![Page 1: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/1.jpg)
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Project Update
March 2020
![Page 2: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/2.jpg)
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084
Incidental Budget $ 4,632,681
Construction Contingency $ 1,564,311
Contracts Awarded $22,848,873
State Contract $ 940,219
![Page 3: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/3.jpg)
Construction Contingency Budget Update
•Construction Contingency Budget $1,564,311
•Additional Co-Op Purchases $ 187,098
•Additional Credit $ 63,092
•Approved Change Orders $1,098,108
•Remaining Construction Contingency $ 342,197
•Construction Project is 76% Complete
•Contingency Budget is 78% spent
•Contract allowance approved totals $0
•Project Team is following approximately $267,739 in pending issues.
![Page 4: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/4.jpg)
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Manor Intermediate
• Rooms 303 and 305 have been
completed and turned over to the
District.
• Construction in the Music Room has
begun.
Transportation Building
• Concrete for the Mezzanine has
been poured.
• Overhead plumbing, ductwork and
electrical conduit are ongoing.
• Masonry block work is ongoing.
Senior High School
• The Display Cases have been installed in the
Lobby.
• Wall tile and floor tile have been installed in
the Kitchen and Cafeteria.
• Ceiling grid is installed throughout the
Cafeteria and Kitchen and ceiling tile is being
dropped.
• The Cougar Mural has been installed in the
stairwell adjacent to the Cafeteria.
• Demolition has begun in the Robotics Lab.
• Demo of B&G has begun.
![Page 5: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/5.jpg)
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Lima Intermediate
• The Main Office has undergone
demolition, framing has begun and
MEP rough-ins are ongoing.
• Rooms 107, 108, 109 and 110 have
been abated and new flooring is going
in.
Middle School
• The building has been switched over to the
new Day Automation platform.
![Page 6: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/6.jpg)
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Manor Intermediate
• Heavy demo will continue in the
Music Room.
Senior High School
• The Cafeteria will be turned over to the
District.
• Construction will continue in the Kitchen
Area.
• The Faculty Lounge will be completed
and turned over to the District.
• Construction in the Robotics Lab will
continue.
• Parking lot work and concrete sidewalks
will continue.
Lima Elementary
• Construction in the Main Office will
continue.
Transportation Building
• Masonry work, drywall, floor leveling
and MEP rough-ins will all continue.
![Page 7: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/7.jpg)
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Progress Photos
![Page 8: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/8.jpg)
New Mezzanine – Transportation Center
![Page 9: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/9.jpg)
New Mezzanine – Transportation Center
![Page 10: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/10.jpg)
Office Space – Transportation Center
![Page 11: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/11.jpg)
Temporary Wall in Manor Cafeteria
![Page 12: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/12.jpg)
New Music Room - Manor
![Page 13: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/13.jpg)
New Music Room - Manor
![Page 14: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/14.jpg)
Cafeteria – High School
![Page 15: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/15.jpg)
Cafeteria – High School
![Page 16: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/16.jpg)
Cafeteria – High School Kitchen
![Page 17: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/17.jpg)
Flexible Learning Lab – High School
![Page 18: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/18.jpg)
Flexible Learning Lab – High School
![Page 19: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/19.jpg)
Robotics Lab – High School
![Page 20: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/20.jpg)
Main Entrance Lobby – High School
![Page 21: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/21.jpg)
Main Entrance Lobby – High School
![Page 22: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/22.jpg)
Main Entrance Lobby – High School
![Page 23: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/23.jpg)
B&G Building Demolition
![Page 24: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/24.jpg)
B&G Building Demolition
![Page 25: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/25.jpg)
B&G Building Demolition
![Page 26: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/26.jpg)
New Concrete Sidewalks – High School
![Page 27: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/27.jpg)
New Concrete Sidewalks – High School
![Page 28: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/28.jpg)
New Main Office – Lima
![Page 29: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/29.jpg)
Room 107 – Lima
![Page 30: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/30.jpg)
Room 108 – Lima
![Page 31: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/31.jpg)
Room 109 – Lima
![Page 32: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/32.jpg)
Room 110 – Lima
![Page 33: Honeoye Falls-Lima Central School District€¦ · •Parking lot work and concrete sidewalks will continue. Lima Elementary •Construction in the Main Office will continue. Transportation](https://reader033.fdocuments.us/reader033/viewer/2022052721/5f0ac2447e708231d42d3333/html5/thumbnails/33.jpg)
Cougar Mural – High School