ICT Construction Plan Evaluation and Reliability Assessment Part 2
description
Transcript of ICT Construction Plan Evaluation and Reliability Assessment Part 2
![Page 1: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/1.jpg)
SPP.org 1
![Page 2: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/2.jpg)
ICT Construction Plan Evaluation and Reliability Assessment Part 2Entergy ICT Transmission Planning Summit
July 29, 2008Astor Crown PlazaNew Orleans, Louisiana
![Page 3: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/3.jpg)
SPP.org 3
Project is not included in
model
Code for Base Plan and Construction Plan Projects Indicated on Maps
BP08-036 = Project Number from 2008 Base PlanCP(2011) = 2008 Construction Plan and Expected In-Service YearDCP(2011) = 2009 Draft Construction Plan and In-Service Year
Map Legend
BP08-036 CP(2011)
DCP(2011)
Background Color Indicates Projects’ Inclusion In Case
Project is in 2017 model
![Page 4: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/4.jpg)
SPP.org 4
![Page 5: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/5.jpg)
SPP.org 5
![Page 6: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/6.jpg)
SPP.org 6
![Page 7: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/7.jpg)
SPP.org 7
NANA
DCP(2013)
![Page 8: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/8.jpg)
SPP.org 8
![Page 9: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/9.jpg)
SPP.org 9
![Page 10: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/10.jpg)
SPP.org 10
![Page 11: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/11.jpg)
SPP.org 11
![Page 12: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/12.jpg)
SPP.org 12
![Page 13: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/13.jpg)
SPP.org 13
![Page 14: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/14.jpg)
SPP.org 14
![Page 15: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/15.jpg)
SPP.org 15
![Page 16: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/16.jpg)
SPP.org 16
![Page 17: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/17.jpg)
SPP.org 17
![Page 18: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/18.jpg)
SPP.org 18
![Page 19: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/19.jpg)
SPP.org 19
![Page 20: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/20.jpg)
SPP.org 20
NANA
DCP(2013)
![Page 21: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/21.jpg)
SPP.org 21
![Page 22: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/22.jpg)
SPP.org 22
Other Areas
These concerns seen in real-time may be relieved by projects in the Base Plan, Construction Plan or Draft Construction Plan.
• Hot Springs-Bismark 115kV FTLO El Dorado-Longwood 345kV (Base Plan Project)
• Liberty-Gillsberg 115kV FTLO Franklin-Bogalusa 500kV (Construction Plan Project with ISD 2009)
• Hartburg-Inland Orange 230kV FLTO Hartburg-Cypress 500kV (Draft Construction Plan Project with ISD 2010)
![Page 23: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/23.jpg)
SPP.org 23
Base Plan Development Next Steps
• Stakeholder Comments
• Discuss Stakeholder Comments at September LTTIWG
• Present Draft Base Plan at October LTTIWG
• Finalize Base Plan and Post January 2009
![Page 24: ICT Construction Plan Evaluation and Reliability Assessment Part 2](https://reader035.fdocuments.us/reader035/viewer/2022062816/56814d62550346895dbaaeb7/html5/thumbnails/24.jpg)
SPP.org 24
Steve PurdyLead Engineer, ICT Planning
Jason RussellEngineer II, ICT Planning