HS2 - evolving thinking on applying circular economy thinking in an infrastructure project

26
www.gov.uk/hs2 Applying circular economy thinking in an infrastructure project Andrea Charlson & Andrew Dunwoody HS2 Ltd CIRCULAR ECONOMY THINKING in CONSTRUCTION 20 th January 2017

Transcript of HS2 - evolving thinking on applying circular economy thinking in an infrastructure project

www.gov.uk/hs2

Applying circular economy thinking in an infrastructure projectAndrea Charlson & Andrew Dunwoody

HS2 Ltd

CIRCULAR ECONOMY THINKING in CONSTRUCTION20th January 2017

www.gov.uk/hs2

HS2 vision:To be a catalyst for growth

across Britain

HS2: a strategic transformation

Phase OneStations:London EustonOld Oak CommonInterchangeBirmingham Curzon Street

Phase TwoStations:East Midlands Hub Leeds Manchester PiccadillyManchester Airport

Capacity and Connectivity

Phase One Construction Statistics

230km ROUTE LENGTH

74kmCUTTINGS

46kmTUNNELS

128 mtEXCAVATED MATERIAL

(90% TO BE RE USED)

145STRUCTURES

OVER BRIDGES

31MAIN COMPOUNDS FOR

CONSTRUCTION

152STRUCTURES UNDER BRIDGES

299SATELLITE COMPOUNDS

2017

Phase One Royal

Assent expected

2017

Phase One construction

starts

2022

Full Phase Two assent expected

2026

Phase One opens to

Birmingham

2033

Phase 2B opens

2027

Phase 2A opens to

Crewe

HS2 timeline

Our Culture

HS2 Strategic Goals

The circular economy:the step change we need?

• Reduced virgin non-renewable material use

• Reduced waste• Reduced carbon

emissions• Reduced potable

water use • Reduced

environmental contamination

• Lower capital cost• Lower operational

costs• Increased whole life

value• Reduced risk from

future legislation, taxes and price rises

• an avenue to resilient growth for the UK

• improved health (of supply chain workforce and general public)

• new job opportunities throughout the supply chain

Putting theory into practice

Keep resources in use for as long

as possible

Keep resources at their highest utility and value

at all times

Recover and regenerate

resources at the end of each use

Resource efficiency

Keep resources in use for as

long as possible

Recover and regenerate resources

Keep resources at their highest utility and value

Use resourcesefficiently

Demolition and site clearance

Civil structures

Railway systems

Stations

Rolling stock

Keep resources in use for as

long as possible

Recover and regenerate resources

Keep resources at their highest utility and value

Use resourcesefficiently

Demolition and site clearance

Pre-demolition audits

Maximise reuse

Civil structures Remote monitoring Material passportsDesign for

maintenanceUse reclaimed

materials

Railway systemsPreventative maintenance

Design for disassembly

Take back &remanufacture

Stations Design for durabilityDesign for

deconstructionDesign for

adaptabilityStructural

optimisation

Rolling stockAvoid premature

obsolescenceRecyclable Cascade Energy efficiency

• Image of excavated material or manufacturing

Maximising value of surplus excavated material

Maximising value of felled timber

• Facilitate the reuse of waste generated by the HS2 programme during demolition and construction, within the programme or on other local projects

Recover and regenerate resourcesUtilising at highest utility

• Procuring lighting as a service

Recover and regenerate resourcesEfficiency and recovery

Design for reuse

Identify if asset/element

should be designed for reuse

Develop design for deconstruction plan

Provide as-built inventory

Yes No

Facilitating recovery of materials in assetsRecovery of materials in assets

Utilising at highest utilityRealising value from verge biomass

Meanwhile uses for purchased property

Just the start

Further information

gov.uk/contracts-finder

Register QuestionsResources

competefor.com

Supplier Guide

Supply Chain FAQs

gov.uk/hs2 [email protected] Opportunities Table