IMS DOCUMENT CONTROL SHEET DOCUMENTATION NO: {HS-PY-037} ISSUE : Draft 1 SHEET 1 of 5 SHEETS TITLE Policy Boilers Maintenance and Inspection DOCUMENTATION APPROVAL This copy is uncontrolled if neither of the stamps below are in RED ink, or the “Quality Co-ordinator” box is blank RESPONSIBILITY LOCATION APPROVAL DATE ISSUE - QA Department AUTHOR Dubai Douglas Brown 06-05- 06 This document has been issued to a controlled distribution by the APPROVED Quality Department APPROVED APPROVED ISSUE - Quality Co-ordinator APPROVED OWNER DOCUMENT CONTROL DOCUMENTATION HISTORY ISSUE DCN NO ORIGINATOR DATE REASON FOR CHANGE Draft 1 - Douglas Brown 06-05- 06 Original i DISTRIBUTION Prepared by Drake & Scull International l.l.c, Facilities Management © 2005 Document Code: HS-PY-037 Page 1 of 5 Effective Date: 06-May-2006

description

Boilers

Transcript of Hs-py-037 Boilers Maintenance and Inspection

Boilers Maintenance and Inspection

IMS DOCUMENT

CONTROL SHEET

DOCUMENTATION NO: {HS-PY-037}

ISSUE : Draft 1

SHEET 1 of 3 SHEETS

TITLEPolicy

Boilers Maintenance and Inspection

DOCUMENTATION APPROVAL

This copy is uncontrolled if neither of the stamps below are in RED ink, or the Quality Co-ordinator box is blank

RESPONSIBILITY

LOCATION

APPROVAL

DATE

ISSUE - QA Department

AUTHOR

Dubai

Douglas Brown

02-05-05

This document has been issued to a controlled distribution by the

APPROVED

Quality Department

APPROVED

APPROVED

ISSUE - Quality Co-ordinator

APPROVED

OWNER

DOCUMENT

CONTROL

DOCUMENTATION HISTORY

ISSUE

DCN NO

ORIGINATOR

DATE

REASON FOR CHANGE

Draft 1

-

Douglas Brown

02-05-05

Original

i

DISTRIBUTION

Statement of Intent

Jumeirah International will ensure safe operation of boilers for the protection of workmen from potential work accidents at all Jumeirah Hotel sites by ensuring that the boilers are properly maintained, tested and recorded as per the UAE regulations.

Who should know and apply this policy

This policy applies to (whom and what)

All Jumeirah International (JI) hotels in the UAE

The Director of Engineering, the Chief Engineer and the Resident Engineers at each site/project are responsible for ensuring that this policy is reflected in supporting procedures, processes and documents and is applied by colleagues, and subordinates within their areas of control.

Cross-references, links and interfaces

The following documents/information supports this policy and demonstrates how its contents are interpreted and implemented at different levels throughout the JI organisation. Where appropriate, these documents also contain further cross-references to related/relevant materials.

Procedures:

Boilers InspectionHS-MP-059

Forms:

Boiler Maintenance Daily CheckHS-FM-038

Boiler Maintenance Monthly CheckHS-FM-039

Boiler Maintenance Semi-annually checkHS-FM-040

This Policy is based on and designed to support the JI Vision, Mission, Hallmarks and Guiding Principles

Key words

Policy Owner

(Title/Designation)

Reviewer(s)

(Title/Designation)

Policy Approver

(Title/Designation)

5.0Policy

5.1 The Engineer Responsible will ensure that the Boiler Attendant will provide a maintenance service which will comprise of:

5.1.1Daily routine maintenance of boilers in the plant rooms.

5.1.2Reactive maintenance to rectify any problems due to equipment failure or malfunction.

5.1.3Planned preventative maintenance as per the scheduled maintenance plan and the manufacturers recommendations.

5.2The inspection of boilers shall be made at the time of installation and at regular intervals of 12 months thereafter. It is essential that inspections should be thorough and complete.

5.2.1Only a technically qualified and experienced person who has been approved as competent to examine and test boilers by the Environmental Protection and Safety Section at the local municipality shall examine and test the equipment.

5.2.2 Before the boiler is entered for inspection, the Resident Engineer shall determine that the boiler may be safely entered by ensuring adequate ventilation inside the boiler and it is free of harmful vapours/gases.

5.2.3 Repairs: All repairs should be carried out under the supervision of competent person to ensure the safe operation of boilers.

5.2.4 Certification by Competent Person: The safety certification shall be done by the competent person on satisfactory completion of tests and examination of boilers.

5.2.5 The test certificate shall indicate the repairs/alternations/re-rating of working pressure etc. made to the boilers.

5.2.6 In the condition of a boiler is unsafe for operation, the competent person shall direct the Resident Engineer to remove it from service and send a report to the local municipality.

5.2.7 The test certificate shall be made available in the workplace and a copy sent to the Environmental Protection and Safety Section at the local municipality.

EMBED WPDraw30.Drawing

Prepared by Drake & Scull International l.l.c, Facilities Management 2005

Document Code: HS-PY-037

Page 1 of 3

Effective Date: 02-May-2005

Prepared by Drake & Scull International l.l.c, Facilities Management 2005

Document Code: HS-PY-037

Page 1 of 3

Effective Date: 02-May-2005