Improving Efficiency at the APS Cholla Power Plant

35
Improving Efficiency at the APS Cholla Power Plant

description

Improving Efficiency at the APS Cholla Power Plant. Team Members. David Bruce - Secretary, Faculty Advisor Liaison, Vendor Liason /Buyer, Document Coordinator Caleb Breazeale - Team Leader, Sponsor Liaison, Presentation Coordinator Joseph Davidson - Treasurer , Website Coordinator. - PowerPoint PPT Presentation

Transcript of Improving Efficiency at the APS Cholla Power Plant

Page 1: Improving Efficiency at the APS  Cholla  Power Plant

Improving Efficiency at the APS Cholla Power Plant

Page 2: Improving Efficiency at the APS  Cholla  Power Plant

Team Members

David Bruce - Secretary, Faculty Advisor Liaison, Vendor Liason/Buyer, Document Coordinator

Caleb Breazeale - Team Leader, Sponsor Liaison, Presentation Coordinator

Joseph Davidson - Treasurer, Website Coordinator

Page 3: Improving Efficiency at the APS  Cholla  Power Plant

NORTHERN ARIZONA UNIVERITY

Tim Vachon – APS Project Sponsor

Ralph Bushman – APS Technical Advisor

Thanks

Dr. David Scott – Capstone Instructor

Dr. Niranjan Venkatraman – Faculty Technical Advisor

David Bruce

Page 4: Improving Efficiency at the APS  Cholla  Power Plant

Summary

Project Overview

Background

- APS Cholla Plant

- Excitation Systems

Procedures

Results

Conclusion

David Bruce

Page 5: Improving Efficiency at the APS  Cholla  Power Plant

Project Overview

The project goal was to research upgrading the generator

excitation systems on units 1, 2, and 3 at the APS Cholla

Power Plant in Joseph City.

The reason for replacing the excitation systems is to

improve efficiency and reduce forced outages.

The project was an investment return study.

David Bruce

Page 6: Improving Efficiency at the APS  Cholla  Power Plant

APS Cholla Power Plant

Unit 1 - 120 MW Westinghouse 1961

Unit 2 - 297 MW Siemens / Westinghouse 1978

Unit 3 - 297 MW Siemens / Westinghouse 1980

Unit 4 - 380 MW General Electric1978

David Bruce

Page 7: Improving Efficiency at the APS  Cholla  Power Plant

APS Cholla Power Plant

David Bruce

Page 8: Improving Efficiency at the APS  Cholla  Power Plant

Coal Fired Generators

David Bruce

Page 9: Improving Efficiency at the APS  Cholla  Power Plant

Introduction to Excitation Systems

Caleb Breazeale

The excitation system provides power to the generator rotor to establish a precisely controllable rotating magnetic field.

Page 10: Improving Efficiency at the APS  Cholla  Power Plant

Unit 1 Rotating Exciter System

Caleb Breazeale

Page 11: Improving Efficiency at the APS  Cholla  Power Plant

Units 2 and 3 Rotating Exciter System

Caleb Breazeale

Page 12: Improving Efficiency at the APS  Cholla  Power Plant

Static Excitation Systems

Caleb Breazeale

Page 13: Improving Efficiency at the APS  Cholla  Power Plant

Thyristor Semiconductor

Caleb Breazeale

Static excitation systems rely upon thyristor semiconductors to regulate power.

Page 14: Improving Efficiency at the APS  Cholla  Power Plant

Digital Regulators

Caleb Breazeale

Static excitation systems use digital automatic voltageregulators (AVR) to control the thyristor semiconductors.

Page 15: Improving Efficiency at the APS  Cholla  Power Plant

Power Potential Transformer

Caleb Breazeale

Static excitation systems require a power potentialtransformer.

Page 16: Improving Efficiency at the APS  Cholla  Power Plant

Static Excitation Systems

Caleb Breazeale

Page 17: Improving Efficiency at the APS  Cholla  Power Plant

Units 2 and 3 Collector Assembly

Caleb Breazeale

Page 18: Improving Efficiency at the APS  Cholla  Power Plant

Benefits for Excitation System Upgrade

Performance Improvements- Quicker response to load changes- More efficient- Generator up-rate

Feature Enhancements

- Remote system operation- Reduced operator demand- Data logging

Improved Reliability / Availability - Redundancy- Reduced maintenance costs- Elimination of moving parts- Parts availability

Siemens exciter meltdown

Caleb Breazeale

Page 19: Improving Efficiency at the APS  Cholla  Power Plant

Procedures

Analyze costs associated with existing systems

Determine cost of upgrade

Predict operational costs of upgrade

Determine payback time

Joseph Davidson

Page 20: Improving Efficiency at the APS  Cholla  Power Plant

Current Operating Conditions

Unit 1 is worth about $112,000 per day.

Unit 1 has about 1 annual forced outage day due to the

exciter system.

Unit 2 is worth about $265,00 per day.

Unit 2 has about .2 annual forced outage days due to

exciter system.

Joseph Davidson

Page 21: Improving Efficiency at the APS  Cholla  Power Plant

Budget Quotes

Vendor Unit 1 Units 2 & 3

$1,405,500 $2,230,500

$1,305,328 $2,850,328

$1,270,500 $2,125,500

Joseph Davidson

Page 22: Improving Efficiency at the APS  Cholla  Power Plant

ABB Unit 1 Budget Quote

Joseph Davidson

Exciter and AVR; Series1;

0.352187833511206; 35%

Transformer; Se-ries1;

0.106723585912487; 11%Enclosure; Series1;

0.064034151547492; 6%Engineering; Se-ries1;

0.0996086801849876; 10%

Remove and In-stall; Series1;

0.295268587691213; 30%

PSS Study / Tune; Series1;

0.0249021700462469; 2%

Training; Series1; 0.0181430096051227; 2%

Commissioning; Series1; 0.0391319815012451; 4%

Page 23: Improving Efficiency at the APS  Cholla  Power Plant

ABB Units 2 & 3 Budget Quote

Joseph Davidson

Exciter and AVR; Series1;

0.221923335574983; 22%

Transformer; Se-ries1;

0.0986325935888815; 10%

Enclosure; Se-ries1;

0.0403496973772697; 4%

Collector Assembly; Series1; 0.336247478143914; 34%

Engineering; Se-ries1;

0.0627661959201973; 6%

Remove and In-stall; Series1;

0.186056937906299; 19%

PSS Study / Tune; Series1; 0.0179331988343421; 2%

Training; Series1; 0.0114324142568931; 1%

Comissioning; Series1; 0.0246581483972204; 2%

Page 24: Improving Efficiency at the APS  Cholla  Power Plant

Efficiency Improvement

Unit 1: 160 kW (from APS)

Units 2 & 3: 0 kW (assumed)

Joseph Davidson

Page 25: Improving Efficiency at the APS  Cholla  Power Plant

Joseph Davidson

Investment Payback Model

PAYBACK YEARS = INSTALLED SYSTEM COST ($)

Efficiency improvementvalue ($/year)

CAPACITY VALUE + REPLACEMENT CAPACITY VALUE + REDUCED OUTAGE VALUE

($/year)

Page 26: Improving Efficiency at the APS  Cholla  Power Plant

Joseph Davidson

Model Parameters

Energy: $ .038 / kWh

Replacement Capacity: $100/kW/year

Unit 1 Capacity: 122,500 kW

Unit 1 Cost: $1,327,109 (averaged)

Units 2 / 3 Capacity: 290,000 kW

Units 2 / 3 Cost: $2,402,109 (averaged)

Page 27: Improving Efficiency at the APS  Cholla  Power Plant

Joseph Davidson

Unit 1 Payback

Page 28: Improving Efficiency at the APS  Cholla  Power Plant

Joseph Davidson

Units 2 & 3 Payback

Page 29: Improving Efficiency at the APS  Cholla  Power Plant

Requirements / Results Comparison

All of the static excitation systems that were quoted met the minimum electrical, environmental, and mechanical requirements.

The key requirement of payback years was determined.

Unable to determine exact efficiency improvement of units 2 and 3.

David Bruce

Page 30: Improving Efficiency at the APS  Cholla  Power Plant

Project Deliverables

System quotes

Research information gathered

Payback model and results- Matlab source code- Excel files

David Bruce

Page 31: Improving Efficiency at the APS  Cholla  Power Plant

Lessons Learned

Be specific when requesting quotes.

Allow ample time for vendors to produce a quote.

David Bruce

Page 32: Improving Efficiency at the APS  Cholla  Power Plant

Possible Future Refinements

David Bruce

Catastrophic failure consideration

Old equipment value

Generator up-rate value

Page 33: Improving Efficiency at the APS  Cholla  Power Plant

Conclusion

Unit 1 – Worth it, the investment payback time is about 7

years.

Units 2 & 3 – Not as good of an investment. With existing

reliability, the payback time is about 45 years.

David Bruce

Page 34: Improving Efficiency at the APS  Cholla  Power Plant

Hours Spent on ProjectProblem Identification and Requirements ~ 20 man-weeks

- Project proposal- ensured we fully understood what APS wanted

Research ~ 9 man-weeks

- Gathered generator performance information.

- Identified excitation systems.

Vendor communication ~ 9 man-weeks

- System Quotes

Results ~ 9 man-weeks

- Payback model

David Bruce

Page 35: Improving Efficiency at the APS  Cholla  Power Plant

PosterRoom A, 2nd floor DuBois Center

Websitewww.cens.nau.edu/Academic/Design/D4P/EGR486/EE/08-Projects/APSCholla/

David Bruce

Questions ?