    How to apply Overtime, and Double time rates in MS PROJECT 2010osted on January 26, 2012

    Hi,

    ne of my Blog reader has a Problem. She has Project and she must apply three different Pay rates for Resource

    n the Task in MS PROJECT 2010. Here is an example:

    ohn is working ontask, and it will have Duration = 14 days! John will work from Monday to Sunday 12

    ours per day! Regular work is 8 hours per day, and 4 hour per day are overtime work. BUT! Every Sunday

    ohn will earn double time fee.

    K! Firs we have toSETUP our Regular work:

    hen:

    enad Trajkovski

    http://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.com/http://ntrajkovski.files.wordpress.com/2012/01/image106.pnghttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    2/16

    Now I will setup working time in my Calendar:

    http://ntrajkovski.files.wordpress.com/2012/01/image107.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    3/16

    will add a brand new Task in my Project:

    Now I will add John as Resource:

    http://ntrajkovski.files.wordpress.com/2012/01/image109.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image108.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    4/16

    Notice the figures in Cost Rate Table:

    From Project start 30.01.2012 John will be paid $100 per hour for Standard work (8 hours per day), and

    $150 for Overtime work (4 hours per day)

    At Sunday, 05.02.2012 John will be paid $200 per hour for Standard work (8 hours per day), and Overtime

    work (4 hours per day). This is what we can call Double Time Rate

    From Monday till Saturday (06.02.2012-11.02.2012) John will be paid $100 per hour for Standard work (8

    hours per day), and $150 for Overtime work (4 hours per day)

    At Sunday, 12.02.2012 John will be paid $200 per hour for Standard work (8 hours per day), and Overtime

    work (4 hours per day). This is what we can call Double Time Rate

    K! Now I Will assign John to the Task:

    Now I will choose the Cost Table:

    http://ntrajkovski.files.wordpress.com/2012/01/image111.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image110.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    5/16

    nd I will get:

    otal Cost is $12.800! Why?

    From Monday, 30.01.2012 till Saturday, 04.02.212 (6 days * 8 hours per day = 48 hours), pay rate is $100.

    48 hours * $100 = $4.800

    At Sunday, 05.02.2012, pay rate is $200. 8 hours * $200 = $1.600

    From Monday, 06.02.2012 till Saturday, 11.02.212 (6 days * 8 hours per day = 48 hours), pay rate is $100.

    48 hours * $100 = $4.800

    At Sunday, 12.02.2012, pay rate is $200. 8 hours * $200 = $1.600

    $4.800 + $ 1.600 + $4.800 + $1.600 = $12.800

    Here is the Task Usage:

    ut, where is the Overtime rate applied? NOWHERE! Why? Remember that you should assign overtime work

    y your own. That means, if someone will work 12 hours on a task per day, it doesnt mean that MS PROJECT

    010 will charge 4 extra hours with overtime rate.

    http://ntrajkovski.files.wordpress.com/2012/01/image114.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image113.pnghttp://ntrajkovski.files.wordpress.com/2012/01/image112.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    6/16

    Now, I will put overtime work in MS PROJECT 2010:

    Now I will click anywhere in Task Form, and on the format Tab select Work:

    http://ntrajkovski.files.wordpress.com/2012/01/image115.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    7/16

    nd I will get:

    http://ntrajkovski.files.wordpress.com/2012/01/image116.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    8/16

    Now what? John has to work 12 hours per day, and 4 hours will be overtime. 14 days * 12 hours per day = 168

    ours. 14 days * 4 overtime hours per day = 56 hours. I will put those figures in Task Form:

    http://ntrajkovski.files.wordpress.com/2012/01/image117.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    9/16

    nd I will get:

    http://ntrajkovski.files.wordpress.com/2012/01/image118.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    10/16

    Now, the Total Cost is $21.600! Why?

    From Monday, 30.01.2012 till Saturday, 04.02.212 (6 days * 8 regular hours per day = 48 hours hours),

    regular pay rate is $100. 48 hours * $100 = $4.800

    From Monday, 30.01.2012 till Saturday, 04.02.212 (6 days * 4 overtime hours per day = 24 hours), overtime

    pay rate is $150. 24 hours * $150 = $3.600

    At Sunday, 05.02.2012, pay rate is $200 (regular and overtime) . 12 hours * $200 = $2.400

    From Monday, 06.02.2012 till Saturday, 11.02.212 (6 days * 8 regular hours per day = 48 hours hours),

    regular pay rate is $100. 48 hours * $100 = $4.800

    From Monday, 06.02.2012 till Saturday, 11.02.212 (6 days * 4 overtime hours per day = 24 hours), overtime

    pay rate is $150. 24 hours * $150 = $3.600

    At Sunday, 12.02.2012, pay rate is $200 (regular and overtime) . 12 hours * $200 = $2.400

    $4.800 + $3.600 + $2.400 + $4.800 + $3.600 + $2.400 = $21.600

    ets look at the Task Usage View:

    http://ntrajkovski.files.wordpress.com/2012/01/image119.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    11/16

    ou can see that Cost per day (except Sunday) is $1.400. (8 hours * $100) + (4 hours * $150) = $1.400. At

    unday Cost is 12 hours * $200 = $2.400.

    hats it.

    egards!

    You May Like

    1.

    You May Like

    1.

    You May Like

    1.

    About these ads

    Like

    e blogger likes this.

    !

    elated

    ow to Assign different Overtime Rate in How to track Actual overtime work in MS Setting Up Overtime Pay Rates and

    http://ntrajkovski.com/2013/09/12/how-to-assign-different-overtime-rate-in-ms-project-2013/http://ntrajkovski.com/2011/06/30/setting-up-overtime-pay-rates-and-assigning-resource-overtime-hours/http://ntrajkovski.com/2012/02/20/how-to-track-actual-overtime-work-in-ms-project-2010/http://ntrajkovski.com/2013/09/12/how-to-assign-different-overtime-rate-in-ms-project-2013/http://widgets.wp.com/likes/#http://en.gravatar.com/galadarhttp://en.wordpress.com/about-these-ads/http://wallstcheatsheet.com/stocks/7-most-corrupt-countries.html/?a=viewallhttp://wallstcheatsheet.com/stocks/7-most-corrupt-countries.html/?a=viewallhttp://wallstcheatsheet.com/stocks/7-most-corrupt-countries.html/?a=viewallhttp://ntrajkovski.files.wordpress.com/2012/01/image120.png
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    12/16

    About Nenad Trajkovski

    Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in

    Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking,

    manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into differentcompanies. He has got a lot of experience working with people in different business processes and also possesses great

    knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in

    PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Vara!din,

    Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of

    WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009

    and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in

    Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager

    Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft

    Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!

    View all posts by Nenad Trajkovski!

    is entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, MS PROJECT 20101, PMI, PRoject Management and tagged Microsoft Project

    10, MS PROJECT 2010 - assigning Overtime Pay Rates, PMI, Project Management. Bookmark the permalink.

    0 Responses toHow to apply Overtime, and Double time rates in MS PROJECT 2010

    S PROJECT 2013 PROJECT 2010 Assigning Resource Overtime Hours

    ow to Assign different Overtime Rate in

    S PROJECT 2013

    How to track Actual overtime work in MS

    PROJECT 2010

    Setting Up Overtime Pay Rates and

    Assigning Resource Overtime Hours

    paul przekowiaksays:

    February 9, 2014 at 5:51 pm

    Hi Nenad,

    Thanks a lot for all posts written

    Please, could you help me to better understand the calculating methods of MS Project because I dont well understand MS

    Project behaviour: To explain my problem, here is my context :

    CONTEX

    Calendar : Std (08:00-12:00 / 13:00-17:00) assigned to all tasks

    Resource R1 :

    Calendar standard excepted for February 10 2014 with working time 08:00 12:00

    Capacity ___

    For February 10, 2014 = 100%

    For February 11 to 15, 2014 = 50%

    Cost rate___

    for February 10 , 2014 Std rate 10!and overtime rate 20!

    Cost for February 11, 2014 std rate 20!overtime rate 40!

    Auto schedule activated

    Task 1 : constraint Start not earlier than February 10, 2014 08:00

    finish date February 11,2014 17:00

    http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-2971http://ntrajkovski.com/2011/06/30/setting-up-overtime-pay-rates-and-assigning-resource-overtime-hours/http://ntrajkovski.com/2012/02/20/how-to-track-actual-overtime-work-in-ms-project-2010/http://ntrajkovski.com/2013/09/12/how-to-assign-different-overtime-rate-in-ms-project-2013/http://ntrajkovski.com/2011/06/30/setting-up-overtime-pay-rates-and-assigning-resource-overtime-hours/http://ntrajkovski.com/2012/02/20/how-to-track-actual-overtime-work-in-ms-project-2010/http://ntrajkovski.com/2013/09/12/how-to-assign-different-overtime-rate-in-ms-project-2013/http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/http://ntrajkovski.com/tag/project-management-2/http://ntrajkovski.com/tag/pmi/http://ntrajkovski.com/tag/ms-project-2010-assigning-overtime-pay-rates/http://ntrajkovski.com/tag/microsoft-project-2010-2/http://ntrajkovski.com/category/project-management/http://ntrajkovski.com/category/pmi/http://ntrajkovski.com/category/ms-project-20101/http://ntrajkovski.com/category/ms-project-2010/http://ntrajkovski.com/category/microsoft-project-2010/http://ntrajkovski.com/category/microsoft-project/http://ntrajkovski.com/author/ntrajkovski/
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    13/16

    fixed Work = 15h

    For the Gantt Chart, I display Resource usage view => 3 panels + 1 chart

    - On the left detail part, I enter 7h on the overtime work field (after manual insert of this field)

    - On the right part of the resource usage view, I enter for :

    February 10 , work 8 => overallocation automatically calculated = 4 => Ok

    February 11, work 7 => overallocation automatically calculated = 3 => Ok

    PROBLEM

    But MS project calculates also overtime work, and I dont understand how because

    For February 10 , overtime work = 3,28h

    For February 11, ovt work = 3,72

    Firstly, no way to change this repartition, automatically calculated. Impossible to type data on ovt work field

    Secondly, its better to overload the ovt work of the Feb. 10 because this ovt rate is lower than the ovt rate of th Feb.11

    Finally the total calculated cost by Project = !327,19 but according to my own calculation it should be egal to !334,40

    Feb 10 = 4h std time x 10 std rate + 3,28h ovt x 20 ovt rate = !105,60

    Feb 11 = (4 x 20 ) + (3,72 x 40) = !228,80

    Total cost = !334,40

    Please, could you help me to better understand the calculating methods of MS Project

    Sorry for my approximate translation

    Thanks a lot

    Paul PRZEKOWIAK

    Reply

    Nenad Trajkovskisays:

    February 11, 2014 at 1:54 pm

    Can you send me an mpp file on [email protected]?

    Reply

    bharanikumarsays:

    August 13, 2013 at 12:29 pm

    if two activity 6 hours and 6 hours for one more then how?

    Reply

    Nenad Trajkovskisays:

    August 26, 2013 at 11:06 am

    I dont understand your question! COuld you be more specific?

    Reply

    Susan Raatzsays:

    August 26, 2013 at 3:30 pm

    I was pretty confused by overtime hours. Maybe it will help to explain that OT hous are a subset of work hours. E.g.,

    if 14 hours total were worked and 2 of those hours were OT, you enter 14 in Work field and 2 in OT field. Now, if you

    dont want to go with Standard OT rate, you can assign any rate to a task but again this is tricky. You need to assign

    http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-2587http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=2581#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-2581http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=2559#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-2559http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=2977#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-2977http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=2971#respond
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    14/16

    the resource to the task, then go to task usage view, select the resource and double click. You will see cost rate table

    on the general tab of the pop up box. You can select the appropriate rate (A,B,C, etc.) from there. You need to load the

    rates in the resource sheet view first. Hope that helps. Took me forever to figure it out.

    Reply

    galadarsays:

    March 28, 2013 at 7:08 am

    Hi dear

    first I would like to say thanks for your above post, after that I would like to share one question with you which I have in

    mind, it is also something about cost calculation thats why I am asking here:

    How to set up different pay rate units such as ($/m, $/m2, $/m3, $/ton and so) and thats it. you know in most

    construction projects like building, roads, tunnel, canal even dam constructions cost of much of items such as excavation,

    drainage and so will calculated based on different pay rates as indicated above. for example if I want to setup cost of

    excavation task how I suppose to do that, if I have to setup unit pay rate of this task in resource sheets ? so which kind of

    resource I suppose to assign (work, material or cost resource) and how I use different pay rate ? or if I suppose to setup this

    kind of cost in different place, where is that place ?

    with thanks and respect

    Reply

    Suasn Raatzsays:

    December 18, 2012 at 4:50 pm

    Thanks for this information! My question is regarding cost per task. I have temp employees working overtime. In a given

    week they are paid overtime rate for hours over 8 per day. In the same week they could leave early so they may have a day

    where I need to assign $0 for 4 hours. I entered a task called Unpaid Time so I could measure how many hours they take off

    but project is not letting me assign rate table cost of $0. Do you know how to report this? Thanks again!

    Reply

    Nenad Trajkovskisays:

    December 18, 2012 at 6:56 pm

    I will write a post for this issue next week! Thank you for a great Idea

    Reply

    Igorsays:October 18, 2012 at 4:30 pm

    Hello Nenad Trajkovski,

    Its a great blog you have over here.

    About overtime, I tried to apply 12 hours a day on Saturday and Sunday, its a 2 day work (driving car) and It allocates 24

    hours on Saturday. Both days are dayoff (rest time), so its 24 hours overtime rate. Is there a way to allocate 12 hours a day?

    Thanks

    Reply

    Nenad Trajkovskisays:

    October 19, 2012 at 12:28 pm

    http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-1302http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=1299#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-1299http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=1796#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-1796http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=1794#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-1794http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=2210#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-2210http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=2587#respond
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    15/16

    Let me clear one thing out! You want to drive your car at Saturday 12 hours and Sunday 12 hours! And 12 hours

    per day are overtime?

    Reply

    Igorsays:

    October 19, 2012 at 3:52 pm

    Yes, thats right. Saturday and Sunday are days off, so if the I work that days its overtime. I cant work more

    than 12 hours, according to the law, so how can I make it happen? When I do it, the microsoft project used to

    change the duration (which is fisically impossible) or It used to allocate to work 24 hours at Saturday.

    Nenad Trajkovskisays:

    October 20, 2012 at 8:46 am

    I wrtoe a post about this, and it will be published at Wednesday, 24.10.2012

    Annasays:

    July 10, 2012 at 2:15 pm

    Hi, do you know how to apply 3 rates in one working day.

    EG on a 12 hr shift,

    upto 8hrs use Std Rate,

    8-10hrs use Overtime Rate,

    10-12 hrs, use triple time Rate

    Reply

    Nenad Trajkovskisays:

    July 11, 2012 at 8:05 am

    YOu can apply only one standard rate and one overtime rate per day!

    Reply

    Nenad Trajkovskisays:

    July 11, 2012 at 1:34 pm

    But yoiu can apply differnt tables (pax / costs) per task, if that can help you!

    Reply

    Annasays:

    July 11, 2012 at 1:47 pm

    Thanks very much Nenad. I appreciate your help. Anna.

    hennrysays:

    June 22, 2012 at 8:51 am

    Hai Mr. Nenad Trajkovski; Im Hennry from Indonesia; I have problem with Peak resources;

    at the beginning I have 200% carpenters; and because of some task so he overlocated and got the red mark; I try to resolve by

    add 200% carpenters, the red mark disappears, but there is information peak for the carpenters are 600%; so I arrange for

    the 4 carpenters to different days, but I still not sure about peak. Would you help me please ? thanks in advance, best

    regards,

    http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-733http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-835http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=834#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-834http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=831#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-831http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=822#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-822http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-1316http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-1309http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=1302#respond
  • 7/25/2019 Horas Extra Ms Project 2010( Ingls)

    16/16

    enad Trajkovski

    hennry

    Reply

    Nenad Trajkovskisays:

    June 22, 2012 at 8:53 am

    Can you send me mpp file?

    Reply

    Gordonsays:

    February 17, 2012 at 9:11 am

    thanks for the info.

    I am trying to update and add OT to a task that has already started.

    I cannot seem to add hours to the OT Work Field.

    I can reduce the work hours, but when I attempt to put those hours into the OT Work fild the hours will not add. Any Ideas? -

    Gordon

    Reply

    Nenad Trajkovskisays:

    February 17, 2012 at 11:52 am

    Can you send me your mpp file? It works fine here

    Reply

    The Twenty Ten Theme Blog at WordPress.com.

    http://wordpress.com/?ref=footerhttp://theme.wordpress.com/themes/twentyten/http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=540#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-540http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=539#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-539http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=735#respondhttp://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/#comment-735http://ntrajkovski.com/2012/01/26/how-to-apply-overtime-and-double-time-rates-in-ms-project-2010/?replytocom=733#respondhttp://ntrajkovski.com/