Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Project Update
November 2018
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084
Incidental Budget $ 4,632,681
Construction Contingency $ 1,564,311
Contracts Awarded $22,848,873
State Contract $ 940,219
Construction Contingency Budget Update
•Construction Contingency Budget $1,564,311
•There are no approved Change Orders at this time
•Contingency Budget is 0% spent
•Contract allowance approved totals $0
•Project Team is following approximately $114,205 in pending issues
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Manor Intermediate
• Colors have been selected materials
are being ordered and work will begin
starting Christmas Break.
Transportation Building
• Foundations around the perimeter of
the Addition have been installed and
back filled.
Middle School
• Turf Field construction is anticipated
to begin in January.
Senior High School
• A temporary road from the Tennis Court
to the H.S. Staging Area has been
installed.
• A temporary wall has been installed
along the Main Entrance.
• Trees near the Main Entrance building
pad have been removed along with the
sidewalk and masonry wall.
•Temporary walls have been installed for
the Art Room and demo has begun.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Manor Intermediate
• Work will begin starting Christmas
Break.
Transportation Building
• Footers and Foundations will be
completed by the end of December.
•Structural steel is scheduled to arrive
the first week of January.
Middle School
• Turf Field construction is anticipated
to begin in January.
Senior High School
• Foundation work for the Main Entrance
is scheduled to be completed by mid
January.
• Art Room demo and abatement will
begin Christmas Break.
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Progress Photos
Demo – High School Art Room
Temporary Walls – High School Art Room
Cutting Trees– High School Main Office
Demo Concrete Sidewalk– High School Main
Office
Demo Front Area– High School Main Office
Demo Brick– High School Main Office
Temp Walls at Lobby– High School Main
Office
Demo and Fence – High School Tennis Courts
Demo Hedge Row – Middle School Turf Field
Fencing – Middle School Turf Field
Digging Footers – Transportation Building
Pouring Foundation Walls – Transportation
Building
Strip Forms & Backfill – Transportation
Building
Stripping for Building Pad - Transportation
Building