In Situ Chemical Reduction (ISCR) Fundamentals related to ... · In Situ Chemical Reduction (ISCR)...
Transcript of In Situ Chemical Reduction (ISCR) Fundamentals related to ... · In Situ Chemical Reduction (ISCR)...
In Situ Chemical Reduction (ISCR)
Fundamentals related to selection, design and
distribution of ISCR technologies at contaminated sites
Ravi Srirangam P.E., Ph.D.
PeroxyChem Environmental Solutions
Design and Application of Insitu Treatment Technologies
CT/MA
May 2016
2
BASIC PRINCIPLES OF ISCR
3
The beginning of ISCR for soil and
groundwater applications
“Rediscovery” of McCarty and Vogel Postulated Abiotic Pathways – “oxidation,
reduction, substitution, and dehydrohalogenation reactions occur
abiotically or in microbial systems”
Started with an interest in Abiotic MNA
Butler, E., Hayes, K., 2000. Kinetics of the transformation of halogenated
aliphatic compounds by iron sulfide. Environ. Sci. Technol. 34, 422–429.
Lee, W., Batchelor, B., 2002. Abiotic reductive dechlorination of chlorinated
ethylenes by iron bearing soil minerals. 1. Pyrite and magnetite. Environ. Sci.
Technol. 36, 5147–5154.
Wilson, J. T. (2003). Abiotic reactions may be the most important mechanism in
natural attenuation of chlorinated solvents. Presented at the AFCEE Technology
Transfer Workshop, Brooks AFB, San Antonio, TX.
4
What is ISCR?
• Reduction adds electrons to the contaminant (need an
electron donor)…… Oxidation removes electrons from the
contaminant (need an electron acceptor)
• ISCR involves transfer of electrons to contaminants from
reduced metals (ZVI, ferrous iron) or reduced minerals
(magnetite, pyrite etc.)
• ISCR of CVOCs occurs via both abiotic as well as abiotic
pathways....because both processes occur simultaneously
in the subsurface
5
• Chlorinated Solvents
PCE, TCE, cis-DCE, 1,1-DCE, VC
1,1, 2,2-TeCA, 1,1,1-TCA
CT, CF
• Pesticides
Toxaphene, Chlordane, Dieldrin, Pentachlorophenol
• Energetics
TNT, DNT, RDX, HMX, Perchlorate
• Heavy Metals
Examples of Contaminants Destroyed
Examples of Contaminants That Require Organic Amendment to ZVI for Destruction
• Chlorinated Solvents
1,2-DCA
DCM, CM
Contaminants Treated via ISCR
6
Direct Dechlorination Reactions
Reactions:
Fe0 Fe2+ + 2e-
2H2O 2H+ + 2OH-
2H+ + 2e- H2(g)
R-Cl + H+ + 2e- R-H + Cl-
7
Role of ZVI and DVI (Fe(II)
• Significantly reduced half-lives of CVOCs in the presence of ZVI
• Requires direct contact with ZVI surface
• Reaction is abiotic reductive dehalogenation; minimizes/eliminates DCE/VC
• ZVI provides a long-term source of DVI
to promote indirect chemical reduction
of CVOCs (formation of reactive iron
and iron sulfide minerals)
• β-elimination is the dominant pathway
(~90%); ZVI generates hydrogen so
some biotic reductive reactions are
supported
Typical CVOC Half-lives (Room temperature)
0
1
2
3
PCE TCE cDCE tDCE 11DCE VC CT TCM 111TCA 112TCA
Ha
lf-l
ife
(h
rs))
8
ISCR CONFIGURATION AND CASE STUDIES
9
Common ISCR Implementation Methods
Hydraulic fracturing/injection (120 ft, 37 m)
soil mixing
(40 ft, 12 m)
pneumatic fracturing
(90 ft, 27 m)
Nitrogen
Gas Source
Overburden
Treatment ZoneInjector
Atomized Slurry
in Gas Stream
Packer
Pneumatic
Injection Module
Ferox Injection
Trailer
Direct
injection
(30ft,9m)
continuous trenching
(35 ft, 11 m)
10
Expansion of Granular Iron Grain
Size Range
• 0.25 to 2 mm (-8 to +50 US mesh) for trenched PRBs
• 0.07 to 1.7 mm (-12 to +200 US mesh) for hydraulic fracturing
• Pneumatic/hydraulic injection (microscale, D90 of 140 micron)
• mixed into clean soil backfill following excavation of contaminated soils (0.25 to 2 mm)
• physical mixing of iron and clay into the contaminated zone ( -50 mesh)
• 10 to 70 micron material in conjunction with other biological amendments-Injections
• Nanoscale materials (50-300 nm)
11
Commercial Facility, Mississauga, ON
(February 2008)
• Former dry cleaner • Risk-assessment to address source
and on-site contamination • PRB to prevent off-site migration
• Continuous trencher • Depth of 9 m • 125 m long
12
First ZVI PRB Installation in the Netherlands
• Continuous trencher (CT) was used to
install 120 m long PRB, with 0.3 m
trench width (1.0 m to 5.5 m bgs).
• Two 30 m long HDPE wing sections
were also installed using the CT.
• The PRB consisted of a granular iron
and sand mix with 40% ZVI (v/v).
Start of
trenching
Continuous Backfill of
Iron/sand
Outline of the installed
Iron/sand PRB
Netherlands PRB-February 2007 Results
0
20
40
60
80
Upgradient Downgradient
Co
nc
en
tra
tio
n (
ug
/L)
Transect 1
Transect 2
0
10
20
30
40
Upgradient Downgradient
Co
nc
en
tra
tio
n (
ug
/L)
Transect 1
Transect 2
cDCE
VC
Advantages
• 13 year operating record at oldest commercial facility
• possible benefits due to hydrogen gas, low Eh conditions
(microbial activity)
• at most sites, if 5 to 8 years can pass before rejuvenation or
replacement, then technology is economically attractive
Disadvantages
• Contact -very critical
• Passivation of Iron surfaces
• Increasing implementation costs with Depth
Long Term Performance of Commercial
Systems
15
Engineered ISCR?
Bacterial
inoculation
Simple carbon
donors
ZVI Complex
carbon
donors/ISRM
Engineered
ISCR
16
Engineered Reductants
Engineered ISCR:
• Amendments that combine chemical reductants (especially ZVI) with
materials that stimulate microbial activity (organic carbon in various
forms) are available as commercial products. The products include
EHC® and Daramend®(PeroxyChem), ABC® + (Redox Tech, LLC),
and emulsified zero-valent iron (EZVI) (National Aeronautics and Space
Administration).
• This approach relies on taking advantage of synergies offered by ZVI
and organic carbon to further enhance the ISCR mechanism.
17
EHC® Reagent Composition
EHC is delivered as a dry powder and includes:
Micro-scale zero valent iron powder(standard
~40%)
Controlled-release, food grade, complex
carbon (plant fibers) (standard ~60%)
Major, minor, and micronutrients
Food grade organic binding agent
Sustainable Solution
o By-product ZVI
o Food production by-products
Mechanisms Zone of Influence
Advection and Dispersion
Bacteria
VFAs Nutrients Fe+2 H2
Diffusion between Solid ISCR seams
Direct Chemical Reduction requires contact with ZVI particle
Extended Zone with Biological Reduction and Indirect Iron Effects
H2 Fe+2
Fe+2 H2
H2
VFAs
VFAs
Hypothesized reaction Pathways
Biotic Abiotic PCE
TCE
Cis 1,2-DCE Trans 1,2-DCE
VC
Ethene
Ethane
PCE
TCE
VC
Ethene
Ethane
Chloroacetylene
Acetylene
cis1,2-DCE
Dichloroacetylene
Hydrogenolysis β-elimination
CO2 – CH4 – H2O
CO2 – CH4 – H2O
Hydrogenation
20
DESIGN AND IMPLEMENTATION OF ENGINEERED ISCR
21
Remediation Strategy
Source Area/ Hotspot Treatment
Injection PRB for Plume Control
Plume Treatment
22
1. What should the strategy be based on the site-specific goals?
• Residual source area treatment / Plume treatment / PRB
2. Which product to use, how much, how frequent ?
• Make up of target contaminants
• Desired reduction in concentration of CVOCs?
• Estimated mass of CVOCs
• Prevailing geochemistry (DO, ORP)
• Pathways required to treat the suite of CVOCs
• Product longevity
• Product distribution under the site-specific geologic/hydrogeologic
conditions (depth, geology)
• Demand from CEAs
• Site-Specific Design Factor
3. Are other additives required (buffer, bioaugmentation etc.)?
• Potassium bicarbonate / dolomite
• SDC-9 / KB-1
Key Design Questions?
23
1. Can the required product be applied in one event or multiple
events are required?
• Available pore volume v/s injected volume
2. Application Method
• DPT
• Injection Wells
• Fracturing
• Soil Blending
3. ROI and number of injection points?
• ROI increases with permeability-less injection points
• ROI increases with high pressure injections
Key Implementation Questions
24
1. Distribution of Slurries (all engineered ISCR products contain ZVI)
• Top Down / Bottom Up for DPT
• Fracturing (pneumatic/hydraulic)
2. Mixing / Pump Requirements
• Good mixing to eliminate clogging
• Positive displacement pumps/ high flow rate
3. Injection Spacing (horizontal/vertical)
• It is not only about how far you can distribute the reagent
4. Verification of Distribution
• Magnetic separation
• Visual inspection of cores
Key Implementation Questions
25
Methods to Validate ROI
Verification of direct product placement:
Visual observation of fractures in soil cores.
Magnetic separation of ZVI from soil cores.
Monitoring of ground deformation using uplift stakes or tilt meters (usually used during fracturing).
Extended zone of influence:
Groundwater Indicator Parameters (TOC, Fe, geochemical parameters)
26
How Far is Substrate Distributed?
27
Solid ISCR® Design Calculation
Steps 1. Calculate quantity of EHC required
• Hydrogen demand from CEAs and CVOCs in the treatment area
• Multiply the hydrogen demand by specific hydrogen capacity of EHC (94 g
H2/kg of EHC),
• Multiply the theoretical EHC demand by a site-specific design factor (1 to 10)
• If the calculated demand is less than the default value, use the default value
• Recommended default values are:
• 0.15 to 0.25% by wt of soil for plume treatment
• 0.25 to 1.0% by wt. for source area treatment
• 0.50 to 1.5% by wt. for a PRB
2. Assess if the quantity estimated can be injected
• If required EHC slurry volume is less than 15% of the total porosity in the
treatment zone, the quantity can be injected.
• If more than 15%, multiple injection events may be required spaced 6 months
apart.
• If slurry volume is less than 10%, increase the volume by diluting the slurry to
inject at a minimum 10% of the PV.
8 out of 10 times selected
dosage is based on default
values
28
Liquid ISCR Design Calculation Steps
1. Calculate quantity of substrate required
1. Hydrogen demand from CEAs and CVOCs in the treatment area
• Multiply the hydrogen demand by amount of H2 produced per unit quantity of
substrate eg: (0.141 HRC , 0.0145 –Lactate 0.322 -EHC Liquid, 0.359 -soy
bean oil
• Multiply the theoretical demand by a site-specific design factor (1 to 10)
• Calculate the required concentration of TOC in pore water. If the calculated
concentration is less than the default value, use the default value
• Recommended default values are:
• 1,000-5,000 mg/L for plume treatment
• 5000-10,000 mg/L for residual source area treatment
• 10,000-15,000 mg/L for source area and PRB
2. Assess if the quantity estimated can be injected
• If required substrate volume after X dilution is greater than 15% but less than
30% of the total porosity in the treatment zone, the quantity can be injected.
• If it is more than 50%, the dilution factor can be reduced to inject a concentrated
solution or perform multiple applications.
• If it is less than 15%, increase the volume by diluting the solution or increasing
the application rate.
8 out of 10 times selected
dosage is based on default
values
29
SOLID-ISCR CASE STUDIES
30
EHC® Case Study – Source Area /
Grid Injection
• Site: Former Dry Cleaner, OR
• Contaminants: PCE ~ 22,000 ug/L
TCE ~ 1,700 ug/L
DCE ~ 3,100 ug/L
VC ~ 7 ug/L
• Treatment: 10K lbs (4.5 kg) in 5 days
32 injection pts
Target area = 825 ft2 x 20 ft deep
Vertical Interval = 10 to 30 ft bgs
Low permeability lithology
Large seasonality in GW flow
Application rate - 0.6% by wt. to soil
• Material Cost: $1.24/ft3, ~$20,000
31
EHC® Case Study Results -
Indicator Parameters
NW sampling cluster NE sampling cluster
SW sampling cluster SE sampling cluster
0 5
10 15 20 25 30 35 40
0 5 10 15 20 25 30 35 40
Conc.
(mg/L
)
Time post EHC injection (months)
Sulfate
0
5
10
15
20
25
0 5 10 15 20 25 30 35 40
Conc.
(mg/L
)
Time post EHC injection (months)
Methane
0
1
2
3
4
5
6
0 5 10 15 20 25 30 35 40
Conc.
(mg/L
)
Time post EHC injection (months)
Dissolved Oxygen
-300 -250 -200 -150 -100 -50
0 50
100 150
0 5 10 15 20 25 30 35 40
OR
P (
mV
)
Time post EHC injection (months)
ORP
32
EHC®
Case Study Results
PCE
TCE
c-DCE
VC
0
2,000
4,000
6,000
8,000
1 5 8 12 14 18 22 24 31 34
Conc.
(ug/L
)
Time post injections (months)
SE sampling cluster
0
2,000
4,000
6,000
8,000
10,000
12,000
1 5 8 12 14 18 22 24 31 34
Conc.
(ug/L
)
Time post injections (months)
SW sampling cluster
0
5,000
10,000
15,000
20,000
25,000
30,000
-18 0 1 5 8 12 14 18 22 24 31 34
Conc.
(ug/L
)
Time post injections (months)
NW sampling cluster
0
1,000
2,000
3,000
4,000
5,000
6,000
-18 0 1 5 8 12 14 18 22 24 31 34
Conc.
(ug/L
)
Time post injections (months)
NE sampling cluster
33
Upstate NY Case Study
ISCR pilot and Full scale Injections
• Manufacturing site with DCE stall historically
• An ISCR (EHC) pilot test was previously
conducted in the CVOC source area in Feb
2011.
• Full scale injections were designed as
multiple events spread over 2 years both in
the source area and downgradient (PRB) to
prevent offsite plume migration
Design parameters:
• The injections were conducted around
monitoring wells MW-11, MW-17 and MW-07
in Sep 2011 and Apr 2013
• Bioaugmentation was done using SDC-09 at
the end of each injection event
34
EHC®
Case Study Results
35
EHC®
Case Study Results
36
• Site: Confidential Site, KS
• Contaminant: Carbon Tetrachloride
2600 ft / 800 m plume
• Treatment: 48K lbs (21.7kgs) EHC PRB
• Application PRB installed down-gradient of
Strategy: source area
Installed line of injection points
10 ft / 3 m apart
PRB extends width of plume =
270 ft / 90 m long
Installed in 12 days using direct
inject
ISCR PRB- Plume Treatment
Courtesy of Malcolm Pirnie (Arcadis)
discharges into
small creek
37
44<1
<1
120067
25<1 <1
19
1575
16
72<1
5.825
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
May 2010
60<1
<1
57062
31<1 <1
21
1635
21
120<1
1334
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
October 2009
70<1
<1
1400130
29<1 <1
21
2117
62
260<1
1589
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
April 2009
150<1
<1
620170
49<1 <1
37
1254
110
490<1
28170
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
October 2008
82<1
<1
1400300
57<1 <1
13
1946
380
650<1
25280
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
April 2008
98<1
<1
1600170
27<1 <1
14
94140
610
540<1
82190
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
August 2007
36<1
<1
2700620
33<1 <1
17
150380
610
410<1
2.485
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
February 2007
47<1
<1
770140
100011 <1
140
49067
280
4606.4
3798
<1
EHC Treatment Zone
Monitoring well andCT concentration (ug/L)
N
Property Line
0 300 600
SCALE IN FEET
March 2005
ISCR - PRB
38
LIQUID ISCR CASE STUDIES
39
E-ZVI Case Study
40
Baseline Concentrations
41
Approach (cont.)
42
Injection design
December 2004 TCE
Contours
Depth 30-50
Feet
April 2008 TCE
Contours
Depth 30-50
Feet
TCE Concentration (ppb)
≥ 10,000 ppb
1,000 ppb
≥ 100 ppb
≥ 10 ppb
Treatment Area
TCE Groundwater Cleanup Target Level is 3.0 ppb
Monitoring Well with Screen Interval
Multi-Chamber Monitoring Well
Case Study #3 – Patrick AFB, Florida RITS Spring 2009: EZVI Treatment of Chlorinated Solvents 43
44
Concord NWS Case Study
Enhanced Reductive Dechlorination Pilot Test:
• An Enhanced Reductive Dechlorination (ERD) pilot test
was previously conducted in the TCE source area from
2011 to 2014.
• The ERD pilot test used buffered emulsified vegetable oil
substrate which was augmented with dechlorinating
microbial consortium (SDC-9™).
ISCR Pilot Study:
• The test was conducted in the TCE source area wells
(S29MW01 and S29MW03) not affected by the ERD pilot
test.
• The aquifer was first primed for substrate distribution by
fracturing the aquifer using the ELS and bioaugmentation
solution.
• Following confirmation of fracture development, ZVI
suspended in guar was injected into the interval followed
immediately by the lactate, ELS solution and
bioaugmentation culture.
• Monitoring was then conducted to verify the degradation
of TCE.
45
Analytical Results
5.0
5.5
6.0
6.5
7.0
7.5
8.0
8.5
-100 0 100 200 300 400 500 600
Sta
nd
ard
Un
its
Days
ISCR vs Biotic Only Treatment ComparisonpH
S29MW10 - Biotic Only
S29MW11 - Biotic Only
S29MW01 - ISCR
S29MW03 - ISCR
-600
-500
-400
-300
-200
-100
0
100
200
300
400
-100 0 100 200 300 400 500 600
mV
Days
ISCR vs Biotic Only Treatment ComparisonOxidation-Reduction Potential
S29MW10 - Biotic Only
S29MW11 - Biotic Only
S29MW01 - ISCR
S29MW03 - ISCR
46
Analytical Results
47
Concord NWPS – Total Chlorinated Ethenes
CHC (field application rate by weight)
Engineered ISCR-treated plumes degrade with half lives one to two orders of magnitude faster
than that seen under anaerobic natural attenuation
Amended and Unamended Field Half Lives
Amended and Unamended Field Half Lives
5,736 5,7366,648 6,648 6,648
2,112 2,112
456552
14
3
14 13
41
2 2 2 2 2
20
400
20
200
400
50
500
200
1
10
100
1,000
10,000
PCE (10%) PCE (0.5%) TCE (10%) TCE (1%) TCE (0.5%) Vinyl Chloride
(10%)
Vinyl Chloride
(1%)
Carbon
Tetrachloride
(0.5%)
Chloroform
(0.5%)
Half
Lif
e (
ho
urs
)
Anaerobic Natural Attenuation Rates (Alvarez & Ilman, 2006)
Injected PRB Field Half Life
Trench PRB Field Half Life
Granular ZVI (Abiotic)
49
Latest Developments
1. Integrated Emulsified Lecithin + ZVI
• Full-scale application at Concord NWS in 2014
2. Ferox Plus by Hepure
• ZVI plus emulsified vegetable oil (SRS)
3. Magnetic Susceptibility Analysis
• Allows us to determine the capacity of the aquifer to intrinsically support
abiotic ISCR
4. Combined Remedies
• Sequential ISCO/ISCR (Klozur Persulfate /EHC)
• ERH/ISCR (CDMSmith, Hunters Point Naval Shipyard)
50
Bench, Pilot, and Design Optimization
Tests
1. Bench tests typically recommended only for unique combination of CVOCs,
CVOCs that have not been tested before, CVOCs concentrations outside
the previously tested range or unique geochemical conditions (e.g. high
sulfate)
2. Pay close attention to how you scale up from bench test data (i.e. the ratio of
water to soil used in the bench is usually skewed compared to what it is in
the aquifer)
3. Perform pilot test to answer questions around distribution, injectability, and
full-scale design
4. Pilot test must be small enough to be cost effective, and add value to the
full-scale, at the same time broad enough to collect sufficient data. As a
general rule, be prepared to collect a lot more data in the pilot then you will
during full-scale application
51
Lessons Learned
1. Geochemistry is important but it is relatively easy to overcome limiting
geochemical conditions
2. It is important to know where the majority of the target contamination
resides….specially for source and residual source areas
3. Distribution is the key to success, so engage a qualified injection
contractor during the design phase
4. Adopt newer site characterization tools to optimize implementation and
achieve desired goals
5. Employ recommended injection pumps, mixing equipment and
procedures
6. Allow flexibility in the design to address unforeseen conditions in the
field
52
CHAPTER 10 IN SITU CHEMICAL REDUCTION FOR SOURCE REMEDIATION Paul G. Tratnyek,1 Richard L. Johnson,1 Gregory V. Lowry2 and Richard A. Brown3
B.H. Kueper et al. (eds.), Chlorinated Solvent Source Zone Remediation, doi: 10.1007/978-1-4614-6922-3_10, # Springer Science+Business Media New York 2014
Reference Documents
Ravi Srirangam P.E., Ph.D.
Technical Manager, Environmental Solutions
PeroxyChem, LLC
One Commerce Square
2005 Market Street, Suite 3200
Philadelphia, PA 19103
P: 312.480.5250| E:[email protected]
www.peroxychem.com/remediation
Questions???