Hydropower Investment Promotion Project (HIPP) HIPP...

57
Hydropower Investment Promotion Project (HIPP) WEDNESDAY, FEBRUARY 1, 2012 This publication was produced for review by the United States Agency for International Development. It was prepared by Deloitte Consulting in collaboration with Black & Veatch and Pierce Atwood Attorneys LLC. HIPP REPORT ON GEORGIA/TURKEY CROSS BORDER ELECTRICITY TRADE AGREEMENT

Transcript of Hydropower Investment Promotion Project (HIPP) HIPP...

Page 1: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

Hydropower Investment Promotion Project (HIPP)

WEDNESDAY, FEBRUARY 1, 2012 This publication was produced for review by the United States Agency for International Development. It was prepared by Deloitte Consulting in collaboration with Black & Veatch and Pierce Atwood Attorneys LLC.

HIPP REPORT ON GEORGIA/TURKEY CROSS BORDER ELECTRICITY TRADE AGREEMENT

Page 2: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

HIPP REPORT ON GEORGIA/TURKEY CROSS BORDER ELECTRICITY TRADE AGREEMENT USAID HYDROPOWER INVESTMENT PROMOTION PROJECT (HIPP) CONTRACT NUMBER: EEM-I-00-07-00005-0 DELOITTE CONSULTING LLP IN COLLABORATION WITH BLACK & VEATCH AND PIERCE ATWOOD ATTORNEYS LLC. USAID/CAUCASUS OFFICE OF ENERGY AND ENVIRONMENT W EDNESDAY, FEBRUARY 1, 2012 DISCLAIMER: The author’s views expressed in this publication do not necessarily reflect the views of the United States Agency for International Development or the United States Government.

Page 3: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

This document was prepared by

Author Organization Contact Details

Julia Weller Pierce Atwood LLP [email protected]

David Lockhart Pierce Atwood LLP [email protected] 1.202.379.6891

Reviewer Organization Contact Details

Jake Delphia Deloitte Consulting LLP [email protected] +995-571-506-287

1

Page 4: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

CONTENTS:

HIPP REPORT ON GEORGIA/TURKEY CROSS BORDER ELECTRICITY TRADE AGREEMENT ............................................................................................. 3 

INTRODUCTION .................................................................................................. 3 RATIONALE FOR CBETA AND ITS IMPORTANCE .......................................... 3 DELOITTE HIPP’S INVOLVEMENT AND PROCESS ......................................... 4 SUMMARY OF CBETA ........................................................................................ 5 NEXT STEPS ....................................................................................................... 7 

APPENDIX 1: ........................................................................................................... 8 

COPY OF THE CROSS BORDER ENERGY TRADE AGREEMENT EXECUTED IN THREE LANGUAGES .................................................................... 8 

2

Page 5: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

HIPP REPORT ON GEORGIA/TURKEY CROSS BORDER ELECTRICITY TRADE AGREEMENT

INTRODUCTION On January 20, 2012 the Cross Border Electricity Trade Agreement between Georgia and Turkey, the official title of which is Agreement between Georgia and the Republic of Turkey concerning Cross-Border Electricity Trade Via Borçka-Akhaltsikhe Interconnection Line (“CBETA”) was signed in Tbilisi by Alexander Khetaguri, the Georgian Minister of Energy and Natural Resources, and Taner Yildiz, the Turkish Minister of Energy and Natural Resources. The signing of this heavily negotiated agreement between the two countries represents a major step forward in the progression towards a trading platform for electricity flows between Georgia and the Republic of Turkey. This Report comprises a synopsis of the CBETA, covering the following:

1. Rationale for CBETA and what it accomplishes; 2. Deloitte HIPP’s involvement and process; 3. Summary of CBETA; 4. Progress from here – next steps.

RATIONALE FOR CBETA AND ITS IMPORTANCE Prior to 2011, Georgia’s transmission system operator GSE and Turkey’s transmission system operator TEIAŞ executed numerous Memoranda of Understanding regarding siting, design and construction of a new cross-border transmission line between Akhaltsikhe in Georgia and Borçka in Turkey, but there was no agreement regarding the basis on which electricity would be exported. A review of Turkey’s legal and regulatory framework by HIPP had uncovered numerous potential barriers to the import of power from Georgia. HIPP therefore proposed a sovereign-to-sovereign agreement which could override these obstacles. In the international energy trade sphere, such agreements between governments are a prerequisite for private investment in cross-border pipelines and transmission lines to mitigate political risk. The planned investment in large numbers of hydropower plants (“HPPs”) in Georgia demanded similar political risk mitigation because only a small portion of the potential power produced by such HPPS could be sold inside Georgia, with the majority intended for the Turkish market. Model agreements between countries that undergird trans-boundary investments have been developed by international organizations and have the advantage of being well-understood and time-tested. The model agreement between host countries crafted by the Energy Charter Secretariat (“Secretariat”) was the basis for the Baku-Tbilisi-Çeyhan oil pipeline and a draft agreement developed by the Secretariat for use with electricity transmission systems was therefore selected as the basis for an agreement between the governments of Turkey and Georgia.

3

Page 6: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

DELOITTE HIPP’S INVOLVEMENT AND PROCESS The need for and importance of having an inter-governmental agreement, ideally at the level of a treaty, was recognized by the US Agency for International Development (“USAID”), which offered its assistance to Georgia’s Ministry of Energy and Natural Resources (“MENR”). This offer was subsequently accepted by MENR and HIPP’s lawyers were called upon to develop the framework for such an agreement. A draft outline for the treaty was prepared by HIPP’s legal team and presented to MENR’s Deputy Minister Marika Valishvili, GSE Board Member Zurab Ezugbaia and other government officials in August 2010. Following consultations and discussions with MENR and GSE in Tbilisi, a fully re-worked draft treaty was prepared and submitted to MENR by HIPP in September, 2010. The draft was sent by MENR to the Turkish counterparts. During the following year, successive drafts and counter-drafts were exchanged by Georgia and Turkey, with Turkey proposing a bare-bones agreement between market operators, and Georgia responding with the HIPP draft, modified to address some of the Turkish counterparts’ concerns. In July 2011, HIPP legal consultants Julia Weller and David Lockhart were asked to assist Georgia in negotiations between representatives of the Turkish and Georgian Ministries in Batumi in July, 2011. Subsequently, in October 2011, David Lockhart attended a meeting between the Deputy Ministers of Energy in Ankara. Differences between the parties were finally ironed out in several high-level follow-up meetings between the two countries’ Deputy Ministers. The agreement--no longer a treaty but an agreement that nonetheless is proposed to be ratified by the legislature of each country--is based on the original model agreement between sovereign states drafted by HIPP’s consultants the previous year.

4

HIPP and GSE staff revising the draft Interconnection Operating Agreement

J. Weller, D.Lockhart, HIPP and Z. Ezugbaia, GSE reviewing the executed copy of the CBETA

Turkish and Georgian Ministers of Energy signing Cross Border Electricity Trade

Agreement

D.Lockhart, HIPP and Z. Ezugbaia, GSE in Batumi, after CBETA Negotiations

Page 7: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

SUMMARY OF CBETA This section contains a summary of the CBETA, a fully signed copy of which is annexed to this Report. The preamble to the CBETA reflects the rationale, described above, for entering into the agreement, recognizing earlier Memoranda of Understanding, a letter of intent and Construction Agreement between the parties, and recognizes the importance of smooth and uninterrupted cross-border electricity trade using the Borçka-Akhaltsikhe Interconnection Line, development of long-term cooperation in energy, and the creation of stable and favorable conditions for economic activity in the region. Article 1, Definitions and Interpretation: A key definition used is “Electricity Trade,” meaning the purchase and sale of electricity generated either country and transported to the other via the Borçka-Akhaltsikhe Line. Article 2, Scope and Subject of Agreement: establishes principles on which the parties agree to facilitate Electricity Trade and on which they or their relevant state Entities will negotiate the Interconnection Operating Agreement (“IOA”) and other agreements covering the operation, dispatch and allocation of capacity on the Borçka-Akhaltsikhe Line, which include the use of international rules envisaged in other international trade and investment agreements, and reflects the intent to jointly facilitate the development of market and power transmission infrastructure in promoting Electricity Trade. Article 3, Objectives: to strengthen cooperation between the parties, by ensuring the successful implementation of Electricity Trade, and to identify the agreements and terms needed to govern the operation of the Borçka-Akhaltsikhe Line. Article 4, Relationship of Agreement to Domestic Laws: confirms that the terms and conditions of the CBETA prevail over any domestic law or regulation. Article 5, Performance and Observance of Agreement: Georgia and Turkey each agree to ensure that the Agreement and the Electricity Interconnection Agreement shall be binding on each entity that is licensed or authorized to perform the functions required to be performed under the Agreement. They also undertake to cooperate in maintaining favorable conditions for implementation of Electricity Trade, to use best endeavors to ensure that laws and regulations allow full utilization of the Borçka-Akhaltsikhe Line, and to maintain maximum Available Transfer Capacity (“ATC”) on the Line. Georgia and Turkey agree to meet as often as required to negotiate and enter into the agreements required in relation to Electricity Trade. Article 6, ATC and Allocation of Capacity: ATC at the time the Borçka-Akhaltsikhe Line commences operation is set at 350 MW, increasing to 650 MW in 2013, and up to 1000 MW in future, depending on market requirements and operation conditions. The allocation of transmission capacity, operating principles and relationship between importers and exporters and technical operators is to be stipulated in the IOA and other agreements in line with the current legislation in both countries. Broadly, the exporting country decides on the entities to which ATC will be allocated, its System Operator provides to the other country’s System Operator relevant information, and the parties initiate the process for issue of needed licenses and permissions.

5

Page 8: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

Article 7, Transport of Electricity: Georgia and Turkey undertake to facilitate cross-border trade of electricity using the transmission systems of TEIAŞ, GSE and Energotrans, and to take all necessary measures and actions to prevent interruptions or curtailments. Exporters and importers are entitled to reserve transmission capacity. Article 8, Interconnection Operation Agreement: Georgia and Turkey undertake to have their System Operator develop and sign the IOA for the Borçka-Akhaltsikhe Line before June 1, 2012 – or the date that the Borçka-Akhaltsikhe Line construction works is completed, if earlier. The IOA will define the conditions for access and efficient congestion management mechanisms that promote electricity trading, and certain agreements between the parties are recorded:

• the maximum capacity of the Borçka-Akhaltsikhe Line will be made available, in compliance with safety standards of secure network operation;

• priority access capacity for export and import will be given to electricity generated by new generation using renewable energy sources;

• consistent, coordinated procedures for market participants to nominate use of capacity will be used

• a consistent approach to the short-term resale or reallocation of unused capacity on the Borçka-Akhaltsikhe Line will be used.

Article 9, Force Majeure: The parties’ responsibilities for non-performance or delay are suspended to the extent caused by Force Majeure (being natural disasters, wars, terrorism and insurrection, and international embargoes). An affected party must take reasonably available actions and expend such funds as are necessary and reasonable to remedy the Force Majeure and resume performance, and must procure that state entities take action to mitigate the loss suffered by the other party. Article 10, Joint Committee: Georgia and Turkey must, within 60 days of signing, establish a Joint Committee implement the Agreement, exchange information, resolve disputes, and conduct meetings and consultations. Article 11, Dispute Settlement: If, through diplomatic channels, the parties are unable to resolve disputes, binding arbitration by an ad hoc tribunal using the premises of the Permanent Court of Arbitration at The Hague, under UNCITRAL Arbitration Rules is to be used, using applicable rules and principles of international law. Article 12, Amendments: Amendments to the Agreement may be made by mutual written consent through diplomatic channels at any time, and no conversion of legal form or status of the System Operators of Georgia and Turkey shall restrict the scope of the Agreement and the responsibilities and duties imposed on the System Operators. Article 13, Validity and Termination: The Agreement is for a period of 10 years, extendable automatically for successive 10 year periods unless 6 months notice to terminate is given. Article 14, Entry into Force: the Agreement becomes effective following notification through diplomatic channels that all necessary requirements for its entry into force under the parties’ respective laws have been fulfilled.

6

Page 9: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

Article 15, Final Expression: The CBETA is the final expression of the parties’ agreement on the matters contained in it. NEXT STEPS The CBETA anticipates execution of an IOA between GSE and TEIAŞ in which numerous issues regarding the operation of the new transmission line will be addressed. HIPP’s legal consultants are assisting in the development of this agreement, in part using models that have been utilized for other trans-boundary transmission lines. In addition, the CBETA requires development of an energy trading platform to allow Georgian HPPs to have access to the Turkish market on the same basis as Turkish HPPs. HIPP has offered its assistance to the Government for elaboration of this project.

7

Page 10: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

8

APPENDIX 1:

COPY OF THE CROSS BORDER ENERGY TRADE AGREEMENT EXECUTED IN THREE LANGUAGES

Page 11: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 12: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 13: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 14: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 15: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 16: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 17: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 18: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 19: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 20: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 21: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 22: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 23: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 24: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 25: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 26: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 27: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 28: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 29: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 30: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 31: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 32: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 33: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 34: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 35: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 36: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 37: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 38: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 39: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 40: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 41: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 42: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 43: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 44: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 45: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 46: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 47: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 48: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 49: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 50: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 51: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 52: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 53: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 54: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 55: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 56: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to
Page 57: Hydropower Investment Promotion Project (HIPP) HIPP ...hydropower.ge/user_upload/3.Report_on_CBETA_Feb_2012.pdfinterruptions or curtailments. Exporters and importers are entitled to

USAID Hydropower Investment Promotion Project (USAID-HIPP)

Deloitte Consulting Overseas Projects - HIPP

11, Apakidze Street, Tiflis Business Center

Tbilisi, 0105, Georgia