Howard Terzigni Presentation and Handouts

129
HVAC DUCT CONSTRUCTION STANDARDS March, 2010 Presented by: Eli Howard Executive Director Technical Services Mark Terzigni Project Manager Technical Services

Transcript of Howard Terzigni Presentation and Handouts

Page 1: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 1/129

HVAC DUCT CONSTRUCTION

STANDARDS

March, 2010

Presented by:

Eli HowardExecutive DirectorTechnical Services

Mark TerzigniProject Manager

Technical Services

Page 2: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 2/129

HVAC DUCT CONSTRUCTION

STANDARDS METAL AND FLEXIBLE

Page 3: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 3/129

Information Required for Duct Construction

1.  A comprehensive duct layout indicatingsizes, design airflows, pressure class,

and routing of the duct system.

2. The types of fittings to be used basedon the designer's calculations of fitting

losses (i.e., square versus 45°

 

entrytaps, conical versus straight taps, etc.).

Page 4: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 4/129

Information Required for Duct Construction

3. Use of turning vanes or splitter vanes.4. Location of access doors.

5. Location and type of control and

balancing dampers.

6. Location and types of diffusers.

7. Requirements for duct insulation.

Page 5: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 5/129

Information Required for Duct Construction

8. Location and types of any fire

protection device including firedampers, smoke dampers, combination

fire/smoke dampers, and ceiling

dampers. Building codes require thisinformation to be shown on the design

documents submitted for building

permit.

Page 6: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 6/129

Information Required for Duct Construction

9. Details of offsets required to route

ductwork around obstructions (columns,

beams, etc.).

Page 7: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 7/129

CONTRACTOR

Construction Considerations:Pressure Class

(as specified)

Panel Thickness (Gage)

Panel Width/Height

Joint Type/Spacing

Intermediate

Reinforcement

Type/Spacing

ENGINEER

Design Considerations:CFM

Static Pressure

Duct Size

Fitting Type

ConstructionPressure Class

Information Required for Duct Construction

Page 8: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 8/129

DEPENDENT V RI BLES

Page 9: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 9/129

Rectangular Transverse Joints

Rectangular

Figure 2-1

Pages 2.6-2.9

Page 10: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 10/129

Rectangular Transverse Joints

Page 11: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 11/129

Rectangular Transverse Joints

Page 12: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 12/129

Rectangular Transverse Joints

Page 13: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 13/129

Rectangular Transverse Joints

Page 14: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 14/129

Rectangular Transverse Joints

Page 15: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 15/129

Rectangular Transverse Joints

Page 16: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 16/129

Rectangular Transverse Joints

Page 17: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 17/129

Rectangular Transverse Joints

Page 18: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 18/129

Rectangular Transverse Joints

Page 19: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 19/129

Figure 2-16 Corners not required up to2 in. w.g.Corners are requiredabove 2 in. w.g.

Page 20: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 20/129

Figure 2-17

Page 21: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 21/129

Longitudinal Seams

Rectangular

Figure 2-17

Page 2.10

Page 22: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 22/129

Longitudinal Seams

Page 23: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 23/129

Longitudinal Seams

Page 24: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 24/129

Longitudinal Seams

Page 25: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 25/129

Intermediate Reinforcement

Figure 2-3

Page 2.12

Rectangular

Page 26: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 26/129

Intermediate Reinforcement

Page 27: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 27/129

Basic Duct Construction Process

Verify pressure class

Check corresponding table

Start with the larger side first

Determine reinforcement spacing options Check joint reinforcement tables

Check intermediate reinforcement tables

if applicable (tie rod options) Repeat for the short side

Page 28: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 28/129

Guide Summary (P 2.5)

Circles are column

numbers Number in box is the

minimum gage

First letter is minimum

reinforcement classrequired.

Second letter isdownsized reinforcement

when used with tie rod Xt – t means tie rod is

required

Page 29: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 29/129

In Words…

If the box in the table shows H-20G

The minimum panel gage is 20

The reinforcement required is class H at the

spacing noted at the top of the column (this can

be a joint or intermediate reinforcement)

You can use G instead of H if you use a tie rod

as well. (If to achieve a class G you are already

required to use a tie rod then you can not usethis option)

Page 30: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 30/129

Rectangular Duct Reinforcement

Page 31: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 31/129

Rectangular Duct Reinforcement

Page 32: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 32/129

Rectangular Duct Reinforcement

Page 33: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 33/129

Rectangular Duct Reinforcement

Page 34: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 34/129

Rectangular Duct Reinforcement

Page 35: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 35/129

Joint Reinforcement

Table 2-31

Starts on page 2.74

Covers all transverse

 joints that qualify as

reinforcement exceptT-1 drive slip

For T-1 drive slip see

Table 2-48 on page2.110

Page 36: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 36/129

Joint Reinforcement

Page 37: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 37/129

Page 38: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 38/129

Table 2-48

Page 39: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 39/129

Example 1

Pressure class is positive 1/2 in. w.g.

Dimensions are 20 in. x 12 in.

5 ft. joint spacing (longer if possible)

Preferred joint type plain Slip and Drive

Page 40: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 40/129

Example 1

Page2.14

Page 41: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 41/129

Example 1 Table 2-48

Not Accepted

Page

2.110

Page 42: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 42/129

Example 1 Solutions

Option 1

Use 24 gage

No reinforcement required either side

Option 2Use 26 gage

T-1 (plain drive) on the 20 in. side at a max

spacing of 10 ftNo reinforcement required on the 12 in. side

Page 43: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 43/129

Intermediate Reinforcement

Table 2-29

Starts on page 2.70

Covers typical

intermediate

reinforcement types.

For struts see Table

2-30 on page 2.72

Page 44: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 44/129

Intermediate Reinforcement

Page 45: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 45/129

Intermediate Reinforcement

H denotes Hot formed

C denotes Cold formed

Page 46: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 46/129

Example 2

Pressure Class is 2 in. w.g.

Dimensions are 60 in. x 26 in.

5 foot joint spacing

TDC or TDF joint No internal reinforcement

Page 47: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 47/129

The Right Table (Pressure Class)

Page

2.18

Page 48: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 48/129

The Right Table (Pressure Class)

Page

2.18

Page 49: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 49/129

The Right Table (Pressure Class)

Page

2.18

Page 50: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 50/129

Joint Reinforcement

Page

2.76

Page 51: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 51/129

Joint Reinforcement

Page

2.76

Page 52: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 52/129

Intermediate Reinforcement

Page

2.70

Page 53: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 53/129

Intermediate Reinforcement

Page

2.70

Page 54: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 54/129

Intermediate Reinforcement

Page 55: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 55/129

The Right Table (Pressure Class)

Page

2.18

Page 56: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 56/129

Joint Reinforcement

Page

2.76

Page 57: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 57/129

Example 2 Solution

Duct gage is 20

Joint spacing is 5 feet (56 ¼ in.)

TDC/TDF for transverse joint

Intermediate reinforcement (2 ½ feet)G class

 Angle 1 ½ x 1 ½ x 1/8

Not required on the 26 in. side

Page 58: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 58/129

Page 59: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 59/129

Reinforced on Two Sides

Page 60: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 60/129

Reinforced on Two Sides

Page 61: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 61/129

Reinforced on Four Sides

Page 62: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 62/129

Reinforced on Four Sides

Page 63: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 63/129

Reinforced on Four Sides

Page 64: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 64/129

Reinforcement Attachment

Page 65: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 65/129

Tie Rods Steel Rod

Threaded (all thread) or partial Plain

Conduit RC

EMT (most common type)

Steel Pipe

Steel Strap (positive pressure only) 1 in. x 1/8 in.

 Angles (rare)

Page 66: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 66/129

Tie Rod Attachment

Figure 2-5

Page 2.82

Page 67: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 67/129

Tie Rod Attachment

Figure 2-5

Page 2.82

Page 68: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 68/129

Tie Rod Attachment

Figure 2-6

Page 2.83

Page 69: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 69/129

Page 70: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 70/129

Tie Rod Layout p 2.98

Page 71: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 71/129

Mid-Panel Tie Rods Do not use in underground/slab apps

Do not use if air velocity > 2500 fpm Do not use where grease or condensation can

collect

Unless no penetration is made Or penetration is sealed water tight

If tie rods occur in 2 directions in the samevicinity they must: (applies to JTR and MPT) Be prevented from touching

Or be permanently attached

Page 72: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 72/129

Example 3

Pressure class is positive 4 in. w.g.

Dimensions are 36 in. x 24 in.

5 ft. joint spacing

Transverse joint TDC/TDF Use tie rod(s) where possible

Page 73: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 73/129

The Right Table (Pressure Class)

Page2.22

Page 74: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 74/129

The Right Table (Pressure Class)

Page2.22

Page 75: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 75/129

Joint Reinforcement

Page

2.76

Page 76: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 76/129

Joint Reinforcement

Page

2.76

Page 77: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 77/129

Joint Reinforcement

Page

2.76

Page 78: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 78/129

Mid Panel Tie Rod Schedule

Page

2.100

Page 79: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 79/129

Tie Rod Load

Page2.106

Table2-46

Page 80: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 80/129

Mid Panel Tie Rod Size

EMT conduit positive pressure

½ in. 900 lbs

¾ in. 1,340 lbs

1 in. 1,980 lbs HVAC DCS p2.80 S1.19.4

Page 81: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 81/129

The Right Table (Pressure Class)

Page

2.22

Page 82: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 82/129

Joint Reinforcement

Page

2.76

Page 83: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 83/129

Example 3 Solution

Duct gage is 22

Joint spacing is 5 feet (56 ¼ in.)

TDC/TDF for transverse joint

Intermediate reinforcement (2 ½ feet)1 MPT

½ in. EMT Conduit

Not required on the 24 in. side

Could use 20 gage and JTR also

Page 84: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 84/129

Mid Panel Tie Rods Negative pressure

uses special tables Concern is buckling

Table 2-38 in HVAC

DCS for EMT P 2.91

Page 85: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 85/129

Mid Panel Tie Rods Neg. Pressure

Page

2.91

Page 86: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 86/129

Tie Rod Loads

Table 2-46 p. 2.100 is for mid panel tie

rods (100% load) Table 2-34 p. 2.84 is for tie rods used to

back up joints or external reinforcement

(75% Load)

1 in. w.g. = 5.2 lbf/ft2

Page 87: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 87/129

Tie Rod Loads

Given information:

48” wide, RS = 28” (TDC/TDF) @ 4 in. w.g.

 Area = 48” x 28” = 1344 in2

Convert to ft2

1344/144 = 9.33 ft2

4 in. w.g. x 5.2 lbs/ft2/in. w.g. x 9.33 ft2

194 lbf 

If backing up a joint or external

reinforcement 194 lbf x .75 = 146 lbf 

Page 88: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 88/129

 An Easier Way?

Newest addition are the TDC/TDF tables

Tables based onPressure class

Joint length

Page 89: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 89/129

Example 3 (revisited)

4 in. w.g.

TDC/TDF

5 ft. joint spacing

36 in. x 24 in.

Page 90: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 90/129

Table 2-19 HVAC DCS

Example 3 (revisited)

Page

2.50

Page 91: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 91/129

Page 92: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 92/129

Table 2-19 HVAC DCS

Example 3 (revisited)

Page

2.50

Page 93: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 93/129

Example 3 (revisited) Solution

Option 1

20 gage

JTR on 36 in. side

No additional reinforcement on 24 in. side

Option 2

22 gage

MPT for 36 in. sideNo additional reinforcement on 24 in. side

Page 94: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 94/129

Example 3 (revisited) Solution

Option 3

20 gage

(2) E class reinforcements at the joints for 36 in. side

No additional reinforcement on 24 in. side

Option 4

22 gage

F class reinforcement at the mid-panel for 36 in. sideNo additional reinforcement on 24 in. side

Page 95: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 95/129

Duct over 120 inches Figure 2-13 in HVAC

DCS Use standard tables

for sizes < 120 in.

P 2.117

Page 96: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 96/129

Duct over 120 inches

Page2.117

Page 97: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 97/129

Duct over 120 inches

Page

2.117

Page 98: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 98/129

Example 4

Duct is 140 x 70 inches at negative 2 in.

w.g.

Page 99: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 99/129

Duct over 120 inches

Page

2.117

Page 100: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 100/129

You need 2 tie rods across the width at

every joint and at every reinforcement. 140/60 = 2.33 (round down) to 2

Need 3 at widths beyond 180”

140/(2+1) = 140/3 = 46 5/8” spacing

The joint length will be 5 ft. (56 inches

using TDC/TDF) and the reinforcementspacing will be 2 ½ ft (28 inches usingTDC/TDF).

Duct over 120 inches

Page 101: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 101/129

Determine the tie rod load:

Tip- You can figure the load on a duct ofhalf of the width using Table 2-46 and

then double the load.

140/2 = 70 inches

RS = 28 inches

Duct over 120 inches

Page 102: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 102/129

Duct over 120 inches

Page

2.106

Page 103: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 103/129

Page 104: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 104/129

Mid Panel Tie Rods Neg. Pressure

Page

2.91

Page 105: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 105/129

Example 4 mid-panel reinforcementPage

2.70

Page 106: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 106/129

Check the short side using the tables for

duct less than 120 inches. In this case since we are using TDC/TDF

we can use those specific tables.

Table 2-17 on page 2.46

Duct over 120 inches

Page 107: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 107/129

Duct over 120 inches

Page2.46

Page 108: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 108/129

Example 4 mid-panel reinforcementPage

2.70

Page 109: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 109/129

Example 4 solution The duct will be 18 gage

The joints will be TDC/TDF The joint length is 56 inches

The 140 inch side will be supported by 1” EMT

conduit spaced 46 5/8” across the width and willbe at each side of the joint and backing up themid-panel reinforcement.

The mid-panel reinforcement for the 140 inchside will be 2 ½ x 2 ½ x 1/8 and will be tiedusing 1 x 1 x 12 gage

Page 110: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 110/129

Example 4 solution The 70 inch side will be reinforced using

only external reinforcement The reinforcement will be 2 x 2 x 1/8 and

installed on both sides of each joint

This reinforcement will not be tied

No mid-panel reinforcement is required

Page 111: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 111/129

Example 4 solution

Page2.117

Page 112: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 112/129

Example 5 Round Duct Positive 10 in. w.g.

24 in. diameter 

Long seam or spiral

Table 3-5 in HVAC DCS Applies to positive pressure up through 10 in.

w.g.

Table 3-5 Page 3.8

Unreinforced Round Duct to Positive 10 in. w.g.

Page 113: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 113/129

Example 3 Round Duct

Table 3-5 Page 3.8

Unreinforced Round Duct to Positive 10 in. w.g.

Page 114: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 114/129

Example 3 Round Duct

Page 115: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 115/129

Example 6 Round Duct Negative 10 in. w.g.

24 in. diameter 

Long seam Spiral

Table 3-9 in HVAC DCS for long seam Table 3-13 in HVAC DCS for spiral

Page 116: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 116/129

Example 4 long seamLongitudinal Seam

Page 3.16

Page 117: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 117/129

Example 4 SpiralSpiral SeamP 3.24

Page 118: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 118/129

Round Reinforcement Tables in the HVAC

DCS 3-2 Reinforcement

3-3 Attachment

Schedule

3-4 Rings Used as

Companion Flanges

P 3.6

Page 119: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 119/129

Page 120: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 120/129

Round Reinforcement

Page 3.6

Page 121: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 121/129

Oval Duct Approved for positive pressure only

Can be used for negative pressure withspecial designs

Table 3-15 for gage

Reinforce like rectangular Based on the flat spanFlat span = major – minor 

Based on reinforcement spacingUse at least one tie rod (Figure 3-7 p 3.32)

Page 122: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 122/129

Oval Duct

Page 3.28

Page 123: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 123/129

Example 7 Oval Duct Flat Oval Duct 20” x 46” @+10 in. w.g.

Major dimension = 46”Minor dimension = 20”

Flat span (Major – Minor) = 26” (46” - 20”)

First step determine gage

Use Table 3-15

Use Major dimension

Page 124: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 124/129

Example 7 Oval Duct

Page 3.28

Page 125: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 125/129

Example 7 Oval Duct Next determine the reinforcement

Based on the flat span (26”)Use the correct rectangular table

Pick reinforcement spacing

Determine reinforcement class

Example 7 Oval Duct

Page 126: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 126/129

Example 7 Oval Duct

Page 2.26

Example 7 Oval Duct Solution

Page 127: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 127/129

Example 7 Oval Duct Solution

Using spiral duct

Build the duct from 22 gage materialReinforce the duct every 5 feet

Use a G class reinforcement

1 ½ x 1 ½ x 1/8 angle

Use either type 1 or type 2 option for tie rod

Figure 3-7 page 3.32

Page 128: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 128/129

Questions?

Page 129: Howard Terzigni Presentation and Handouts

8/20/2019 Howard Terzigni Presentation and Handouts

http://slidepdf.com/reader/full/howard-terzigni-presentation-and-handouts 129/129

Questions?

Technical Inquiries:

www.smacna.org

Click on technical services (left side)

Click on technical inquiries (center)

http://www.smacna.org/technical/index.cfm?fuseaction=inquiry