Transcript of Houston Airport Marriott
-
7/29/2019 Houston Airport Marriott
1/22
Houston Airport
MarriottJuly 2013
-
7/29/2019 Houston Airport Marriott
2/22
Introduction to Host
S&P 500 and Fortune 500 company
Largest lodging REIT, $18 billion total market value
Portfolio of irreplaceable assets in premier markets:
Consolidated Portfolio + Joint Ventures: 145 hotels
4 hotels in Houston Houston Airport Marriott, JW Houston Galleria,
Houston Marriott Texas Medical Center and The St. Regis Houston
11 airport hotels
Hotels managed by best operators under strongestbrand names
2
-
7/29/2019 Houston Airport Marriott
3/22
Host Credentials
Manage over $500 million annual capital investmentplan (over $3.1 billion since 2007)
Technical specialists in design, architecture,
engineering, procurement, project management,estimating and sustainability
Strategic relationships + scale ensure favorable pricing
and quality workmanship from vendors, suppliers,consultants and contractors
3
-
7/29/2019 Houston Airport Marriott
4/22
Lobby / Great Room Elements
State-of-the-art, high-energy lobby to elevate thecustomer experience
3-meal-a-day dining / lobby bar concept
Expansive lobby seating area
New guest reception experience
Relocate and upgrade fitness facility
4
-
7/29/2019 Houston Airport Marriott
5/22
Conceptual Lobby Layout
5
BEFORE
-
7/29/2019 Houston Airport Marriott
6/22
Conceptual Lobby Layout
6
BAR
PANTRY
BUFFETBAR LOUNGE
RESTAURANT
DINING
SERV.
LOBBY LOUNGE
ADDITIONAL
SEATING
ADDITIONAL
SEATING REGISTRATION AFTER
-
7/29/2019 Houston Airport Marriott
7/22
Reception Desk
7
-
7/29/2019 Houston Airport Marriott
8/22
Lobby Lounge - Feature Wall
8
-
7/29/2019 Houston Airport Marriott
9/22
Bar Concept
9
-
7/29/2019 Houston Airport Marriott
10/22
Design Inspiration
10
-
7/29/2019 Houston Airport Marriott
11/22
Restaurant Concept
11
-
7/29/2019 Houston Airport Marriott
12/22
Feature Wall
12
-
7/29/2019 Houston Airport Marriott
13/22
Public Area & Grand Stair Concept
13
-
7/29/2019 Houston Airport Marriott
14/22
Tram Level Concept
14
Existing Tram Level
Tram Level Design Concept
-
7/29/2019 Houston Airport Marriott
15/22
Guestroom
15
Before: Existing typical king guestroom
After: Typical king guestroom (Chicago Marriott OHare)
-
7/29/2019 Houston Airport Marriott
16/22
Comparable Renovations
16
Chicago Marriott OHareLobby / Great Room
-
7/29/2019 Houston Airport Marriott
17/22
Recent Renovations
17
Chicago Marriott Suites OHare
-
7/29/2019 Houston Airport Marriott
18/22
Recent Renovations
18
Washington Dulles
Airport MarriottGreat Room
-
7/29/2019 Houston Airport Marriott
19/22
Business Terms
40-year lease
$40.5 million capital investment
$6.0 million within first year $34.5 million within 42 months
Rent = 10% of gross revenue
Minimum annual rent is $1,560,000
No additional hotels in the terminal complex within10 years from the effective date
19
-
7/29/2019 Houston Airport Marriott
20/22
Community Impact
175-200 jobs created during renovation
Industry day MWBE construction goal (and ACDBE concession goal)
LEED concepts and comprehensive sustainability program
Recycling construction and packaging waste Installation of energy and water saving devices Use of recycled products
Donate beds, furniture and other materials to localcharities
20
-
7/29/2019 Houston Airport Marriott
21/22
Renovation Plan
21
Anticipated Construction Schedule
Building Exterior / Grounds 3Q 2014
Building Systems 3Q 2014
Rooms 4Q 2014
Lobby / Great Room 1Q 2015
Elevators and Escalators 1Q 2015
Ballrooms and Meeting Rooms 2Q 2016
-
7/29/2019 Houston Airport Marriott
22/22
Questions?