MD 30 Business (Main Street) Community Safety and Enhancement Project
Public Informational Meeting
Thursday, November 20, 2014
![Page 2: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/2.jpg)
In this Presentation….
Project OverviewKey IssuesElements of DesignFunding and Schedule
![Page 3: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/3.jpg)
Project Location
MD 30 BUS from south of North Woods Trail to the CSX Railroad north of Hampstead.
![Page 4: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/4.jpg)
Project Overview
MD 30 Business is an undivided, two-lane urban minor arterial.
Existing roadway has 11-12 ft. lanes with parking lanes or shoulders.
Speed limit is 30 mph.
![Page 5: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/5.jpg)
Project Overview (continued)Rehabilitate the roadwayProvide Americans With Disabilities Act (ADA)
compliant sidewalks and sidewalk rampsImprove curb and gutter, driveway entrances,
crosswalks, and pedestrian signals Address drainage concerns, upgrade drainage
system, and provide new storm water management facilities
![Page 6: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/6.jpg)
Project Overview (continued)
Modify traffic signals and improve traffic markings and signage
Pedestrian lightingLandscaping and aesthetics improvements Relocate utilities (BGE, Verizon, Comcast)Minimize adverse impacts to environment;
environmental enhancements
![Page 7: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/7.jpg)
MD 30 Business Main Street Corridor Typical Sections
![Page 8: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/8.jpg)
MD 30 Business Main Street Corridor Typical Sections
![Page 9: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/9.jpg)
Plans Overview
![Page 10: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/10.jpg)
Plans Overview (continued)
![Page 11: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/11.jpg)
Elements of Design
Pedestrian ImprovementsIntersection and Roadway ImprovementsDrainage Landscaping and Aesthetic Improvements
![Page 12: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/12.jpg)
Pedestrian Safety and Connectivity
Sidewalk ConnectivityADA ComplianceSidewalk Maintenance
![Page 13: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/13.jpg)
Key Issues - Pervious Concrete Sidewalk
LocationsFunctionMaintenance
![Page 14: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/14.jpg)
Elements of Design - Pedestrian Improvements
ADA Compliant Sidewalk Sidewalk RampsDriveway Apron CrossingsPedestrian SignalProper Pedestrian Signage
![Page 15: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/15.jpg)
Elements of Design - Pedestrian Improvements (cont’d)
High Visibility CrosswalksEntrance-way Consolidation
(where feasible)Pedestrian Refuge Areas
![Page 16: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/16.jpg)
Elements of Design - Intersection and Roadway ImprovementsSignal timingPedestrian SignalsSignageResurfacingRestriping
![Page 17: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/17.jpg)
Elements of Design - Drainage
New Curb & GutterUpgrade Drainage SystemStorm Water Management
Facilities
![Page 18: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/18.jpg)
Elements of Design- Landscaping and Aesthetic Improvements
LandscapingPotential Retaining Wall Aesthetics
![Page 19: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/19.jpg)
Project Funding & ScheduleFundingProject is fully funded for Preliminary Engineering and ConstructionScheduleTown’s waterline project to Advertise spring 2015, to be completed
by spring 2016Design Completion - Fall 2015Construction – NTP Spring 2016 (SHA will hold another meeting
regarding construction activities prior to Notice To Proceed)Construction completion – approximately 3 years
![Page 20: In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.](https://reader036.fdocuments.us/reader036/viewer/2022081603/56649e4c5503460f94b41b71/html5/thumbnails/20.jpg)
Questions?