Implementing a F OUNDATION ™ Fieldbus Project · In a World of Choices, FOUNDATION ™ Brings it...
Transcript of Implementing a F OUNDATION ™ Fieldbus Project · In a World of Choices, FOUNDATION ™ Brings it...
In a World of Choices, FOUNDATION™ Brings it All Together. ® 2013 Fieldbus Foundation 1
Implementing a FOUNDATION™ Fieldbus Project
Part Seven of Eight
Contents
Introduction User Guide – Implementing a FOUNDATION Fieldbus Project
Chapter 1 Introducing the User Guide
1.1 Executive Summary
1.2 Recommended Technical Resources
Chapter 2 Overview of FOUNDATION Fieldbus
Chapter 3 FOUNDATION Fieldbus Project Management – Minimising Project Risk
3.1 Proven Technology
3.2 Project Evaluation
3.3 Training
3.4 Project Partners
3.5 Procedures, Work Processes and Documentation
3.6 Risk Management
3.7 Testing
Chapter 4 FOUNDATION Fieldbus Project Investment
4.1 Project Planning – CAPEX
4.2 Project Engineering and Installation – CAPEX
4.3 Commissioning – CAPEX
4.4 Project Start-Up – CAPEX
4.5 Operations and Maintenance – OPEX
Chapter 5 FOUNDATION Fieldbus Project Design & Engineering
5.1 Host Selection Considerations
5.2 Field Device Selection Considerations
5.3 Segment Component Selection Considerations
5.4 Network/Segment Topology Design Considerations
5.5 Host/Device Interoperability Testing
Chapter 6 FOUNDATION Fieldbus Project Implementation – Conclusion & Checklist
Appendix References/Sources
In a World of Choices, FOUNDATION™ Brings it All Together. ® 2013 Fieldbus Foundation 2
Implementing a FOUNDATION™ Fieldbus Project
Chapter 5: FOUNDATION Fieldbus Project Design &
Engineering
5.1: Host System Selection Considerations The correct selection of the host system for the project is a key element to the
project’s success. The various hosts on the market reflect different levels of
FOUNDATION fieldbus development but should all support EDDL as well as FDT/DTM
technology. The selection of the host supplier is equally as important as the selection
of the system itself as the project team will need to work very closely with the vendors
and suppliers to ensure a smooth-running project.
Since the functionality of FOUNDATION devices is not directly comparable
with conventional devices, a thorough review and comparison of device
data, functionality and specifications is advised in the context of the
proposed FOUNDATION network and the selection of potential hosts and
asset management packages. Consideration will now need to be given
to input and output, control and diagnostics. The selection of the host,
devices, components and asset management package needs to be done
in parallel and with active input and support from suppliers at the initial
stages to minimise compatibility or commissioning issues further down
the line.
The host system should use a manufacturer’s standard hardware,
systems software and firmware that may be configured to meet the
application requirements but does not require modification to the
system operating software to suit individual applications. Any updates
to the standard system operating software should not affect the
operation of the installed system.
The DCS FOUNDATION fieldbus H1 network topology and settings should comply with
recommended FOUNDATION fieldbus practices to enable communication with all
targeted fieldbus devices. The FOUNDATION fieldbus host should have an integrated
“Since the functionality
of FOUNDATION devices
is not directly
comparable with
conventional devices, a
thorough review and
comparison of device
data, functionality and
specifications is advised
in the context of the
proposed FOUNDATION
network and the
selection of potential
hosts and asset
management packages.”
In a World of Choices, FOUNDATION™ Brings it All Together. ® 2013 Fieldbus Foundation 3
configuration tool that allows easy commissioning, set-up, operation and maintenance
of all FOUNDATION fieldbus devices using consistent methods and a common ‘look and
feel’ with conventional configuration, typically from a single host workstation/control
room. The configuration tool should seamlessly and transparently integrate with, and
maintain the master configuration database. Any separate tools, displays or
procedures that are specific for FOUNDATION fieldbus and are different from the
conventional should be avoided.
The host system should be able to automatically identify new fieldbus devices as they
are connected to the network and offer easy to use ‘drag and drop’ commissioning.
Similarly, complex calculations and bus scheduling can often be automatically
generated through an auto-macrocycle and optimisation function.
Asset Management: To gain the full benefits of FOUNDATION fieldbus functionality
during commissioning and lifecycle activities, an integrated instrument health
monitoring (asset management) package is required. The successful integration and
implementation of asset management requires the early definition and development
of operations and maintenance work processes to utilise the diagnostic tools fully. A
single smart device can potentially provide hundreds of different parameters about
the process or instrument to the operator, technician, inspector, engineer or plant
manager according to the system configuration and established monitoring systems.
Spare Capacity: The FOUNDATION fieldbus host system should include a minimum of
20% spare capacity in terms of hardware capacity; spare performance capacity
(communication idle time); spare H1 interfaces/ports; power supplies and redundant
power supplies; and junction boxes at mechanical completion of the initial project.
This spare capacity allows for an element of future system expansion with minimum
implications on system re-design and additional costs. In the event of incorrect
segment risk assessments in the original project, spare capacity may prevent initial
set-up problems.
Redundancy: Depending on the nature of the process and the consequences of device
failure on production or safety, redundancy may be a critical consideration. Project
designers need to consider the provision of the following redundant parts: power
feeds for the bulk power supplies; bulk power supplies to feed the FOUNDATION power
supplies; system controller power supplies; system controllers; FOUNDATION H1
In a World of Choices, FOUNDATION™ Brings it All Together. ® 2013 Fieldbus Foundation 4
interfaces; and FOUNDATION fieldbus power supplies. Spare standard FOUNDATION
devices may also be kept in stock but the effectiveness of this policy may be limited
unless the devices are always of a consistent specification (e.g. utilising the same
function blocks and having PID control residing consistently in either the DCS or in
the device but not a mixture of the two).
Control Room/Workstations: Consideration should be given to the location of the host
or engineering workstation(s) and maintenance workstation(s). Only one engineering
workstation (control room) is required to perform all control and FOUNDATION fieldbus
configuration, database generation and editing. However, since the automation system
uses a single, global configuration database, it is possible to use additional
workstations to access the configuration, database generation and editing functions.
Any additional maintenance workstation(s) should ideally be integrated with the main
engineering workstation. The location of any asset management packages and tools
will depend on the FOUNDATION host used and the function of the packages.
Data Integrity: In order to maintain the integrity of the FOUNDATION fieldbus device
parameters within the master database in the host, external configuration tools such
as handheld communicators and laptops should not be used. Similarly, diagnostic data
within field devices should only be accessed via a fully integrated asset management
package.
Host System Evaluation: Once the system is up and running, the host system should
be evaluated to determine whether the execution times are as published and whether
the segment loading has adversely affected the host’s performance in any way. The
system diagnostics should be assessed for their usefulness and a check on the
implementation of software revisions and device descriptions should be made.
In a World of Choices, FOUNDATION™ Brings it All Together. ® 2013 Fieldbus Foundation 5
5.2: Field Device Selection Considerations When specifying FOUNDATION registered field devices, it is recommended that project
engineers also ensure that the host supplier can verify that all versions of devices are
fully compatible with the host and integrated asset management packages at the
outset. Additional interoperability testing prior to commissioning is time well spent
and may avoid costly trouble-shooting later on in the project.
Function Blocks: FOUNDATION fieldbus devices contain two types of blocks – device
application blocks and configuration blocks. The resource block and transducer block
(which holds the device diagnostic data) are configuration blocks used to configure
devices whereas user-configurable function blocks are built-in, as required, to
configure the application and define the control strategy or functionality.
The Fieldbus Foundation has defined ten standard function blocks, nineteen advanced
function blocks, four additional function blocks, one flexible function block and two
Safety Instrumented Function (SIF) function blocks in its FOUNDATION technology
specifications. However, not all function blocks are suitable, tested and registered, or
even available for all field device types. It is recommended that function block
availability is checked with the device supplier and that compatibility with, and support
by, the host system is confirmed at the outset to avoid possible redesign at a later
stage of the project.
Since the Fieldbus Foundation testing of function blocks does not address the internal
workings, there is scope for the manufacturers to configure the internal operations to
provide competitive advantages. Users need to compare these carefully to select the
optimum solution in terms of their process and macrocycle efficiency requirements,
particularly in application when Control in the Field is implemented.
Device Configuration: Wherever possible, it is recommended that as much of the
device configuration as is feasible is conducted by the device supplier prior to
shipment – in particular any instantiation of the function blocks. Similarly, if device
identifiers, tag names and FOUNDATION fieldbus addresses are configured by the
manufacturer then on-site configuration and potential confusion can be minimised.
In a World of Choices, FOUNDATION™ Brings it All Together. ® 2013 Fieldbus Foundation 6
Power: FOUNDATION fieldbus devices are usually powered from the segment/bus. When
selecting devices, consideration must be given to power consumption requirements to
ensure that the segment can sustain the devices otherwise provision for separate
power is required for the high consumption devices. Allowance must also be made for
short-circuit protection and additional test equipment on the segment.
Safety Instrumented Functions: For FOUNDATION Fieldbus for Safety Instrumented
Functions (FF-SIF) applications, the host and devices must support the FF SIF protocol
which has been approved by TÜV to IEC-61508, including diagnostics, to reduce the
potential for undetected dangerous failures to a level acceptable for SIL 3 applications.
5.3: Segment Component Selection Considerations Additional components required to complete a FOUNDATION fieldbus segment include
bulk power supplies, power supplies, power conditioners, terminators, surge
protection, field device couplers, cables, and on-line diagnostic tools. In certain
circumstances, repeaters may be used to extend the segment distance.
The primary issue is that, wherever relevant, components must be Fieldbus Foundation
tested and registered. This applies to power supplies (excluding bulk power supplies),
field device couplers and spur cabling. The specifying of components for a
FOUNDATION fieldbus segment is contingent upon the fact that host system supplier
verifies that they are compatible with their system. Consideration must also be given
to the recommendations relating to cable specifications, grounding and shielding.
When segments are required to be intrinsically safe, the specific recommendations and
methods for installation in hazardous areas should be followed, for example there is a
significant impact on power consumption, the number of devices permitted on a
segment and permitted cable lengths. Installation therefore may include the use of
barriers, power supplies, terminators, high power trunk cabling, devices and
components approved for IS areas.