Transcript of Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin...
![Page 1: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/1.jpg)
Horse Creek DamolitionHorse Creek Damolition
Presenters:Matt Stoecker, Stoecker
Ecological and
Thomas B. Dunklin Productions
Presenters:Matt Stoecker, Stoecker
Ecological and
Thomas B. Dunklin Productions
![Page 2: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/2.jpg)
Horse Creek
Santa Barbara
![Page 3: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/3.jpg)
Sisquoc River Steelhead Barrier Assessment and
Recovery 2003
Sisquoc River Steelhead Barrier Assessment and
Recovery 2003 Funded by the Coastal Conservancy Identified migration barriers Historic steelhead documentation/current observations Habitat assessment Prioritize barriers for fish passage projects
Funded by the Coastal Conservancy Identified migration barriers Historic steelhead documentation/current observations Habitat assessment Prioritize barriers for fish passage projects
![Page 4: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/4.jpg)
Key FindingsKey Findings
Santa Maria R. was 2nd largest steelhead run in SB Co. Twitchell Dam (1950’s) blocked 264 miles, Cuyama R. Majority spawners used Sisquoc R. (Shapovalov, 1945) Over 203 miles historically accessible in Sisquoc River. Abundant high quality spawning and rearing habitat. Historic documentation and current wild O. mykiss
population. 31 anthropogenic barriers identified, plus natural
barriers. Horse Creek Dam blocks the most habitat at 19 miles Most limiting factor to Sisquoc steelhead is reduced
surface flow for migration on the Santa Maria River caused by inadequate releases from Twitchell Dam and excessive groundwater withdrawal
Santa Maria R. was 2nd largest steelhead run in SB Co. Twitchell Dam (1950’s) blocked 264 miles, Cuyama R. Majority spawners used Sisquoc R. (Shapovalov, 1945) Over 203 miles historically accessible in Sisquoc River. Abundant high quality spawning and rearing habitat. Historic documentation and current wild O. mykiss
population. 31 anthropogenic barriers identified, plus natural
barriers. Horse Creek Dam blocks the most habitat at 19 miles Most limiting factor to Sisquoc steelhead is reduced
surface flow for migration on the Santa Maria River caused by inadequate releases from Twitchell Dam and excessive groundwater withdrawal
![Page 5: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/5.jpg)
Historic Steelhead Documentation
Historic Steelhead Documentation
Sisquoc River 1916 (above) “ The stream is so full of mountain trout. I am
confident that we saw in some places more than 500 at one sight….and had no difficulty capturing all we wanted with our hands.” Stephen Bowers 1879
Sisquoc River 1916 (above) “ The stream is so full of mountain trout. I am
confident that we saw in some places more than 500 at one sight….and had no difficulty capturing all we wanted with our hands.” Stephen Bowers 1879
![Page 6: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/6.jpg)
Current Steelhead Documentation
Current Steelhead Documentation
![Page 7: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/7.jpg)
Sisquoc R. Habitat
Sisquoc R. Habitat
![Page 8: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/8.jpg)
Sisquoc R. Steelhead Survey 2005
Sisquoc R. Steelhead Survey 2005
Adult Steelhead over-summering 6 feet down in a cave under this bedrock ledge.
Adult Steelhead over-summering 6 feet down in a cave under this bedrock ledge.
Funded by DFG
![Page 9: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/9.jpg)
Looking up Horse Creek Canyon
Looking up Horse Creek Canyon
Dam
Sisquoc River
![Page 10: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/10.jpg)
Horse Ck. DamHorse Ck. Dam Built 11/3/1969 after
Wellman Fire Sacrete bags on
concrete footing, with re-bar
Dam crest 62 feet Dam height 10 feet
(5’ Dam, 5’ perched) Filled with sediment Stream gage, never
used
Built 11/3/1969 after Wellman Fire
Sacrete bags on concrete footing, with re-bar
Dam crest 62 feet Dam height 10 feet
(5’ Dam, 5’ perched) Filled with sediment Stream gage, never
used
![Page 11: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/11.jpg)
Horse Creek Habitat and Barriers
Horse Creek Habitat and Barriers
21.8 mi2, 1000-5000’ elev
Dam 850 feet upstream from Sisquoc River
19 miles of habitat (poor to good) upstream of dam to natural barriers.
Both perennial and intermittent reaches.
No trout observed, Arroyo Chub present.
21.8 mi2, 1000-5000’ elev
Dam 850 feet upstream from Sisquoc River
19 miles of habitat (poor to good) upstream of dam to natural barriers.
Both perennial and intermittent reaches.
No trout observed, Arroyo Chub present.
![Page 12: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/12.jpg)
Horse Ck. Upstream of the DamHorse Ck. Upstream of the Dam
![Page 13: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/13.jpg)
Also Upstream in Horse Creek
Also Upstream in Horse Creek
![Page 14: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/14.jpg)
Channel Assessment Study 2005
Channel Assessment Study 2005 Funded by American
Rivers/NOAA Fisheries Michael Love and Assoc.
and Stoecker Ecological Longitudinal Profile
2,200’ 7 channel cross
sections 2 downstream, 1 at
dam, 4 upstream Wolman pebble count of
stored sediment 250’ u/s
Funded by American Rivers/NOAA Fisheries
Michael Love and Assoc. and Stoecker Ecological
Longitudinal Profile 2,200’
7 channel cross sections
2 downstream, 1 at dam, 4 upstream
Wolman pebble count of stored sediment 250’ u/s
![Page 15: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/15.jpg)
Plan MapPlan MapPlan Map
Longitudinal Profile Survey
![Page 16: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/16.jpg)
Sediment Deposit Upstream of Dam
Sediment Deposit Upstream of Dam
Horse CreekHorse Creek
![Page 17: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/17.jpg)
Cross Section at DamCross Section at Dam
![Page 18: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/18.jpg)
![Page 19: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/19.jpg)
Downstream Reference Channel
Downstream Reference Channel
![Page 20: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/20.jpg)
Anticipated Removal Outcome
Anticipated Removal Outcome
Channel incision 2,321’ upstream 15,400 cubic yards of sediment u/s mobilized
(Annual Sisquoc R. 255,000-367,000 yd3)4-6% increase in one year, but will take more
Sediment released relatively course (gravel and cobble) Wolman pebble count.
Minimal to no negative impacts downstream Unobstructed wildlife/fish passage and
improved habitat and surface flow upstream
Channel incision 2,321’ upstream 15,400 cubic yards of sediment u/s mobilized
(Annual Sisquoc R. 255,000-367,000 yd3)4-6% increase in one year, but will take more
Sediment released relatively course (gravel and cobble) Wolman pebble count.
Minimal to no negative impacts downstream Unobstructed wildlife/fish passage and
improved habitat and surface flow upstream
![Page 21: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/21.jpg)
The Preferred AlternativeThe Preferred Alternative Removal Obsolete Not consistent with
Wilderness and Wild Scenic management
Most effective fish and wildlife passage
Restore surface flows and channel complexity
Inexpensive vs. fishway
Removal Obsolete Not consistent with
Wilderness and Wild Scenic management
Most effective fish and wildlife passage
Restore surface flows and channel complexity
Inexpensive vs. fishway
Explosives Staged release of sediment
not necessary No danger to people Difficult access Inexpensive vs. heavy
equipment Reduced impact to bank and
channel DFG and CCC technical
support and explosives (ammonium nitrate) available for project
Interest in gaining experience/knowledge with this technique
Explosives Staged release of sediment
not necessary No danger to people Difficult access Inexpensive vs. heavy
equipment Reduced impact to bank and
channel DFG and CCC technical
support and explosives (ammonium nitrate) available for project
Interest in gaining experience/knowledge with this technique
![Page 22: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/22.jpg)
Detonation Cords Going Off
Detonation Cords Going Off
![Page 23: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/23.jpg)
![Page 24: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/24.jpg)
Coastal Conservancy, Los Padres Nat. Forest, American Rivers, NOAA Fisheries, Dept. Fish and Game, California Conservation Corps, Community Environmental Council, Sisquoc Ranch, Thomas B. Dunklin Productions/Joan Dunning, Stoecker Ecological, Forest Watch
Coastal Conservancy, Los Padres Nat. Forest, American Rivers, NOAA Fisheries, Dept. Fish and Game, California Conservation Corps, Community Environmental Council, Sisquoc Ranch, Thomas B. Dunklin Productions/Joan Dunning, Stoecker Ecological, Forest Watch
![Page 25: Horse Creek Damolition Presenters: Matt Stoecker, Stoecker Ecological and Thomas B. Dunklin Productions.](https://reader036.fdocuments.us/reader036/viewer/2022062408/56649e7a5503460f94b7a630/html5/thumbnails/25.jpg)
Un-Dam it and they will come!Un-Dam it and they will come! Matt Stoecker [email protected]
Photo/Assistance thanks: Bob, Doug, Jim Stoecker Thomas Dunklin Michel Love Shaw Allen Kevin Cooper Tony Llanos Donna Toth
Matt Stoecker [email protected]
Photo/Assistance thanks: Bob, Doug, Jim Stoecker Thomas Dunklin Michel Love Shaw Allen Kevin Cooper Tony Llanos Donna Toth