slab during day time causes the slab corners

    to curl downwards, while a negative temperature

    difference during night time results in upward

    curling of slab corners. Since concrete can recover

    its original shape after the effects of temperature

    variation are removed, the curling due to temperature

    variation from daily or seasonal weather condition

    can be considered as a transient component of slab

    curvature behavior due to environmental loading.

    Curling induces stresses in the pavement, since the

     pavement is restrained by its weight. The thermally

    induced stress caused by such interaction may result

    in early pavement cracking. At present, in India

    IRC:58 “Guidelines for the Design of Plain Jointed

    Rigid Pavements for Highways,” is used for design

    of cement concrete pavements. IRC:58 suggests

    temperature differential values for different zones in

    India to evaluate temperature stresses.

    Mechanistic-empirical design is a method of

    designing highway pavements. It combines empirical

    relationships obtained from the eld data withtheoretical predictions based on the mechanics of

    materials. This method relates inputs such as trafc,

    loadings, soil strength, climate, etc. to the actual pavement response. Mechanistic-empirical method

    * Research Scholar, Department of Civil Engineering, Bangalore University, Bangalore, E-mail: [email protected].

    ** Professor in Highway Engineering, Bangalore University, Bangalore, E-mail: [email protected].

    *** Assistant Engineer, Water Resources Department, KPWD, Belgaum

    INFLUENCE OF ENVIRONMENTAL FACTORS ON

    TEMPERATURE DIFFERENTIAL IN HIGH PERFORMANCE

    CEMENT CONCRETE PAVEMENTS

    K.S. SURESH K UMAR *, M.S.AMARNATH** AND G.B. AVINASH***

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    20/100

    TECHNICAL PAPERS

      18 INDIAN HIGHWAYS, MAY 2013

    is more accurate than empirical method because the

    empirical method only relies on the eld performance,while the Mechanistic-empirical method combines

     both eld performance and theoretical prediction

    models. A Mechanistic – Empirical design approach ismade in this study by considering the environmentalfactors, solar radiation and humidity in addition to

    air temperature to determine the realistic temperature

    differentials in HVFAC.

    2 EXPERIMENTAL INVESTIGATIONS

    The present study is part of a comprehensive study

    on High Performance Cement Concrete Pavements

    (HPCCPs) conducted at Bangalore University.

    Amongst the HPCs an approach is made in this paper

    to determine the realistic temperature differential inHigh Volume Fly Ash Concrete (HVFAC) only. An

    existing HVFAC pavement slab free from vehicular

    movement is identied for conducting temperaturestudies. The study area is located in the southern part

    of India at Bangalore City, Karnataka, geographically

    located at latitude 12º 95`N and longitude 77˚54̀ E. Dimensions of the HVFAC pavement slab are

    4400 mm x 3300 mm and thickness 300 mm. The

    shoulders have a minimum CBR value of 10% andcompacted with vibratory roller at OMC to achieve

    density of 97% MDD. M40 Grade concrete havingmix proportions 1:1.22:1.78 consisting of Binder50:50 (53 Grade cement conrming to IS12269:1987and Fly Ash- Pulverized Fuel Ash conrming toIS3812:2003), water binder ratio 0.38 is used to

    cast the slab. To determine the compressive strength

    of HVFAC pavement under study, cylindrical core

    samples were taken two years after the pavement

    was laid. The cylindrical compressive strength was

    44.35MPa. The equivalent cube compressive strength

    (calculated as per IS: 516-1999 Clause 5.6.1) was

    55.44MPa.

    3 SLAB INSTRUMENTATION

    To record the temperature at different depths of the

    concrete slab temperature sensors called thermocouples

    are used. A thermocouple is a sensor for measuring

    temperature. It consists of two dissimilar metals,

     joined together at one end, which produces a small

    unique voltage at a given temperature. This voltage is

    measured, converted and displayed by an electronic

    digital temperature indicator directly as temperature

    in degree Celsius. In this study K–type thermocoupleand a temperature indicator capable of measuring

    0.1ºC with a range of -10.0ºC to 100.0ºC is used.20 mm diameter holes are drilled at interior, edge andcorner region of the slab. Thermocouples are xed toa wooden bead 16 mm square and 300 mm long such

    that the tips of the thermocouples are exactly 25 mm,

    150 mm and 275 mm from top of the slab as shown in

    Plate 1. The wooden beads are inserted into the hole

    and the space around it is grouted using cement slurry.

    Fig.1 shows a typical schematic representation of slab

    instrumentation.

    Plate 1 Thermocouples Fixed to Wooden Bead and

    Data Recording

    Fig.1 Schematic Representation of Slab Instrumentation

      A = 275 mm, B = 150 mm, C = 25 mm,

    T = Tip of the Thermocouple

    4 DATA ACQUISITION

    Each thermocouple has two leads. The leads

    are connected to a digital temperature indicator

    which directly shows temperature at the tip of the

    thermocouple in degree Celsius. Plate 1 shows

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    21/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 19

    thermocouples xed to wooden bead at three levelsand digital temperature indicator connected to leads

    for recording temperature. Temperatures at top,

    middle and bottom of the slab and air temperature at

    about 300 mm from slab top are recorded every hourfor seven days during each season. The temperature

    data are manually recorded. Environmental data such

    as solar radiation hours and humidity are taken from

    the Indian Meteorological Department for Bangalore

    region.

    5 MONITORING RESULTS AND DATA

    ANALYSIS

    Pavement top temperatures ranged from 45ºC to52ºC during summer season (last week of April)

    and the average air temperature was 34ºC. Duringwinter season (last week of December) pavement

    top temperatures ranged from 22ºC to 36ºC and theair temperature ranged from 20ºC to 36ºC. During

    monsoon season (last week of June) pavement top

    temperatures ranged from 31ºC to 39ºC and the airtemperature ranged from 29ºC to 34ºC. The hourlyvariation of temperature at top, middle and bottom

    in the corner region for monsoon season is shown inFig.2.

    The temperature of slab is more at the top during day

    time and more at the bottom during night time. This is

     because the top of the slab is exposed to direct solar

    radiation. Variation of temperature at top of slab is

    more than that at bottom. This could be due to loss

    of heat during transmission. Variation of temperature

    is more at edge region than at corner region. This is

    due to more loss of heat at edge region as the slab is

    in contact with the shoulder. Maximum and minimumtemperatures and day time and night time temperature

    differential for summer, winter and monsoon seasons

    in HVFAC slab are shown in Table 1.

    Fig.2 Hourly Variation of Temperature in HVFAC Slab

    Table 1 Temperature and Temperature Differential in HVFAC Pavements

    Summer season Winter season Monsoon season

    Data Position I E C I E C I E C

    Min.

    Temp.

    T 28.90 28.80 28.40 19.50 22.30 19.60 22.80 21.10 24.20

    B 30.10 29.90 29.40 - 18.60 23.60 24.30 20.10 25.60

    Max.

    Temp.

    T 53.90 52.00 51.80 42.30 39.20 37.70 33.90 33.00 38.60

    B 49.80 44.30 50.40 - 32.00 31.10 33.80 29.70 34.80

    T Diff  Night -8.00 -6.80 -8.00 - -6.10 -6.00 -8.80 -6.10 -8.30

    T Diff  Day 11.40 13.50 13.40 - 13.00 10.30 5.20 5.90 5.00

    I is the Interior region, E the edge region and C the corner region. T is top and B is bottom of slab.

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    22/100

    TECHNICAL PAPERS

      20 INDIAN HIGHWAYS, MAY 2013

    Note :

    1. The temperature differentials in the slab refer to the

    difference between the top and bottom temperature.

    2. Temperature at bottom of slab in the Interior region is

    not recorded due to malfunctioning of thermocouple.

    It is observed that the day time temperature differential

    in the edge region is more than that at interior and

    corner regions where as the night time temperature

    differential is more in interior region. There is not

    much difference between average air temperature

    during winter and monsoon season. From Table 1 it

    is seen that the temperature differentials are positive

    during day time and negative during night time,

     Negative night time temperature differential values

    are less signicant than positive day time temperaturedifferentials and negative differentials occur much less

    often than positive differentials this can be attributed

    to the presence of solar radiation during day time.

    The pavement top temperature and the temperature

    differential are lower during monsoon than winter.

    This could be due to precipitation and the presence

    of clouds during monsoon thus causing lesser solar

    radiation.

    6 DEVELOPMENT OF PREDICTION

    MODEL FOR TEMPERATURE

    DIFFERENTIAL IN HVFAC SLAB

    A statistical model is attempted to predict the

    temperature differential as a function of pavement top

    temperature and depth of the slab. As the pavement

    temperature depends on environmental factors it is

    desirable to rst develop a model for pavement toptemperature which is dependant on air temperature,

    humidity and accumulated solar radiation. For datacorrelation, it is necessary to dene the following;

    a) Solar Radiation Hours (SRH): This is denedas the number of hours elapsed from sunrise

    to the time peak pavement top temperature is

    reached.

     b) Percent Humidity (H): It is the humidity at the

     peak period.

    c) Average daily air temperature (AAIRT): The

    average of daily air temperature that occurs

     between 9 a.m. to 2 p.m.

    6.1 Pavement Top Temperature PredictionModel

    The pavement top temperature prediction models are

    described by the following equations:

    Winter pavement top temperature prediction

     model 

    TTOP=16.25+0.21*AAIRT+1.91*SRH+0.01*H (1)

    (n = 7, R 2 = 0.92)

    Summer pavement top temperature prediction

     model  

    TTOP=51.51+1.11AAIRT-4.88SRH+0.14*H (2)

    (n = 7, R 2 = 0.75)

     Monsoon pavement top temperature prediction

     model 

    TTOP=16.69+0.42*AAIRT+1.53*SRH–0.41*H (3)

    (n = 7, R 2 = 0.76)

    Combined pavement top temperature prediction

     model (summer, winter and monsoon season)

    TTOP=32.18–0.03*AAIRT+1.48*SRH–0.15*H (4)

    (n = 14, R 2 = 0.73)

    Where; TTOP is the maximum pavement top

    temperature and AAIRT is the average air temperature

    in degree Celsius, SRH is the solar radiation period in

    hours and H = Humidity in percent.

    6.2 Temperature Differential Prediction Model

    The prediction models for positive day time

    temperature differentials are developed using the

     pavement top temperature developed from equations

    (1) to (4) and depth of the slab as variables.

      ΔT+ = -27.87 + 0.68*TTOP + 0.04*D (5)

    Where; ΔT is the positive day time temperaturedifferential in degree Celsius, TTOP is the pavement

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    23/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 21

    top temperature in degree Celsius and D is the

    thickness of the concrete slab.

    The maximum temperature differentials actually

    recorded during each season are shown in Table 2. The

    temperature differentials arrived at using temperature

    differential prediction models are shown in

    Table 3. The comparison between actual and predicted

    temperature differentials during winter season at

    edge region is shown in Fig.3. Table 4 shows the

    comparison between actual and predicted temperaturestresses.

    Table 2 Actual Temperature Differentials Recorded During Each Season

    SUMMER SEASON WINTER SEASON MONSOON SEASON

    Day I E C I E C I E C

    1 4.9 8.8 8.5 - 11.4 9 5.2 5.9 4.2

    2 4.9 8.8 8.5 - 13 8.93 3.2 3.3 2.4

    3 1.1 6.6 7.6 - 10.4 10.3 2.5 3.1 2.3

    4 4.7 8.6 8.3 - 10.2 8.8 0.8 2.8 1.4

    5 1.7 7.1 8 - 8.8 9 3.2 2.7 1

    6 4.7 8.6 8.3 - 11.3 8.8 3.2 5.2 3.5

    7 4.7 8.6 8.3 - 10.6 6.6 5.1 3.1 4.7

    Table 3 Temperature Differentials Arrived at Using Prediction Models

    SUMMER SEASON WINTER SEASON MONSOON SEASON

    Day I E C I E C I E C

    1 4.52 7.36 7.44 - 12.38 12.46 7.99 9.8 4.71

    2 4.06 7.28 7.56 - 13.82 12.11 6.33 9.3 3.74

    3 4.01 7.25 7.57 - 12.62 12.83 7.11 8.25 3.524 4.54 7.36 7.47 - 10.77 11.75 3.8 7.23 2.05

    5 3.65 7.16 7.69 - 10.98 11.05 7.13 6.82 2.54

    6 3.97 7.23 7.57 - 12.13 11.68 6.83 8.39 3.18

    7 4.11 7.25 7.56 - 11.04 10.92 7.79 8.43 3.34

    Fig.3 Comparison Between Actual and Predicted Temperature Differentials

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    24/100

    TECHNICAL PAPERS

      22 INDIAN HIGHWAYS, MAY 2013

    Table 4 Comparison Between Actual and Predicted Temperature Stresses

    SUMMER SEASON WINTER SEASON MONSOON SEASON

    ACTUAL

    TEMPERATURE

    STRESSES

    Day I E C I E C I E C

    1. 0.51 0.82 0.41 - 1.06 0.43 0.54 0.55 0.202. 0.51 0.82 0.41 - 1.21 0.43 0.33 0.31 0.11

    3. 0.12 0.61 0.36 - 0.97 0.49 0.26 0.29 0.11

    4. 0.49 0.80 0.40 - 0.95 0.42 0.08 0.26 0.07

    5. 0.18 0.66 0.38 - 0.82 0.43 0.33 0.25 0.05

    6. 0.49 0.80 0.40 - 1.05 0.42 0.33 0.48 0.17

    7. 0.49 0.80 0.40 - 0.99 0.32 0.53 0.29 0.22

    1. 0.47 0.68 0.36 - 1.15 0.60 0.84 0.91 0.22

    CALCULATEDTEMPERATURE

    STRESSES

    2. 0.42 0.68 0.36 - 1.29 0.58 0.66 0.86 0.18

    3. 0.42 0.67 0.36 - 1.17 0.61 0.74 0.77 0.174. 0.48 0.68 0.36 - 1.00 0.56 0.40 0.67 0.10

    5. 0.38 0.67 0.37 - 1.02 0.53 0.75 0.63 0.12

    6. 0.42 0.67 0.36 - 1.13 0.56 0.71 0.78 0.15

    7. 0.43 0.67 0.36 - 1.03 0.52 0.82 0.78 0.16

    It is observed from Table 2 that the actual temperature

    differential on day three and day ve during summerseason is very low. This is because on these days the

     pavement top temperatures dropped when it became

    cloudy and there were sudden heavy rainfalls during

    the day. After the rain ceased the sky remained cloudy,

    that prevented any possibility of increase in pavement

    top temperature. It is observed that the temperature

    differential from predicted models is slightly more

    than the actual temperature differentials, except for

    summer season. This could be due to sudden rainfall

    on two days. Similarly the temperature stresses

    evaluated from the prediction models are on the

    higher side. Fig.4 shows the comparison between

    actual temperature stresses and predicted temperature

    stresses during winter season at edge region.

    Fig.4 Comparison Between Actual and Predicted Temperature Stresses

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    25/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 23

    7 CONCLUSIONS

    Analysis of the instrumented concrete slab temperature

    data recorded for the three season’s summer, winter

    and monsoon yielded the following main ndings:

    ● The air temperature, solar radiation andhumidity are factors inuencing temperaturedifferential in concrete slabs.

    ● Negative night time temperature differentialvalues are less signicant than positive day timetemperature differentials. Moreover, negative

    differentials occur much less often than positive

    differentials.

    ● There is not much difference between average

    air temperature during winter and monsoonseason.

    ● It is observed that the minimum top temperatureduring summer, winter and monsoon season is

    22.8˚C, 21.30˚C, and 21.10˚C respectively.

    ● It is observed that the maximum top temperaturesduring summer, winter and monsoon season are

    53.9 ˚ C, 42.30 ˚C and 38.60˚ C respectively.

    ● The maximum pavement top temperature during

    summer is 21.5% higher than that during winterand 28.4% higher than that during monsoonrespectively.

    ● The pavement top temperature and thetemperature differential are lower during

    monsoon than winter; this can be accredited

    due to the presence of clouds thus causing

    lesser solar radiation.

    REFERENCES

    1. Choubane and Tia, 1995 “Analysis and Verication ofThermal Gradient Effects on Concrete Pavements”,

    Journal of Transportation Engg., Vol. 121, No. 1.

     pp.75-81.

    2. IRC:58 “Guidelines for the Design of Plain Jointed Rigid

    Pavements for Highways” The Indian Road Congress,

     New Delhi.

    3. Khanna S.K. and Justo C.E.G. 1996, “Highway

    Engineering,” Nem Chand & Bros Roorkie.

    4. Liu Wei, 2005, “Improved Model for Analysis of

    Load and Thermal Effects on Concrete Pavements”,

    Ph.D. Dissertation Report (Unpublished) submitted to

    Department of Civil Engineering, National University of

    Singapore.

    5. Yang H. Huang, 1993, “Pavement Analysis and Design,”Prentice Hall.

    6. Yoder E.J. and Witczak M.W., 1975, “Principles of

    Pavement Design”, John Wiley and Sons Inc.

    7. Wei LIU and Tien Fang FWA, 2003. “Effects of Nonlinear

    Temperature Distribution on Thermal Stresses in Concrete

    Pavements”, Journal of the Eastern Asia Society for

    Transportation Studies, Vol.5, pp 1023 to 1034.

    8. Puttappa C.G., 2006, “Investigations on High Performance

    Cement Concrete for Pavements”. Ph.D. Dissertation

    Report (Unpublished) submitted to Bangalore University.

    9. Jose T. Balbo, Andrea A. Severi, 2002, “Thermal Gradientsin Concrete Pavements in Tropical Environment: An

    Experimental Appraisal”, Laboratory of Pavement

    Mechanics, Sao Paulo, Brazil. TRB paper No. 02-2560.

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    26/100

      24 INDIAN HIGHWAYS, MAY 2013

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    27/100

      INDIAN HIGHWAYS, MAY 2013 25

    Audit involves ofcial inspection of an organizationaccount typically by an inspecting body. In respect of

    concrete structures it will mean a critical inspection of

    concrete structures, ascertain damages, distresses and

    defects appeared during construction or in service life.

    The author had an occasion to inspect more than 100

    concrete structures which developed either problem

    during construction or during in service life, if these

    are summarized subject wise, the main issues are as

     below:-

    A concrete structure is subjected to the effect of water,

    disturbances in the earth such as settlements and

    earthquakes, the effect of wind and environmental

    effects. In ancient Vastushastra there used to be a

     prayer at the foundation ceremony and even at the

    completion of the work stating that “Let the god of

    Rains (Varuna) protect this Vastu, let the earth on

    which Vastu is laid protect it from destruction, let the

    effect of wind and let the god of Environment protectthis structure”.

    In the concrete structures which developed some

    defects following main issues cropped up:-

    1. Erosion and cavitations of Bridge piers and

    foundations due to high velocity.

    2. Damage of concrete in buildings and bridges

    due to Alkali-Silica Reaction (ASR) or Delayed

    Ettrigingite Formation (DEF).

    3. Plastic Shrinkages in the newly laid concrete

    due to lack of appropriate curing.

    4. Inappropriate construction methods.

    QUALITY AUDIT FOR CONCRETE CONSTRUCTIONS

    DR . C V KAND*

    5. In respect of Aqueducts damages caused due

    to failure of joints and rubbing of canal water

    containing sand and pebbles on the bottom

    surface of the ducts are seen.

    6. Wrong procedure of well sinking and instances

    of well sinking in rock.

    1 EROSION AND CAVITATIONS

      (Fig. 1.1, Fig. 1.2, Fig.1.3)

    1.1 Hydro Dynamic Effects

    According to current practice and codal requirements,

     bridge piers are designed for the static effects caused

    due to velocity head, differential head etc. Recent

    observations have shown that the bridge piers are

    subjected to hydro-dynamic effects such as erosion

    and cavitation caused at high stream velocities. The

    hydro-dynamic effects are smaller and insignicant

    at lower stream velocities and may be ignored but at

    higher velocities these effects can cause damage and

    failure of structure.

    In high level bridges hydro-dynamic effects are

     predominantly on piers. Effects on abutments are

    not signicant. In submersible bridges the decking,

    is subjected to hydro-dynamic effects which are

    ultimately transferred to piers. The theoretical background and method of assessment of the effect

    is well known. The same is, however, critically

    examined, in the light of bridges.

    * Retd. Chief Engineer, PWD, Bhopal (MP), E-mail: [email protected]

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    28/100

    TECHNICAL PAPERS

      26 INDIAN HIGHWAYS, MAY 2013

    1.2 Erosion Due to Suspended Particles in

    Streams

    Rivers which carry coarse sand or gravel of large

     pebbles wears away the masonry or concrete of piers

    through abrasion. The deterioration of the submerged

    surfaces of masonry or concrete brought about by the

    abrasive action of solids in motion in uids is callederosion. The rate of erosion is dependent upon the

    following factors.

    i. Quantity of sand and gravel in water.

    ii. Shape, size and hardness of particles.

    iii. Velocity of the current.

    There is a relationship between the competent bottom

    velocity (the velocity at or above which a certain

     particle can be transported) and the size of particle

    dragged by the stream. This is given by d  = 36.15 V b2 

    where d  is in mm and V b is in m/sec.

    The diameter of particles own by current for variousvelocities will be

    Velocity m/sec Diameter mm

    1.5 80

    3.0 330

    4.5 730

    6.0 1300

    7.5 2030

    9.0 2930

    Model studies, to establish quantum of erosion of

    surface of structure in a given period at different

    velocities of current in sandy bed, are not available.

    According to ACI, if the quantity and size of solids

    are small; for example silt in irrigation canal, no

    appreciable erosion takes place on good concrete

    surface at bottom for velocity up to stream velocities

    of 3m/sec. Signicant erosion effect has been observedin structure in sandy river beds where the velocity of

    current is more than 4.5m/sec. Hard stone masonrystructures can stand higher velocities without abrasive

    action.

    Erosion of surface of submerged concrete structure

    will take place at velocities higher than 3m/sec. even

    if the ow is undisturbed and the shape of the surfaceis smooth and streamlined. If the shape of structure is

    not streamlined and the surface has depressions and

    there are projected corners, the ow will be disturbed.Separation of ow and formation of eddies will take place at such even spots. The velocity at the disturbed

    zone will increase and the stream would scoop out

    more quantity of sand from the bed. Increase in

    quantity of sand and increase in the velocity will

    thus aggravate abrasive action at uneven and un-

    streamlined spots in the structure. Movement of sand

    is vertical due to pushing up from bed by whirlpool

    action and horizontal due to current.

    Fig.1.1 Shape of Piers and Current Directions at Pier.

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    29/100

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    30/100

    TECHNICAL PAPERS

      28 INDIAN HIGHWAYS, MAY 2013

    1.5 Hasdeo Bridge at Champa

    In 1956, a submersible bridge was undertaken across

    Hasdeo River velocity of current is 9m/sec. During

    construction some foundation and decks got washed

    away in oods, due to high velocity. The bridge wasthen converted into a high level bridge. The high

    level bridge is provided with some wall type piers

    and some piers with 3 circular columns connected by

    diaphragms. Within 3 to 4 years of completion, it was

    observed that surfaces of concrete are eroded exposingthe metal in concrete matrix. Colcrete steining of one

    of the well foundation was damaged in nearly 75%circumference of upstream dredge hole of an ‘eight’

    shaped well. Depth of damaged portion was 1.8m. In

    another well, after damage of colcrete steining, RCC

    columns inside were also damaged due to erosion.

    These damages were obviously due to erosion caused

     by high stream velocity and further that the concrete

    was not suitable to withstand the fury of water currents.

    The plain concrete piers of Railway Bridge on d/s of

    this road bridge also showed surface erosion. The

    old railway bridge was provided with stone masonry piers. The bridge was deserted. However, one pier

    is standing. The stones of the masonry have large

     bushes. The bushes show seriations along bedding

     plane of the stone due to erosion. The case shows that

    circular columns with diaphragms are not suitable for

    high stream velocity. Detailed investigation of this

    case brought out that specications of concrete piersmust be compatible with stream velocity. Colcrete is

    not suitable for well steining. It is not being used now

    a day.

    1.6 Deolon Bridge (Sone River) Near Shahhol

    (M.P.)

    This submersible bridge was completed in 1950.

    In the oods of 1975 the bridge was submerged fornearly 36 hours with 5.8m, water above the bridge. On

    receding of the oods it was noticed that the bridgehad almost completely washed away. Maximum mean

    velocity of the stream was 6.1 m/sec. At 300m on the

    downstream, rocky hillocks project in the river on both

     banks. The channel is constricted and the river takes

    a sharp turn. All these caused disturbance of the owand increase in velocity. The structure was designed

    for a velocity of 3m/sec only. It was noticed that piers

    fell in different directions. Foundations of the bridge

    were laid on bouldery strata. Some piers got uprooted

    even from foundation level. Investigations showed

    that at the location where river width is constricted

    there is a fault zone, a deep hole in rocky bed having

    depth of 15m. This has occurred due to high velocity

    of water at construction site.

    A tower of a high power line on the bank of river

    consisted of 4 steel rail sections. The rails sheared off

    at the top of footing of the concrete block as if cut by

    a hacksaw. A large vortex was formed at the bridge

    site on account of physical features and it appears

    the tower was in worst zone of the vortex. This was

    a typical effect of cavitation, caused due to vortices

    Fig. 1.3

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    31/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 29

    at high velocity as explained in previous paragraph.

    Fall of piers was not along the direction of river. Piers

    fell in various directions and this shows turbulent owhaving deviations angles larger than 200. Inadequate

    assessment of velocity, bad seating and foundations

    on Bouldary strata are the causes of failure of the

     bridge.

    Photo 1.1, Photo 1.2, Photo 1.3, Photo 1.4 and

    Photo 1.5

    Cavitations and Erosion Damages

      Photo.1.1 Photo.1.2

    Photo 1.3 Erosion of the Stone Masonry at High Velocity

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    32/100

    TECHNICAL PAPERS

      30 INDIAN HIGHWAYS, MAY 2013

    2 ALKALI SILICA REACTION (ASR) OR

    DELAYED ETTRIGINGITE FORMATION

    (DEF)

    2.1  Alkali silica (aggregate) reaction is a recent

     phenomenon and is known as cancer of concrete. It

    attacks when moisture for one reason or another gets

    into the concrete structure and reacts with the alkali

     produced by certain types of cements. The resulting

    alkaline solution then reacts with silica found in

    some types of aggregate and sand and make the gel

    a powerfully moisture attracting element. The gel

    expands as it gathers more moisture and causes the

    concrete to crack. These cracks allow more moisture

    into the concrete and the problem gets worse. Several

    concrete structures in U.K. have suffered premature

    damage due to ASR. In India recently, we have come

    across this phenomenon in Hirakud dam spillway and

    Rihind dam power house structure and repairs are

    done. High alkali content in cement also causes ASR.

    Cements in India contain 0.4 to 1 percent alkali. It

    is advisable to restrict it to 0.6 percent. The reaction

    takes place in presence of moisture. Alkali silica

    reaction can be controlled by selection of non-

    reactive aggregate, use of low alkali cement, by

    adding pozollana in cement, by controlling moist

    condition. Alkali silica reaction will be at surface

    due to presence of rain water. Surfaces can be given

    waterproong paint treatment to minimize the effect.ASR occurs only when aggregate contains such

    element which can react with alkalis in cement. It

    does not occur in all concretes. ASR cause pot holes

    in deck slab of bridges. Such holes were observed in

    several bridges in western Madhya Pradesh where

    local sand was used. This local sand contains 30%

    Ferruginous compounds. The tests were carried out at

     National soil and material laboratory at CWPC, Delhi.

    IS 383 (Table 1) says that deleterious material should

    not be more than 5% in river sands. Chemical tests of

    sand should be obligatory.

    2.2  Delayed Ettringite Formation (DEF) – in steam

    cured precast concrete slabs of M40 strength, the slabs

    were staked and these were to be placed on precast

    girders and provide composite deck slab. Several cracks

    were noticed in the precast slabs. This can happen due

    to: a.) presence of sulphate in aggregates which cause

    delay in gaining strength, this phenomenon is caused

    due to delay in Ettringite formation. However, there

    are no precedence of DEF in India. b.) If water cement

    ratio in precast steam cured slab is less than 0.4 the

    slabs have to be cured for two days after removal from

    the steam curing. According to Neveele if this is not

    done cracks appear in the slab.

    Photo 2.1, Photo 2.2 and Photo 2.3

    Photo 1.4 Cavitation Damage

    Photo 1.5 Cavitation Damage

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    33/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 31

    3 CRACKS IN DECK SLAB OF THREE

    BRIDGES

    3.1 Background

    Cracks in the deck slabs of bridges were observed in the

    longitudinal and lateral direction of three Bridges.

    3.2 Nature of Crack:-

    In Bridge No.1 the cracks are in the longitudinal and

    lateral directions over the location of steel. Width

    of crack at top of slab was found to be 25,15,10,10

    and 5mm at ve locations, there are 36 cracks in thewidth of 11.2m. In Bridge No.2 & 3 similar cracks

    were observed. Cracks in Bridge No.1 & 2 are

    wider, in Bridge No.3 Cracks are not wide but these

    are throughout the span. At bottom of slab, precast

    concrete sacricial slab was used as a formworkand hence it was not possible to see if cracks have

    occurred. However, the core data showed that cracks

    are not extended generally below top of steel in top

    slab.

    3.3 The Likely Reasons of Cracks are Generally

    as below:-

    1. When steel inside the concrete is corroded, its

    volume is increased and the concrete cracks,

    such cracks are found along the vertical steel in

    columns and at the bottom of deck slab.

    2. Cracks can also occur due to defective that is

    weak concrete.

    3. If the Structure is in hot areas and where hot

    winds are present and where curing of concrete

    is not started as per the requirements of the type

    of cement used, plastic shrinkage cracks occur.

    3.4 Material Used & Method of Construction

    The materials used in all the bridges is crushed granite

    aggregate of black colour, the river sand, Grade 53

    cement of Ultratech (as per clause 302.1 of IRC:21

    & IS 12269), construction chemicals (IS-9103), water

    for concreting. All these materials have been tested

    according to codal requirements and no defect was

    found in the materials of concreting. Aggregate &

    sand are as per IS 383. Testing of these is as per IS

    2386. Concreting was done by using concrete pumps

    and the slump was 80 to 100mm. This is also alright.

    Cement and Fly Ash: Ultratech cement of 53 Grade is

    used for the RCC work. But this also causes shrinkage

    effects as observed in many Bridges and Buildings.

    Photo 2.1 RCC Box Type Deck in an Area Which Contains Sand

    with Ferruginous Compounds

    Photo 2.2 Beginning of Pot Holes in Deck 

    Photo 2.3 Pot Holes in Deck due to ASR 

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    34/100

    TECHNICAL PAPERS

      32 INDIAN HIGHWAYS, MAY 2013

    For RCC bridges & buildings grade 33 or grade 43 are

     preferable. However there is no codal ban on using

    53 Grade cement for RCC work. 20% Fly ash if addedin the cement, this should in fact reduce shrinkage.

    The above information reveals that there is no faultin the material used or in the procedure of concreting.

    It is therefore necessary to examine the procedure

    adopted for curing of concrete.

    3.5 Testing of Concrete Laid at Site by Non

    Destructive Tests

    Following Non-Destructive test were carried out:

    1. Ultrasonic Pulse Velocity Test and 2. Core Test

    UTPV test show that there are no doubtful or medium

    results. The depth of crack was also measured and itwas found to be from 20mm to 40mm that is up to the

    top of Steel bars only in one case the depth is more.

    3.6 Reasons for Cracks

    Since the materials used for concreting and the method

    of concreting did not display any defect, cracks might

    have occurred due to method adopted for curing of

    concrete in the hot weather with low humidity which

    is prevalent in this region. The record of temperature

    during concreting and the ambient temperature

    shows that the bridges are located in hot region and

    the temperature during concreting has been more

    than 30ºC. It is a hot area where besides temperaturehot winds also exist. It appears, on completing the

    concrete curing or watering of concrete was started

    late. Normally when Grade 53 cement is used the

     practice is to cover the concrete by Tarpaulin placed

    on test cubes on fresh concrete so that Tarpaulin does

    not touch the concrete. After 2 hours ponds are made

    with earth and these are gradually lled with water. If

    curing is delayed and if the concrete is in hot weather,it suffers from plastic shrinkage. Since the steel

    reinforcement is approximately has 40mm cover, the

    shrinkage will go up to the top of the steel bar without

    interruption. It cannot go deeper due to presence of

     bar and the cracks will be developed on steel along

    the direction of steel. This is what appears to have

    happened at site as can be seen from photographs of

    cracks.

    3.7 Plastic Shrinkage Cracks

    The American concrete Institute in ACI 116 denesPlastic Shrinkage Cracking as cracking that occurs in

    the surface of fresh concrete soon after it is placed and

    while it is still plastic. These cracks forms becauseof loss of bleed water from the surface of the fresh

    concrete by evaporation. The tensile strength of fresh

    concrete is very low since the concrete has not had time

    to set, the volume changes caused by this evaporation

    of the bleed water results in the formation of plastic

    shrinkage cracks. The critical condition exists when

    the rate of evaporation of surface moisture exceeds

    the rate at which the rising bleed water can replace

    it. Water reaching below the surface forms menisci

     between ne particle of cement and aggregate causinga tensile force to develop in the surface layer. If the

    concrete layers have started to set and has developed

    sufcient tensile strength to resist the tensile forces,cracks do not form. If the surface dries very rapidly,

    the concrete may still be plastic, and the cracks do not

    develop at that time; but the plastic cracks will surely

    form as soon as the concrete stiffens a little more.

    3.8 Rehabilitations Measures

    The test results show that the strength of concrete

    is not reduced. There is no need of providing epoxyconcrete. However, cement mortar 1:1.5 with ne sandand 15% polymer should be grouted. The procedurefor grouting will be to make small holes in the concrete

    going up to 30mm at 300mm c/c. An area of about

    1m x 1m be selected and perplex pipe of 10mm

    diameter be xed in the holes, all except one hole beclosed at top and grouting should be done at pressure

    from the open hole till the grout comes in the other

    holes. A specialized agency be engaged to do this work.

    In this manner grouting should be done and the wider

    cracks be nished by the same mortar if not lled bygrouting. In future the freshly laid concrete be covered

     by Tarpaulin and placed above test cubes as mentioned

    above, after about 2 hours. Earthen pond be made and

    water should be lled in the ponds gradually, 7 daysafter grouting the wearing coat can be laid. IS: 456

    of 2000 Para 13.5 contained instructions for curing.

    These should be followed.

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    35/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 33

    Photo 3.1, Photo 3.2, Photo 3.3 and Photo 3.4

    4 INAPPROPRIATE CONSTRUCTION

    METHODS

    Geotechnical investigations was carried out for two

    separate bridges. Each bridge has two separate 2-lane

     bridges. Thus there are total 4 bridges which contain

    18 well foundations. Geotechnical investigations was

    carried out by three different organizations namely

     by DPR consultants, by proof consultants and also by

    the contractor. All these three separate geotechnical

    consultants concluded that the soft rock is available

    at different depths in the well foundations, and

    recommended Safe Bearing Capacity of not more than80 T/m2. The design consultants proposed sinking of

    wells 5 to 7m in the soft rock and considered passive

    resistance in the design of wells, when the work was

    in progress sinking of wells in rock could be done

    only by blasting. In that process the wells are

    ● badly tilted and shifted,

    ● the well steining is cracked

    The investigation of these tilted and shifted well

    was carried out and following glaring facts came tonotice.

    i. In about less then 300m from the site of these

     bridges there are existing bridges constructed

     before Independence during British regime.

    These are submersible bridges. The bridge

    register shows that the foundations are taken

    only 4m below the bed level and laid on hard

    Photo 3.1 Plastic Shrinkage

    Photo 3.2 Plastic Shrinkage on Location of Steel Bars

    Photo 3.3 Core Test

    Photo 3.4 Core Test

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    36/100

    TECHNICAL PAPERS

      34 INDIAN HIGHWAYS, MAY 2013

    rock. However, this data was not collected

    during geotechnical investigation.

    ii. During sinking of the well large pieces of rock

    extracted by blasting could be seen at the site

    near the wells. Cubes of 100 mm x 100 mm x

    100 mm were chiseled out from these pieces

    and tested in the laboratory. In one case the

    safe bearing capacity was 300 T/m2, in another

    case it was 400 T/m2  (by adopting factor of

    safety 8) against the recommended capacity by

    the geotechnical experts of 80 T/m2.

    iii. The rectication of tilted and shifted pier wellswhich is causing more than 33% base area in

    tension is being done by providing Anchorrods in the tension zones and also all around

    the periphery. 32 mm Anchor rods are anchored

    2.5 m in rock and grouted by 1:1.5 cement

    mortar with 15% polymer. 2 bars of 32 mm are proposed to be anchored in 110 mm diameter

     bore. The bars are raised and anchored in the

    well cap with transverse circular stirrups. These

    anchor rods will take entire tension coming

    on the foundations and the direct load will be

    taken by the rock below. The cracks in the wellsteining have occurred because of blasting.

    These will be grouted by 1:3 Epoxy mortar. The

    entire well is lled up by concrete of the samestrength of well steining.

    iv. In respect of abutment well there are 2

    alternatives:

      a. To provide pre-stressed concrete active

    anchorages and x them in the rock below and in the well cap above.

      b. To provide RCC block wall near the well

    and lay the well cap on the well and this

     block with a view to relive the well from

    lot of tension and provide also some

    anchor rods, similar to pier wells.

    v. IRC:78 clause 705.3.2 recommends that in

    case of hard rock the seating of the well shall

     be such that the 75% perimeter is seated onrock and a sump (shear key) of 300mm is

    cut in hard rock and 6 dowel bars of 25 mm

    diameter are anchored in rock. The same code

    also recommends that the boring chart shall bereferred to constantly during sinking for taking

    adequate care while piercing different type of

    strata by keeping boring chart at the site and

     plotting the soil as obtained for the well sinking

    and comparing it with earlier bore data to take

     prompt decision. Ignoring these precautions can

    cause distresses of the type as explained above.

    There is no fault of concrete; the fault lies in the

    construction methodology.

    Photo 4.1, Photo 4.2, Photo 4.3 and Photo 4.4

    Photo 4.1 Tilted Well

    Photo 4.2 Tilted Well

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    37/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 35

    5 CONDITION SURVEY OF AQUEDUCT

    CUM BRIDGE

    5.1 Background and Details of Aqueduct

    This Aqueduct cum Road Bridge was completed in

    March 1991 on lump sum contracts with contractors

    design. It is now about 20 years old. Certain problems

    are being faced in the Aqueduct.

    The structural details of the Aqueduct are as below

    Total Length 966 meters

    Span arrangement 19 spans of 38.5 metres

    main spans

    10 spans of 9.97 metres

    Height from Lowest 33 m

     bed to Soft

    Duct size Twin duct 3.425 x 2.60

    5.2 Observations

    5.2.1  The conventional copper expansion joint are

     provided on the inner side of the duct. There is a gap

    of 50mm on the inner side of the aqueduct wall. This

    is lled up by Shalitex board to make it water tight.While nalizing the estimate there was a proposal to provide 25mm water proof coat on the inside of the

    duct. It was however proposed to do after observing

    the performance of the aqueduct during its operation.

    5.2.2  Canal water coming from Dam carries sand

    and pebbles and these rub on the top surface of the

     bottom slab of the duct. Concrete is badly eroded and

    aggregate get exposed.

    5.2.3  Besides Sand and the pebbles as mentioned

    above some larger stones of the size of masonry

    stones were found inside the duct. Nobody could

    explain how these stones have come because such

    stones cannot ow with a small velocity of 3.9 m/s.These appears to have been brought later and may be

    for some maintenance operation but not removed.

    5.2.4  Five Expansion joints of the aqueduct are

    damaged by miscreants who have broken the concrete

    outside the copper plate in the joint and removedthe copper plate. There is a leakage through joints

    when the canal water is let in the vertical steels in the

    concrete which was broken is exposed at some place.

    5.2.5  The Shalitex board at joints which are not

     broken is also damaged at places. The depth of water

    at highest water level inside the canal is only 2.5 m.

    5.2.6  The expansion joints at road level are only in

    the road way width. These are not extended in the

    footpath portion; therefore the rain water is leaking

    through the joints and caused dirty water marks on

    the soft of cantilever slab, on the vertical sides of theducts. Then due to water owing from the top of piercap down to the pier such dirty water marks are also

    seen on the pier.

    5.2.7  The aqueduct was inspected after severe

    Earthquake of 1997. It was brought out that plants have

    Photo 4.3 Tilt & Shift

    Photo 4.4 Tilt Being Reduced by Eccentric Loading

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    38/100

    TECHNICAL PAPERS

      36 INDIAN HIGHWAYS, MAY 2013

    sprouted on the pier cap and at the expansion joints

    outside. It was suggested that this should be removed

    and the roots lled with lime powder and Asafoetida.Generally these are Pipal trees. It appears that this has

    not been done; more such plants are supported on pier

    cap.

    5.3 Causes of Distresses and Rectications

    5.3.1  The canal water in the aqueducts bring with

    it silt, sand and pebbles. These ow along with thewater slowly but when the discharge is stopped these

    get accumulated and the ow characteristics expectedin the aqueduct is affected. That is why water gets

    stagnant inside the aqueduct even when the canal

    discharge is stopped. Inquiry reveled that there is no

    maintenance manual for the aqueduct. Criterion for

    the maintenance for the bridges is adopted for the

    aqueduct. But the IRC criterion does not have any

    guidelines for the ow of water inside of the duct andthe expansion joints in the duct. It has now become

    necessary to have such a maintenance manual for the

    aqueduct which will take into account the effect of

    ow inside the duct.

    5.3.2  These types of expansion joints are giving

    trouble in many aqueducts. Incidences of braking of

     joints with a view to remove costly metal like copper

     plates are observed. This is an age old joint and

    its replacement is not easy. In case of bridges strip

    seal expansion joints are provided replacement of

    these joints is simple. Polymer expansion joints are

    available It is better to change these expansion joints

     by elastomeric expansion joints.

    5.3.3  It is advised that details of the expansion jointand the procedure of its xing should be obtained fromthe manufacturers. Normally the expansion joints are

    xed by the manufacturer and they take the guaranteeof its functioning.

    5.3.4  It has been brought out that the top surface of the

     bottom slab has eroded. Erosion resistance capacity of

    M35 concrete is rather low. However, epoxy mortar

    with three parts of calcenite sand and one part of

    epoxy has erosion resistance nearly three times than

    that of M35 concrete. Therefore 15mm thick epoxy

    mortar should be laid over the bottom slab and also

    on the sides of this aqueduct to improve the erosion

    resistance.

    5.3.5  The accumulation of sand, silt & pebbles shows

    that duct has not been cleaned for years. It is felt that

    every year this must be cleaned at least twice once

     before the ood season and second after the oodseason.

    5.3.6  The canal alignment on both sides also needs to

     be cleaned of the debris and branches of trees, which

    get accumulated around the columns in the transition

    structures. It is better to avoid columns in transition

    structure as has been done in recent aqueducts.

    5.3.7  The erosion of concrete in the piers and wells is

    not signicant at this stage but this should be observedevery year.

    5.3.8  Wherever stalactite phenomenon is observed it

    is due to minor leakages. It is advisable to grout these

    spots by cement grout and stop these leakages. Since

    this is bridge cum aqueduct, the bridge engineers

    cannot ignore such defects in the duct.

    Photo 5.1, Photo 5.2, Photo 5.3, Photo 5.4, Photo 5.5

    and Photo 5.6

    Photo 5.1 Erosion at Base of Aqueduct

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    39/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 37

    6 AUTOGENEOUS HEALING OF

    CONCRETE (Figs. 6.1 and 6.2)

    6.1  Human body has a property to heal up woundsand restore it to its original texture. Similarly, it is

    observed that observed that cracks in concrete also

    heal up. Three examples are cited.

    6.2  In one bridge 15 m precast pre-tensioned

    girders closely spaced (18 girders in a width of

    8m) are provided. The pre-tensioned girders were

     brought on the river bank and stacked on the river bed

    Photo 5.2 Damage of Expansion Joint.

    Photo 5.3 Obstruction at Canal Transition

    Photo 5.4 Stalactite Phenomenon

    Photo 5.5 Damage at Junction of Well Cap and Well Steining

    Photo 5.6 Expansion Joints in Aqueduct

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    40/100

    TECHNICAL PAPERS

      38 INDIAN HIGHWAYS, MAY 2013

     before lifting. 4 girders showed cracks at mid span.

    Investigation showed that only half length of the

    girder was supported on bed and the remaining half

    was overhanging. These girders were not designed

    for such a cantilever prole. Vertical cracks occurredat the mid span. When the girders were placed on

    level supports on both ends cracks closed. Water was

    sprayed for 24 hours on the girders. Cracks healed up.

    This is called autogenous healing of cracks. One girder

    was then tested for full design load and it behaved as

    expected like an un-cracked girder. Four such girders

    are used in the bridge two girders at each end and

     bridge is serving the trafc since 1964 without anytrouble.

    6.3  It was decided to erect a small full scale model

    with ve girders on the bank and test it for destructionwith a view to ascertain share of load among girders

    and maximum destruction load. Two and half times

    design live load was placed. More than 100 cracks

    developed but the structure did not collapse. Loadwas retained for 48 hours and then removed. This was

    in 1969. The model is preserved at site. Not a single

    crack was visible when observed on 19/6/97. Cracks

    closed.

    6.4  An RCC bracket was constructed at site and it

    was desired to ascertain destruction load and behavior

    of joints. Two and half time design load was placed

    and retained for 48 hours. Bracket cracked profusely.

    This was in 1980. The bracket was retained. In ood

    of 1996 it fell down. All cracks have healed up.

    Load Test for Destruction, Cracks Totally Closed on Removal of Loads.

    Model Preserved at Sher Bridge Near Narsinghpur in Madhya Pradesh.

      Fig. 6.1 Fig. 6.2

    7 CONCLUSIONS

    The Audit for quality control Constructions of 6 case

    studies deliberated in this paper has brought out thatsome distresses in the concrete bridge structures have

    occurred not on account of any defect in the concrete.

    These have occurred due to inadequate appreciation

    of forces of nature like water current and environment

    or due to wrong methods of construction. Following

    lessons should be kept in mind:-

    1. The shape of bridge piers and specication of

    concrete should be compatible with the velocity

    of the stream.

    2. Velocity of the stream more than 6m/sec cancause not merely hydro-static effects but also

    hydro-dynamic effects such as erosion and

    cavitation of piers and this should be considered

    in the design and specications.

    3. If the chemical impurities in the aggregates and

    sands are more than 5% (IS 383) it can causeAlkali-Silica reaction, which is the cancer of

    the concrete. Therefore, aggregate and sands

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    41/100

    TECHNICAL PAPERS

      INDIAN HIGHWAYS, MAY 2013 39

    should be tested for chemical impurities.

    4. Cracks caused in concrete structures can be

    autogenously healed by removing the causes of

    the cracks and constantly watering the cracked

    concrete for 24 hours. Such cracked beamswhich are healed up are provided in bridges and

    are surviving for more than 25 years.

    5. The green concrete done in hot weather (more

    than 30ºC) should be covered by Tarpaulinand providing water ponds for curing after 2

    hours. It is extremely necessary to follow the

     precautions of curing contained in clause 13.5

    of IS 456 of 2000. This is more obligatory for

    structures where Grade 53 concrete is used. If

    the precautions are not taken, Plastic Shrinkage

    cracks occur on the surface of concrete slabs.6. The bed level inside aqueducts gets badly

    eroded on account of sand and pebbles owingin canal water. It is therefore, necessary to

     provide epoxy mortar 1:3 on the inner surfaces

    of aqueducts below water level.

    7. The conventional expansion joints of aqueducts

    are not easy to replace. The copper plate is

     broken and stolen. It is advisable to provide

     polymer type of expansion joints. The surfaces

    of concrete where steel is exposed & corroded

    should be repaired by polymer modied mortar

    on removing the rust on steel bars by sand blasting or by chemicals.

    8. While carrying out geotechnical investigations

    the foundation levels and the type of strata in

    the existing bridges must be investigated and

    the actual strata obtained during sinking be

    compared with the data given in the bore log

    and modications may be carried out in thedesigns if necessary.

    9. Expected life of concrete structures is 100

    years. This life can be ensured by keeping in

    mind some of the issues during constructionas mentioned above and also by frequent

    inspection i.e. Audit for quality concrete.

    REFERENCES

    1. Hydraulic investigations and problems of Bridges by

    C.V.Kand & A.K.Saxena, IRC 1989.

    2. Environment and materials investigations and problems

    of Bridges by C.V.Kand, IRC 1997.

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    42/100

      40 INDIAN HIGHWAYS, MAY 2013

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    43/100

      INDIAN HIGHWAYS, MAY 2013 41

    ABSTRACT

    The last decade witnessed unprecedented raise in output to the

    tune of 7% of world’s GDP. The BRIC countries contributedlargely to this unprecedented growth. Paradoxically, the gathered

    momentum of growth rate of Asia Pacic region had made thedeveloping countries to subtly suggest the growth as a proigacytowards un sustainability demanding in the controlled growth rate

    who were ironically talking about red tapism and bureaucracy not

    in very far past.

    Ironically, by the turn of 2008 and the beginning of 2009, the

    global recession led by United States had put India and Chinaon centre stage, where they were expected to play major roles

    in reviving the world’s economy by growth rates enabled by

    mammoth infrastructure development plans. As this paper being

    written during August 15, 2012, once again the European and

    Western economies which were showing the signs of recovery till

    then, seem to be plummeting.

    With the emphasis on fast growing economy, the developing

    countries will aim at achieving the above by creation of

    facilities to provide housing, sanitation and water supply, public

    transportation facilities, reach-ability to education and adequate

    employment opportunities which demands mammoth materials

    and energy consumption.

    Apart from this, the governmental efforts to bring in vast foreign

    investment to cater for thickly populated big markets, will warrant

    major chunk of the allocation in the plans for infrastructure

    development, where the civil engineering fraternity can contribute

    in optimizing and reducing the costs of the projects, which can be

    used for further sustainable development.

    Whenever, the sustainability in construction is addressed and

    discussed in any kind of forums, it is always conned to that part ofconcrete technology where Ordinary Portland Cement is partially

    replaced by mineral admixtures to reduce energy consumption

    from fossilised sources and also CO2 emissions to environment.The author has been advocating sustainable construction beyond

    this connement by extending the same to Value engineering,Rationalization of codes, Hazard mitigation, New technologies

    and materials, Sustainable structural systems since 2002 in

     National and International forums.

    SUSTAINABILITY, CHALLENGES & OPPRTUNITIES

    IN BRIDGE BUILDING

    V. N. HEGGADE*

    1 INTRODUCTION

    By virtue of enormous performance of China, India

    and Russia in 2007, the world output was raised by 7%in GDP (with out adjusting for ination), catapultingthe world economy. The Chinese and Indian economy

    with its unprecedented economic growth of more than

    5% might have potentially elevated the Asia and pacicregion on par with economies of European Union and

    United States with in a decade. The alarming growth

    rate of the developing countries caused concerns to

    the globe as a whole as there were sufcient evidenceto establish the relationship between depletion in non

    renewable energy resources (fossilised) with Climate

    change and the Growth rate.

    The Fig.111  projects the accelerated consumption in

    non-renewable energy sources while the GHG (Green

    House Gas) emissions leading to climate change as

     presented in Fig.211  depicts that the emissions in

    developing countries would cross over developed

    countries by around 2015.

    * Member-Board of Management, Gammon India Ltd., Mumbai, E-mail: [email protected]

    Fig.1 Projected Energy Consumption Sources

  • 8/19/2019 Indian Highways Vol.41 5 May 13

    44/100

    TECHNICAL PAPERS

      42 INDIAN HIGHWAYS, MAY 2013

    While the energy consumption

     per capita of developed countrieswhose GDP is high, is glaring

    from the Fig.3 that warrants the

    austerity measures for reducing

    the consumption, the developing

    countries like China and India

    whose growth rates are high

    have also very high population

    (Table 1) which can make the

    consumption leapfrog for a small

    increment in growth rate.

     paradoxically, the developed Western and European

    world are in the phase of their infra structure

    maintenance as such have to nd market in developingcountries for their growth.

    Obviously, the statistics above indicate that the

    countries living standards improve with the increase

    in the GDP and decreases with enhanced population.

    The increased consumption of energy and materials

    culminate in the growing accumulation of construction

    waste, hazards and emissions, necessitating the

    sustainability options to reduce the depletion in non

    renewable energy resources and potential climate

    change and their consequences.

    2 SUSTAINABLE CONSTRUCTION

    Whenever, we are talking about sustainability in

    transportation sector, we are inadvertently pushed in

    to ancient realm of bridges, materials and practices

    that are testimony of endurance. It is not surprising

    that the English word sustainability itself has its origin

    in ancient Latin word ‘sustenere’, meaning long term

    compatibility. Hither to, though the methodology to

    quantify the sustainability measure is not evolved, there

    are universal indicators viz Ecological, Economical

    and Social8. (Fig.4)

    Fig.2 Green House Gas Emission by Region

    Fig.3 Energy Consumption Country Wise

    The strongest enabl