Randomized Trial of KEEP-P, a Preventive Intervention for ...
How to keep the project on budget in the clinical trial study
-
Upload
kevin-lee -
Category
Technology
-
view
214 -
download
0
description
Transcript of How to keep the project on budget in the clinical trial study
www.cytel.com
How to keep the project on budget in the clinical trial study
1
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Disclaimer
2
Any views or opinions presented in this presentation are solely those of the author and do not necessarily represent those of the company.
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Agenda
3
• Introduction of budgeting in Biometric department• Budget Items in clinical trial• Budget Template• Reasons of going over budget• How to save a budget• Review on the budget management after study
completion• Conclusion• Questions & Answers
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Introduction of budget
4
The project budget is the budget that is required to complete the project and it is based on• the number of deliverables required• the duration of the project• the accurate assessments of the resources However, a budget is meant to be an estimate, so it could change during the course of the project. The precision of estimation at the early stage becomes very important. In order to do the more accurate estimate, the budget items should be identified in the project.
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Budget items in clinical study (1)
5
Usual budget items in biometric department• Creation of SAP and Mock Up tables• The number of SDTM and ADaM• The number of Tables, Listings and Graphs• The frequency of deliverables
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Budget items in clinical study (2)
6
Additional budget items in Biometric department• The number of project meeting• The number of data transfer (external and
internal)• Data reconciliation (e.g. LAB and IVRS)• Coding(e.g. WhoDrug and MedDRA)• Programming support to other department
such as data management and marketing• Ad hoc reports
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Budget items in clinical study (3)
7
Additional budget items in Biometric department• Controlled Terminology• CDISC compliance checks (e.g.Opencdisc
checks on SDTM and ADaM)• The creation of Define document ( xml and pdf)• A complex analysis such as lab toxicity in
oncology and some efficacy analyses.• Project management
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Example of Budget Template
8
Number Task Hours for each task
Total Hours (hr)
Programmer’s Rate ($/hr)
Total Cost ($)
30 SDTM 10 300 $100 $30,00020 ADaM 10 200 $100 $20,000
100 TFL 10 1,000 $100 $100,000Total 1,500 $150,000
According to Budget Template, the budget for programming on 30 SDTM, 20 ADaM and 100 TFL with rate of $100/hr is $150,000.
Assumption : the same level of programmers and same hours for each task.
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Reasons of going over the budget
9
1. Incorrect budget in the contract2. Improper resources3. Poor Execution4. Incorrect deliverables5. Miscommunication
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
1 - Incorrect budget in the contract
10
The number of budget items in the contract is less than the number of actual items delivered to clients.• 20 ADaM in the contract vs 30 ADaM in the
actual deliverables.• 100 TFL in the contact vs 120 TFL in the actual
deliverables
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
2 - Improper Resourcing (1)
11
• Level – Junior-level programmers are assigned to senior-level tasks.
• Experience – Incorrect therapeutic assignment (ex,
Oncology, PK/PD, and so on) – Non-SDTM expert to SDTM projects / non-
ADaM expert to ADaM projects• No proper training or no mentoring
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
2 - Improper Resourcing (2)
12
• The incorrect number of programmers assigned to the project - More personnel means more training and learning curve
• Frequent reassignment rather than longer and consistent assignment
• No personal choices by programmers
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Resourcing Assignment Logic
13
Number Task Hours for each task
Total Hours (hr)
30 SDTM 10 30020 ADaM 10 200
100 TFL 10 1,000Total 1,500
1. Given 3 programmers• 30 hours per a week, so 3 programmers – 90 hours per a week
for 3 programmers• 1500/90 ~ 16 weeks, so about 4 months
2. Given 10 weeks• 30 hours per a week, so 10 weeks – 300 hours per 10 weeks• 1500/300 = 5, so about 5 programmers
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
3 - Poor Execution
14
• A lack of detailed, well-thought plan• A lack of leadership• A lack of the prompt and appropriate decision
making
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
4 - Incorrect deliverables
15
• It will be better to be a correct deliverable at the first time.
• Did not meet the expectation of clients
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Example of Costs for second deliverables
16
Number Task Hours for each task
Total Hours
Programmer’s Rate
Total Cost
30 SDTM 0.5 15 $100 $1,50020 ADaM 0.5 10 $100 $1,000
100 TFL 0.5 50 $100 $5,000Total 75 $7,500
According to Budget Template, the second deliverables will cost about $7,500
Assumption: • each task takes about 0.5 hour for rerunning and revalidating
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
5 - Miscommunication
17
Miscommunication• Miscommunication with the clients• Miscommunication within the teamProper Communication• A team needs a regular project meeting with the
clients and with the team.• A team needs to communicate the process and
current status of the projects.• A team communicates the issues or concerns
early.
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
How to save a budget (1)
18
• Clear understanding of the projects• Detailed planning for the projects and execution of
plans. • Proper resources (e.g. keeping the same
personnel in the similar studies, proper allocation of works and so on)
• Efficiency in programming( e.g. the proper usage of macros and process).
• Effective communication – internally and externally.
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
How to save a budget (2)
19
• Regular budget monitoring (especially at project milestone such as interim analysis)
• Monitoring the budget and adjusting the project process accordingly.
• Keeping the records of out-of-scope works –probably for the change order.
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Review on budget management after study completion
20
• Review the task times spent in the study. • Review the discrepancies between the contract
and the deliverables.• Review the current project process.• Gather projects’ historical data and analyze
them.
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Conclusion
21
• Budgeting – a programmer’s job?• A programmers wants to care about budget?• More accurate estimation • Gap analysis between contracts and
deliverables• More accurate feedback about the project and
budget
www.cytel.com ©2012 Cytel Statistical Software & Services Pvt. Ltd.
Questions?
22