Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project...

36
Hot Springs Public Hot Springs Public Meeting Meeting Reconstruction of US 18 & US Reconstruction of US 18 & US 385 385 Paul Knofczynski, P.E. Paul Knofczynski, P.E. Project Identification Coordinator Project Identification Coordinator South Dakota Department of South Dakota Department of Transportation Transportation

Transcript of Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project...

Page 1: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Hot Springs Public Hot Springs Public MeetingMeeting

Reconstruction of US 18 & US Reconstruction of US 18 & US 385385

Paul Knofczynski, P.E.Paul Knofczynski, P.E.Project Identification CoordinatorProject Identification CoordinatorSouth Dakota Department of South Dakota Department of TransportationTransportation

Page 2: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Project Locations

Page 3: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Why are we here?Why are we here?

Involve the publicInvolve the public

Discuss needsDiscuss needs

Exchange ideas or needsExchange ideas or needs

Page 4: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Why do we need these Why do we need these projects?projects?

SafetySafety

Capacity of the Capacity of the highwayhighway

Pavement conditionPavement condition

Page 5: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Existing ConditionsExisting Conditions

Roadway section Roadway section

Sidewalk Sidewalk

ROW widthROW width

Roadway LightingRoadway Lighting

Traffic Signal Traffic Signal

Intersecting roadsIntersecting roads

Current number of cars per day = 3,300 to Current number of cars per day = 3,300 to 6,7006,700

Future number of cars per day = 3,900 to 7,900Future number of cars per day = 3,900 to 7,900

Page 6: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Discussion Items:Discussion Items:

Scope of workScope of work Construction TimingConstruction Timing Access: before, during, and afterAccess: before, during, and after Crash HistoryCrash History Parking/Roadway sectionsParking/Roadway sections

Pedestrian facilitiesPedestrian facilities

Highway RouteHighway Route

Intersecting RoadwaysIntersecting Roadways

Page 7: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Scope of WorkScope of Work

Complete Urban ReconstructionComplete Urban Reconstruction– Replace asphalt pavement with concrete Replace asphalt pavement with concrete

– Curb & gutter Curb & gutter

– Update storm sewer Update storm sewer

– Update lighting and traffic signalUpdate lighting and traffic signal

– Improve pedestrian facilitiesImprove pedestrian facilities

– Accommodate parking…Accommodate parking…

Page 8: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Currently Scheduled for 2017 and Currently Scheduled for 2017 and 20182018

South project first, then north projectSouth project first, then north project

Timeline is being reviewedTimeline is being reviewed

(Pending any unforeseen issues)(Pending any unforeseen issues)

Construction TimingConstruction Timing

Page 10: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

EncroachmentsEncroachments

Page 11: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Crashes

Page 12: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Crash DataCrash Data

Data for 2010-2012Data for 2010-2012

No Fatal CrashesNo Fatal Crashes 12 Injury Crashes12 Injury Crashes 43 Property Damage Crashes43 Property Damage Crashes

Crash rate ranges from 5.55 to 6.53Crash rate ranges from 5.55 to 6.53 Crash rate, statewide average = 2.41 Crash rate, statewide average = 2.41

(similar type highway in SD)(similar type highway in SD)

Page 13: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Types of CrashesTypes of Crashes

Crash Type US 385US18

(parking)

US 18 (non-

parking)

% of Crashes

Hit Parked Car 7 1 15%

Parking Maneuver 6 4 19%

Approach Related 4 1 3 15%

Rear End 3 1 1 9%

Pedestrian/Crosswalk

2 3 9%

U Turn 1 2%

Tight corner 2 4%

Turning left on 4 Lane

1 2%

Page 14: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

ParkingParking

Page 15: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Different Types of Different Types of ParkingParking

Diagonal Diagonal ParkingParking

Parallel Parallel ParkingParking

Page 16: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Different Types of Different Types of ParkingParkingReverse Diagonal Reverse Diagonal ParkingParking

Advantages &

Disadvantages

Page 17: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Head out angled parking

http://vimeo.com/35268340#at=0

Dan Burden from the Walkable and Livable Communities Institute

Page 18: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Which type of parking is Which type of parking is better?better?

Diagonal vs. Parallel•Both affect traffic flow

•Can see approaching traffic

•Crash reduction

Diagonal vs. Reverse Diagonal•Same parking movement, but performed in opposite order

•Driver has to back into a parking spot

•View of approaching traffic

•Reduces crashes

Page 19: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Parking Reviewed

Parking utilization was reviewed using a variety of methods and times

Page 20: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Typical Sections and Typical Sections and ParkingParking

Sections will vary throughout each projectSections will vary throughout each project

3 lane section with through lanes & a 3 lane section with through lanes & a center left turn lane and no parking center left turn lane and no parking allowed allowed

Page 21: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Typical Sections and Typical Sections and ParkingParking

2 lane section with turn lanes and parallel parking

Page 22: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Typical Sections and Typical Sections and ParkingParking

2 lane section with reverse diagonal parking 2 lane section with reverse diagonal parking and width available for commuting bicyclesand width available for commuting bicycles

Page 23: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Highway Realignment Highway Realignment ConsideredConsidered

Page 24: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Intersecting Intersecting RoadwaysRoadways

Page 25: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Intersecting Intersecting RoadwaysRoadways

Page 26: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Right of Way (ROW)Right of Way (ROW)

Will use existing ROW where feasibleWill use existing ROW where feasible

ROW needs will be discussed in more detail ROW needs will be discussed in more detail

at individual Landowner Meetingsat individual Landowner Meetings

DOT will meet with affected landowners 2 or DOT will meet with affected landowners 2 or

more times regarding the projectmore times regarding the project

AppraisalsAppraisals

NegotiationsNegotiations

Page 27: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

UtilitiesUtilities

Utilities will be coordinated with construction

Page 28: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

City Work to be Coordinated

City contract let in combination with the State contract

Work performed at same time as roadway work

Upgrades include both water and sewer facilities, and are still being reviewed. Upgrades will likely include several different locations.

Page 29: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Lane CapacityLane Capacity

Future ADT: 3,900 to 7,900Future ADT: 3,900 to 7,900

3 lane section: up to 16,000 cars/day

2 lane section: up to 8,000 cars/day

Page 30: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

CostsCosts

Current programmed cost (2014 STIP):Current programmed cost (2014 STIP):– $ 6.647 M – US 385 (north project)$ 6.647 M – US 385 (north project)– $ 6.387 M – US 18 (south project)$ 6.387 M – US 18 (south project)

Programmed costs do not currently Programmed costs do not currently include:include:– Realignment of US 385Realignment of US 385– Structure replacement Structure replacement

Page 31: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Environmental, Environmental, Social, and Economic Social, and Economic

ConcernsConcernsSection 4(f) property: parks, refuges, and historic sites

Section 106: National Historic Preservation Act

Page 32: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Environmental, Environmental, Social, and Economic Social, and Economic

ConcernsConcerns

Historic Districts

Page 33: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Environmental, Environmental, Social, and Economic Social, and Economic

ConcernsConcerns

Contaminated materials are always a concern

Page 34: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Summary of ChangesSummary of Changes

Change pavement from asphalt to concreteChange pavement from asphalt to concrete Improved pedestrian facilitiesImproved pedestrian facilities Parking modificationsParking modifications Modify lane configurationsModify lane configurations Realignment of US 385/move signal locationRealignment of US 385/move signal location Realignment of intersecting streetsRealignment of intersecting streets Modification of lightingModification of lighting Potential bridge modificationPotential bridge modification Reduce crashesReduce crashes

Page 35: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

Questions?Questions?

Page 36: Hot Springs Public Meeting Reconstruction of US 18 & US 385 Paul Knofczynski, P.E. Project Identification Coordinator South Dakota Department of Transportation.

WebsiteWebsite– http://www.sddot.com/pe/projdev/planning_pubmeet.asphttp://www.sddot.com/pe/projdev/planning_pubmeet.asp

Submit Comments by: Submit Comments by: Wednesday,Wednesday, June 26, 2013June 26, 2013– Leave in box on front tableLeave in box on front table– Mail:Mail:

Paul KnofczynskiPaul KnofczynskiSDDOTSDDOT700 E Broadway Ave 700 E Broadway Ave Pierre, SD 57501Pierre, SD 57501

– Email: Email: [email protected]@state.sd.us