Transcript of IGD
![Page 1: IGD](https://reader031.fdocuments.us/reader031/viewer/2022020716/5511d5d14a7959df028b47a5/html5/thumbnails/1.jpg)
IGD - Gasco - Habshan 5 Gas Processing
[email protected], [email protected] ,
Country:UAE [email protected]
Project Value
:USD 4,700,000,000 Estimated
Sector:Oil and Gas | Processing & Separation
Consultant :Fluor Mideast (FEED)
PMCs :KBR Middle East (for FEED) | Worley Parsons Engineering (PMC for EPC)
Contractors :Kharafi National (Civil, mechanical and electrical sub-contractor) | Consolidated Contractors Company (Construction sub-contractor) | JV of JGC Corporation and Tecnimont (EPC)
Profile Type: Contract Package | Related Projects (6)
By end of 2009, Consolidated Contractors Company (CCC)
was awarded a USD 300 million
construction sub-contract by JGC .
On 29 October 2009, Gasco and the joint
venture of JGC and Tecnimont
![Page 2: IGD](https://reader031.fdocuments.us/reader031/viewer/2022020716/5511d5d14a7959df028b47a5/html5/thumbnails/2.jpg)
signed the official EPC contract.
On 15 July 2009, the EPC contract was awarded to the JV of JGC
Corporation and Tecnimont
.
On 9 July 2009, bids were opened .
On 7 July 2009, bidders submitted their EPC proposals .
On 22 June 2009, the PMC for the EPC contract was awarded to WorleyParsons .
On 30 April 2009, bidders submitted their technical proposals for the EPC contract. The bids submission deadline was extended from 1 March 2009. The JV of Fluor and CCC is the
prefferred bidder .
28 January 2009 was the deadline for bidders to submit their unpriced commercial proposals .
In November 2008, bidders submitted their technical proposals for the PMC contract .
In July 2008, the FEED studies were completed and the ITB for the EPC contract was issued .
![Page 3: IGD](https://reader031.fdocuments.us/reader031/viewer/2022020716/5511d5d14a7959df028b47a5/html5/thumbnails/3.jpg)
In May 2007, KBR Leatherhead was awarded the PMC for the FEED contract on the whole onshore part of the IGD program .
In December 2006, ITB was issued for the PMC contract overseeing FEED .
In July 2006, the FEED contract was awarded to Fluor.