IID Generating Facility Interconnection Process
1
IID Generating Facility Interconnection Process Interconnection customer submits Interconnection Request § 3.1 Interconnection Provider assigns a queue position § 4.1 Is the Interconnection Request complete? § 3.3.3 Post Interconnection Request on OASIS § 3.4 Conduct Scoping Meeting § 3.3.4 Sign Interconnection System Impact Study Agreement § 7.1 & § 7.2 Interconnection customer provides more information? § 3.3.3 No Yes Withdraw Interconnection Request § 3.6 No Sign Interconnection Facilities Study Agreement § 8.1 Perform Interconnection System Impact Study § 7.3 & § 7.4 Perform Interconnection Facilities Study § 8.2 & § 8.3 Sign Interconnection Agreement
-
Upload
neil-stephenson -
Category
Documents
-
view
50 -
download
1
description
IID Generating Facility Interconnection Process. Interconnection customer submits Interconnection Request § 3.1. Interconnection Provider assigns a queue position § 4.1. Yes. Withdraw Interconnection Request § 3.6. Is the Interconnection Request complete? § 3.3.3. - PowerPoint PPT Presentation
Transcript of IID Generating Facility Interconnection Process
![Page 1: IID Generating Facility Interconnection Process](https://reader038.fdocuments.us/reader038/viewer/2022102818/56812c26550346895d9096f8/html5/thumbnails/1.jpg)
IID Generating Facility Interconnection
Process Interconnection customer submits
Interconnection Request§ 3.1
Interconnection Provider assigns aqueue position § 4.1
Is the Interconnection Requestcomplete? § 3.3.3
Post Interconnection Requeston OASIS § 3.4
Conduct Scoping Meeting§ 3.3.4
Sign Interconnection SystemImpact Study Agreement
§ 7.1 & § 7.2
Interconnection customer providesmore information?
§ 3.3.3No
Yes WithdrawInterconnection
Request § 3.6
No
Sign Interconnection Facilities Study Agreement § 8.1
Perform Interconnection System Impact Study § 7.3 & § 7.4
Perform Interconnection FacilitiesStudy § 8.2 & § 8.3
Sign Interconnection Agreement